Spring Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: mxmas70

Home > Scrum > PSPO > PSPO-I

PSPO-I Professional Scrum Product Owner (PSPO I) Exam Question and Answers

Question # 4

The " cone of uncertainty " can be used to do what?

(choose the best answer)

A.

Determine whether to cut quality, similar to the " Iron Triangle " of projectmanagement.

B.

Determine the cost of a project before it begins.

C.

Illustrate that as a project forecast lengthens, it is increasingly less certain.

D.

Determine the length of the next Sprint.

Full Access
Question # 5

A Scrum Master is working with a Scrum Team that has Developers in different physical

locations. The Developers meet in a variety of meeting rooms and have much to do logistically

(for example: reserve meeting rooms and set up conference calls) before the Daily Scrum.

What action should the Scrum Master take?

(choose the best answer)

A.

Allow the Developers to self-manage and determine for themselves what to do.

B.

Ask the Developers to alternate who is responsible for meeting setup.

C.

Set up the meeting and tell the Scrum Team that is how it will be done.

D.

Inform management and ask them to solve it.

Full Access
Question # 6

Who determines when it is appropriate to update the Sprint Backlog during a Sprint?

(choose the best answer)

A.

The Project Manager.

B.

The Scrum Team.

C.

The Developers.

D.

The Product Owner.

Full Access
Question # 7

Which of the following is an example of an Increment?

(choose the best answer)

A.

A plan for the overall product release.

B.

A mock-up of the product marketing materials.

C.

A design for the product.

D.

A product roll-out plan.

E.

A valuable, useful set of product features.

F.

All of the above.

Full Access
Question # 8

Who must attend the Daily Scrum?

(choose the best answer)

A.

The Scrum Master and Product Owner.

B.

The Developers and Scrum Master.

C.

The Developers.

D.

The Developers and Product Owner.

E.

The Scrum Team.

Full Access
Question # 9

When should the Product Owner update the project plan?

(choose the best answer)

A.

Before the Sprint Planning to know how much work will have to be done in the Sprint.

B.

The Product Backlog is the plan in Scrum. It is updated as new information and insights emerge.

C.

After the Daily Scrum to ensure an accurate daily overview of project progress.

D.

The project plan must be updated prior to the Sprint Retrospective.

Full Access
Question # 10

When does the next Sprint begin?

(choose the best answer)

A.

The Monday following the Sprint Review.

B.

Immediately after the conclusion of the previous Sprint.

C.

Immediately following the next Sprint Planning.

D.

When the Product Owner is ready.

Full Access
Question # 11

Several Sprints into a project, the Product Owner tells the Scrum Master that a key stakeholder

just started using the product. The stakeholder is unhappy with the quality of the product. What

are two good options for the Scrum Master?

(choose the best two answers)

A.

Coach the Product Owner on how to talk with the Developers about thisconcern.

B.

Wait to bring this up until the Sprint Retrospective.

C.

Explain to the Product Owner that it is up to the Developers to decide onacceptable quality standards.

D.

Encourage the Product Owner to put quality specifications on the ProductBacklog and express the stakeholder ' s concern to the Developers.

E.

Bring the concern to the testers to improve how the Product is verified.

Full Access
Question # 12

When multiple Scrum Teams are working on a single product, what best describes the

Definition of Done?

(choose the best answer)

A.

Each Scrum Team defines and uses its own. The differences are discussed andreconciled during a hardening Sprint.

B.

The Scrum Masters from each Scrum Team define a common Definition of Done.

C.

Each Scrum Team uses its own, but must make their definition clear to all otherteams so the differences are known.

D.

When multiple Scrum Teams are working together on a product, they must mutuallydefine and comply with the same Definition of Done.

Full Access
Question # 13

As the Developers start work during the Sprint, they realize they have selected too much work to finish in the Sprint. What should they do?

(choose the best answer)

A.

Find another Scrum Team to give the excess work to.

B.

As soon as possible in the Sprint, work with the Product Owner to remove some work or Product Backlog items.

C.

Inform the Product Owner at the Sprint Review, but prior to the demonstration.

D.

Reduce the Definition of Done and get all of the Product Backlog items done by the new definition.

Full Access
Question # 14

Who is accountable for creating a valuable and usable Increment each Sprint?

(choose the best answer)

A.

The Scrum Master.

B.

The CEO.

C.

The Developers.

D.

The Scrum Team.

E.

The Product Owner.

Full Access
Question # 15

A Sprint Retrospective should be held:

(choose the best answer)

A.

Only when the Scrum Team determines it needs one.

B.

At the end of the last Sprint in a project or a release.

C.

At the end of each Sprint.

D.

At the beginning of each Sprint.

Full Access
Question # 16

Which of the following are true about the length of the Sprint?

(choose the best answer)

A.

The length of the Sprint should be proportional to the work that is done in betweenSprints.

B.

All Sprints must be one month or less.

C.

Sprint length is determined during Sprint Planning, and should hold the time it willtake to build the planned features in the upcoming Sprint, but does not include timefor any testing.

D.

Sprint length is determined during Sprint Planning, and should be long enough tomake sure the Scrum Team can deliver what is to be accomplished in the upcomingSprint

Full Access
Question # 17

Why does the Product Owner want the Developers to adhere to its Definition of Done?

(choose the best answer)

A.

To predict the team ' s productivity over time.

B.

To have complete transparency into what has been done at the end of each Sprint.

C.

To know what the team will deliver over the next three Sprints.

D.

To be able to reprimand the team when they do not meet their velocity goal for the Sprint.

Full Access
Question # 18

The Product Owner is the person who will be held accountable if a product does not achieve its goals or deliver value. Does this mean that the Product Owner has the final say over the Definition of Done?

(choose the best answer)

A.

Yes, the Product Owner decides the Definition of Done. The Developers may beconsulted.

B.

No, the Scrum Team decides the Definition of Done, if it is not a standard of the organization. The Product Owner is just one member of the Scrum Team.

Full Access
Question # 19

The Scrum Team should have all the skills needed to:

(choose the best answer)

A.

Complete the project within the date and cost as calculated by the Product Owner.

B.

Do all of the development work, except for specialized testing that requires additionaltools and environments.

C.

Turn Product Backlog items into a valuable, useful Increment.

Full Access
Question # 20

True or False: Dependencies could influence how the Product Owner orders Product Backlog items.

A.

True

B.

False

Full Access
Question # 21

What enhances the transparency of an Increment?

(choose the best answer)

A.

Keeping track of and estimating all undone work to be completed in a " hardening " Sprint.

B.

Doing all work needed to meet the Definition of Done.

C.

Reporting Sprint progress to the stakeholders daily.

D.

Updating Sprint tasks properly in the electronic tracking tool.

Full Access
Question # 22

Who is responsible for the sizing of Product Backlog items?

(choose the best answer)

A.

The Product Owner with input from the Developers.

B.

The Scrum Master.

C.

The Developers, alone.

D.

The Developers after clarifying requirements with the Product Owner.

E.

The most senior people in the organization, including architects and subject matterexperts.

Full Access
Question # 23

How much time must a Product Owner spend with the Developers?

(choose the best answer)

A.

Enough so that the Product Owner is confident the Increment will meet the intended value.

B.

40%, or more if the stakeholders agree.

C.

As much time as the Developers tell the Product Owner to be present.

D.

100%

Full Access
Question # 24

What is the accountability of the Product Owner during Sprint 0?

(choose the best answer)

A.

Determine the composition of the Scrum Team to meet the release plan.

B.

There is no such thing as Sprint 0.

C.

Create the overall release plan to ensure that organizational goals are met.

D.

Make sure enough Product Backlog items are refined to fill the first 3 Sprints.

E.

Gathering, eliciting, and analyzing the requirements to build the Product Backlog.

Full Access
Question # 25

True or False: When there are multiple teams working on one product, each Scrum Team should have a separate Product Owner.

A.

True

B.

False

Full Access
Question # 26

True or False: A Product Owner with multiple teams working on one product should maintain separate Product Backlogs for each team.

A.

True

B.

False

Full Access
Question # 27

Which of the following is required by Scrum?

(choose the best answer)

A.

Sprint Retrospective.

B.

Developers must stand up at the Daily Scrum.

C.

Sprint Burndown Chart.

D.

Release Planning.

E.

All of the above.

Full Access
Question # 28

Which two things are appropriate for a Scrum Master to do, if the Scrum Team does not have

the tools and environment to completely finish each selected Product Backlog item?

(choose the best two answers)

A.

Coach the Scrum Team to improve its skills, tools and environment over timeand adjust the Definition of Done accordingly.

B.

Refocus the current Sprint on establishing the Scrum Team ' s environmentinstead of delivering an Increment.

C.

Encourage the Product Owner to accept partially done Increments until thesituation improves.

D.

Have the Scrum Team establish a Definition of Done that is actually possible toachieve given current circumstances.

E.

Declare the Scrum Team not ready for Scrum.

Full Access
Question # 29

True or False: Scrum has a role called " Project Manager " .

A.

True

B.

False

Full Access
Question # 30

Five new Scrum Teams have been created to build one product. A few of the Developers on one of the Scrum Teams ask the Scrum Master how to coordinate their work with the other teams. What should the Scrum Master do?

(choose the best answer)

A.

Teach them that it is their responsibility to work with the other teams to create anintegrated Increment that is inclusive of all five team ' s work.

B.

Collect the Sprint tasks from the teams at the end of their Sprint Planning and merge that into a consolidated plan for the entire Sprint.

C.

Visit the five teams each day to inspect that their Sprint Backlogs are aligned.

D.

Teach the Product Owner to work with the lead developers on ordering ProductBacklog in a way to avoid too much overlap during a Sprint.

Full Access
Question # 31

Who is on the Scrum Team?

(choose all that apply)

A.

Scrum Master.

B.

Product Owner.

C.

Developers.

D.

Project Manager.

E.

None of the above.

Full Access
Question # 32

True or False: Multiple Scrum Teams working on the same product or system all select work

from the same Product Backlog.

A.

True

B.

False

Full Access
Question # 33

Which three of the following are true about Scrum?

(choose the best three answers)

A.

Scrum implements self-management by replacing Project Managers with ScrumMasters.

B.

Scrum is based on empiricism and lean thinking.

C.

Scrum is a framework for developing and sustaining complex products.

D.

Scrum is a methodology where you can pick and choose which parts of Scrumyou think will work for your environment.

E.

Each component of Scrum serves a specific purpose and is essential to Scrum ' ssuccess and your usage of Scrum to develop complex products.

Full Access
Question # 34

You are the Scrum Master of a new, to be developed Product. Development is going to require

45 people. What is a good first question for you to suggest the group thinks about when forming into teams?

(choose the best answer)

A.

What is the right mixture of senior and junior people on each team?

B.

Who are the subject matter experts on each team?

C.

Who are going to be the team leads?

D.

How will we make sure all teams have the right amount of expertise?

Full Access
Question # 35

What is the timebox for the Sprint Planning event?

(choose the best answer)

A.

Monthly.

B.

Whenever it is done.

C.

8 hours for a one-month Sprint.

D.

4 hours for a one-month Sprint.

Full Access
Question # 36

How much work is required of the Developers to complete a Product Backlog item selected during the Sprint Planning?

(choose the best answer)

A.

As much as they can fit into the Sprint, with remaining work deferred to the next Sprint.

B.

As much as is required to meet the Scrum Team ' s Definition of Done.

C.

All development work and at least some testing.

D.

A proportional amount of time on analysis, design, development, and testing.

Full Access
Question # 37

Who is accountable for clearly expressing Product Backlog items?

(Choose the best answer)

A.

The Product Owner.

B.

The business analyst who represents the Product Owner.

C.

The Scrum Master.

D.

The Scrum Master, or the Scrum Master may have the Developers do it.

Full Access
Question # 38

Which three of the following are feedback loops in Scrum?

(choose the best three answers)

A.

Sprint Review.

B.

Refinement Meeting.

C.

Daily Scrum.

D.

Sprint Retrospective.

E.

Release Planning.

Full Access
Question # 39

Which outcome is expected as a Scrum Team matures?

(choose the best answer)

A.

The Sprint Retrospectives will grow to be longer than 4 hours.

B.

They will improve their Definition of Done to include more stringent criteria.

C.

A Scrum Master is no longer needed since they are a mature team now.

D.

There will be no need for a timeboxed Sprint.

E.

Sprint Reviews will no longer be needed.

Full Access
Question # 40

Who determines how work is performed during the Sprint?

(choose the best answer)

A.

The Scrum Master.

B.

The Scrum Team.

C.

Team manager.

D.

The Developers

E.

Subject matter experts.

Full Access
Question # 41

True or False: During the Sprint Review the stakeholder ' s role is to reorder the Product Backlog.

A.

True

B.

False

Full Access
Question # 42

Who is accountable for managing the progress of work during a Sprint?

(choose the best answer)

A.

The Developers.

B.

The most junior member of the team.

C.

The Scrum Master.

D.

The Product Owner.

Full Access
Question # 43

For the purpose of transparency, when does Scrum say a valuable and useful Increment must

be available?

(choose the best answer)

A.

At the end of every Sprint.

B.

Every 3 Sprints.

C.

Before the Release Sprint.

D.

After the Acceptance Testing phase.

E.

When the Product Owner asks to create one.

Full Access
Question # 44

What are two effective ways for the Scrum Team to make non-functional requirements visible?

(choose the best two answers)

A.

Add them to the Product Backlog to ensure transparency.

B.

Run the integration and regression tests before the end of the Sprint, andcapture the open work for the Sprint Backlog of the next Sprint.

C.

Add them to the Definition of Done so the work is taken care of every Sprint.

D.

Put them on a separate list on the Scrum board, available for all to see.

Full Access
Question # 45

What are two effective ways for a Scrum Team to ensure security concerns are satisfied? (choose the best two answers)

A.

Add security concerns to the Definition of Done.

B.

Delegate the work to the security department.

C.

Have the Scrum Team create Product Backlog items for each concern.

D.

Add a Sprint to specifically resolve all security concerns.

E.

Postpone the work until a specialist can perform a security audit and create a list of security-related Product Backlog items.

Full Access
Question # 46

The Developers find out during the Sprint that they are not likely to build everything they forecast. What would you expect a Product Owner to do?

(choose the best answer)

A.

Skip Product Backlog refinement activities.

B.

Inform management that more Developers are needed.

C.

Change the Sprint Goal.

D.

Re-work the selected Product Backlog items with the Developers to meet the Sprint Goal.

E.

Cancel the Sprint.

Full Access
Question # 47

The Product Owner is the person who will be held accountable if a product does not achieve its

goals or deliver value. Does this mean that the Product Owner has final say over the Definition

of Done?

(choose the best answer)

A.

Yes, the Product Owner decides the Definition of Done. The Developers may beconsulted.

B.

No, the Scrum Team decides the Definition of Done, if it is not a standard of theorganization. The Product Owner is just one member of the Scrum Team.

Full Access
Question # 48

When must the Product Owner participate in the Daily Scrum?

(choose the best answer)

A.

When the Scrum Master asks the Product Owner to attend.

B.

When the Product Owner is actively working on items on the Sprint Backlog;however, they participate as a Developer.

C.

When there are impediments to discuss.

D.

When the Product Owner needs to represent the stakeholders ' point of view to theDevelopers.

Full Access
Question # 49

True or False: Cross-functional teams are optimized to work on one component or layer of a system only.

A.

True

B.

False

Full Access
Question # 50

Why would you expect a Product Owner to care that the Scrum Team adheres to its Definition of Done?

(choose the best two answers)

A.

The Product Owner should not concern themselves with meeting the Definitionof Done, it is the Developer ' s responsibility.

B.

To be able to punish the team when they do not meet their velocity goal for the Sprint.

C.

To forecast the team ' s productivity over time.

D.

The Definition of Done can affect the product ' s total cost of ownership.

E.

To have complete transparency into what has been done at the end of eachSprint.

Full Access
Question # 51

The length of a Sprint should be:

(choose the best answer)

A.

Short enough to keep the business risk acceptable to the Product Owner.

B.

Short enough to be able to synchronize the development work with other business events.

C.

No more than one calendar month.

D.

All of the above.

Full Access