Labour Day Sale - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: mxmas70

Home > CIPS > CIPS Level 4 Diploma in Procurement and Supply > L4M3

L4M3 Commercial Contracting Question and Answers

Question # 4

Under a framework agreement, which of the following are supplier selection mechanisms? Select TWO that apply:

A.

Rescission of contract

B.

Mini competition

C.

Contract for lease

D.

Direct call-off

E.

Call off contract

Full Access
Question # 5

XYZ Ltd is negotiating a long-term supply contract of important parts with a supplier. Dave, procurement manager teams up with Alla, legal manager to construct a service level agreement. Dave is concerned that poor performance of supplier may cause damages to the operations of the organisation. Which of the following can be used in conjunction with SLA to compensate the buying organisation in case of supplier's poor performance?

1. Warranties

2. Force majeure clauses

3. Penalty clauses

4. Service credits

A.

1 and 3 only

B.

3 and 4 only

C.

1 and 2 only

D.

4 and 2 only

Full Access
Question # 6

GPP, the employer, and Prosolia UK, the contractor, entered into five EPC contracts for the development of five different solar power generation plants in the United Kingdom. Four out of the five developments failed to be commissioned by the relevant due dates, with the delays ranging from 44 to 285 days.

Among other claims, GPP, acting through its two investment vehicles, claimed liquidated damages of £500 per day in all four contracts for Prosolia UK's failure to achieve completion of the plants by the due date. The liquidated damages claimed amounted to £1,804,221 across the four delayed contracts.

Prosolia, alongside various other defences, raised the defence that the liquidated damages provision in each contract was a penalty, and therefore unenforceable against it. Is Prosolia contractually obliged to make the payment to the plaintiff?

A.

No, the amount claimed is too excessive and it may put Prosolia into insolvency. The clause must be void

B.

No, the clause must be treated as a penalty clause which is unenforceable in UK

C.

Yes, the amount is a reward to the employer as they have supervised and monitored the projects

D.

Yes, the clause is a genuine estimate of possible losses that GPP may have suffered and therefore, it is enforceable.

Full Access
Question # 7

Cleveland Insurance (Cleveland) offers a range of insurance services. The main software used in the call centre is a customer relationship management (CRM) system. Cleveland perceived an urgent need to replace the existing CRM system to deal with the increasing number of customers and services.

Urgent Digital Ltd (Digital) is one of the bidders of Cleveland’s ITT. Its bid team is led by Hank Irvine, its technical director. Hank realises that winning the Cleveland contract (valued at approximately £50M) will enhance his career. During discussions with Cleveland, Hank offers certain assurances regarding timescales for the project. He has not carried out any investigations into the viability of the timescales. Hank has little idea whether the timescales can be met.

Cleveland decides that Digital’s bid meets with its requirements, especially given the assurances in timescale offered by Hank, and decides to proceed with it, subject to a formal contract. Eventually, a formal contract is signed by both parties. The initial assurances given by Hank about the timing of the project are never going to be achieved and are at best grossly exaggerated.

Hank’s pre-contractual assurance is most likely to be an example of which of the following?

A.

Inaccuracy in communication

B.

Threat

C.

Initial impossibility

D.

Fraudulent misrepresentation

Full Access
Question # 8

Infra Constructions receive a contract for construction of a building, and following terms were agreed upon. "The entire cost of the project will be reimbursed to Infra Constructions (estimated cost of the project being $ 25 million). The profits will be 20% of the entire cost of a project subject to a max of $ 5 million." This arrangement is an example of...?

A.

Incentive pricing arrangement

B.

Gain-share/pain-share arrangment

C.

Cost-plus pricing arrangement

D.

Fixed-pricing arrangement

Full Access
Question # 9

Which of the following should be taken to avoid the conflicts between orally negotiated terms before the conclusion of contract and the final written contract?

A.

Finding signs of misrepresentation of the other contracting party

B.

Prevailing orally negotiated terms over the final written contract

C.

Embedding a term excluding all prior oral discussions that are not mentioned in the final written contract

D.

Avoiding long negotiation

Full Access
Question # 10

Which of the following shall help the purchaser control the selection of tier 2 suppliers?

A.

Subcontracting clause

B.

Warranty clause

C.

Guarantee clause

D.

Insurance clause

Full Access
Question # 11

A large company supplies a lot of products. Their shipments are often delayed and customers are not satisfied. Which of the following KPIs is most likely to be applied to this situation?

A.

Technical support

B.

OTIF delivery

C.

Delay damages

D.

Consignment stock availability

Full Access
Question # 12

Which of the following is the set of principles that enables courts to determine exactly what the written contract says and what that must mean, then the court will uphold that?

A.

Order of precedence

B.

Rules of interpretation

C.

Unfair Contract Act 1977

D.

Rules of contract formation

Full Access
Question # 13

Which of the following should be taken to avoid the conflicts between orally negotiated terms before the conclusion of contract and the final written contract?

A.

Finding signs of misrepresentation of the other contracting party

B.

Prevailing orally negotiated terms over the final written contract

C.

Embedding a term excluding all prior oral discussions that are not mentioned in the final written contract

D.

Avoiding long negotiation

Full Access
Question # 14

Which of the following is set down in statute as a liability that exists without any need to prove fault?

A.

Strict liability

B.

Current liability

C.

Contingent liability

D.

Non-current liability

Full Access
Question # 15

XYZ Ltd and Engineer Corp signed a long-term supply contract in which both parties had agreed on performance targets. Recently, due to increased customer demands, XYZ Ltd realises that they should make changes to the contract with Engineer Corp with regards to performance management. These changes are approved and signed by both the buyer and seller. The changes to the contract are known as...?

A.

An amendment to the prime contract

B.

A stand-alone subcontract to the prime contract

C.

An appendix to the prime contract

D.

A separate counter-offer to the supplier

Full Access
Question # 16

Transformers & Rectifiers Ltd wanted to buy some specialist gaskets. They sent a request for quotation with specification to Needs Ltd. The supplier replied with a quotation in which had its own terms and conditions. The buyer edited delivery terms on the quotation and sent the document back to Needs Ltd. Gaskets were delivered to Transformers’ premise with an invoice from Needs Ltd. Which of the following is most likely to be the governing terms if the two companies must settle the dispute at court?

A.

Edited terms and conditions

B.

Terms and conditions in the request for quotation

C.

Terms and conditions in the invoice

D.

Terms & conditions in the original quotation

Full Access
Question # 17

Which of the following statement is true about insurance?

A.

An insurance policy can be mechanism of substance to back up indemnity

B.

The supplier must always pay the insurance premium for goods-in-transit

C.

An insurance policy transfers the legal liabilities from the insured to the insurer

D.

Professional indemnity insurance provides the insured business with financial protection against the liabilities caused by or arising out of the products supplied

Full Access
Question # 18

Which of the following are NOT covered by CISG? Select TWO that apply:

A.

Transfer of risks

B.

Contract validity

C.

Remedies for breach of contracts

D.

Liability of the seller for death or personal injury

E.

Liability to pay damages

Full Access
Question # 19

Which of the following are most likely to be liabilities of suppliers under a guarantee clause? Select A. TWO that apply

B. Repair

C. Decommissioning

D. Upgrading

E. Replacement

F. Installation

Full Access
Question # 20

In a contract, both buyer and supplier agreed the lead time is 3 days. The contract also requires that any variation must be made in writing. Then the buyer places an order by phone call and requests delivery the next day, but the supplier delivers on the third day since the order. Can buyer refuse to pay as supplier did not deliver per time?

A.

No, the supplier delivers within a reasonable time

B.

Yes, late delivery is a force majeure event

C.

Yes, the supplier has breached the contract

D.

No, supplier has shortened lead time to 1 day

Full Access
Question # 21

If service level agreement is used as a schedule that makes up the contract, it will be most likely to be a part of...?

A.

Pricing arrangement

B.

Performance management framework

C.

Exclusion of liabilities

D.

Specifications

Full Access
Question # 22

Which of the following is likely to reduce risks of different rules regarding when offers and acceptance become effective between legal systems?

A.

Withdrawal protocol

B.

Letter of intent

C.

Time lapse

D.

Deemed receipt protocol

Full Access
Question # 23

Which of the following are true statements about RFQ process? Select TWO that apply.

A.

Buying organisation should only send RFQ to pre-qualified suppliers

B.

RFQ process requires the suppliers to submit their technical proposals

C.

RFQ process creates heavier administrative burdens than tendering process

D.

Price is often the only variable in the RFQ and quotations

E.

RFQ process is not suitable for low value purchase

Full Access
Question # 24

If service level agreement is used as a schedule that makes up the contract, it will be most likely to be a part of...?

A.

Pricing arrangement

B.

Performance management framework

C.

Exclusion of liabilities

D.

Specifications

Full Access
Question # 25

In common law, which of the following documents is legally binding without the need for consideration?

A.

One-off contract

B.

Hire purchase agreement

C.

Deed

D.

Blanket order

Full Access
Question # 26

A construction company often subcontracts approximately 50% of the project works because of unpredictable customer's demand. Although larger corporate customers require quick response to RFQ, the time lapse between tender bid submission and contract commencement is usually long. Which of the following arrangement would benefit both the contractor and customer?

A.

Collateral contract

B.

Bilateral contract

C.

Indemnity agreement

D.

Framework agreement

Full Access
Question # 27

Southwark is negotiating a contract with Orchard to provide software and IT services. Orchard will manufacture and install the products which are contractually supplied by IBM. Southwark’s procurement manager is worried that during the contract there would be some problems that they would not able to claim for damages from Orchard. Which of the following should be included in the head contract so that Southward can sue IBM, should the need arise?

A.

Negligence

B.

Indemnity

C.

Collateral warranty deed

D.

Insurance

Full Access
Question # 28

Which of the following are likely to be implied terms in a contract? Select TWO that apply:

A.

Legal precedence

B.

Definition & interpretation

C.

Contract appendix

D.

Statute

E.

Contract clause

Full Access