Question # 4

Which describes an off-specification?

A.

An interdependency between products that was previously unidentified

B.

The addition of an improvement to a product description

C.

A prototype demonstrating a possible design solution

D.

The production of more than the defined quantity of a specialist product

Full Access
Question # 5

Which is a purpose of the 'closing a project' process?

A.

To provide the project board with information to judge the success of a stage

B.

To confirm the project has nothing more to deliver

C.

To establish mechanisms to judge whether the project is still viable

D.

To establish mechanisms for forecasting project objectives

Full Access
Question # 6

What information should be recorded in the quality register?

A.

Planned activities to determine whether the products are fit for purpose

B.

Potential threats to the project's objectives and how they will be managed

C.

Lessons that the project will capture and use during the project

D.

Off-specifications that will occur during the project

Full Access
Question # 7

Who represents the three project interests on a project?

A.

Project manager

B.

Project support

C.

External project stakeholders

D.

Project board

Full Access
Question # 8

Which is a minimum requirement for applying the plans theme?

A.

The project must have at least two management stages

B.

The team managers in the project must prepare team plans

C.

Scope tolerance must be prioritized using MoSCoW

D.

The project plan must be presented as a Gantt chart

Full Access
Question # 9

What is described as an organization's unique attitude towards risk taking

A.

Risk appetite

B.

Risk management

C.

Risk evaluation

D.

Risk tolerance

Full Access
Question # 10

Which is a minimum requirement when applying the business case theme?

A.

To specify the solution to be used to deliver the business option selected

B.

To ensure the corporate business plan is updated with the project costs and benefits

C.

To define the management actions required to ensure the project's outcomes are achieved

D.

To integrate the benefits management approach with the project and stage plans

Full Access
Question # 11

Within which integrated element does PRINCE2 set minimum requirements?

A.

Themes

B.

Processes

C.

Principles

D.

Project environment

Full Access
Question # 12

To meet the minimum requirements for applying the progress theme, what must be considered?

A.

How lessons will be learned

B.

How time-driven reports will be produced

C.

Which management products will be baselined

D.

Who is responsible for reporting on progress

Full Access
Question # 13

Which statement describes the 'Implement' step within the recommended risk management procedure?

A.

Take planned action to respond to a risk

B.

Implement the responsibilities for risks defined in the Risk Management Strategy

C.

Assess the proximity of a risk

D.

Identify the level of risks that can be tolerated by the project

Full Access
Question # 14

What must be included in the risk management approach, as a minimum requirement for applying the risk theme?

A.

A description of the risk management procedure

B.

An explanation of the company's risk appetite

C.

The names of the assigned actionees for each risk

D.

Estimations of the likelihood and impact of risks

Full Access
Question # 15

Why is the 'initiating a project' process used?

A.

To decide which project approach is suitable for the project

B.

To fully understand how the project objectives will be achieved before committing significant resources

C.

To produce the required work packages

D.

To enable corporate or programme management to give authorization to deliver a project

Full Access
Question # 16

How is the tailoring approach defined for a project?

A.

The project board approves the approach

B.

The project board documents the approach

C.

Project assurance approves the approach

D.

Project assurance documents the approach

Full Access
Question # 17

As a minimum requirement for applying the risk theme, what must specifically be assessed?

A.

Whether a risk may cause the project to exceed its cost tolerance

B.

Whether a risk may affect the project-level quality tolerances

C.

Whether a risk may impact the underlying technical assumptions

D.

Whether a risk may alter the project's business justification

Full Access
Question # 18

Which PRINCE2 principle is being applied when tolerances are set for the three levels of plan?

A.

Manage by stages

B.

Manage by exception

C.

Continued business justification

D.

Learn from experience

Full Access
Question # 19

Where should a team manager look for information about the quality required for a product?

A.

Project initiation documentation

B.

Product description

C.

Team plan

D.

Quality management approach

Full Access
Question # 20

Which describes a risk event?

A.

The area of uncertainty in terms of the threat or opportunity

B.

The derivation or sources of a potential risk to the project

C.

The achievement of a milestone on the project plan

D.

The sequence of events and actions that will be put in place if a risk occurs

Full Access
Question # 21

Where should decisions regarding the tailoring of the project be recorded?

A.

Project brief

B.

Project initiation documentation

C.

Project mandate

D.

Stage plan

Full Access
Question # 22

Which is a purpose of the plans theme?

A.

To identify, assess and control any potential changes to the baseline

B.

To establish the project's structure of accountability

C.

To assess and control uncertainty

D.

To understand whether the targets are achievable

Full Access
Question # 23

Which are advantages of a clear end to a project?

1. No further costs will be incurred by the project

2. Project products will be transferred to operations and support

3. All benefits will have been achieved

4. The project brief will be re-baselined

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 24

Which is a responsibility of a risk owner?

A.

Identify risks to the project that might occur in their department

B.

Own and authorize the use of the risk budget to fund risk responses

C.

Manage, monitor and control all aspects of an assigned risk

D.

Determine project risk appetite

Full Access
Question # 25

What is a supplier of a PRINCE2 project responsible for?

A.

Providing the project mandate

B.

Providing resources to deliver the project outputs

C.

Establishing the project's governance

D.

Realizing the benefits from the project

Full Access
Question # 26

Which of the following is the Business Case used for during the Managing a Stage Boundary process?

A.

Enable the Project Board to decide whether or not to authorize the project

B.

Justify the continuing viability of the project

C.

Enable the Project Board to decide whether or not to authorize project closure

D.

Justify the initiation of a project

Full Access
Question # 27

Which document should record the agreed amount of risk budget for a project?

A.

Project Brief

B.

Project Plan

C.

Risk Management Strategy

D.

Risk Register

Full Access
Question # 28

Which is a purpose of the Managing a Stage Boundary process?

A.

Provide the Project Board with sufficient information for approving the next stage

B.

Approve the next Stage Plan

C.

Review and close any risks and issues identified during the previous stage

D.

Control the link between the Project Manager and the Team Manager(s)

Full Access
Question # 29

Which is the first task of PRINCE2's recommended approach to 'defining and analyzing the products'?

A.

Creating a product flow diagram

B.

Writing the product description

C.

Writing a project product description

D.

Documenting the plan

Full Access
Question # 30

During the Managing a Stage Boundary process what product is updated with estimated costs and time for the stage that is about to begin?

A.

End Stage Report

B.

Team Plan

C.

Work Package

D.

Project Plan

Full Access
Question # 31

Which should be provided by corporate or programme management before the Starting up a Project process commences?

A.

A Project Brief

B.

Sufficient information to identify the prospective Executive

C.

The Project Initiation Documentation

D.

Authority to initiate a project

Full Access
Question # 32

Which describes risk probability?

A.

Level of risks which the project can tolerate before escalating to the Project Board

B.

Probable effect on the project delivering its objectives

C.

Timeframe within which the risk may occur

D.

A measure of the likelihood of the risk occurring

Full Access
Question # 33

Which is a purpose of the change theme?

A.

To prevent change to baselined products

B.

To identify, assess and control any potential and approved changes to baselined products

C.

To establish mechanisms to monitor and compare actual achievements against those planned

D.

To assess and control uncertainty

Full Access
Question # 34

Which process provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification?

A.

Controlling a Stage

B.

Closing a Project

C.

Directing a Project

D.

Managing a Stage Boundary

Full Access
Question # 35

Which is an objective of the 'directing a project' process?

A.

To review and approve a project mandate

B.

To ensure corporate or programme management has an interface to the project

C.

To define how risks, issues and changes will be managed

D.

To obtain approval for completed products

Full Access
Question # 36

Which is a purpose of the Controlling a Stage process?

A.

Produce a Team Plan for the work to be assigned to a Team Manager

B.

Select and implement actions that will resolve deviations from a plan within tolerance

C.

Obtain approvals for products delivered in a Work Package

D.

Update a Project Plan to incorporate the actuals from a Stage Plan

Full Access
Question # 37

Identify the missing words in the following sentence. At the end of a stage, the [ ? ] should be used to check whether there is a requirement to send copies of the End Stage Report to external interested parties.

A.

Stage Plan

B.

Communication Management Strategy

C.

Follow-on action recommendations

D.

Quality Management Strategy

Full Access
Question # 38

Which role is responsible for creating Checkpoint Reports?

A.

Senior Supplier

B.

Team Manager

C.

Change Authority

D.

Project Support

Full Access
Question # 39

Which statement about the Directing a Project process is true?

A.

Provides a mechanism for the Project Board to assure that there is continued business justification

B.

Covers the day-to-day activities of the Project Manager

C.

Ensures there are regular progress meetings

D.

Begins on completion of the Initiating a Project process

Full Access
Question # 40

Which is NOT included in the PRINCE2 definition of a project?

A.

A project is a temporary organization

B.

A project's purpose is to deliver one or more business products

C.

A project is part of 'business as usual'

D.

A project is based on an agreed Business Case

Full Access
Question # 41

Which is an objective of the Directing a Project process?

A.

Create and authorize the project mandate

B.

Provide management control and direction

C.

Control the day-to-day running of the project

D.

Provide accurate progress information to the Project Manager

Full Access
Question # 42

Which is a true statement about acceptance criteria?

A.

Acceptance criteria are used to produce the customer's quality expectations

B.

Acceptance criteria are less specific and precise than customer's quality expectations

C.

Once agreed, acceptance criteria CANNOT be changed

D.

Acceptance criteria should be agreed between the customer and the supplier

Full Access
Question # 43

Whose approval is needed to replace a Stage Plan with an Exception Plan?

A.

Corporate or programme management

B.

Project Board

C.

Project Manager

D.

Team Manager

Full Access
Question # 44

Which is NOT a purpose of the Organization theme?

A.

Define a project management team structure

B.

Define the level of tolerance for each level of the project management team

C.

Define the Project Board's responsibility for directing the project

D.

Define which role is accountable for the project's success

Full Access
Question # 45

Which project management team member represents the interest of those who will operate the project's products to realize the benefits after the project is complete?

A.

Executive

B.

Senior User

C.

Senior Supplier

D.

Project Manager

Full Access
Question # 46

Which characteristic distinguishes a project from regular business operations?

A.

Produces benefits

B.

Introduces business change

C.

Manages stakeholders

D.

Incurs cost

Full Access
Question # 47

Identify the missing word in the following sentence. The guiding obligations and good practices which determine whether the project is genuinely being managed using PRINCE2 form the [ ? ] of the method.

A.

Principles

B.

Themes

C.

Processes

D.

Techniques

Full Access
Question # 48

Which of the following statements about customer's quality expectations and acceptance criteria are true?

1. Customer's quality expectations form a specific and precise list of measurable criteria that a project product should meet in order to be acceptable to key stakeholders.

2. Acceptance criteria are often expressed in broad terms as a means to gain common understanding of general quality requirements.

A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 are true

Full Access
Question # 49

A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?

A.

Raise a request for change

B.

Raise an off-specification

C.

Write an Exception Report

D.

Amend the Work Package

Full Access
Question # 50

What needs to be in place to ensure effective issue and change control?

A.

Configuration management system

B.

Manage by exception

C.

Quality planning

D.

Information needs for stakeholders

Full Access
Question # 51

What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?

A.

Directing a Project

B.

Controlling a Stage

C.

Managing a Stage Boundary

D.

Managing Product Delivery

Full Access
Question # 52

Which is part of quality control?

A.

Document the project's acceptance criteria in the Project Product Description

B.

Define the quality responsibilities of those involved in the production of the products

C.

Produce quality records to show that the planned quality activities have been carried out

D.

Maintain the corporate organization's quality management system

Full Access
Question # 53

Which aspect of project performance must be managed to ensure the project's products are fit for purpose?

A.

Benefits

B.

Quality

C.

Risk

D.

Scope

Full Access
Question # 54

Which is a true statement about PRINCE2 event-driven controls?

A.

Event-driven controls take place at predefined periodic intervals

B.

Event-driven controls are produced at the frequency defined in a Work Package

C.

Event-driven controls are used for decision making

D.

Checkpoint Reports are event-driven controls

Full Access
Question # 55

Which step in the issue and change control procedure considers alternative options for responding to an issue that is being managed formally?

A.

Capture

B.

Examine

C.

Propose

D.

Decide

Full Access
Question # 56

Which is a purpose of the Directing a Project process?

A.

Create and authorize the project mandate

B.

Ensure that work on products allocated to the team is authorized and agreed

C.

Control the day-to-day running of the project

D.

Delegate day-to-day management of the project to the Project Manager

Full Access
Question # 57

Identify the missing word(s) in the following sentence. The Quality theme provides a set of rules and procedures which ensure that the [ ? ] created meet(s) the needs of the business.

A.

controls

B.

products

C.

project management team

D.

stages

Full Access
Question # 58

What process aims to ensure accurate progress information is provided to the Project Manager?

A.

Starting up a Project

B.

Managing a Stage Boundary

C.

Managing Product Delivery

D.

Directing a Project

Full Access
Question # 59

Which is an objective of the Managing Product Delivery process?

A.

Sign-off completed Work Packages

B.

Ensure the Business Case is kept under review

C.

Report progress to the Project Board

D.

Ensure that work on products is authorized and agreed with the team

Full Access
Question # 60

Which is a purpose of the Directing a Project process?

A.

Provide the information required to confirm if it is worthwhile to initiate a project

B.

Enable overall control of a project to be exercised by the Project Board

C.

Establish the level of control required by the Project Board after initiation.

D.

Provide sufficient information so that the current stage can be reviewed and the next Stage Plan approved

Full Access
Question # 61

Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system?

A.

Corporate group

B.

Project Board

C.

Project Assurance

D.

Executive

Full Access
Question # 62

Which is NOT a purpose of a Benefits Review Plan?

A.

Define the period over which the cost-benefit analysis will be based

B.

Describe how to measure the performance of the project's products in operational use

C.

Define the scope, timing and ownership of the benefit reviews required

D.

Describe how to measure and confirm any benefits that are to be realised after the project is closed

Full Access
Question # 63

Who should act as the communication channel between a project and corporate or programme management?

A.

Project Board

B.

Project Assurance

C.

Project Manager

D.

Project Support

Full Access
Question # 64

Which of the following statements about lines of authority and reporting are true?

1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.

2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.

A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 are true

Full Access
Question # 65

What theme estimates the cost of delivering the project?

A.

Business Case

B.

Change

C.

Plans

D.

Progress

Full Access
Question # 66

Which is an objective of the Closing a Project process?

A.

Review and approve the plan for project closure

B.

Review the performance of the project against its baseline

C.

Perform any post-project reviews

D.

Create a Benefits Review Plan

Full Access
Question # 67

Why is it crucial that the Project Product Description clearly defines acceptance methods?

A.

Enables Project Assurance to authorize quality activities

B.

Defines how all project products will be reviewed and approved

C.

Defines how it will be proven that the completed project product meets the customer's expectations

D.

Provides confirmation that all project products have met their quality criteria

Full Access
Question # 68

Which product identifies the management stages and timescales of a project?

A.

Project Brief

B.

Project Product Description

C.

Project Plan

D.

Initiation Stage Plan

Full Access
Question # 69

Which is a difference between management and technical stages?

A.

Management stages require planning and technical stages do not

B.

Technical stages can overlap and management stages cannot

C.

Management stages deliver products and technical stages do not

D.

Technical stages require resources and management stages do not

Full Access
Question # 70

What is the first task of product-based planning?

A.

Produce the Initiation Stage Plan

B.

Write the Project Product Description

C.

Identify dependencies

D.

Create the product breakdown structure

Full Access
Question # 71

Which is an objective of the 'controlling a stage' process?

A.

To review the business justification for the project

B.

To replan the current stage when directed

C.

To develop products to defined quality criteria

D.

To produce a learn plan for the work package

Full Access
Question # 72

What is the result of the change derived from using the project’s product?

A.

Benefit

B.

Dis-benefit

C.

Outcome

D.

Output

Full Access
Question # 73

When is the 'managing a stage boundary' process used?

A.

Immediately alter the project board has authorized the previous stage

B.

Immediately after the project board has authorized the next stage

C.

Near the end of each stage

D.

Near the end of delivery stages

Full Access
Question # 74

What should be recorded in a quality register?

1. Activities to ensure the products are fit for purpose

2. Identified threats and opportunities

3. Problems and concerns to be managed informally

4. Roles responsible for reviewing the project's products

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 75

Which is a purpose of the 'directing a project' process?

A.

To create and authorize the project mandate

B.

To ensure that work on products allocated to the team is authorized and agreed

C.

To control the day-to-day running of the project

D.

To delegate day-to-day management of the project to the project manager

Full Access
Question # 76

What is an advantage of dividing the project into stages?

A.

Detailed plans can be prepared closer to the time events will take place

B.

the project board can delegate management of the project to team managers

C.

The project can be authorized by the project manager on a stage by stage basis

D.

The project brief can be updated towards the end of each stage

Full Access
Question # 77

What is an advantage of applying the 'manage by stages' principle?

A.

The PRINCE2 method can be used for any type of project

B.

The project delivers benefits that are aligned with strategic objectives

C.

The project has decision points so that it does not run on in an uncontrolled manner

D.

Tolerances can be defined for delegated authority

Full Access
Question # 78

Which statement about applying the 'tailor to suit the project' principle is CORRECT?

A.

PRINCE2 can be tailored to be used with any type of project

B.

A technically complex project should NOT tailor PRINCE2

C.

The tailoring of PRINCE2 is MOST appropriate for agile projects

D.

A project which is part of a programme should NOT tailor PRINCE2

Full Access
Question # 79

Identify the missing word in the following sentence relating to one of the principles:

A PRINCE2 project should have [?] defined for each project objective.

A.

themes

B.

principles

C.

processes

D.

tolerances

Full Access
Question # 80

Which process has the objective of confirming that acceptance criteria have been met?

A.

Controlling a stage

B.

Directing a project

C.

Managing product delivery

D.

Closing a project

Full Access
Question # 81

In which process is the work to be done assigned to a team manager?

A.

Directing a project

B.

Managing a stage boundary

C.

Controlling a stage

D.

Managing product delivery

Full Access
Question # 82

Which is an assumption about the PRINCE2 customer/supplier environment?

A.

The supplier will pay for the project

B.

The customer will provide the resources to deliver the products

C.

The customer will specify the desired result

D.

The supplier will tailor the project's application of PRINCE2

Full Access
Question # 83

Identify the missing words in the following sentence.

Project assurance personnel [ ? ] the project manager.

A.

are able to overturn the decisions of

B.

must be accountable to

C.

should support

D.

report to the project board and

Full Access
Question # 84

What is documented in the project plan to support the 'manage by exception' principle?

A.

The project's tolerances for cost and time

B.

A project product's quality criteria

C.

The expected project benefits

D.

Activities to mitigate project risks

Full Access
Question # 85

How often should the 'controlling a stage' process be used during a project?

A.

Once, for the whole project

B.

For each delivery stage in the project

C.

Whenever the project board meets

D.

Twice, for initiation and for the rest of the project

Full Access
Question # 86

Which activity is part of the recommended risk management procedure?

A.

Allocating a budget to investigate issues

B.

Reviewing risk management practices to ensure that they are performing effectively

C.

Sending information to stakeholders about risks to the projects

D.

Resolving conflicts between the project and the programme board

Full Access
Question # 87

Which process is used by the project board to respond to on exception report?

A.

Controlling a stage

B.

Managing a stage boundary

C.

Managing product delivery

D.

Directing a project

Full Access
Question # 88

Which is a purpose of the quality theme?

A.

To establish how the project will ensure that all products created meet their requirements

B.

To establish baselines against which any changes to products can be assessed

C.

To identify all the products of the project to ensure the scope has been adequately defined

D.

To determine the communication needs of the organization’s quality assurance function

Full Access
Question # 89

Which term is defined-as the amount and type or risk that the business is willing to take in pursuit of is objectives?

A.

Risk appetite

B.

Opportunity

C.

Risk tolerance

D.

Risk cause

Full Access
Question # 90

Identify the missing word in the following sentence.

[ ? ] is the measurable decline resulting from a negative outcome.

A.

An exception

B.

A dis-benefit

C.

An off-specification

D.

A risk

Full Access
Question # 91

Which management level should approve a course of action if project-level tolerance is exceeded?

A.

Corporate, programme management or the customer

B.

Project board

C.

Project manager

D.

Team manager

Full Access
Question # 92

What is a goal of the 'implement' step within the recommended risk management procedure?

A.

To prepare specific management responses to identified risks

B.

To monitor the effectiveness of actioned risk responses

C.

To estimate the risk to the project in terms of probability and impact

D.

To communicate information related to the risks faced by the project

Full Access
Question # 93

Which is an objective of the ‘directing a project’ process?

A.

To tailor the project’s products and roles so that the project suits the circumstances

B.

To respond to the project mandate by starting up a project

C.

To provide an interface between the project and corporate management

D.

To ensure the stage products are delivered to the stated quality standards

Full Access
Question # 94

Which is a benefit of using PRINCE2?

A.

It promotes consistency of project work and the ability to reuse project assets.

B.

It includes techniques for critical path analysis and earned value analysis

C.

It enables a project manager to be accountable for the success of a project

D.

It prevents any changes once the scope of a project has been agreed

Full Access
Question # 95

What should be implemented using a risk budget?

1. A request for change

2. A contingent plan

3. Actions to avoid a risk from occurring

4. Responses to dis-benefits

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 96

What is established during the 'initiating a project' process?

A.

The agreed protect acceptance criteria

B.

The need for a configuration library

C.

A plan for the work or project initiation

D.

An understanding of the project's funding

Full Access
Question # 97

What is the minimum number of management stages required by PRINCE2?

A.

Two stages: to initiate and to deliver the project

B.

One stage: to cover the whole project

C.

Three stages: to initiate, to deliver and to close the project

D.

Four stages: to start, to initiate, to deliver and to close the project

Full Access
Question # 98

According to the ‘continued business justification’ principle, what should happen to the funds when a project can no longer be justified?

A.

They should be returned to corporate, programme management or customer

B.

They should be used to create an alternative business case for the project

C.

They should be transferred back to the project board to reassign

D.

They should be used to deliver a reduction in the scope of the project

Full Access
Question # 99

Which statement is CORRECT about the customer and suppliers of a project in a commercial environment?

A.

Each party may have their own business case for undertaking the project

B.

Both parties must apply the same external governance to the project

C.

The risk appetite should be collaboratively set before the project starts

D.

Management systems need to be unified for successful project delivery

Full Access
Question # 100

What should the benefits management approach define?

A.

What actions will be taken to ensure the project's outcomes are achieved

B.

What will be used to record the effectiveness of the project's approaches

C.

How the project has progressed against its plans

D.

The suitability of the project management team structure

Full Access
Question # 101

Which TWO are objectives of the ‘controlling a stage process?

1. To focus attention on achieving Work Within) the agree tolerances

2. To create follow on action recommendations for all open issues and risks

3. To understand how the quality required will be achieved

4. To ensure that the stage’s products meet-agreed quality expectations

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 102

What process provides information on a team’s work to the project manager?

A.

Controlling a stage

B.

Directing a project

C.

Managing a stage boundary

D.

Managing product delivery

Full Access
Question # 103

How does PRINCE2 ensure that the specific management needs of an organization are met?

A.

By incorporating tailoring

B.

By mandating training

C.

By focusing on viability

D.

By representing best practice

Full Access
Question # 104

How are team managers involved in tailoring PRINCE2 suit the project?

A.

Team managers are accountable for the tailoring of the work packages

B.

Team managers may advice on tailoring to improve the management of work packages

C.

Team managers should not be involved in tailoring PRINCE2

D.

Team managers should document the tailoring of the work packages

Full Access
Question # 105

What 15the purpose of the ‘progress! practice?

A.

To review whether the use of the products is likely to lead to the expected benefits

B.

To define the roles and responsibilities for monitoring progress

C.

To measure actual achievements against the planned time and cost targets for the project

D.

To control events that could have a positive or negative effect on project objectives

Full Access
Question # 106

In which process should the specified quality methods he used to/prove that a product meets its quality criteria?

A.

Managing product delivery

B.

controlling a stage

C.

Managing a stage boundary

D.

closing a project

Full Access
Question # 107

Which should define how tools will be used to support the information needs of the project team?

A.

Digital and data management approach

B.

Quality management approach

C.

Issue management approach

D.

Commercial management approach

Full Access
Question # 108

Which is a description of a purpose of the 'managing product delivery’ process?

A.

To agree requirements for the delivery of specific products between the project manager and the team manager

B.

To report progress towards the delivery of a stage’s products to the project board

C.

To recognize that the project has no further contribution make towards achieving project objectives

D.

To plan how the project will approach the work to deliver the project products

Full Access
Question # 109

In which step of the 'risk management technique should the organization's environment be considered?

A.

Identify

B.

Assess

C.

Plan

D.

Implement

Full Access
Question # 110

Which control is time-driven?

A.

The creation of a highlight report

B.

The completion of the PID

C.

The creation of an exception report

D.

The end of the financial year

Full Access
Question # 111

The project manager needs to define key information so that the project board can decide whether to proceed with planning the project in more detail.

In which process should the project manager define this information?

A.

Starting up a project

B.

Initiating a project

C.

Directing a project

D.

Managing a stage boundary

Full Access
Question # 112

According to the ‘manage by exception’ principle, which aspect of performance sets limits against the cost of aggregated threats?

A.

Risk

B.

Scope

C.

Quality

D.

Cost

Full Access
Question # 113

How is uncertainty identified, assessed and controlled?

A.

By avoiding or reducing a threat

B.

By analysing the risk cause in detail

C.

By applying the risk practice

D.

By allocating a risk budget to the project

Full Access
Question # 114

Which TWO are objectives of the ‘starting up a project’ process?

1. To provide an interface between the corporate layer and the project

2. To provide the required authority to initiate the project

3. To plan the work required for project initiation

4. To provide business justification for initiating the project

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 115

According to the 'manage by exception’ principle, which statement about tolerances is CORRECT?

A.

Whenever authority is delegated to the project manager, the project board should set tolerances for the stage

B.

Whenever there is a forecast to exceed a tolerance, it should be escalated to the project board

C.

Whenever there is a forecast to exceed a tolerance, it should be resolved at the next monthly project board meeting

D.

Whenever authority is delegated to the team manager, the focus should be on delivering within time and cost tolerances

Full Access
Question # 116

Which action should the project manager take when reviewing progress to assess the 'health' of a stage?

A.

Capture lessons that may assist in the monitoring and control of this project

B.

Review the quality of the relationships in the organizational

C.

Increase the frequency of event-driven controls to monitor stage progress

D.

Identify whether issues are resolved in a timely manner or left unmanaged

Full Access
Question # 117

Which describes a management activity within a project?

A.

Encouraging a project team to continue working on a particularly challenging product

B.

Discussing project objectives with key stakeholders during a requirements gathering workshop

C.

Agreeing a work package with a team manager to deliver products within agreed tolerances

D.

Seeking feedback from team members to ensure they are still aligned to the project's objectives

Full Access
Question # 118

The project manager needs to know whether the response to a threat to the project has been actioned.

Which should the project manager review?

A.

Risk register

B.

Product register

C.

Risk management approach

D.

Checkpoint report

Full Access
Question # 119

Which statement BEST describes how approved plans enable control?

A.

By defining the quality specifications of individual products in product descriptions

B.

By enabling the controlled consideration of business opportunities

C.

By defining the benefits that need to be realized through the benefits management approach

D.

By defining what is within the approved project scope to avoid scope creep

Full Access
Question # 120

The senior user needs to ensure that the outputs will be used effectively to achieve the autcomes and realize the benefits.

Which element of effective business case management is the senior user applying?

A.

Aligning products to business objectives and tolerances

B.

The business case lifecycle

C.

Establishing business justification

D.

Planning benefit reviews during the project

Full Access
Question # 121

Which is the definition of a requirement?

A.

A need or expectation that has been documented in an approved management product

B.

An event relevant to the project that requires project management consideration

C.

A prediction about future performance made by studying historical data and past patterns

D.

An uncertain event that, should it occur, will have an effect on the project.

Full Access
Question # 122

What is a temporary organization that is treated for the purpose of delivering Business Products according an-agrees business casa?

A.

A project

B.

A baselined product

C.

The project scope

D.

The business

Full Access
Question # 123

Which statement about capability and competency within a project is CORRECT?

A.

People who appear to have the same skills and experience will probably undertake the same tasks in different ways

B.

People within a team will perform equally when working with different people

C.

People who have participated in developing ways of working are more willing to be managed

D.

People working as team members often have conflicting priorities contrary to the project's needs

Full Access
Question # 124

The project manager needs to record what will make file Users satisfied with the final product

Where should the project manager record this?

A.

Quality register

B.

Project plan

C.

Project product description

D.

Quality management approach

Full Access
Question # 125

Which statement about the 'manage by stages’ principle is CORRECT?

A.

The project board should authorize multiple stages at the same time

B.

The end of a stage should provide a control point for the project board

C.

A project should have fewer, longer stages when the risk exposure is high

D.

A project should have separate stages to plan, deliver and close the project

Full Access
Question # 126

The project manager needs to document how risk management will be undertaken during the project.

In which step of the 'risk management’ technique should the project manager document this?

A.

Identify: define context and objectives

B.

Identify: identify threats and opportunities

C.

Assess: prioritize risks

D.

Assess: combine risk profile

Full Access
Question # 127

Which is a description of a purpose of the communication management approach?

A.

To document for stakeholders the future business required to meet project objectives

B.

To document how the project team should control its interactions with stakeholders

C.

To document how to use financial incentives to motivate project team members

D.

To document the responsibilities of project team members for testing whether products are acceptable to users

Full Access
Question # 128

The project manager has proposed that a request for change be implemented, but the change authority has asked for more information.

In which step of the ‘issue management technique should the change authority request this information?

A.

Deciding on changes

B.

Implementing changes

C.

Assessing issues

D.

Capturing issues

Full Access
Question # 129

What is being addressed when the project manager plans to keep the CO2 emissions of the project aligned with the business strategy?

A.

Benefits sustainability

B.

Product sustainability

C.

Delivery sustainability

D.

Quality sustainability

Full Access
Question # 130

As part of the 'business case management’ technique, how is the business case maintained during the project lifecycle?

A.

By linking the outcomes and benefits to the business objectives included in the business case

B.

By updating the business case during each management stage, as actual costs are incurred

C.

By providing a robust justification for the entire project in a detailed business case

D.

By justifying to the project board that the project should be initiated

Full Access
Question # 131

Which TWO are objectives of the 'managing a stage boundary" process?

1. To confirm to the project board that there are no products outstanding for the stage

2. To ensure that expectations are managed via accurate reporting to the project manager during a stage

3. To ensure that the project management team is not distracted by delivering additional products during the stage

4. To request the project board to approve work to start on the next stage

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 132

What is the BEST reason to perform the risk practice?

A.

To ensure risks are assigned to people who will own and action them satisfactorily

B.

To establish a supportive risk culture to enable decision-making

C.

To ensure stop-go decisions at stage boundaries are risk-informed

D.

To identiDfy and manage risks to project objectives

Full Access
Question # 133

Which is definition of culture?

A.

The set of shared attitudes, values, goals, and ways of working that characterize a group of people

B.

The process when people from across the project ecosystem work together

C.

An essential aspect of project management that needs to be continually addressed

D.

The tailoring required to take into account the complexity or simplicity of a project

Full Access
Question # 134

What does qualitative analysis of a risk assess, as a minimum?

A.

How soon each risk might occur

B.

The fallback plan for each risk

C.

The likelihood and the effect of each risk on objectives

D.

The speed with which the effect of each risk will be felt

Full Access
Question # 135

The project manager needs to record the impact assessment for a specific business opportunity.

In which management product should the project manager record this?

A.

Issue report

B.

Issue register

C.

Risk register

D.

Quality register

Full Access
Question # 136

Which describes user's quality expectations?

A.

They are documented in the project product description

B.

They are documented in the quality management approach

C.

They are documented in the stage plan

D.

They are documented in the product descriptions

Full Access
Question # 137

Which term is defined as the means by which an organization transitions to a desired future state?

A.

Change management

B.

Risk management

C.

Issue management

D.

Communication management

Full Access
Question # 138

Identify the missing word in the following sentence.

An (?) is the result of change, normally affecting real-world behavior and circumstances:

A.

outcome

B.

exception

C.

output

D.

off-specification

Full Access