A global program is being kicked off, and various distributed teams are involved in delivering the initiative.Besides planning and executingthe scope for the initiative, team interactions must be considered.
How should the project teams interact in their meetings?
A project manager was recently assigned to a new project that is about to start. The organization has already signed a fixed-cost contract with the customerdetailing the scope and final delivery date, but the project manager has identified several internal constraints and conditions that will certainly prevent theproject from being completed in the number of iterations initially planned.
What should the project manager do next?
A system migration project is in its closing stage. The project manager is being pressured to close the project. The project manager communicated to allstakeholders; however, the last department to migrate indicated that they have not received the notification.
What should the project manager do?
A vendor has manufactured a complex product. During a factory acceptance test, several deficiencies were identified. Product delivery is on the critical path,
and any delay would impact project completion.
What should the project manager do?
A scrum team's daily meetings are conducted by teleconference between three teams, each located in different countries. The meetings typically last 45 minutes with manymisunderstandings due to language barriers.
How should the project manager resolve this issue for the next iteration?
A project is scheduled to end in 2 weeks. The team is expected to continue working long hours and is showing signs of weariness and fatigue.
What should the project manager do to encourage the team?
A project manager has access to risk management tools but chooses to use a quantitative method to evaluate the project risks. During
project execution, the project sponsor asks for an updated risk matrix.
What should the project manager do next?
An agile team has completed five sprints. The final product is expected to be delivered in another three sprints. The project manager receives a callfrom the technical resource manager that one of the developers must take leave for the next 4 weeks, with no temporary replacement available.
This is going to significantly impact the deliverable.
What should the project manager do?
A project sponsor has requested atrend analysis of all risks that the project has monitored over the past 12 months. What should the agile project manager do?
A project manager at a large corporation has been assigned to oversee a customer experience project. Within the project,customer satisfaction is a bigissue and there are many unresolved customer queries on a daily basis. The project manager has been informed that the customer service team isoverwhelmed with these unresolved queries.
Which two actions should the project manager take to correct this problem? (Choose 2)
An organization is about to start a multiphased project. Due to strict regulations, some of the phases must be completely planned in advance. However, other phases allowfor more flexibility and experimentation on scope and schedule. The sponsor wants to pursue the project objectives as planned, butalso wants to accommodate newinformation and changes as the project progresses.
Which project management approach should the project manager select for this project?
A project manager for a large, multiyear, industrial project has a project with diversified stakeholders from various geographical areas.Recently, the project managerencountered an issue with stakeholder engagement.
Which two tools should the project manager use to determine the underlying reason for why engagement is not having the planned effect? (Choose two.)
A project manager invites the company CEO, sponsor, team members, and an external client representative to a meeting to review the project management plan. The
project manager starts to present the budget, but the CEO suddenly asks to end the meeting.
What should the project manager have done to avoid this situation?
A project manager is working on multiple building construction projects using a predictive project management approach. Senior leadership within the
organization is promoting the inclusion of more agile practices into the current project methodologies. The project sponsor now wants the projects to use
more agile methodologies.
Before mandating any agile methods to be used in a project, what should the project manager do first?
A project manager is building a team to work on a service integration project that will transition technology management services from company A tocompany B. The project team will consist of members from both companies. Prospective team members for the project are located all over the world, havedifferent types of technology backgrounds, and use different approaches for work.
How should the project manager build a cohesive, high-performing team?
A defect is identified during user acceptance testing that could significantly impact the system's performance. The project team has advised that this defectputs the delivery date at risk.
Which risk management process should be performed?
An agile project manager notices that one of the team members is developing extensive knowledge in a specific matter. Other team members are likely to require this
knowledge in the future.
What should the agile project manager do?
A project manager is working on an enterprise resource planning (ERP) implementation project that spans divisions within and outside the country. The project manager understands the importance of gatereviews and periodic checks.
Which of the following should the project manager leverage?
While managing a project, the project manager has just noticed that the last several monthly invoices have been challenged by the client when they were clearly defined.
The actual invoice payments received have also been late and were outside of the contracted payment schedule. Recent invoices have only been partially paid.
What should the project manager do?
A project manager is working on a project nearing completion using a hybrid approach. During the last daily standup, the team identified a risk of not delivering on time
because team members have not initiated any of the tasks assigned to them. The project has a hard deadline to complete the agreed-on deliverables.
What should the project manager do in this situation?
A project manager has been assigned to an education project with the objective of training a workforce in application development. One ofthe deliverables is to provideinternships to the best students in the customer's active projects. However, the customer does not have enough projects in progress right now. The project manager decidesto create several internal projects in order to ensure the internships.
Which three actions should the project manager take to fulfill this scenario without adding costs for the customer? (Choose 3)
A key team member informs the project manager that they have been accepted to a master's degree program. The team member explains that the first semester of the master'sprogram will coincide with thelast phase of the project.
What should the project manager do?
A project manager is managing a project with team members who are working all over the globe. The project manager notices that each team member'sdeliverables do not meet the requirements.
What should the project manager do first?
During a project's planning session, the project team discussed selecting the required information to be included in the monthly progress report This report will be produced in the Executing and Monitor and Controlling phases and will be used when communicating project progress to the client
Match the scenario on the left with the action on the right.
A project team is in the planning phase of a product migration project. The project manager schedules a meeting with the project team, telecommunications team, and the department leaders with group productaccounts. The purpose of the meeting is to determine the project timeline based on how much content needs to be transferred to or created in the new system and the processing procedures and time frames.
Who should the project manager also invite to the meeting?
An agile coach and technical writer for a globally distributed agile team are in a country with a 9-hour time zone difference from the agile team. The agile coach and project lead disagree
on the timing for the daily standup. The project lead thinks the standup should be at 10:00 am local time, but the agile coach and technical writer feel that is an inconvenient time for
them.
How does the project lead ensure adherence to agile practices?
A project manager is asked to implement a hybrid approach that will replace a predictive approach on an upcoming project.How should the project manageradjust their responsibilities accordingly?
A project team member is sick and will not be able to return to the project for a few weeks. During the daily meeting, the team shares their concerns as the sick team member was the only one skilled in the component they were developing.
What should the project manager have done to prevent this?
A member of a testing team in an agile project works well with the project team. However, in the previous two iterations, this team member's performance was poor, and the
team had difficulty meeting the iteration goals.
How should the project manager handle this situation?
A product is undergoing its last iterative increment, and the project team is ready to make the final deployment. The company's financial manager is asking the project teamto complete the deployment andclose the project as soon as possible so it can be capitalized.
What should the project manager do?
A project manager finds a mistake with an important server acquisition. The acquisition was expected for a critical path activity but has not arrived yet, causing significant impacts on time and cost. The team member responsible for this activity argues that they sent several emails to the supplier but received no reply.
Which document should be used to help avoid this kind of situation?
A project scope was developed with numerous assumptions. During the execution phase, the assumptions changed, which has jeopardized the planned business value of the project.
What should the project manager do next?
A project manager was recently assigned to a banking IT project. The project team has been developing products using a predictive approach for more than 10 years, butmanagement wants the team to change to an agile approach. The project manager met with the team to introduce the agile approach.Most of the team memberscomplained about changing approaches because the performance of this team has always been above average among the IT teams in the bank.
Which two actions should the project manager take? (Choose 2)
A company has undertaken a large transformation project in preparation for the changing economy. During the planning of the transformation project, the key resource from human resources (HR) refuses toapprove the proposed project plan.
What should the project manager do to gain an understanding of the cause for the resource’s refusal?
During the daily standup meeting that is assessing progress against the current sprint, ateam member reports some delayscomponent managed by an external vendor. How should the project manager address the team member's concern?
A new team member inquires about how much they need to learn about the organizational process assets (OPAs) residing on the company intranet. Another team member states they only need to know the basics. However, the project manager believes the team member should know everything regarding the OPAs.
What should the project manager do?
Product implementation portions of a project are nearing completion. The project manager schedules a series of meetings to meet with the marketing management team. During the meeting, the marketing
manager tells the project manager that some key members of the department will not be available to work on the implementation for the next 3 months.
What should the project manager do?
A project manager is part of a cross-functional agile team. Throughout the project, it has become obvious that team members from different functional units have different perspectives of what the outcomeshould be.
What should the project manager do to resolve this?
A project manager is leading an agile project in an organization that has not executed this type of project before. In order to ensure the project is following the compliance requirements, what should the project manager do?
A company has decided to implement a new archiving system. A data breach occurred during the implementation of the project.
What should the project manager do first?
A project manager has recently joined a small company. The company's chief operating officer (COQ) asked the team to skip some steps in the process inorder to work more quickly. The project manager wants to ensure that these steps are not skipped in the future.
What should the project manager do?
A project manager is struggling to figure out the performance of the project teams in an agile environment. For the same scope of work, team A has calculated 100 story
points and team B has calculated 125 story points.
Which team is performing better?
A project manager is leading a global team that they have worked with in the past and has a high level of trust with them. The team is located in different countries and time zones and will need decisions in a
timely manner.
In order to ensure that the project runs smoothly across the team, how should the project manager approach delegation?
A construction project to build a fish hatchery is in execution. The operations group notified the project manager about a concern that might turn into a potential issue, however, the
concern could not be addressed.
In which project document should the project manager record the concern?
A company is initiating a project to enhance one of its existing products. All of its products are developed internally.
What should the project manager do?
A project manager in an automotive company is scheduling activities for a complex project Some of the project requirements are fixed and some are flexible Match the items on the left with the methodology on the right that the project manager is using.
Afew key team members recently left the project team. The remaining members took time to understand the details and found it difficult to make progress. As a result, theproject schedule is seriouslydelayed.
What should the project manager do?
In an effort to modernize the technology for a project, the project manager has been discussing risk prioritization with the project team. The project manager determines that additional parameters are needed to iteratively assess and prioritize the project risks.
Match the project manager's goals on the left with the relevant risk parameter on the right.
The change control board (CCB) rejects a change request submitted by a subject matter expert (SME). The SME refuses to accept thisrejection and does not want tocontinue the project without the change.
What should the project manager have done to avoid this situation?
A client wants to create an innovative software for the travel industry using an agile approach. A project manager from the company was assigned
to work on the details and estimates as requested by the client.
What should the project manager do before sending the information to the client?
An organization is embarking on the deployment of a new digital solution that will revolutionize purchasing services. The project manager has created all the necessary plans and activities to ensure a successful integration and solution launch. There is a risk of a partner's system being unavailable which could impact the project negatively.
What key activity is needed to ensure the project's success?
A company is transitioning from a predictive to an agile approach. During the last two sprint reviews, the product owner complained about the development team, indicating that the
increments do not meet the acceptance criteria defined in the user stories. The development team complained about the product owner, who is defining sprint backlog items, because
the backlog items cannot be delivered during the 2-week sprints agreed to at the beginning of the project.
How should the project manager resolve this situation in their new role as servant leader?
A project manager has just been assigned to a team that is developing a new design product. The work breakdown structure (WBS) has been created and the activities have been assigned to the team members. The project manager finds that there are activities that could be completed sooner by other team members. If the current assignments are left as is, the project could be delayed 2 weeks.
What should the project manager do in this situation?
A project manager has been hired to lead a governance consulting project that is in the initial phase. The project manager has been assigned to evaluate the supplier search activity. There are many interested
candidates, including former suppliers and suppliers recommended by the sponsor.
What should the project manager do in this situation?
A project team was asked to resume development activities on a project that was suspended for a few months due to the fast-changing environment and conditions. What should the project lead do?
A project manager is asked to negotiate between two team members who frequently have misunderstandings in order to reach an agreement that will advance the project. What should the project manager to?
A project is in the final stages, and a key stakeholder demands a change to a product feature that will add 2 weeks to the critical path. What should the project manager do?
A new project manager is assigned to an ongoing agile innovation project that started 2 weeks ago. After reviewing the project, the new project manager discovered that the previous
project manager was planning to use a predictive approach. The previous project manager planned to present the first major deliverable to the client when the project was completely
finished in 8 months.
What should the new project manager do?
According to this burnup chart for the last 7-day sprint, what should the project lead address with the product owner and team?
A project manager is assigned to a project with a long time line and complex scope. The client requires a high-level, long-termplan as well as something thatwill work immediately, adding features to the product as the project progresses.
How should the project manager plan and deliver this project?
A project manager is using an agile approach. During the sprint planning meeting, the product owner flagged a backlog item as high business value and easy to implement.
However, the other team members identified a high dependency between this item and another item that is flagged as low business value and high complexity.
What should the project manager do to support the backlog prioritization?
How can agile measurements improve upon predictive measurements in cases where the final 10% of a project takes longer than planned?
During the execution of a project within an operations function, the project manager encounters scope changes and a delay in the delivery ofcritical tasks. How should the project manager address this situation?
A project manager for an IT company starts a project with members distributed across five different countries and four different time zones. In the first meetings with the sponsor and some stakeholders, theproject manager notices that people do not join the meetings on time, have internet connection issues, or experience language barriers during some conversations.
What should the project manager do to improve communication among the team?
A project team has finished its first iteration out of six. The iteration's delivery performance (velocity) was 50%. During the iteration retrospective, the team realizes that the
complexity of the work was underestimated.
What should the project manager do?
Aretail chain is evaluating a project to replace payment systems across all its stores in multiple locations. The project does not pass the financial threshold but is alsoexpected to increase marketshare, improve customer services, and retain more customers. The project is planned as a phased implementation, building on learningfromthe retrospectives during each phase.
How should the business increase the value of the project?
During project execution, a project manager discovers that the budget at completion has shifted significantly and is higher than expected.
What should the project manager do?
A project team is executing a project to replace an existing system with a new one. A new project manager has been hired and observes that the team consist of professionalswho have worked with the oldersystem, and others who have little previous experience.
What should the project manager do to ensure project success?
Due to organizational changes, several key stakeholders are replaced by new ones in the middle of a project. As a result, numerous new requirements are raised.
What should the project manager do to ensure success of the project?
A project for a new product launch is in a very initial stage and the requirements are evolving. Due to stiff competition in the market, the customer would liketo launch the product keeping the scope flexible. The project team intends to start the work based on the forecast of a similar project delivered last year.
Which project approach suits the scenario?
A project manager has been running an agile project for 6 months and has been reporting that the project is on track every week. However, on the last week before releasing the final product, the team found atechnical impediment that put the project delivery in jeopardy overnight.
What should the project manager have done to prevent this situation?
A project manager is assigned to a new project. The project management office (PMO) and the project manager agree that this is the right opportunity to include daily standup meetings. The project team has
never used such tools, and a few members are challenging the decision.
What should the project manager do in this situation?
The project team is experiencing schedule delays due to issues arising with suppliers. Some of the tasks are on the critical path.
What should the project manager do in this situation?
Several components of an expensive manufacturing project have been returned by the customer. The customer is complaining that the quality of thecomponents is poor and is concerned that, as a result, their products will be returned due to quality issues. The project manager is certain that quality has
been maintained.
How should the project manager communicate with the customer to help assure them that the project has produced quality products?
A key challenge that a project manager is facing is the lack of discipline by various team members and their inability to harness energy to achieve the project objectives. What should the project manager do toovercome this challenge?
A project requires the procurement of a large amount of equipment that needs to be on-site before any other activity can begin. The procurement department has a lengthy
approval process.
What should the project manager do?
In a complex development project with many clients and team members, there have been delays in completing the required work. What should the project manager do?
A project that has to be delivered by the targeted date has been delayed due to an unforeseen risk occurrence. How should the project manager compress the project to ensure the completion date is not
affected?
For some time now, doubts have been raised about who is responsible for delivering a key benefit of a project. What should the project manager do next?
A project has recently kicked off. The project manager observes that there are different expectations among the project team members. These growingmisunderstandings are affecting team productivity.
Which document should the project manager use as a guide to resolve the issue?
A project team consists of eight resources working on a complex project. The chief technical designer prefers to work alone and seldom talks in meetings, but produces good designs. The technical lead is always energetic, has lots of opinions about the project, and constantly clarifies their thoughts in discussions.
What should the project manager do to improve overall team performance?
A project manager works with a global virtual team. The team is facing difficulty in communicating with each other and often misses important messages.
This difficulty leads to missed deadlines.
What should the project manager do to enhance project team effectiveness?
A new project has been kicked off following a planning session. The project is under direct oversight of an executive in the organization. After a review meeting, the project manager overhears an executive request a dashboard from one of the team members to show the overall project status.
What should the project manager do?
A project manager has been assigned to an important project that will help set the future of the company. Meanwhile, the project management office (PMO) is implementing
adaptive tools in a mostly predictive environment and has requested that the project manager follow this process as well. However, the functional manager has expressed
concerns about the use of new tools on such an important project.
What should the project manager do?
The project team is planning a schedule with limited information. The team is having issues identifying the detailed tasks and estimating task duration.
Which three techniques should the project manager use? (Choose 3)
A project manager is acting as a servant leader and is struggling to make deadlines on a critical roadway construction project that is falling behind schedule due to a lowperforming team. In order to get the project back on track, what should the project manager do first?
An organization is using a hybrid delivery approach for a complex project. In the iteration review, a senior manager is asking for a complete redesign of the functionality presented.This may require a significantchange in the technical architecture and an additional release.
What should the project lead do first?
A project sponsor has requested that the project manager reprioritize the team's tasks to include a feature that is not part of the minimum viable product (MVP) for the project. Although the project sponsor isvery keen on the feature, adding it has the potential of causing team burnout and/or delaying the release.
How should the project manager address this situation?
An experienced project manager is leading an enthusiastic team but realizes the team lacks the experience to complete thejob successfully. What shouldthe project manager do to reduce the risk of project failure?
A software project using an agile approach is facing quality issues with every release, generating many production problems. What should theproject manager do to fix theproblem and improve the quality?
During project execution, the project manager observes lower velocity and a high volume of tasks in the testing queue. The project is using a hybrid approach and there are
only a few sprints remaining.
What should the project manager do?
One team member is complaining about an agreement made during the last meeting. That team member was present at the meeting and participated in thedecisions registered in the meeting minutes.
What should the project manager do next?
The project management office (PMO) assigns a project manager who specializes in hybrid approaches to apredictive project that is offtrack from both the cost and schedule perspectives. The project runs into further delays as the project manager is ramping up on theproject. The stakeholders are unhappy and ask senior management to replace the project manager.
How should the project manager approach this situation?
A local company is developing a new product and, for the first time, using a remote team for the programming tasks of features. The design for the product comes from the
local team. During the third sprint review, the product owner has concerns about the project's outcomes. The remote development team is complaining that they do not
clearly understand the requirements conveyed in the daily standup meetings.
How should the project manager address this situation?
A project interfaces with other projects that are in the same portfolio but are being developed in international locations. One ofthe international projects hassuggested a tactical change that needs to be implemented in this project.
What should the project manager do next?
A project is halfway through its execution phase. The quality specifications for the project deliverables are formally accepted. However, a key stakeholder is
dissatisfied, stating that the deliverables do not meet the quality specifications.
What should the project manager do in this situation?
A company is moving its headquarters to another city. The project manager responsible for the assignment has been using a predictive approach during the transition.
However, the information systems will be migrated using an agile approach. The project manager needs to decide which kind of contract to sign with the vendor responsible
for migrating the systems. The project manager is concerned about controlling finances while delivering results.
How should the project manager address this situation?
A project manager is working on a project for a startup company. The company launched cloud-based agile project management and DevOps training modules via the learning platform to support multiple self-paced and virtual learning formats. In a recent sprint, the quality assurance team failed to thoroughly inspect the modules before deployment, resulting in a poor customer experience.
Which of the following issues is the project manager facing?
During the planning stage of a project the project manager realizes that a standard stakeholder engagement approach will not suffice. One of the client representatives, who
is not a key decision maker, is extremely opinionated. This client representative could become a roadblock to progress due to their perceived level of authority during
meetings.
How should the project manager handle this moving forward?
A project manager realizes that the team members are new to the hybrid approach and do not value standup meetings. Team members often arrive late, digress into solutioning, or skip the meetings altogether.
How should the project manager improve this situation with the project team?
A project manager is managing a hybrid project. There is software in place to access the repository of project artifacts. However, a few stakeholders are
reporting that they are unable to find the latest project schedule.
What should the project manager do?
A project manager is leading a small project with a low budget and a short, tight schedule. Many of the stakeholders are within the
organization and have varying levels of interest.
Which approach should the project manager use with the stakeholders?
A project delivers every 2 weeks. The customer raises a complaint because they do not perceive business value in the products delivered even though deliveries have been completed in a timely manner.
Which activity should the project manager undertake?