Labour Day Sale - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: mxmas70

Home > PMI > Project-Management-Professional > PMP

PMP Project Management Professional (2023 Version) Question and Answers

Question # 4

A global program is being kicked off, and various distributed teams are involved in delivering the initiative.Besides planning and executingthe scope for the initiative, team interactions must be considered.

How should the project teams interact in their meetings?

A.

Videoconferencing

B.

Chat conversations

C.

Encrypted emails

D.

Phone conversations

Full Access
Question # 5

A project manager was recently assigned to a new project that is about to start. The organization has already signed a fixed-cost contract with the customerdetailing the scope and final delivery date, but the project manager has identified several internal constraints and conditions that will certainly prevent theproject from being completed in the number of iterations initially planned.

What should the project manager do next?

A.

Create a contingency plan in case the project deviates from the initial plan.

B.

Create an assumption log and map assumptions to impediments based on the impact to the project value.

C.

Create an issue log template that will be used to identify and track impediments.

D.

Create a schedule management plan to ensure the project meets the delivery date.

Full Access
Question # 6

A system migration project is in its closing stage. The project manager is being pressured to close the project. The project manager communicated to allstakeholders; however, the last department to migrate indicated that they have not received the notification.

What should the project manager do?

A.

Report the issue during the next status meeting at the end of the week.

B.

Escalate the issue to the project sponsor and upper management.

C.

Close out the project and tell the manager to open a service desk ticket.

D.

Log the issue and assign it to the project team member(s).

Full Access
Question # 7

A vendor has manufactured a complex product. During a factory acceptance test, several deficiencies were identified. Product delivery is on the critical path,

and any delay would impact project completion.

What should the project manager do?

A.

Assess the schedule impact and evaluate the most feasible solution to keep the project on track.

B.

Ship the package as is, complete carryover work on-site, and back charge the vendor for the rework.

C.

Initiate regular conference calls with the vendor for status updates to keep this item in focus.

D.

Hold the shipment until the rework is completed at the vendor's facility to eliminate extra work on-site.

Full Access
Question # 8

A scrum team's daily meetings are conducted by teleconference between three teams, each located in different countries. The meetings typically last 45 minutes with manymisunderstandings due to language barriers.

How should the project manager resolve this issue for the next iteration?

A.

Instruct the meeting participants to speak only about blockers during the meeting.

B.

Transfer half of the backlog items to the next iteration to allow more time to complete the meetings.

C.

Extend the meeting to 1 hour and request that all of the participants bring up all of the issues.

D.

Train the three team leads to conduct a local meeting, then run an overall status meeting.

Full Access
Question # 9

A project is scheduled to end in 2 weeks. The team is expected to continue working long hours and is showing signs of weariness and fatigue.

What should the project manager do to encourage the team?

A.

Add new team members to help the project finalization.

B.

Initiate rewards and incentives according to assessment results,

C.

Schedule working lunch meetings until the project is complete.

D.

Schedule training courses to enhance team performance.

Full Access
Question # 10

A project manager has access to risk management tools but chooses to use a quantitative method to evaluate the project risks. During

project execution, the project sponsor asks for an updated risk matrix.

What should the project manager do next?

A.

Use integrated risk management software to evaluate the risks.

B.

Use their own professional knowledge to reassess the risks.

C.

Add new risks and send the risk matrix to leadership for approval.

D.

Trust in the quantitative method already chosen as it is a precise method.

Full Access
Question # 11

An agile team has completed five sprints. The final product is expected to be delivered in another three sprints. The project manager receives a callfrom the technical resource manager that one of the developers must take leave for the next 4 weeks, with no temporary replacement available.

This is going to significantly impact the deliverable.

What should the project manager do?

A.

Perform an impact analysis, readjust the schedule as needed, and communicate the changes to the customer.

B.

Ask the product owner to stretch the delivery team further to complete the final product in the original timeline.

C.

Request additional funding from the sponsor to obtain a new resource to fill in the gap.

D.

Inform the customer of the impact immediately and prepare for escalation.

Full Access
Question # 12

A project sponsor has requested atrend analysis of all risks that the project has monitored over the past 12 months. What should the agile project manager do?

A.

Organize a stakeholder meeting to brainstorm on general project risks.

B.

Extract this from the project risk register tracking tool and issues log.

C.

Share the annual report with the sponsor.

D.

Refer the sponsor to the contract document.

Full Access
Question # 13

A project manager at a large corporation has been assigned to oversee a customer experience project. Within the project,customer satisfaction is a bigissue and there are many unresolved customer queries on a daily basis. The project manager has been informed that the customer service team isoverwhelmed with these unresolved queries.

Which two actions should the project manager take to correct this problem? (Choose 2)

A.

Ask senior management to replace the customer service manager with a more qualified one.

B.

Contact the customers in batches and inform them that the issues are being worked on currently.

C.

Deploy solutions that will track, prioritize, and resolve queries as soon as possible.

D.

Request that the customer service team prioritizes work on queries that are received this week.

E.

Confirm the issues truly exist by conducting a survey and other analyses that may detect the real issue.

Full Access
Question # 14

An organization is about to start a multiphased project. Due to strict regulations, some of the phases must be completely planned in advance. However, other phases allowfor more flexibility and experimentation on scope and schedule. The sponsor wants to pursue the project objectives as planned, butalso wants to accommodate newinformation and changes as the project progresses.

Which project management approach should the project manager select for this project?

A.

Hybrid

B.

Agile

C.

Phased

D.

Incremental

Full Access
Question # 15

A project manager for a large, multiyear, industrial project has a project with diversified stakeholders from various geographical areas.Recently, the project managerencountered an issue with stakeholder engagement.

Which two tools should the project manager use to determine the underlying reason for why engagement is not having the planned effect? (Choose two.)

A.

Communications management plan

B.

Ishikawa diagrams

C.

Open-space meetings

D.

Issue log

E.

Five whys

Full Access
Question # 16

A project manager invites the company CEO, sponsor, team members, and an external client representative to a meeting to review the project management plan. The

project manager starts to present the budget, but the CEO suddenly asks to end the meeting.

What should the project manager have done to avoid this situation?

A.

Performed a root cause analysis with the external client representative and documented the findings in the lessons learned register.

B.

Sent the presentation slides to internal participants first and then to the external client representative prior to the meeting.

C.

Reviewed the communications management plan before inviting an external client representative to the meeting.

D.

Reviewed the cost management plan with internal participants and CEO prior to inviting an external client representative to the meeting.

Full Access
Question # 17

A project manager is working on multiple building construction projects using a predictive project management approach. Senior leadership within the

organization is promoting the inclusion of more agile practices into the current project methodologies. The project sponsor now wants the projects to use

more agile methodologies.

Before mandating any agile methods to be used in a project, what should the project manager do first?

A.

Pause the current projects to align them to the new agile cadence.

B.

Shift all existing projects to agile methodologies with a strict timeline.

C.

Provide agile training to those who will be part of the project team.

D.

Assess the organizational culture and readiness for the transformation.

Full Access
Question # 18

A project manager is building a team to work on a service integration project that will transition technology management services from company A tocompany B. The project team will consist of members from both companies. Prospective team members for the project are located all over the world, havedifferent types of technology backgrounds, and use different approaches for work.

How should the project manager build a cohesive, high-performing team?

A.

Organize the team members into several kick-off sessions based on technology type.

B.

Review the list of team members’ skills and understand how they will work together to deliver the project outcomes.

C.

Ask the human resources (HR) department to arrange interview meetings to select the team.

D.

Ask prospective team members to write a short biography explaining how they can contribute to the team's success.

Full Access
Question # 19

A defect is identified during user acceptance testing that could significantly impact the system's performance. The project team has advised that this defectputs the delivery date at risk.

Which risk management process should be performed?

A.

Perform Qualitative Risk Analysis, to assess the extent of the system performance impact

B.

Monitor Risks, to install system performance monitoring tools and update the risk register

C.

Perform Quantitative Risk Analysis, to outline the details of the system performance issues

D.

Plan Risk Responses, to outline the possible options to bypass the system performance issue

Full Access
Question # 20

An agile project manager notices that one of the team members is developing extensive knowledge in a specific matter. Other team members are likely to require this

knowledge in the future.

What should the agile project manager do?

A.

Ask the team member to produce a lessons learned document and share it with the team.

B.

Ask the team member to develop more expertise and become a subject matter expert (SME).

C.

Ask the team member to record highlights the team may want to know.

D.

Ask the team member to provide a training session for the rest of the team.

Full Access
Question # 21

A project manager is working on an enterprise resource planning (ERP) implementation project that spans divisions within and outside the country. The project manager understands the importance of gatereviews and periodic checks.

Which of the following should the project manager leverage?

A.

Project management office (PMO)

B.

Integration plan

C.

Project management plan

D.

Governance framework

Full Access
Question # 22

While managing a project, the project manager has just noticed that the last several monthly invoices have been challenged by the client when they were clearly defined.

The actual invoice payments received have also been late and were outside of the contracted payment schedule. Recent invoices have only been partially paid.

What should the project manager do?

A.

Review past projects for payment-related lessons learned.

B.

Conduct a meeting with the project team to update the procurement management plan.

C.

Add nonpayment to the issue log and keep tracking payments.

D.

Hold a meeting with the client to address the issue.

Full Access
Question # 23

A project manager is working on a project nearing completion using a hybrid approach. During the last daily standup, the team identified a risk of not delivering on time

because team members have not initiated any of the tasks assigned to them. The project has a hard deadline to complete the agreed-on deliverables.

What should the project manager do in this situation?

A.

Hire additional resources to increase capacity using the contingency budget.

B.

Empower the team to self-organize and make decisions to overcome the delay.

C.

Reassign the remaining tasks to the most experienced team members.

D.

Inform the sponsor about the degraded performance of the team members.

Full Access
Question # 24

A project manager has been assigned to an education project with the objective of training a workforce in application development. One ofthe deliverables is to provideinternships to the best students in the customer's active projects. However, the customer does not have enough projects in progress right now. The project manager decidesto create several internal projects in order to ensure the internships.

Which three actions should the project manager take to fulfill this scenario without adding costs for the customer? (Choose 3)

A.

Influence the client to initiate a new project.

B.

Create a change request with the scope of the new internal projects.

C.

Use the project's contingency budget.

D.

Manage the quality of the delivery.

E.

Create a work breakdown structure (WBS) of the new scope with the internal projects.

Full Access
Question # 25

A key team member informs the project manager that they have been accepted to a master's degree program. The team member explains that the first semester of the master'sprogram will coincide with thelast phase of the project.

What should the project manager do?

A.

Ask the team member to inform human resources (HR) about their enrollment in the master's program.

B.

Ask the team member to delegate some of their tasks to another colleague during the last phase of the project.

C.

Suggest the team member postpone their enrollment in the master's program until the project is completed.

D.

Assess the team member's commitment to the master's program and its impact on project performance.

Full Access
Question # 26

A project manager is managing a project with team members who are working all over the globe. The project manager notices that each team member'sdeliverables do not meet the requirements.

What should the project manager do first?

A.

Discuss the process used to create the noncompliant deliverables with the project team to see if there was a potential misunderstanding.

B.

Meet with the project team to explain that noncompliant deliverables must be reworked and submitted immediately to avoid project delays.

C.

Schedule time with the project sponsor to inform them that the project schedule is slipping due to the time it will take to rework the deliverables.

D.

Assemble the project team via conference call to tell them that disciplinary action will be taken if any more noncompliant deliverables are submitted.

Full Access
Question # 27

During a project's planning session, the project team discussed selecting the required information to be included in the monthly progress report This report will be produced in the Executing and Monitor and Controlling phases and will be used when communicating project progress to the client

Match the scenario on the left with the action on the right.

Full Access
Question # 28

A project team is in the planning phase of a product migration project. The project manager schedules a meeting with the project team, telecommunications team, and the department leaders with group productaccounts. The purpose of the meeting is to determine the project timeline based on how much content needs to be transferred to or created in the new system and the processing procedures and time frames.

Who should the project manager also invite to the meeting?

A.

Representative from the service desk team

B.

Representative from the provisioning team

C.

Representative from the network team

D.

Representative from the reimbursement team

Full Access
Question # 29

An agile coach and technical writer for a globally distributed agile team are in a country with a 9-hour time zone difference from the agile team. The agile coach and project lead disagree

on the timing for the daily standup. The project lead thinks the standup should be at 10:00 am local time, but the agile coach and technical writer feel that is an inconvenient time for

them.

How does the project lead ensure adherence to agile practices?

A.

Escalate to management that the agile process is not going to work and ask them to speak to the agile coach.

B.

Inform the agile coach that the daily standup will be at 10:00 am local time and ensure all parties can attend.

C.

Have two separate daily standups, one for the agile coach and technical writer and one for the agile development team.

D.

Have a discussion with the team on the approach and come to a decision on when the daily standups should be.

Full Access
Question # 30

A project manager is asked to implement a hybrid approach that will replace a predictive approach on an upcoming project.How should the project manageradjust their responsibilities accordingly?

A.

Introduce new communication tools to the project team members.

B.

Request a scrum master to focus on the collaboration while the project manager focuses on the coordination.

C.

Become a servant leader by supporting team collaboration and removing impediments.

D.

Delegate coordination activities to the product owner so the project manager can focus on managing collaboration.

Full Access
Question # 31

A project team member is sick and will not be able to return to the project for a few weeks. During the daily meeting, the team shares their concerns as the sick team member was the only one skilled in the component they were developing.

What should the project manager have done to prevent this?

A.

Requested robust documentation for the component's build.

B.

Outsourced development of the specific component to another team.

C.

Facilitated cross-functional knowledge transfer during the project.

D.

Acquired more than one resource skilled in each component.

Full Access
Question # 32

A member of a testing team in an agile project works well with the project team. However, in the previous two iterations, this team member's performance was poor, and the

team had difficulty meeting the iteration goals.

How should the project manager handle this situation?

A.

Discuss the issue with the team member's functional manager.

B.

Inform the human resource (HR) department about the issue.

C.

Speak to the team member regarding the need to improve performance.

D.

Allow the project team to discuss the problem with this team member.

Full Access
Question # 33

A product is undergoing its last iterative increment, and the project team is ready to make the final deployment. The company's financial manager is asking the project teamto complete the deployment andclose the project as soon as possible so it can be capitalized.

What should the project manager do?

A.

Ignore the stakeholder's request as there is a defined plan.

B.

Update the acceptance criteria for the iteration.

C.

Check on the definition of done (DoD) for the project.

D.

Expedite the final deployment and close the project.

Full Access
Question # 34

A project manager finds a mistake with an important server acquisition. The acquisition was expected for a critical path activity but has not arrived yet, causing significant impacts on time and cost. The team member responsible for this activity argues that they sent several emails to the supplier but received no reply.

Which document should be used to help avoid this kind of situation?

A.

Statement of work (SOW)

B.

Escalation process

C.

Communications management plan

D.

Stakeholder register

Full Access
Question # 35

A project scope was developed with numerous assumptions. During the execution phase, the assumptions changed, which has jeopardized the planned business value of the project.

What should the project manager do next?

A.

Deliver what was planned in the project management document according to the specifications.

B.

Update the assumptions log and change log, and implement the change control process.

C.

Inform the client that the project cannot meet the project timeline and additional costs will be incurred.

D.

Report on the changed assumptions to the project sponsor and seek support to prioritize the change requests.

Full Access
Question # 36

A project manager was recently assigned to a banking IT project. The project team has been developing products using a predictive approach for more than 10 years, butmanagement wants the team to change to an agile approach. The project manager met with the team to introduce the agile approach.Most of the team memberscomplained about changing approaches because the performance of this team has always been above average among the IT teams in the bank.

Which two actions should the project manager take? (Choose 2)

A.

Interview the most resistant team members to persuade them to try to accept an agile approach.

B.

Meet with management to explain the team's resistance to the agile approach and request that they formally ask the team to implement agile.

C.

Ask the team to identify the product backlog and create a kanban board for the team to manage and follow the approach.

D.

Brainstorm with the team to understand the specifics of the team's project and to identity possible alternative approaches for the team.

E.

Conduct training sessions with the team so that the team can understand what the agile approach and mindset are.

Full Access
Question # 37

A company has undertaken a large transformation project in preparation for the changing economy. During the planning of the transformation project, the key resource from human resources (HR) refuses toapprove the proposed project plan.

What should the project manager do to gain an understanding of the cause for the resource’s refusal?

A.

Communicate with their supervisor.

B.

Speak directly with the resource.

C.

Organize a team meeting.

D.

Speak with their colleague.

Full Access
Question # 38

During the daily standup meeting that is assessing progress against the current sprint, ateam member reports some delayscomponent managed by an external vendor. How should the project manager address the team member's concern?

A.

Implement fast tracking to reduce the impact of the delay on the sprint.

B.

Ask the team member to provide details to address the issue with the vendor.

C.

Update the communications management plan to prevent future reoccurrence.

D.

Ask the team member to resolve the issue independently to minimize further delays.

Full Access
Question # 39

A new team member inquires about how much they need to learn about the organizational process assets (OPAs) residing on the company intranet. Another team member states they only need to know the basics. However, the project manager believes the team member should know everything regarding the OPAs.

What should the project manager do?

A.

Clarify the relevance of reviewing the documentation on the intranet.

B.

Create a training schedule for the new team member to follow over the next few weeks.

C.

Ask a senior team member to help the new team member navigate through all the documentation.

D.

Escalate the inquiry to the team member's functional manager.

Full Access
Question # 40

Product implementation portions of a project are nearing completion. The project manager schedules a series of meetings to meet with the marketing management team. During the meeting, the marketing

manager tells the project manager that some key members of the department will not be available to work on the implementation for the next 3 months.

What should the project manager do?

A.

Cancel the meeting series until the marketing team provides a solution.

B.

Consult the project team and discuss the key team members’ availability.

C.

Shift those key members and assign them to another project.

D.

Consult the resource management plan and escalate to the sponsor.

Full Access
Question # 41

A project manager is part of a cross-functional agile team. Throughout the project, it has become obvious that team members from different functional units have different perspectives of what the outcomeshould be.

What should the project manager do to resolve this?

A.

Schedule a meeting with the stakeholders to determine a consensus regarding the outcome.

B.

Invite the project sponsor to the sprint review to provide clarity on the sprint outcome.

C.

Ask the product owner to address the concerns about the project outcome during the sprint retrospective.

Check to ensure the project outcome aligns with the project charter and statement of work (SOW).

Full Access
Question # 42

A project manager is leading an agile project in an organization that has not executed this type of project before. In order to ensure the project is following the compliance requirements, what should the project manager do?

A.

Use the risk register to document all of the compliance vulnerabilities generated by the project so that all decisions are well documented and approved by stakeholders.

B.

Meet with the project management office (PMO)/compliance entity to work on process tailoring to ensure that the agile deliverables support the compliance requirements of the organization.

C.

Follow the organization's process and deliverables for predictive projects, even if they compromise the agility and performance of the project.

D.

Coach upper management on agile practices, explaining that an agile project is concerned with value delivery, and negotiate a way out of the compliance requirements.

Full Access
Question # 43

A company has decided to implement a new archiving system. A data breach occurred during the implementation of the project.

What should the project manager do first?

A.

Ask the team to fix the system to resolve the issue.

B.

Update the risk register with the risk and proposed impact.

C.

Implement the planned risk response to handle the issue.

D.

Review possible alternative documentation methods with team.

Full Access
Question # 44

A project manager has recently joined a small company. The company's chief operating officer (COQ) asked the team to skip some steps in the process inorder to work more quickly. The project manager wants to ensure that these steps are not skipped in the future.

What should the project manager do?

A.

Escalate the issue to the other executive leadership members.

B.

Notify all team members that all steps in the process must be completed.

C.

Schedule a review of the process steps with the team and the COO.

D.

Redesign the process so the team can move more quickly.

Full Access
Question # 45

A project manager is struggling to figure out the performance of the project teams in an agile environment. For the same scope of work, team A has calculated 100 story

points and team B has calculated 125 story points.

Which team is performing better?

A.

Team B as they have calculated more story points than team A.

B.

The team that completes the most stories selected from the sprint backlog.

C.

The team with the least amount of defects in their deliverables.

D.

Team A as they have calculated fewer story points than team B.

Full Access
Question # 46

A project manager is leading a global team that they have worked with in the past and has a high level of trust with them. The team is located in different countries and time zones and will need decisions in a

timely manner.

In order to ensure that the project runs smoothly across the team, how should the project manager approach delegation?

A.

Delegate certain authorities and share information to allow fair decision-making.

B.

Delegate most authorities and control the authority by withholding important information.

C.

Delegate most authorities and share information to allow fair decision-making.

D.

Delegate certain authorities and control the authority by withholding important information.

Full Access
Question # 47

A construction project to build a fish hatchery is in execution. The operations group notified the project manager about a concern that might turn into a potential issue, however, the

concern could not be addressed.

In which project document should the project manager record the concern?

A.

Request for information

B.

Risk register

C.

Issue log

D.

Scope statement

Full Access
Question # 48

A company is initiating a project to enhance one of its existing products. All of its products are developed internally.

What should the project manager do?

A.

Ensure the stakeholder engagement plan is accurate and properly documented.

B.

Create a lessons learned document for the initiation phase.

C.

Identify the risk of implementing the new solution and evaluate the impact on the project.

D.

Review the lessons learned from the previous project

Full Access
Question # 49

A project manager in an automotive company is scheduling activities for a complex project Some of the project requirements are fixed and some are flexible Match the items on the left with the methodology on the right that the project manager is using.

Full Access
Question # 50

Afew key team members recently left the project team. The remaining members took time to understand the details and found it difficult to make progress. As a result, theproject schedule is seriouslydelayed.

What should the project manager do?

A.

Request additional resources to be incorporated to the project team.

B.

Observe the project team and give them time to catch up before escalating.

C.

Review the issues and adjust the project plan to give a realistic schedule.

D.

Escalate to the project sponsor and seek alternatives to resolve the issue.

Full Access
Question # 51

In an effort to modernize the technology for a project, the project manager has been discussing risk prioritization with the project team. The project manager determines that additional parameters are needed to iteratively assess and prioritize the project risks.

Match the project manager's goals on the left with the relevant risk parameter on the right.

Full Access
Question # 52

The change control board (CCB) rejects a change request submitted by a subject matter expert (SME). The SME refuses to accept thisrejection and does not want tocontinue the project without the change.

What should the project manager have done to avoid this situation?

A.

Ensured that the change request was aligned with the project scope.

B.

Requested that the sponsor approved the change request first.

C.

Submitted the change request directly to the CCB.

D.

Assessed the change's overall impact to the project before submission.

Full Access
Question # 53

A client wants to create an innovative software for the travel industry using an agile approach. A project manager from the company was assigned

to work on the details and estimates as requested by the client.

What should the project manager do before sending the information to the client?

A.

Analyze the tasks, provide estimates, include a prototype demo, and send to the client directly.

B.

Sequence the tasks with estimates and add standard risk reserves to use for software development.

C.

Put the tasks with estimates in the backlog and clarify that the project will not need any reserves.

D.

Work with the team to understand their views and add the appropriate dependencies and risks.

Full Access
Question # 54

An organization is embarking on the deployment of a new digital solution that will revolutionize purchasing services. The project manager has created all the necessary plans and activities to ensure a successful integration and solution launch. There is a risk of a partner's system being unavailable which could impact the project negatively.

What key activity is needed to ensure the project's success?

A.

Continuously monitor the risk of the partner system's unavailability, and put the proper resolution plans in place in case the risk materializes into an actual issue.

B.

Communicate to the project stakeholders that full integration may not be possible and that the project will potentially be delayed as a result.

C.

Eliminate the risk by mandating the partner to change the system settings to facilitate an easier integration with the new solution.

D.

Mitigate the risk by developing alternative plans to make the solution ready and available without full integration capabilities.

Full Access
Question # 55

A company is transitioning from a predictive to an agile approach. During the last two sprint reviews, the product owner complained about the development team, indicating that the

increments do not meet the acceptance criteria defined in the user stories. The development team complained about the product owner, who is defining sprint backlog items, because

the backlog items cannot be delivered during the 2-week sprints agreed to at the beginning of the project.

How should the project manager resolve this situation in their new role as servant leader?

A.

Extend the sprints to 3 weeks to allow the work requested by the product owner to be completed.

B.

Request that the team use the next sprint to complete all technical debt remaining from the previous sprints.

C.

Encourage the whole team to be empowered and accountable for the decisions made according to their roles.

D.

Review the organizational process assets (OPAs) to find similar situations and review the resolution actions taken.

Full Access
Question # 56

A project manager has just been assigned to a team that is developing a new design product. The work breakdown structure (WBS) has been created and the activities have been assigned to the team members. The project manager finds that there are activities that could be completed sooner by other team members. If the current assignments are left as is, the project could be delayed 2 weeks.

What should the project manager do in this situation?

A.

Maintain the task assignments as planned and compress the other tasks to keep the project on schedule.

B.

Ask the team members to work overtime to finish the tasks on time according to the schedule.

C.

Keep the task assignments unchanged since the project management plan has been approved.

D.

Review the work allocation and reassign some tasks to shorten the critical path.

Full Access
Question # 57

A project manager has been hired to lead a governance consulting project that is in the initial phase. The project manager has been assigned to evaluate the supplier search activity. There are many interested

candidates, including former suppliers and suppliers recommended by the sponsor.

What should the project manager do in this situation?

A.

Evaluate the suppliers based on their experience and skills in similar projects.

B.

Prioritize evaluation of the suppliers recommended by the sponsor.

C.

Evaluate suppliers who have worked successfully with the company before.

D.

Request the contracting area take charge of the supplier evaluation process.

Full Access
Question # 58

A project team was asked to resume development activities on a project that was suspended for a few months due to the fast-changing environment and conditions. What should the project lead do?

A.

Review the items remaining in the backlog with the project team.

B.

Ask the program manager to approve the backlog with the client.

C.

Review the items remaining in the backlog with the project sponsor.

D.

Ask the project team to approve all of the remaining backlog items.

Full Access
Question # 59

A project manager is asked to negotiate between two team members who frequently have misunderstandings in order to reach an agreement that will advance the project. What should the project manager to?

A.

Encourage a positive ongoing relationship between both of the team members.

B.

Coach and mentor the team members to build consensus and to resolve the ongoing conflict.

C.

Organize a team-building event to improve the morale among team members.

D.

Establish common ground through collaboration and understanding the team members’ needs.

Full Access
Question # 60

A project is in the final stages, and a key stakeholder demands a change to a product feature that will add 2 weeks to the critical path. What should the project manager do?

A.

Reject the changes as the project is in the final stages.

B.

Perform a detailed assessment to analyze the impact.

C.

Use schedule compression methods to alter the critical path.

D.

Initiate a risk response strategy from the risk register.

Full Access
Question # 61

A new project manager is assigned to an ongoing agile innovation project that started 2 weeks ago. After reviewing the project, the new project manager discovered that the previous

project manager was planning to use a predictive approach. The previous project manager planned to present the first major deliverable to the client when the project was completely

finished in 8 months.

What should the new project manager do?

A.

Meet with the team to review the backlog and create small iterations that can deliver incremental value to the client.

B.

Continue working with the predictive approach to deliver the value at the end of the project.

C.

Use a hybrid approach in which agile practices are used but the value is provided to the client at the end of the project.

D.

Submit a change request to the project board to adjust the delivery date to 2 months earlier than planned.

Full Access
Question # 62

According to this burnup chart for the last 7-day sprint, what should the project lead address with the product owner and team?

A.

The team is not meeting the expectations of the product owner.

B.

The product owner should not ask the team to change their sprint commitments.

C.

The teant…the sprint after it has started.

D.

The team should have stopped on day 4 and started a new sprint.

Full Access
Question # 63

A project manager is assigned to a project with a long time line and complex scope. The client requires a high-level, long-termplan as well as something thatwill work immediately, adding features to the product as the project progresses.

How should the project manager plan and deliver this project?

A.

Plan the project with a predictive approach and a work breakdown structure (WBS) following the plan and deliver value at the end of the project.

B.

Select an agile approach and manage the project according to best practices to ensure value is delivered to the client.

C.

Agree on a minimum viable product (MVP) first to be delivered immediately with the client and then release the restof the scope at the end of theproject.

D.

Plan the project with a predictive approach with a work breakdown structure (WBS) and then execute it using an agile approach to deliver valueincrementally.

Full Access
Question # 64

A project manager is using an agile approach. During the sprint planning meeting, the product owner flagged a backlog item as high business value and easy to implement.

However, the other team members identified a high dependency between this item and another item that is flagged as low business value and high complexity.

What should the project manager do to support the backlog prioritization?

A.

Facilitate the discussion until the team reaches an agreement about the two items.

B.

Prioritize the item flagged as a dependency with low business value and high complexity.

C.

Prioritize the item flagged as high business value and low complexity for this sprint.

D.

Support the team to move both items to the next sprint when the team will know more

Full Access
Question # 65

How can agile measurements improve upon predictive measurements in cases where the final 10% of a project takes longer than planned?

A.

By scheduling iterative meetings with the product owner to improve project tracking

B.

By reviewing burnup charts to determine the effort required against estimated earned value

C.

By conducting daily standups to more accurately track project deliverables

D.

By focusing on the delivery of incremental working products to the customer

Full Access
Question # 66

During the execution of a project within an operations function, the project manager encounters scope changes and a delay in the delivery ofcritical tasks. How should the project manager address this situation?

A.

Call for a team meeting to decide if the changes should be included.

B.

Communicate the concerns to the project management office (PMO) during the weekly project reports.

C.

Initiate the change request to modify the scope and adjust the timelines.

D.

Conduct an impact analysis and present the results to the steering committee for approval.

Full Access
Question # 67

A project manager for an IT company starts a project with members distributed across five different countries and four different time zones. In the first meetings with the sponsor and some stakeholders, theproject manager notices that people do not join the meetings on time, have internet connection issues, or experience language barriers during some conversations.

What should the project manager do to improve communication among the team?

A.

Setup a team communications management plan for the company and team members to follow immediately.

B.

Explain the benefits of common working hours to aid better communication among the project team.

C.

Share a contact log document for all the team members to make communication easier.

D.

Arrange for some initial face-to-face team meetings for the project team to meet each other.

Full Access
Question # 68

A project team has finished its first iteration out of six. The iteration's delivery performance (velocity) was 50%. During the iteration retrospective, the team realizes that the

complexity of the work was underestimated.

What should the project manager do?

A.

Update the issue log and escalate it to the project sponsor.

B.

Ask to replace some team members with more experienced ones.

C.

Meet with the team to review internal actions to resolve the situation.

D.

Ask the technical manager to help the team with the issue.

Full Access
Question # 69

Aretail chain is evaluating a project to replace payment systems across all its stores in multiple locations. The project does not pass the financial threshold but is alsoexpected to increase marketshare, improve customer services, and retain more customers. The project is planned as a phased implementation, building on learningfromthe retrospectives during each phase.

How should the business increase the value of the project?

A.

Ask the benefits owner to reassess the identified risks that are impacting the outcomes of the financial benefits.

B.

Consult with experts on methods to reduce costs and increase the financial value of the project. ®

C.

Quantify the expected tangible and intangible benefits in the benefits management plan for each phase.

D.

Use a fishbone diagram to find the root cause of the lower financial benefits with the benefits owner.

Full Access
Question # 70

During project execution, a project manager discovers that the budget at completion has shifted significantly and is higher than expected.

What should the project manager do?

A.

Adjust the original budget estimates with the current cost variance.

B.

Perform a root cause analysis of the project performance.

C.

Review the activity duration to reforecast the project completion date.

D.

Negotiate the project changes and adjust stakeholder expectations.

Full Access
Question # 71

A project team is executing a project to replace an existing system with a new one. A new project manager has been hired and observes that the team consist of professionalswho have worked with the oldersystem, and others who have little previous experience.

What should the project manager do to ensure project success?

A.

Evaluate the current effectiveness of the team and define development needs.

B.

Assign team member roles and responsibilities based on past experience.

C.

Request a performance assessment for the team from the functional manager.

D.

Allow each team member to use their individual strengths for project success.

Full Access
Question # 72

Due to organizational changes, several key stakeholders are replaced by new ones in the middle of a project. As a result, numerous new requirements are raised.

What should the project manager do to ensure success of the project?

A.

Escalate the issue to the project sponsor and seek support to keep the original requirements.

B.

Review and prioritize new requirements with stakeholders to determine which change requests are needed.

C.

Emphasize to the new stakeholders that new requirements are not allowed at this stage of the project.

D.

Seek immediate approval to amend the project timeline and budget in order to deliver all new requirements.

Full Access
Question # 73

A project for a new product launch is in a very initial stage and the requirements are evolving. Due to stiff competition in the market, the customer would liketo launch the product keeping the scope flexible. The project team intends to start the work based on the forecast of a similar project delivered last year.

Which project approach suits the scenario?

A.

Execute it as a Scrum project.

B.

Execute it as a predictive project.

C.

Execute it as a project with stage gates.

D.

Execute it using the same approach as the reference project.

Full Access
Question # 74

A project manager has been running an agile project for 6 months and has been reporting that the project is on track every week. However, on the last week before releasing the final product, the team found atechnical impediment that put the project delivery in jeopardy overnight.

What should the project manager have done to prevent this situation?

A.

Sought and implemented alternative ways to track progress and impediments to identify potential threats

B.

Considered historical data from previous projects with similar impediments to help identify the possible solutions

C.

Provided technical training to the team in advance to ensure the team had high-level technical skills

D.

Developed a risk response plan that would have provided options and strategies regarding project risk exposure

Full Access
Question # 75

A project manager is assigned to a new project. The project management office (PMO) and the project manager agree that this is the right opportunity to include daily standup meetings. The project team has

never used such tools, and a few members are challenging the decision.

What should the project manager do in this situation?

A.

Engage an external vendor to perform the design phase under an iterative approach.

B.

Define the ground rules, responsibilities, and conflict management strategies.

C.

Request that new team members familiar with iterative approaches be assigned to this project.

D.

Update the project schedule to consider a daily standup as part of the project design phase.

Full Access
Question # 76

The project team is experiencing schedule delays due to issues arising with suppliers. Some of the tasks are on the critical path.

What should the project manager do in this situation?

A.

Discuss the critical path issues with the purchasing department.

B.

Escalate the supplier-related issues to the sponsor for resolution.

C.

Review the critical path with the stakeholders to define next steps.

D.

Review the work breakdown structure (WBS) with the suppliers.

Full Access
Question # 77

Several components of an expensive manufacturing project have been returned by the customer. The customer is complaining that the quality of thecomponents is poor and is concerned that, as a result, their products will be returned due to quality issues. The project manager is certain that quality has

been maintained.

How should the project manager communicate with the customer to help assure them that the project has produced quality products?

A.

Show the customer the tolerance and control limits.

B.

Show the customer sample results from the current batch.

C.

Show the customer a sample history of quality.

D.

Show the customer the quality control measurements.

Full Access
Question # 78

A key challenge that a project manager is facing is the lack of discipline by various team members and their inability to harness energy to achieve the project objectives. What should the project manager do toovercome this challenge?

A.

Approach the project sponsor and request help in discussing the project deliverables with team members.

B.

Assign multiple managers to the various teams and delegate all of the tasks to them.

C.

Explain to the team that the project manager is ultimately responsible for the delivery.

D.

Meet with each team member separately and apply an appropriate approach with each one.

Full Access
Question # 79

A project requires the procurement of a large amount of equipment that needs to be on-site before any other activity can begin. The procurement department has a lengthy

approval process.

What should the project manager do?

A.

Ask the project sponsor to expedite the vendor selection process.

B.

Use the existing equipment and replace it later with the new equipment.

C.

Contact the vendor that supplied similar equipment for a previous project.

D.

Work with the procurement team to find alternative options.

Full Access
Question # 80

In a complex development project with many clients and team members, there have been delays in completing the required work. What should the project manager do?

A.

Empower the team members to do their work.

B.

Inform the project sponsor about this situation.

C.

Work with the team to develop a risk response plan.

D.

Send an email to human resources (HR) about this situation.

Full Access
Question # 81

A project that has to be delivered by the targeted date has been delayed due to an unforeseen risk occurrence. How should the project manager compress the project to ensure the completion date is not

affected?

A.

Reduce the project scope.

B.

Increase the project cost.

C.

Add more project resources.

D.

Fast-track the project.

Full Access
Question # 82

For some time now, doubts have been raised about who is responsible for delivering a key benefit of a project. What should the project manager do next?

A.

Document the risk in the risk register and generate the risk responses and their respective associated plans.

B.

Meet with the customer to obtain consensus with the recipient of the benefit and determine a means to deliver the benefit.

C.

Understand the context of the situation and escalate the problem to the steering committee.

D.

Meet with the stakeholders involved to clearly define their roles and responsibilities with regard to the benefit

Full Access
Question # 83

A project has recently kicked off. The project manager observes that there are different expectations among the project team members. These growingmisunderstandings are affecting team productivity.

Which document should the project manager use as a guide to resolve the issue?

A.

Project organization charts

B.

Team charter

C.

Project charter

D.

Stakeholder register

Full Access
Question # 84

A project team consists of eight resources working on a complex project. The chief technical designer prefers to work alone and seldom talks in meetings, but produces good designs. The technical lead is always energetic, has lots of opinions about the project, and constantly clarifies their thoughts in discussions.

What should the project manager do to improve overall team performance?

A.

Ask the chief technical designer to provide their feedback by email.

B.

Let the team dynamics continue as is since the current team mix works well.

C.

Encourage the chief technical designer to engage more with the team.

D.

Ask the technical lead to drive the project's technical discussions.

Full Access
Question # 85

A project manager works with a global virtual team. The team is facing difficulty in communicating with each other and often misses important messages.

This difficulty leads to missed deadlines.

What should the project manager do to enhance project team effectiveness?

A.

Schedule a communications control board meeting.

B.

Implement team colocation to improve communication.

C.

Identify the root cause of communication issues,

D.

Initiate daily communication of project progress.

Full Access
Question # 86

A new project has been kicked off following a planning session. The project is under direct oversight of an executive in the organization. After a review meeting, the project manager overhears an executive request a dashboard from one of the team members to show the overall project status.

What should the project manager do?

A.

Ask the team member to develop a dashboard to fulfill the request.

B.

Tell the team member to route the request through the project manager.

C.

Update the communications management plan to include informal requests.

D.

Update the stakeholder engagement assessment matrix.

Full Access
Question # 87

A project manager has been assigned to an important project that will help set the future of the company. Meanwhile, the project management office (PMO) is implementing

adaptive tools in a mostly predictive environment and has requested that the project manager follow this process as well. However, the functional manager has expressed

concerns about the use of new tools on such an important project.

What should the project manager do?

A.

Follow the project management office's (PMOs) request to implement the adaptive tools in the project.

B.

Review the adaptive tools' impact and obtain agreement from the functional manager.

C.

Follow the functional manager's recommendation to implement only predictive tools in the project.

D.

Make the decision on which project approach to use that would best fit the project.

Full Access
Question # 88

The project team is planning a schedule with limited information. The team is having issues identifying the detailed tasks and estimating task duration.

Which three techniques should the project manager use? (Choose 3)

A.

Iterations and reviews to continuously keep adapting the plan

B.

Gantt chart that includes milestones and deadlines

C.

Rolling wave planning and an adaptive approach

D.

Bottom-up estimating based on a work breakdown structure (WBS)

E.

Relative estimation to determine the task or deliverable sizes

Full Access
Question # 89

A project manager is acting as a servant leader and is struggling to make deadlines on a critical roadway construction project that is falling behind schedule due to a lowperforming team. In order to get the project back on track, what should the project manager do first?

A.

Empower the team members to conduct their job activities and hold each person accountable to improve the schedule.

B.

Notify the project sponsor that the team is underperforming and request additional resources to compress the schedule,

C.

Contact each team member to inform them that further schedule slips will not be tolerated by the project sponsor.

D.

Begin holding daily meetings to assign each team member discrete tasks with specific due dates.

Full Access
Question # 90

An organization is using a hybrid delivery approach for a complex project. In the iteration review, a senior manager is asking for a complete redesign of the functionality presented.This may require a significantchange in the technical architecture and an additional release.

What should the project lead do first?

A.

Discuss with the solution architect

B.

Discuss with the development team

C.

Discuss with the product owner

D.

Discuss with the technical lead

Full Access
Question # 91

A project sponsor has requested that the project manager reprioritize the team's tasks to include a feature that is not part of the minimum viable product (MVP) for the project. Although the project sponsor isvery keen on the feature, adding it has the potential of causing team burnout and/or delaying the release.

How should the project manager address this situation?

A.

Ensure the feature's tasks are included in the iteration backlog, explain to the sponsor the consequences of the request, and ask the team to deliver the feature in the current iteration.

B.

Ensure the feature has been included in the product backlog, then hold a meeting with the team and sponsor to determine how to deliver the feature within the current iteration.

C.

Ensure the feature is included in the iteration backlog, ask the team to work on the current tasks first, and include the new tasks after those tasks are completed.

D.

Ensure the feature has been included in the product backlog, explain to the sponsor the consequences of the request, and ask the team to include the features tasks in the next iteration.

Full Access
Question # 92

An experienced project manager is leading an enthusiastic team but realizes the team lacks the experience to complete thejob successfully. What shouldthe project manager do to reduce the risk of project failure?

A.

Ask the sponsor to add experienced professionals to the team.

B.

Approve the appropriate training program for team members.

C.

Provide team members with the necessary coaching and mentoring.

D.

Assign a dedicated resource to check the quality of each deliverable.

Full Access
Question # 93

A software project using an agile approach is facing quality issues with every release, generating many production problems. What should theproject manager do to fix theproblem and improve the quality?

A.

Hire an external company to add an additional layer of testing, making sure that the final product is well inspected before releasing.

B.

Create a reward system granting incentives to the team members who are able to catch more defects.

C.

Use the retrospective meeting to better understand the root cause of the quality problems and put together a plan with the team to address the problems.

D.

Seek extra funding approval with the sponsor to replace junior team members for more experienced ones.

Full Access
Question # 94

During project execution, the project manager observes lower velocity and a high volume of tasks in the testing queue. The project is using a hybrid approach and there are

only a few sprints remaining.

What should the project manager do?

A.

Add a new resource with testing skills to the team.

B.

Work with the team to understand and solve the issues.

C.

Provide testing training to all the project team members.

D.

Increase the sprint duration so the testing can be completed.

Full Access
Question # 95

One team member is complaining about an agreement made during the last meeting. That team member was present at the meeting and participated in thedecisions registered in the meeting minutes.

What should the project manager do next?

A.

Meet with the team member and search for the root cause of their behavior.

B.

Arrange an additional meeting with the team to communicate the agreement made during the last meeting.

C.

Schedule a new meeting to evaluate the agreement and negotiate a new one.

D.

Talk with the team member and explain that once the meeting ended, the agreement must be respected

Full Access
Question # 96

The project management office (PMO) assigns a project manager who specializes in hybrid approaches to apredictive project that is offtrack from both the cost and schedule perspectives. The project runs into further delays as the project manager is ramping up on theproject. The stakeholders are unhappy and ask senior management to replace the project manager.

How should the project manager approach this situation?

A.

Socialize with the stakeholders to better understand their needs and reset expectations.

B.

Escalate the stakeholder issue to the management team and ask for help with resolving the conflict.

C.

Continue to work on the project until the stakeholders and management come to a decision.

D.

Meet with the stakeholders to understand their concerns and define an action plan to resolve issues.

Full Access
Question # 97

A local company is developing a new product and, for the first time, using a remote team for the programming tasks of features. The design for the product comes from the

local team. During the third sprint review, the product owner has concerns about the project's outcomes. The remote development team is complaining that they do not

clearly understand the requirements conveyed in the daily standup meetings.

How should the project manager address this situation?

A.

Review lessons learned from previous projects and organizational process assets (OPAs).

B.

Evaluate and reassign the developing tasks to a local vendor who has worked on previous projects.

C.

Determine the communication needs, environment, and tools to get the message across.

D.

Document the risk in the risk management plan and use contingency reserves to hire a local vendor.

Full Access
Question # 98

A project interfaces with other projects that are in the same portfolio but are being developed in international locations. One ofthe international projects hassuggested a tactical change that needs to be implemented in this project.

What should the project manager do next?

A.

Reject the change request since it may negatively impact the project's performance.

B.

Implement the change request as soon as possible to avoid accumulating new scope.

C.

Keep the focus on the priority items while the change goes through the change control process.

D.

Use the team's connections with international colleagues to get early warnings on future changes.

Full Access
Question # 99

A project is halfway through its execution phase. The quality specifications for the project deliverables are formally accepted. However, a key stakeholder is

dissatisfied, stating that the deliverables do not meet the quality specifications.

What should the project manager do in this situation?

A.

Notify the stakeholder that arbitration procedures will be followed.

B.

Review the requirements traceability matrix and conduct inspections.

C.

Document the issue in the issue log and send a report to management.

D.

Inform the project sponsor of the stakeholder's dissatisfaction.

Full Access
Question # 100

A company is moving its headquarters to another city. The project manager responsible for the assignment has been using a predictive approach during the transition.

However, the information systems will be migrated using an agile approach. The project manager needs to decide which kind of contract to sign with the vendor responsible

for migrating the systems. The project manager is concerned about controlling finances while delivering results.

How should the project manager address this situation?

A.

Sign a single agreement for the whole project.

B.

Negotiate payment after all project migration is completed.

C.

Use fixed-price increments as user stories are completed.

D.

Confirm payment after each project retrospective.

Full Access
Question # 101

A project manager is working on a project for a startup company. The company launched cloud-based agile project management and DevOps training modules via the learning platform to support multiple self-paced and virtual learning formats. In a recent sprint, the quality assurance team failed to thoroughly inspect the modules before deployment, resulting in a poor customer experience.

Which of the following issues is the project manager facing?

A.

Nonconformance issue

B.

Unmet planned-to-done ratio

C.

Undetected error

D.

Escaped defect

Full Access
Question # 102

During the planning stage of a project the project manager realizes that a standard stakeholder engagement approach will not suffice. One of the client representatives, who

is not a key decision maker, is extremely opinionated. This client representative could become a roadblock to progress due to their perceived level of authority during

meetings.

How should the project manager handle this moving forward?

A.

Update the project schedule to cater to this particular stakeholder.

B.

Allocate time to gain buy-in from the stakeholder prior to key decision meetings.

C.

Ask that only key decision makers attend the project meetings. O

D.

Update the risk register to consider the possible project impacts.

Full Access
Question # 103

A project manager realizes that the team members are new to the hybrid approach and do not value standup meetings. Team members often arrive late, digress into solutioning, or skip the meetings altogether.

How should the project manager improve this situation with the project team?

A.

Send a daily retrospective report to all team members instead of holding standup meetings.

B.

Engage the project team in implementing and improving key aspects of the standup meetings.

C.

Include a daily brainstorming session in the standup meetings to resolve pending issues.

D.

Ask the product owner to remove team members who do not comply with standup meeting rules.

Full Access
Question # 104

A project manager is managing a hybrid project. There is software in place to access the repository of project artifacts. However, a few stakeholders are

reporting that they are unable to find the latest project schedule.

What should the project manager do?

A.

Send the project schedule via email to the stakeholders who need that information.

B.

Make sure all stakeholders have access to the system and know where to find project artifacts.

C.

Escalate the issue to the steering committee and ask them to deal with the stakeholders’ lack of training.

D.

Advise the project management office (PMO) that there is a resource gap for sharing project artifactseffectively.

Full Access
Question # 105

A project manager is leading a small project with a low budget and a short, tight schedule. Many of the stakeholders are within the

organization and have varying levels of interest.

Which approach should the project manager use with the stakeholders?

A.

Schedule one-on-one meetings with stakeholders to provide project updates.

B.

Provide daily reports to maximize stakeholder communication.

C.

Share all relevant project information with the stakeholders.

D.

Minimize communication until project completion as it will be finished quickly.

Full Access
Question # 106

A project delivers every 2 weeks. The customer raises a complaint because they do not perceive business value in the products delivered even though deliveries have been completed in a timely manner.

Which activity should the project manager undertake?

A.

Change the delivery project approach.

B.

Perform a cost-benefit analysis.

C.

Review the risk analysis.

D.

Review the definition for the minimum viable product (MVP).

Full Access