Labour Day Sale - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: mxmas70

Home > Scrum > Professional Scrum Master > PSM-I

PSM-I Professional Scrum Master level I Question and Answers

Question # 4

Which two activities will a Product Owner engage in during a Sprint? (Choose two.)

A.

Run the Daily Scrum.

B.

Prioritize the Development Team’s work on the Sprint Backlog.

C.

Update the Sprint burndown chart.

D.

Answer questions from the Development Team about items in the current Sprint.

E.

Work with the stakeholders.

Full Access
Question # 5

True or False Developers do not meet with stakeholders: only the Product Owner meets with stakeholders

A.

True

B.

False

Full Access
Question # 6

The Scrum Master observes the Product Owner struggling with ordering the Product Backlog. What is an appropriate action for the Scrum Master to take?

A.

Suggest the Product Owner extend the Sprint, so he can have more time to order the Product Backlog.

B.

Suggest that the Development Team does the ordering to be sure that it is a feasible ordering of work.

C.

Offer the Product Owner help in understanding that the goal of ordering the Product Backlog is to maximize value.

D.

Present the Product Owner with an ordered Product Backlog to use.

E.

Encourage the Product Owner to work with the Development Team to see which items technically are fastest to implement.

Full Access
Question # 7

A member of the Development Team takes the Scrum Master aside to express his concerns about data security issues. What should the Scrum Master do?

A.

Add security to the definition of “Done”.

B.

Tell the Product Owner to stop further development of features until the issues are fixed.

C.

Create a Product Backlog item for security.

D.

Go check with the testers.

E.

Ask the person to share the issue with the team as soon as possible.

Full Access
Question # 8

When multiple teams work together on the same product, each team should maintain a separate Product Backlog.

A.

True

B.

False

Full Access
Question # 9

A Scrum Team has been working on a product for nine Sprints. A new Product Owner comes in, understanding he is accountable for the Product Backlog. However, he is unsure about his responsibilities. Which two activities are part of the Product Owner role according to Scrum? (Choose two.)

A.

Ensuring that the most valuable functionality is produced first, at all times.

B.

Interacting with stakeholders.

C.

Providing the Development Team with detailed specifications.

D.

Describing features as Use Cases.

E.

Creating detailed functional test cases.

Full Access
Question # 10

Which best describes the Product Backlog?

A.

It is allowed to grow and change as more is learned about the product and its customers.

B.

It provides just enough information to enable a Scrum team to start the design phase of a product.

C.

It contains all foreseeable tasks and requirements from which the Scrum team can develop and maintain a complete project plan.

D.

It is baselined to follow change management processes.

Full Access
Question # 11

Which three behaviors demonstrate that a team is self-organizing? (Choose three.)

A.

Stakeholders walking in at the Daily Scrum to check progress and work with the Scrum Master to optimize the functional scope for the Sprint.

B.

The Development Team members are working within the boundaries of their functional description and nicely handing off work from analyst to developer to tester to integration.

C.

The Product Owner doesn’t need to be at Sprint Retrospectives.

D.

The Development Team creating their own sprint backlog, reflecting all work that is part of the definition of “Done”.

E.

The Development Team has all the skills needed to create a releasable Increment.

F.

Development Team members collaboratively selecting their own work during the Sprint.

G.

The Development Team inviting external people to the Sprint Planning to ask them how to turn a Product Backlog item into an Increment via a complete and detailed Sprint Backlog.

Full Access
Question # 12

Which technique is the best way the Scrum Master can ensure that the Development Team communicates effectively with the Product Owner?

A.

Monitor communications between them and facilitate direct collaboration.

B.

Teach the Development Team to talk in terms of business needs and objectives.

C.

Teach the Product Owner about the technologies employed during the Sprints.

D.

Act as a go-between for them.

Full Access
Question # 13

What are two ways that regulatory compliance issues are dealt with in Scrum?

(choose the best two answers)

A.

They are addressed by a separate team who is responsible for compliance

issues.

B.

They are addressed along with functional development of the product.

C.

They are discussed, determined, and documented before the actual feature

development Sprints.

D.

They are added to the Product Backlog and addressed in early Sprints, while

always requiring at least some business functionality, no matter how small.

Full Access
Question # 14

When many Development Teams are working on a single product, what best describes the definition of “Done”? (Choose the best answer.)

A.

Each Development Team defines and uses its own. The differences are discussed and reconciled during a hardening Sprint.

B.

It depends.

C.

Each Development Team uses its own but must make their definition clear to all other teams so the differences are known.

D.

All Development Teams must have a definition of “Done” that makes their combined work potentially releasable.

Full Access
Question # 15

Who is accountable for managing the progress ot work during a Sprint?

(choose the best answer)

A.

The Product Owner.

B.

The Developers.

C.

The Scrum Master.

D.

The most junior member ot the team.

Full Access
Question # 16

A Product Owner wants advice from the Scrum Master about estimating work in Scrum. Which of these is the guideline that a Scrum Master should give?

A.

Product Backlog items must be estimated in story points.

B.

Estimates are made by the Development Team.

C.

Estimates must be in relative units.

D.

Scrum forbids estimating.

E.

Estimates are made by the Product Owner, but are best checked with the Development Team.

Full Access
Question # 17

When is a Sprint over?

A.

When the Product Owner says it is done.

B.

When all Product Backlog items meet their definition of “Done”.

C.

When all the tasks are completed.

D.

When the time-box expires.

Full Access
Question # 18

Who determines how many Product Backlog items the Developers select tor a sprint? (choose the best answer)

A.

The Scrum Master

B.

The Scrum Team

C.

The Developers

D.

The stakeholders attending Sprint Planning

E.

The Product Owner

Full Access
Question # 19

How should a Development Team deal with non-functional requirements?

A.

Ensure every Increment meets them.

B.

Make sure the release department understands these requirements, but it is not the Development Team’s responsibility.

C.

Handle them during the Integration Sprint preceding the Release Sprint.

D.

Assign them to the lead developers on the team.

Full Access
Question # 20

What are three ways Scrum promotes self-organization? (Choose three.)

A.

By not allowing documentation.

B.

By the Development Team deciding what work to do in a Sprint.

C.

By preventing stakeholders from entering the development room.

D.

By removing titles for Development Team members.

E.

By being a lightweight framework.

Full Access
Question # 21

A Development Team selects a set of Product Backlog items for a Sprint Backlog with the intent to get the selected items “Done” by the end of the Sprint. Which three phrases best describe the purpose of a definition of “Done”? (Choose three.)

A.

It controls whether the developers have performed their tasks.

B.

It provides a template for elements that need to be included in the technical documentation.

C.

It creates transparency over the work inspected at the Sprint Review.

D.

It trucks the percent completeness of a Product Backlog item.

E.

It guides the Development Team is creating a forecast at the Sprint Planning.

F.

It defines what it takes for an Increment to be ready for release.

Full Access
Question # 22

When must a Product Owner release each Increment? (Choose the best answer.)

A.

When it makes sense.

B.

When the Scrum Team finishes their work.

C.

Whenever the product is free of defects.

D.

After every Sprint, Without exception.

Full Access
Question # 23

How much time is required after a Sprint to prepare for the next Sprint?

A.

The break between Sprints is time-boxed to 1 week for 30 day Sprints, and usually less for shorter sprints.

B.

Enough time for the requirements for the next Sprint to be determined and documented.

C.

Enough time for the Development team to finish the testing from the last Sprint.

D.

None. A new Sprint starts immediately following the end of the previous Sprint.

E.

All of the above are allowed depending on the situation.

Full Access
Question # 24

Scrum has a role called “Project Manager”.

A.

True

B.

False

Full Access
Question # 25

Who should make sure everyone on the scrum Team does their tasks for the sprint? (choose the best answer)

A.

The Project Manager

B.

The Product Owner

C.

The Scrum Master

D.

The Scrum Team

E.

All of the above

Full Access
Question # 26

When does the second Sprint start?

A.

Once the architectural changes for the second Sprint have been approved by the senior architect.

B.

After the Product Backlog for the second Sprint has been selected.

C.

Immediately after the first Sprint.

D.

After the customer completes acceptance testing of the first Sprint.

Full Access
Question # 27

When is implementation of a Product Backlog item considered complete?

A.

At the end of the Sprint.

B.

When the item has no work remaining in order to be potentially released.

C.

When QA reports that the item passes all acceptance criteria.

D.

When all work in the Sprint Backlog related to the item is finished.

Full Access
Question # 28

Which of the following are true about the Product Owner role? (Choose two.)

A.

The Product Owner is one person.

B.

The Product Owner is accountable for ordering the Product Backlog.

C.

Multiple people can share the Product Owner role on a Scrum Team.

D.

The Product Owner role can be played by a committee or a team of people.

Full Access
Question # 29

When does a Sprint conclude?

(choose the best answer)

A.

When the Product Owner decides enough has been delivered to meet the Sprint

Goal.

B.

When the Sprint Retrospective is complete.

C.

When all the tasks are completed by the Developers.

D.

When all Product Backlog items meet their Definition of Done.

Full Access
Question # 30

Which approach is best for Scrum Teams in order to produce valuable Increments? (Choose the best answer.)

A.

Each Developer works on the component where they feel that they can contribute.

B.

Each Scrum Team is accountable for developing functionality from beginning to end.

C.

Each Scrum Team works on an independent set of components.

D.

Each Scrum Member works only as an independent layer of the system.

Full Access
Question # 31

True or False: An increment must be released to customers or users at the end of each sprint.

A.

True

B.

False

Full Access
Question # 32

A Scrum Team is experiencing a growing list of impediments. Which techniques would be most

helpful in this situation?

(choose the best two answers)

A.

As a Scrum Team, prioritize the list and work on them in order.

B.

The Scrum Master discusses the impediments with the Scrum Team.

C.

The Product Owner should add the open impediments to the Product Backlog.

D.

Arrange a triage meeting with management.

Full Access
Question # 33

You have just been hired by a company new to Scrum. Your management has assigned you to be the Scrum Master of six new Scrum Teams. These teams will build one product. Select two conditions you should strive for in this scenario. (Choose two.)

A.

There should be six Product Owners, one for each Scrum Team.

B.

There should be six Product Owners, reporting to a chief Product Owner.

C.

The product has one Product Backlog.

D.

Each Scrum Team should have a separate Product Backlog.

E.

There should be only one Product Owner.

Full Access
Question # 34

Developers are self-managing, which of the following do they manage? (choose the best answer)

A.

When lo release, based on this progress.

B.

Stakeholders for the Sprint Review

C.

Sprint Backlog.

D.

Sprint length

E.

Product Backlog ordering

Full Access
Question # 35

Which of the following are true about the length of the Sprint? (Choose two.)

A.

The length of the Sprint should be proportional to the work that is done in between Sprints.

B.

It is best to have Sprints of consistent length throughout a development effort.

C.

Sprint length is determined during Sprint Planning, and should hold the time it will take to code the planned features in the upcoming Sprint, but does not include time for any testing.

D.

Sprint length is determined during Sprint Planning, and should be long enough to make sure the Development Team can deliver what is to be accomplished in the upcoming Sprint.

E.

All Sprints must be 1 month or less.

Full Access
Question # 36

Cross-functional teams are optimized to work on one technical layer of a system only (e.g. GUI, database, middle tier, interfaces).

A.

True

B.

False

Full Access
Question # 37

What is the tactic a Scrum Master should use to divide a group of 100 people into multiple Development Teams?

A.

Create teams based on their skills across multiple layers (such as database, UI, etc.)

B.

Ask the Product Owner to assign the people to teams.

C.

Ask the developers to divide themselves into teams.

Full Access
Question # 38

Why does a Development Team need a Sprint Goal?

A.

A Sprint Goal only gives purpose to Sprint 0.

B.

Sprint Goals are not valuable. Everything is known from the Product Backlog.

C.

The Development Team is more focused with a common yet specific goal.

D.

A Sprint Goal ensures that all of the Product Backlog items selected for the Sprint are implemented.

Full Access
Question # 39

Who is accountable for tracking the remaining work toward the Sprint Goal? (Choose the best answer.)

A.

The Developers.

B.

The Scrum Master.

C.

The Product Owner.

D.

The Project Manager.

Full Access
Question # 40

Which topics should be discussed in the Sprint Review? (Choose the best answer.)

A.

The Scrum process, and how it was used during the Sprint.

B.

Coding and engineering practices.

C.

The product Increment.

D.

All of the above.

Full Access
Question # 41

Who does the work to make sure Product Backlog items conform to the Definition of Done?

(choose the Best answer)

A.

The Quality Assurance Team

B.

The Scrum Team

C.

The Product Owner

D.

The Scrum Master

E.

The Developers

Full Access
Question # 42

At the seventh Sprint Review, the stakeholders are disappointed and angry. They have determined that the product or system being built will not meet their needs and will cost more than they are willing to spend. What factors likely led to this? (Choose two.)

A.

The Project Management Office (PMO) has not been engaged adequately.

B.

The Product Owner has not been keeping the stakeholders aware of the progress of the project.

C.

The stakeholders haven’t been using the Sprint Reviews to inspect and evaluate progress.

D.

The stakeholders were not allowed to enter the development area.

Full Access
Question # 43

When must the Product Owner participate in the Dairy Scrum? (choose the best answer)

A.

When the Product Owner is actively working on items on the Sprint Backlog; however, they participate as a Developer

B.

When the Product Owner needs to represent the stakeholders point of view to the Developers

C.

When there are impediments to discuss

D.

When the Scrum Master asks the Product Owner to attend

Full Access
Question # 44

Who can abnormally terminate a Sprint?

A.

The Scrum Master

B.

The Development Team or its members.

C.

The Product Owner

D.

The Stakeholders

Full Access
Question # 45

How much work must a Development Team do to a Product Backlog item it selects for a Sprint?

A.

A proportional amount of time on analysis, design, programming, testing, and documentation.

B.

As much as it can fit into the Sprint. Any remaining work will be transferred to a subsequent Sprint.

C.

All development work and at least some testing.

D.

As much as it has told the Product Owner will be done for every Product Backlog item it selects in conformance with the definition of “Done”.

Full Access
Question # 46

A Scrum Master is keeping a list of open impediments, but it is growing and he/she has been able to resolve only a small portion of the impediments. Which three techniques would be most helpful in this situation? (Choose three.)

A.

Consulting with the Development Team.

B.

Prioritizing the list and working on them in order.

C.

Arranging a triage meeting with all project managers.

D.

Alerting management to the impediments and their impact.

Full Access
Question # 47

The IT manager asks a Development Team for a status report describing the progress throughout the Sprint.

The Development Team asks the Scrum Master for advice. The Scrum Master should:

(Choose the best answer.)

A.

Talk to the IT manager and explain that progress in Scrum comes from inspecting an Increment at the Sprint Review.

B.

Tell the Development Team to figure it out themselves.

C.

Tell the Development Team to fit the report into the Sprint Backlog.

D.

Create and deliver the report to the manager herself.

E.

Ask the Product Owner to send the manager the report.

Full Access
Question # 48

A new Developer is having continuing conflicts with existing members or the scrum Team, which is impacting the delivery of the Increment It necessary, who is responsible for removing the Developer from the Scrum Team?

(choose the best answer)

A.

The Scrum Master is responsible, they remove impediments

B.

The Product Owner is responsible, they control the return on investment (ROI)

C.

The hiring manager is responsible, they hired the Developer

D.

The Scrum Team is responsible

Full Access
Question # 49

How is management external to the Scrum Team involved in the Daily Scrum? (Choose the best answer.)

A.

The Scrum Master speaks on their behalf.

B.

Managers are not required at the Daily Scrum.

C.

Management gives an update at the start of each Daily Scrum.

D.

The Product Owner represents their opinions.

Full Access
Question # 50

You have six teams using a traditional method to deliver a product. Your management has asked you to start using Scrum. In the initial project there were separate plans and teams for the layers of a software system, i.e. one for the front-end, one for the middle tier, one for the back-end, and one for the interfaces and services. This resembles what is known as component teams. But you have read that it’s a good idea to have teams organized by feature.

What are the advantages of keeping component teams while starting Scrum?

A.

There’s less initial disruption than organizing into new teams. As they start, they will discover what works best, and how to potentially re-organize towards this.

B.

Component teams generally have the skills needed to create a working Increment of software that provides business value.

C.

Because they have worked together for some time, they are likely able to start producing shippable Increments faster that new feature teams would.

D.

There are fewer cross-team dependencies than working in feature teams.

Full Access
Question # 51

For which is the Scrum Master responsible?

A.

Managing the performance of the Scrum Team.

B.

The meetings and the objectives that a Scrum Team sets for itself.

C.

The Scrum framework being adopted and used properly.

D.

Keeping track of resource allocation.

Full Access
Question # 52

As the Sprint Planning progresses, the Developers realize that the workload may be greater

than their capacity to complete the work. Which two are valid actions?

(choose the best two answers)

A.

Recruit additional Developers before the work can begim

B.

The Developers ensure that the Scrum Team is aware, start the Sprint, and

monitor progress.

C.

The Developers work overtime during this Sprint

D.

Cancel the Sprint

E.

Remove or change selected Product Backlog items.

Full Access
Question # 53

Who is responsible for tracking the remaining work of the Sprint?

A.

The Development Team.

B.

The Scrum Master.

C.

The Project Manager.

D.

The Development Team is consultation with the Product Owner.

E.

The Product Owner.

Full Access
Question # 54

When might a Sprint be abnormally cancelled?

A.

When the Development Team feels that the work is too hard.

B.

When the Sprint Goal becomes obsolete.

C.

When the sales department has an important new opportunity.

D.

When it becomes clear that not everything will be finished by the end of the Sprint.

Full Access
Question # 55

What happens if the Development Team cannot complete its work by the end of the Sprint?

A.

The Sprint is extended and future Sprints use this new duration.

B.

The Sprint length holds and the Development Team continuously learns what is actually possible to do within a Sprint of this length.

C.

The Sprint is extended temporarily. Lessons are taken to ensure it doesn’t happen again.

Full Access
Question # 56

During a Sprint Retrospective, for what is the Scrum Master responsible?

A.

Prioritizing the resulting action items.

B.

Participating as a Scrum team member and facilitating as requested or needed.

C.

Acting as a scribe to capture the Development Team’s answers.

D.

Summarizing and reporting the discussions to management.

Full Access
Question # 57

Which of the following might the Scrum Team discuss during a Sprint Retrospective?

A.

Methods of communication.

B.

The way the Scrum Team does Sprint Planning.

C.

Skills needed to improve the Development Team’s ability to deliver.

D.

Its Definition of “Done”.

E.

All of the above.

Full Access
Question # 58

Scrum is a methodology that tells in detail how to build software incrementally.

A.

True

B.

False

Full Access
Question # 59

The Sprint Goal is a result of Sprint Planning, as is the Sprint Backlog.

A.

True

B.

False

Full Access
Question # 60

If burndown charts are used to visualize progress, what does a trend line through a release burndown chart indicate?

A.

The evolution of the cost spent on the project.

B.

When all work will be completed to the Scrum Team can be released for other work.

C.

When the work remaining will likely be completed if nothing changes on the Product Backlog or the Development Team.

D.

When the project will be over if the Product Owner removes work that is equal in effort to any new work that is added.

Full Access
Question # 61

Which topics should be discussed in the Sprint Review?

A.

The Scrum process, and how it was used during the Sprint.

B.

Coding and engineering practices.

C.

Sprint results.

D.

All of the above.

Full Access
Question # 62

Which statement best describes a Product Owner’s responsibility?

A.

Optimizing the value of the work the Development Team does.

B.

Managing the project and ensuring that the work meets the commitments to the stakeholders.

C.

Directing the Development Team.

D.

Keep stakeholders from distracting the Development Team.

Full Access
Question # 63

To get started in terms of what to build, Scrum requires no more than a Product Owner with enough ideas for a first Sprint, a Development Team to implement those ideas and a Scrum Master to help guide the process.

A.

True

B.

False

Full Access
Question # 64

How should Product Backlog items be chosen when multiple Scrum Teams work from the same Product Backlog?

A.

The Scrum Team with the highest velocity pulls Product Backlog items first.

B.

The Development Teams pull in work in agreement with the Product Owner.

C.

The Product Owner should provide each team with its own Product Backlog.

D.

Each Scrum Team takes an equal numbers of items.

E.

The Product Owner decides.

Full Access
Question # 65

The length of a Sprint should be:

A.

Short enough to keep the business risk acceptable to the Product Owner.

B.

Short enough to be able to synchronize the development work with other business events.

C.

No more than one calendar month.

D.

All of these answers are correct.

Full Access
Question # 66

Which two things should the Development Team do during the first Sprint? (Choose two.)

A.

Make up a plan for the rest of the project.

B.

Analyze, describe, and document the requirements for the subsequent Sprints.

C.

Develop at least one piece of functionality.

D.

Define the major product features and release plan architecture

E.

Create an increment of potentially releasable software.

Full Access
Question # 67

When multiple Scrum Teams are working on a single product, what best describes the

Definition of Done?

(choose the best answer)

A.

Each Scrum Team uses its own, but must make their definition clear to all other

teams so the differences are known.

B.

The Scrum Masters from each Scrum Team define a common Definition of Done.

C.

When multiple Scrum Teams are working together on a product, they must mutually

define and comply with the same Definition of Done.

D.

Each Scrum Team defines and uses its own. The differences are discussed and

reconciled during a hardening Sprint.

Full Access
Question # 68

A Scrum Master is working with a Development Team that has members in different physical locations. The Development Team meets in a variety of meeting rooms and has much to do logistically (for example, set up conference calls) before the Daily Scrum. What action should the Scrum Master take?

A.

Allow the Development Team to self-manage and determine for itself what to do.

B.

Set up the meeting and tell the Development Team that is how it will be done.

C.

Ask the Development Team members to alternate who is responsible for meeting setup.

D.

Inform management and ask them to solve it.

Full Access
Question # 69

Who has the final say on the order of the Product Backlog?

A.

The Development Team.

B.

The Product Owner.

C.

The Scrum Master.

D.

The Stakeholders.

E.

The CEO.

Full Access
Question # 70

What is the accountability of the Product Owner during Sprint 0? (Choose the best answer.)

A.

There is no such thing as Sprint 0.

B.

Gathering, eliciting, and analyzing the requirements that will be inserted into the Product Backlog.

C.

Make the complete project plan to commit date, budget, and scope to the stakeholders.

D.

Determine the composition of the Development Teams so they have the capacity to deliver the completed

forecast.

E.

Make sure enough Product Backlog items are refined to fill the first 3 Sprints.

Full Access
Question # 71

What factor should be considered when establishing the Sprint length?

(choose the best answer)

A.

The organization has mandated similar length sprints.

B.

The need for the team to learn based on doing work and measuring results.

C.

The frequency at which team formation can be changed.

D.

The organization's release schedule.

Full Access
Question # 72

A Scrum Team is only allowed to meet with stakeholders during Sprint Review.

A.

True

B.

False

Full Access
Question # 73

Every Scrum Team should nave:

(choose the best answer)

A.

One Lead Developer and no more than 8 other members.

B.

The competencies and skills needed to deliver an Increment in a Sprint

C.

At least one representative from each major department, such as, Quality Assurance, Development, and Marketing.

Full Access
Question # 74

Which two things should the Scrum Team do during the first Sprint?

(choose the best two answers)

A.

Define the major product features and a release plan architecture.

B.

Build at least one piece of valuable functionality.

C.

Create at least one valuable, useful Increment

D.

Make up a plan tor the rest of the project

E.

Analyze, describe, and document the requirements for the subsequent Sprints.

Full Access