Labour Day Sale - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: mxmas70

Home > PMI > PMI Professional in Business Analysis > PMI-PBA

PMI-PBA PMI Professional in Business Analysis (PMI-PBA) Question and Answers

Question # 4

A business analyst has started a project for a system enhancement. In order to determine how the requirements will be approved, the business analyst schedules a meeting with the stakeholders to discuss the proposed approval process.

Which measure of effective decision making allows the business analyst to finalize the process for requirement approval?

A.

The requirements verification process is documented.

B.

The requirements elicitation process is documented.

C.

The requirements validation process is documented.

D.

The requirements approval process is documented.

Full Access
Question # 5

A business analyst is conducting a cost-benefit analysis of potential solution options. The stakeholders have indicated that the estimated growth rate is very important to them.

Which technique will allow the business analyst to determine this information?

A.

Payback period

B.

Net present value (NPV)

C.

Internal rate of return

D.

Return on investment (ROI)

Full Access
Question # 6

How should a business analyst determine whether a solution satisfies business requirements?

A.

By reviewing the results of user acceptance testing

B.

By evaluating the solution against the project charter

C.

By conducting a brainstorming session with end users

D.

By reviewing the traceability matrix

Full Access
Question # 7

An organization is in the process of replacing its current system. The business analyst is charged with ensuring that all current connections to other systems remain functional after the upgrade.

What analysis should the business analyst conduct to facilitate a successful migration?

A.

Document

B.

User interface

C.

Interface

D.

Systems

Full Access
Question # 8

Which tool can be used to analyze how the system responds to various combinations of input conditions with the probability of each outcome?

A.

Decision tree

B.

Functional decomposition

C.

Expected monetary value

D.

Weighted criteria

Full Access
Question # 9

The project team is working on test scripts to test a solution. Which source can be used for building tests of end-to-end business processes across business functions and systems?

A.

Prototype model

B.

Feature model

C.

Context diagram

D.

Use case

Full Access
Question # 10

The project sponsor needs to know which requirements will be implemented. Which of the following would be the most valuable for a business analyst to provide?

A.

Requirements traceability matrix

B.

Requirements baseline document

C.

Requirements management plan

D.

Requirements impact analysis

Full Access
Question # 11

A type of requirements document that would be the most valuable to a database administrator would be:

A.

a data flow diagram.

B.

a business process diagram.

C.

an entity relationship diagram.

D.

an object diagram.

Full Access
Question # 12

In order to reduce product and project risk for a large, complex project, a business analyst is asked to help develop a change process that includes formal authorization and tracking throughout the life cycle of the project. The business analyst needs a capability that will help ensure that the product conforms to approved requirements, changes can be documented, and the status of each change can be

reported.

What should the business analyst use?

A.

Configuration management system

B Work breakdown structure

B.

Traceability matrix

C.

Context models

Full Access
Question # 13

The customer and the business analyst are collaborating in the development of a solution scope. It is important for the customer to:

A.

communicate changes to requirements only when they are completely defined.

B.

spend the time required to provide, clarify, and elaborate requirements.

C.

challenge assessments of the cost and feasibility of requirements.

D.

perform an alternatives analysis for requirements implementation.

Full Access
Question # 14

What should a business analyst do after discovering that two solution requirements conflict?

A.

Consult the sponsor(s) and log the constraint.

B.

Perform an impact analysis and propose a lower-cost alternative.

C.

Update the requirements baseline and upload it to the project repository.

D.

Communicate the conflict to stakeholders and facilitate a resolution.

Full Access
Question # 15

The client produced a specification for a new product to be developed by Company A. Company A designed and successfully tested the new product against the test plan, yet the client does not agree that it meets the specification.

What could have caused this?

A.

The product was not adequately tested in accordance with the test plan.

B.

The requirements matrix did not adequately track back to client requirements.

C.

Requirement changes were not properly identified in the project charter.

D.

The product design was not properly reviewed by the quality department.

Full Access
Question # 16

A company is developing a new product for a customer and is required to verify and validate the product against the customer's acceptance test plan and requirements. The product was successfully verified against the acceptance test criteria, but the customer

does not believe that the product meets the requirements.

This occurred because the customer's acceptance test plan:

A.

was not included in the work breakdown structure.

B.

did not have measurable and testable requirements.

C.

was not formally accepted by the company.

D.

was incomplete and missing requirements.

Full Access
Question # 17

When determining the value of a business case, which tool or technique should be used?

A.

Variance analysis

B.

Cost-benefit analysis

C.

SWOT analysis

D.

Feasibility analysis

Full Access
Question # 18

A business analyst has been assigned to a project team that is redesigning the company's website. The business analyst has been documenting the relationships between requirements and has found requirements that do not trace to a business need.

Which type of requirements are these?

A.

In-scope

B.

Tested

C.

Implemented

D.

Out-of-scope

Full Access
Question # 19

The business analysts have concluded a requirements elicitation workshop. They now need to define rationale for each requirement.

Which of the following pairs of items would be important to include in the rationale?

A.

Reasons and assumptions

B.

Product vision and operational relationships

C.

Stakeholder impact and design decisions

D.

Functional relationships and work breakdown structure code

Full Access
Question # 20

When managing a product backlog, which statement best describes how to determine the value of backlog items?

A.

The stakeholders provide recommendations with the product owner having the final say.

B.

The stakeholders follow the value-ranking criteria.

C.

The stakeholders do not typically play a major role.

D.

The stakeholders provide input about backlog value when the item is first identified.

Full Access
Question # 21

During the initial phase of a project, which technique could assist in identifying and categorizing the stakeholders?

A.

Business activity model

B.

RAC! matrix

C.

Power/interest grid

D.

Organization modeling

Full Access
Question # 22

After completing the requirements, the project manager and business analyst realize that the project scope is not feasible in the projected schedule. The business analyst needs to review the amount of work the team is capable of delivering based on the approved project schedule.

Which prioritization technique should the business analyst use?

A.

Time-boxing

B.

SWOT analysis

C.

Weighted ranking

D.

Multivoting

Full Access
Question # 23

During validation of a project solution, the business analyst discovers that a requirement has been altered. Instead of placing the company logo in the upper-left corner of the window, it is displayed in the upper-right corner. When the business analyst asks the developer about the change, the developer says that one of the stakeholders asked directly for the change.

Which corrective action should the business analyst take?

A.

Ask the developer to correct the logo as stated in the requirement.

B.

Confront the stakeholder that requested the change.

C.

Follow the change control process as defined in the business analysis plan.

D.

Discuss the change in the next stakeholder meeting.

Full Access
Question # 24

What should be done to ensure that the product design meets the stated requirements?

A.

Conduct multiple internal design reviews.

B.

Use a traceability matrix.

C.

Review lessons learned results.

D.

Engage an experienced development team.

Full Access
Question # 25

Projects have been managed well and completed on schedule and on budget. However, successful completion of the projects has not improved the company’s performance and profitability.

Which of the following should have been implemented to ensure that the projects would improve the company’s performance and profitability?

A.

review with appropriate stakeholders

B.

A project management plan

C.

A risk plan

D.

A strategies and goals analysis

Full Access
Question # 26

What is a standardized, effective, and efficient way to manage changes to project documentation?

A.

A configuration verification and audit system

B.

A requirements traceability matrix

C.

A configuration management system

D.

A change control board

Full Access
Question # 27

A company’s management team has decided to deploy a new product. However, there is concern that users may not accept a new product that forces them to change existing practices.

The business analyst should:

A.

adhere to the project plan to achieve project objectives.

B.

voice user concerns to management and recommend that the project be closed.

C.

clearly communicate project objectives and attempt to defuse tensions.

D.

delay the application's deployment until the conflicts have been resolved.

Full Access
Question # 28

Which document best provides the boundaries for product development?

A.

Scope definition

B.

Requirements baseline

C.

Project plan

D.

Scope document

Full Access
Question # 29

After several meetings with different groups of users, a business analyst has gathered the requirements for a large IT project. Now, the business analyst needs to document those requirements in a way that is clearly understood by the development team and provides

enough information to check if the requirement has been met.

Which of the following would work best in this case?

A.

User stories

B.

Functional specifications

C.

Flow chart

D.

Prototyping

Full Access
Question # 30

A business analyst is discussing the acceptance criteria for a new measurement system with the operations manager. The operations manager is particularly concerned about the accuracy of the new system because mistakes in data measurements could be extremely costly to fix.

Which of the following is the best strategy to define the appropriate acceptance criteria?

A.

Quantify the risks associated with the measurement errors and update the risk register.

B.

Ask the operations manager to formally accept the requirements documents.

C.

Plan a training session for the new system before it is handed over to the operations manager.

D.

Clearly define the maximum acceptable error rate for the new system.

Full Access
Question # 31

When faced with a tight timeline, the project sponsor suggests that the project team start development without creating traceability artifacts. What should the business analyst do?

A.

Start development activities without traceability items.

B.

Explain the value of requirements traceability.

C.

Negotiate for a quick approval of a reduced set of traceability artifacts.

D.

Eliminate traceability activities for the project.

Full Access
Question # 32

After reviewing a business case, project goals, and objectives, a business analyst determines that the organization prefers taking an exploratory approach to finding the solution that best meets the business need. Which approach best aligns with the business need for this organization?

A.

Plan-driven approach

B.

Waterfall approach

C.

Analytical approach

D.

Change-driven approach

Full Access
Question # 33

The document that defines the process for managing requirements revisions is the:

A.

project management plan.

B.

change management plan.

C.

communications management plan.

D.

scope management plan.

Full Access
Question # 34

A business analyst is documenting the acceptance criteria to support a minor modification in a user portal. The analyst submits the criteria for review, but it is deemed incomplete and returned.

What could have caused the documentation to be returned?

A.

The analyst did not include the scope document in the acceptance criteria paperwork.

B.

The analyst failed to gather any baseline information.

C.

The analyst performed forward and backwards traceability.

D.

The analyst utilized user stories as a requirements document tool.

Full Access
Question # 35

A new business analyst has taken over on a project that is in the development phase. The project manager is looking for an update on requirements status.

What should the business analyst use to help communicate the status?

A.

Project charter

B.

Communication plan

C.

Business analysis plan

D.

Traceability matrix

Full Access
Question # 36

A business analyst has been assigned to a project that will design and build two new bridges and, at the same time, redesign a failing bridge for a local structural engineering company. All three bridges must be constructed and meet all safety requirements before flood season next spring.

How would the business analyst define the scope of this project?

A.

Perform a work breakdown structure.

B.

Perform a feasibility study.

C.

Perform process modelling.

D.

Perform a structured walkthrough.

Full Access
Question # 37

A project that was going well for the last few months has encountered a situation—regulatory authorities have deemed that the project does not meet their requirements. Although regulatory requirements were identified during an earlier phase of the project, there is no substantial evidence to prove that the requirements were formally rejected.

This could have been avoided if:

A.

the project team documented customer requests and obtained sign-off.

B.

a change control process for requirements and their statuses was followed.

C.

the project manager circulated the meeting minutes after the discussions with all the attendees.

D.

the customer met with regulatory authorities to verify that their requirements were also considered.

Full Access
Question # 38

To reduce the amount of time and effort needed to create a product specification for a project, the business analyst plans to reuse:

A.

quantitative analysis.

B.

risk assessments.

C.

qualitative analysis.

D.

requirements.

Full Access
Question # 39

A document is being created that will detail the customer's needs for a product and will include a functional model, a data model, and a glossary of terms. This document is called a:

A.

standard operating manual.

B.

business case.

C.

project charter.

D.

requirements specification.

Full Access
Question # 40

Which of the following is the best approach to enable developers and product owners to be in constant communication so that changes or issues that occur during development are exposed and discussed as they develop?

A.

Iterative

B.

Waterfall

C.

Linear

D.

Agile

Full Access
Question # 41

A business analyst created requirements for production of a product extract file for several systems. After reviewing the complex systems and dividing the processes into manageable tasks, the business analyst is able to identify the tasks required to implement the deliverable.

Which analysis technique has the business analyst used?

A.

Organization

B.

Decomposition

C.

Dependency

D.

Interface

Full Access
Question # 42

A business analyst captures an application's current limitations and consults with end users to identify new features for the next version.

What can be used to analyze this information and determine project scope?

A.

Capability table

B.

As-is process

C.

Requirements traceability matrix

D.

Root cause analysis

Full Access
Question # 43

A business analyst is ready to begin requirements elicitation; however, stakeholders are not available to participate for another two weeks. Which elicitation technique should the business analyst use during this time?

A.

Cost-benefit analysis

B.

Benchmarking

C.

Brainstorming

D.

Document analysis

Full Access
Question # 44

The following requirement was included in a business requirements document: “An API shall be built to send data back and forth from the accounting system to the customer relationship system so that name and address data can be synchronized.” What should be done with this business requirement?

A.

It should remain because it specifies the reason why the business requirement is needed.

B.

It should be removed because it does not state how often the data should be synchronized.

C.

It should be revised because it states a solution to the problem rather than the business need.

D.

It should remain because it specifies the type of data and the source system.

Full Access
Question # 45

The quality function deployment is best suited to assist in the process of:

A.

relating the product features to customer value.

B.

quality control by determining the control charts and the run charts.

C.

quality assurance by structuring the quality audits.

D.

controlling the effects between the quality functions.

Full Access
Question # 46

Company A has set aside capital to invest in an upgrade to their scheduling system. Documentation of the current structure was presented to the business analyst. However, the description of certain steps is not documented clearly, and the business analyst has not been allowed to inspect the existing system. During elicitation, the business analyst asked questions of the schedulers as they performed functions in order to gain an understanding of the process.

Which type of elicitation technique did the business analyst use in this instance?

A.

Active observation

B.

Participatory observation

C.

Interview

D.

Simulation

Full Access
Question # 47

A business analyst in organization Y is assigned to elicit requirements in a project within a defined timeline. The business analyst has identified and invited key stakeholders to a requirements workshop. However, the stakeholders are not giving clear and concise requirements; their opinions about requirements are changing and conflicting with each other in the meeting. In the end, the business analyst could not elicit and define the requirements and therefore adjourned the meeting.

Which tool or technique could have been used by business analyst to avoid this situation?

A.

Prototyping

B.

Surveys

C.

Document analysis

D.

Decision tree

Full Access
Question # 48

The business analyst generated a design specification for a new product. What is the best type of formal review to conduct with the customer to establish an approved requirements baseline?

A.

Test readiness review

B.

Production readiness review

C.

System requirements review

D.

Critical design review

Full Access
Question # 49

A business analyst is preparing a requirements management plan and needs to define a method to deal with a complex project with stakeholders who find it difficult to articulate their needs. Which method would best minimize requirements risk?

A.

Questionnaires

B.

Group decision making

C.

Stakeholder analysis

D.

Prototyping

Full Access
Question # 50

A new product was designed and delivered to the customer. The product exceeded customer expectations but did not meet the baseline budget for the product. What could be the issue?

A.

Risks identified in the risk management plan were not addressed properly.

B.

There is no issue since the product exceeded the customer expectations.

C.

The sponsor approved the release of the product without reviewing the budget.

D.

Requirements were not properly traced and monitored.

Full Access
Question # 51

The business analyst has completed the requirements gathering and documentation processes in developing a baseline document. Several signoffs are needed. During the joint review process with the key stakeholders, the stakeholders announce that they are still not ready to sign off due to a communication gap.

Which technique should the business analyst have followed to ensure consensus?

A.

The business analyst should have performed a complete review of each requirement with one of the stakeholders’ peers before the meeting.

B.

The business analyst should have performed a complete review of each requirement with the key stakeholders prior to the meeting.

C.

The business analyst should have reviewed the requirements of the project sponsor first before reviewing other requirements.

D.

The business analyst should have invited the key stakeholders to the meeting.

Full Access
Question # 52

A business analyst conducts an initial review to define scope. The analysis includes the review of the business case, project goals, and objectives to obtain the necessary and required context. Based on that information, the business analyst determines that this is a large project with multiple interfaces which could cost the company money that was not initially included in the budget.

What characteristics of the project are needed to determine the approach so that the business analyst can validate whether they will

need to have a discussion about the budget?

A.

Selected project life cycle

B.

Business analysis deliverables to be produced

C.

Type of elicitation activities to be conducted

D.

Decision on the type of models to be used

Full Access
Question # 53

Requirements for a project have already been approved and finalized when a stakeholder approaches the project team with a change to one of their requirements. Which method of document control should the business analyst use to document changes in requirement(s)

versioning?

A.

Statement of work

B.

Project plan

C.

Problem or opportunity statement

D.

Traceability matrix

Full Access
Question # 54

A company is developing a new risk management system. The company expects the system to evolve in the near future due to changing government regulations.

Which approach will better cope with the requirements’ volatility?

A.

Storyboarding

B.

Multivoting

C.

Phased baselining

D.

Comparative analysis

Full Access
Question # 55

A business analyst is working on a system enhancement project and has completed the requirements according to the requirements management plan. The business analyst is now ready to request approval from the stakeholders.

How should the business analyst obtain approval?

A.

Conduct a formal or informal review of the requirements.

B.

Create and maintain an audit history log of changes to requirements.

C.

Provide a defect tracking log for review.

D.

Send an email requesting approval of requirements.

Full Access
Question # 56

After a project was delivered, the business analyst learns of a project objective with no associated requirement. What would have helped determine this issue before delivery?

A.

Context diagram

B.

Use cases

C.

Process flow

D.

Tracing requirements

Full Access
Question # 57

During the project execution phase, the client requests the addition of a new feature. Which of the following would allow the business analyst to determine the impact for the specific requirement change?

A.

Requirements cards

B.

Requirements baseline

C.

Requirements management tool

D.

Requirements traceability matrix

Full Access
Question # 58

A project team has completed the system use cases along with accompanying screen mockups. The business analyst schedules a review meeting with the client team to walk through the artifacts.

What is the purpose of this meeting?

A.

To verify that the system is aligned with the quality requirements

B.

To verify that the documents are aligned with the transition requirements

C.

To validate that the system is aligned with the stakeholder requirements

D.

To validate that the documents are aligned with the solution requirements

Full Access
Question # 59

A business analyst from Company A has been assigned a project to document and identify requirements for a new commercial software implementation. The first step is to break down the business analysis deliverables into activities and tasks. Then, the business analyst

will add an estimate of the time needed to complete the work.

Which type of estimation technique is the business analyst using?

A.

Delphi

B.

Bottom-up

C.

Analogous

D.

Parametric

Full Access