Summer Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: myex65

Home > AACE International > Professional Level Certifications > PSP

PSP Planning & Scheduling Professional (PSP) Exam Question and Answers

Question # 4

Using the "normal" schedule, and assuming you are billing on the last day of the month for previous month and for appropriate partial months, how many invoices will you have for this project?

A.

42.

B.

36.

C.

40.

D.

37.

Full Access
Question # 5

What problems can a soils engineer deal with on a project?

A.

Survey error.

B.

Hidden subsurface conditions.

C.

Archeological findings.

D.

Toxic soils.

Full Access
Question # 6

What is accurate about Activity 7001 in the precedence diagram?

A.

The successor FF lag from 7001 to 11001 is not shown

B.

The LF is correct

C.

The TF is not calculated correctly

D.

The LF is not correct

Full Access
Question # 7

The addition of which of the following relationships would cause a logic loop?

A.

O H - D

B.

O C - J

C.

O F-I

D.

O l-C

Full Access
Question # 8

Resource planning must take all of the following into account except for:

A.

Types of materials, equipment and labor skills required to complete the project.

B.

Earned value techniques established for the project.

C.

Time available to complete the project.

D.

Cash flow (expenditure) limitations for completing work on the project.

Full Access
Question # 9

Who will receive the most benefit from a master schedule of the Spring Highway project?

A.

ALPHA

B.

GOUGE. Inc

C.

BILCO

D.

SDOT

Full Access
Question # 10

When resource leveling craft labor for a critical path schedule, the scheduler

A.

Must consider breaks in continuity of work for subcontractors, thereby possibly incurring additional subcontractor mobilization and demobilization costs.

B.

Can depend on the results of the resource leveling operation to reflect a useful realignment of all schedule activities without 'further analysis.

C.

Need not consider its effects, as it is a theoretical concept with limited application to construction projects.

D.

Need only consider the non-union crafts persons.

Full Access
Question # 11

Control Level Schedule activities are NOT one of the following:

A.

always analogous with Control Accounts

B.

always used to establish the scope and track the status of automation control systems

C.

may be composed form multiple WBS deliverable packages

D.

always reporting the status of phase deliverables

Full Access
Question # 12

The sum of all budgets for work scheduled to be accomplished within a given time period is the ____________.

A.

Estimate at completion (EAC)

B.

Budget at completion (BAC)

C.

Budgeted cost of work performed (BCWP)

D.

Budgeted cost of work scheduled (BCWS)

Full Access
Question # 13

What activities are concurrent to Activity 2001 in the "normal" schedule?

A.

7001.

B.

1001.

C.

1000.

D.

2003.

Full Access
Question # 14

Which letter of the alphabet best approximates the graphical shape of a project's cumulative cost baseline, or budgeted cost of work scheduled?

A.

C.

B.

B.

C.

S.

D.

W.

Full Access
Question # 15

When reconstructing a CPM schedule electronically from a hardcopy, which of the following is NOT required to determine the critical path?

A.

Detailed listing of working days for each calendar used

B.

Predecessor and successor listing with logic type and lag duration, preferably sorted by activity ID

C.

Assigned party responsibility for each work task

D.

Tabular listing of activities showing duration, calendar ID, early and late dates

Full Access
Question # 16

Using the normal schedule, given Activity 3001 and the relationship with Activity 4001. what is indicated?

A.

The activities are independent, with Activity 4001 starting 15 days earlier than the start

of Activity 5001

B.

These activities are partially concurrent, with Activity 4001 starting 15 days after the

start of Activity 3001

C.

These activities are sequential, with Activity 4001 starting 15 days earlier than the start of Activity 3001.

Full Access
Question # 17

The work breakdown structure is used to organize

A.

"Smart activity ID codes" representing similar items of scheduled work

B.

The chart of accounts

C.

Similar activity coding of schedule activities

D.

The smallest defined work packet

Full Access
Question # 18

Due to the delayed completion of Product Testing, the Release for Manufacture milestone was delayed by 5 workdays which thus delayed starting the Draft Product Manual activity. If the Print Product Manual activity is also delayed by 10 workdays, what is the delay to completing the Product Available milestone?

A.

15 days

B.

0 days

C.

10 days

D.

5 days

Full Access
Question # 19

Which of the following statements is true?

A.

In the absence of contrary contractual language network float, as opposed to project float, there is a shared commodity between the owner and contractor

B.

In the absence of a contrary contractual language total float, as opposed to free float, there is a commodity belonging to the contractor

C.

In the absence of contrary contractual language total float, as opposed to tree float, there is a commodity belonging to the owner

D.

In the absence of contrary contractual language free float, as opposed to project float, there is not a shared commodity between the owner and the contractor

Full Access
Question # 20

The expected remaining cost needed to complete an activity, group of activities or the project is the____________.

A.

Budget at completion (BAC)

B.

Budgeted cost of work performed (BCWP)

C.

Estimate to complete (ETC)

D.

Estimate at completion (EAC)

Full Access
Question # 21

What is the actual duration as of the status date or data date of Activity B?

A.

7.

B.

3.

C.

0.

D.

4.

Full Access
Question # 22

Using the normal schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?

A.

407 days

B.

255 days

C.

267 days

D.

477 days

Full Access
Question # 23

What does the narrow band at "Y" represent?

A.

Resource limitation period

B.

A delaying event

C.

You cannot tell with the information supplied

D.

A rework period

Full Access
Question # 24

Scenario: You are providing construction management services for a small office building project. Your duties include reviewing and approving the contractor's baseline schedule. The contractor has submitted the first baseline schedule for the project.

The contractor's baseline schedule submittal includes a bar chart, but no CPM diagram. Which of the following is the most significant shortcoming to using a bar chart to review the baseline?

A.

A bar chart cannot accurately reflect the impact of changes in durations or logic to the baseline

B.

A bar chart is always an oversimplified view of the project schedule

C.

A tor chart does not show all the activities required to construct the project

D.

A bar chart does not show whether the project with be completed within the allowable time

Full Access
Question # 25

Which of these letters, symbols or words best approximates the graphical shape of a project's cumulative BCWS?

A.

/

B.

Bell curve

C.

S

D.

_

Full Access
Question # 26

What method offers the best chance of the schedule being used effectively to implement the project in the field?

A.

Issue detailed schedule updates as frequently as possible.

B.

Obtain consent and agreement to the schedule from the key project personnel.

C.

Include detailed and stringent set of scheduling specifications in the contract.

D.

Allow large time contingencies on milestones and completion deadlines.

Full Access
Question # 27

A good change management plan___________.

A.

is provided to stakeholders after it is created

B.

is detailed during the planning phase

C.

tracks minor decisions

D.

involves only the project controls team

Full Access
Question # 28

You are developing a detailed critical path schedule for a proposed petrochemical plant. The schedule will become a part of the project baseline document, which will be sent to the company's board of directors for its consideration. What document or resource is likely to be MOST valuable in determining the schedule's work activity durations?

A.

Industry publications.

B.

Critical path schedules prepared by you for similar completed projects.

C.

The Petrochemical Industry New Plant Task Duration Handbook.

D.

The cost estimate for the plant prepared by your firm's estimating department.

Full Access
Question # 29

When using a detailed estimate as the basis for work package/activity durations, which element does NOT need to be identified before the activity durations can be calculated?

A.

Projected crew size

B.

Estimated labor hours

C.

Hours in a standard work day

D.

Estimated cost

Full Access
Question # 30

Under which circumstance should one perform resource-leveling calculations?

A.

When the contract contains a provision for float-banking.

B.

When you believe that known resource limitations may override schedule logic.

C.

Never, unless required by the contract.

D.

When the schedule is resource-loaded.

Full Access
Question # 31

Scenario:

The entire network consists of the following activities and relationships. Activity A is twenty days long and is tied to Activity B, a ten-day activity, with a finish-to-finish tie with a lag value of five Activity B is tied to Activity C, a twenty-day activity, with a start-to-start relationship with a lag value of five.

PSP Activities Table

Scope Known about Rock-Filled Dam Project:

The dam requires river diversion and work over two or more rainy seasons. The contract is lump sum, competitively bid, and will be self-performed. The owner has attempted to shift all risk to the contractor by employing "no differing sit conditions" and "no damage for delay" clauses. There is a bonus/penalty provision of $2,500 per calendar day for early or late delivery. The early completion bonus is capped at $500,000, with no cap for late delivery penalty.

Liquidated damages end at the finish of demobilization. Indirect costs per calendar day are $2,800 for the "normal" schedule and $3,200 for the "crashed" schedule. The winter/wet weather season is 151 days between October 15 and March 25 of each year, reduces the efficiency of the contractor's operations by 20% and costs the contractor $10,000 per day. Assume a start date of March 5, 2001 and use a 7-day work week.

The following table lists work activities as planned by the contractor.

Theoretically construct a summary activity for only those activities with a finish-to-start relationship for Activities 8001 through 10001. Using the "normal" schedule, what is the cost of this hammock?

A.

$420,000.

B.

$307,000.

C.

$524,000.

D.

$552,000.

Full Access
Question # 32

The linear scheduling velocity diagram has the following two-axis:

A.

Location and crew size

B.

Time and location

C.

Time and rate of progress

D.

Time and crew size

Full Access
Question # 33

As the project plan is developed a mechanism is developed to communicate the projects organic structures that will facilitate reporting against the baseline schedule and cost estimate or budget Which of the following is NOT used for reporting?

A.

The Resource Breakdown Structure (RBS)

B.

The Work Breakdown Structure (WBS)

C.

The Organization Breakdown Structure (OBS)

D.

The Cost Breakdown Structure (CBS)

Full Access
Question # 34

Which is NOT an industry-recognized methodology for quantifying critical delay?

A.

Gantt Chart.

B.

Periodic Windows.

C.

Collapsed As-Built.

D.

Time Impact.

Full Access
Question # 35

: 20

Constraints control events or activities that __________________.

A.

Affect only the forward pass.

B.

Are not based on project relationships.

C.

Affect only the backward pass.

D.

May be over-ridden by activity logic.

Full Access
Question # 36

What is the cycle time?

A.

5 minutes

B.

17 minutes

C.

14 minutes

D.

6 minutes

Full Access
Question # 37

Scenario: You are providing construction management services for a small office building project. Your duties include reviewing and approving the contractor's baseline schedule. The contractor has submitted the first baseline schedule for the project.

The contractor subsequently submits a CPM schedule for its baseline schedule submittal. As part of your review, you look at the durations for each activity in the schedule. How do you determine if a duration of 10 work days for drywall installation is accurate?

A.

The duration for drywall installation should De proportional to how critical the activity is

B.

Review the drywall quantity, methods and location with the project superintendent to determine a reasonable duration

C.

Review the location of drywall work in the contract drawings

D.

Divide the quantity of drywall by the construction crew's dairy production rate for this work

Full Access
Question # 38

Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?

A.

Multiple calendars.

B.

Start and finish constraints.

C.

Preferential logic.

D.

Front end loading.

Full Access
Question # 39

In analyzing a logical chain of activities in a critical path method (CPM) schedule, what do differing total float values within that chain typically indicate?

A.

The schedule has too much detail to reflect an accurate critical path.

B.

Different calendars are assigned to certain activities in the logical chain.

C.

The schedule is projecting an "early completion".

D.

Certain activities in the critical path have no successors.

Full Access
Question # 40

Free float is the

A.

Difference between the early dates and late dates of an activity.

B.

Amount of time the early start of an activity can be delayed without impacting the early start of the successor activity.

C.

Difference between the early finish dates and late finish dates of an activity.

D.

Difference In float value of the critical path activities and the float value of the specific activity being analyzed.

Full Access
Question # 41

Activity 1001 started on the scheduled date but has slipped 10 days. Activity 10002 will slip 35 days. All remaining activities retain their original duration. What is the revised completion date?

A.

11 Mar 2024

B.

21 Mar 2024

C.

19 Feb 2024

D.

20 Mar 2024

Full Access
Question # 42

The Baseline Plan does NOT reflect which of the following:

A.

scope of worn and work plans

B.

stakeholders deliverables

C.

approved budget

D.

schedule milestones

Full Access
Question # 43

In its simplest form, what is the main drawback of critical path method scheduling?

A.

It requires a backward pass to calculate late dates.

B.

It assumes that resources are unlimited.

C.

It doesn't account for interdependent between activities.

D.

It allows for Precedence Diagramming Method to be used in place of Arrow Diagramming Method.

Full Access
Question # 44

The Scope of Work divides the major deliverables into smaller more manageable components for all of the following EXCEPT to:

A.

improve the accuracy of cost, time, and resource estimates

B.

facilitate clear responsibility assignments

C.

define a baseline for performance measurement and control

D.

establish the Performance Measurement Baseline values

Full Access
Question # 45

When are KPIs defined?

A.

At project initiation

B.

At NTP

C.

At the start of the Construction Phase

D.

After the Bidding Phase

Full Access
Question # 46

By subtracting a measured unit productivity rate during an impacted period from the unit productivity rate during an unimpacted period, the resulting value represents:

A.

Acceleration.

B.

Production output.

C.

Productivity loss.

D.

Productivity efficiency.

Full Access
Question # 47

Why does activity 11001 not show successor activities?

A.

The early finish and late finish are circular

B.

It is the penultimate work required for the project

C.

The scheduler forgot to add the successor activities

D.

It is the final activity for the required work for the project

Full Access
Question # 48

Which of the following options is NOT a feasible method to reduce the overall completion time of the toll road program?

A.

Subcontract outside forces to accelerate the Phase A Schedule

B.

Allocating forces from other BILCO contracts to the toll road project

C.

Proceeding with the work in advance of the environmental studies

D.

Reduce the phasing from 5 phases to 3 phases

Full Access
Question # 49

These are the activities on the critical path:

A.

A, D, & I.

B.

A, C, E, & H.

C.

A, B, G, & H.

D.

A, B, F, & J

Full Access
Question # 50

Which of the following procedures is generally recognized as acceptable when updating a schedule?

A.

Report an actual date when the activity is on a non-work calendar for that date

B.

Change a previously reported actual date

C.

Change the WBS assignment for an activity

D.

Change a calculated date in the future

Full Access
Question # 51

Determine the correct formula and date for the late finish for Activity 2001.

A.

LF.2001 - 1 day -> 08-28-01.

B.

LS.2002- 1 day-> 08-29-01.

C.

LS.2002 + 1 day -> 08-30-01.

D.

LS.2002 - 1 day -> 08-28-01.

Full Access
Question # 52

Which of the following is NOT a tool or technique used to perform scope planning?

A.

Benefit cost analysis.

B.

Schedule performance indexing.

C.

Expert Judgment.

D.

Alternatives identification.

Full Access
Question # 53

What is the result of a forward pass calculation?

A.

Value of total float for individual activities

B.

Early start and early finish date for individual activities

C.

Value of free float for individual activities

D.

Critical path

Full Access
Question # 54

Based on the available scope information and required accuracy, different cost estimated models or methodologies are utilized Which of the following statements is NOT true?

A.

The Deterministic model is used when Class 3 through 1 estimates are required

B.

The Parametric model is used when Class 5 or Class 4 estimates are required

C.

The Deterministic model is used when Class 5 through 3 estimated are required

D.

The Parametric model is used when detailed quantities are not known

Full Access
Question # 55

For which of these delays should an owner grant a time extension?

A.

Structural steel shop drawings.

B.

Shop drawings and centrifuge delay.

C.

Differing site conditions at parking structure.

D.

Differing site conditions and centrifuge delay.

Full Access
Question # 56

If Activity E's duration changes to 4 months, what is the overall duration of the project.

A.

19 months.

B.

20 months.

C.

22 months.

D.

21 months.

Full Access
Question # 57

In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):

A.

The delay must affect the critical path.

B.

The delay must be concurrent with the delay attributable to both parties.

C.

The delay must not cause monetary harm to the defendant.

D.

The delay must affect the contractor's planned construction schedule.

Full Access
Question # 58

Considering the information provided for the project, what is the factor that most influences the successful crashing of the schedule?

A.

Avoiding a late delivery penalty from the owner

B.

Maximizing the $500,000 bonus

C.

Avoiding the 2023-2024 winter/wet weather season

D.

Minimizing the indirect expenditure chargeable to the contractor

Full Access
Question # 59

EBS is an acronym for:

A.

Elongated Budget Synopsis

B.

European Basic Schedule

C.

Enterprise Breakdown Structure

D.

Eventual Base Structure

Full Access
Question # 60

Determine the correct formula and date for the late finish for Activity 2002.

A.

LS.2003 - 1 day -> 11.06.01.

B.

LS.2003 - 1 day -> 10-06-01.

C.

LS.2003 + 1 day -> 10-07-01.

D.

LS.2003 - 1 day -> 10-05-01.

Full Access
Question # 61

Using one crane capable of 30 lifts per day. for 3 column pours requiring 28 lifts each, plus assorted work in the area requiring an additional 150 lifts, what are the lowest planned workdays for this work?

A.

3 workdays

B.

18 workdays

C.

8 workdays

D.

7 workdays

Full Access
Question # 62

The EBS is established by:

A.

The contractor s planning and scheduling office

B.

The government entity with the authority to approve/stop the work

C.

The entity with the authority to fund and direct the enterprise

D.

The contractors and subcontractors

Full Access
Question # 63

The schedule or budget at completion less the estimate at completion is___________.

A.

the schedule variance

B.

the variance at completion

C.

the cost variance

D.

the profit or loss for the project

Full Access
Question # 64

Which of the following risks CANNOT be estimated by BILCO with only a resource-loaded schedule?

A.

Delay due to SDOT's other projects

B.

Delay due to labor shortage

C.

Liquidated damages on the SDOT contract

D.

Cost overruns due to cement shortage

Full Access