Weekend Sale - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: mxmas70

Home > PRINCE2 > PRINCE2 Agile > PRINCE2-Agile-Foundation

PRINCE2-Agile-Foundation PRINCE2 Agile Foundation (Version 2) Exam Question and Answers

Question # 4

What is typically displayed on a board to show progress to people working on a project?

A.

Agilometer assessment

B.

Product backlog

C.

Information radiator

D.

User story

Full Access
Question # 5

Which of the following is used to monitor progress?

A.

Delegation matrix

B.

Swarming

C.

T-shirt sizing

D.

Burn-down chart

Full Access
Question # 6

Which is a collaborative technique for defining decision-making within teams?

A.

Delegation poker

B.

Team skills matrix

C.

Personas

D.

Magic estimation

Full Access
Question # 7

How does PRINCE2 Agile describe Scrum?

A.

Scrum is an IT method

B.

Scrum is agile and agile is Scrum

C.

Scrum is the most well-known agile framework

D.

Scrum is a project management framework

Full Access
Question # 8

In Lean Startup, what is based on the concept of ‘learn the most with the least effort’?

A.

A structured, timeboxed event

B.

A minimum viable product

C.

A measurement of lead times

D.

A set of criteria to determine whether work can be started

Full Access
Question # 9

Which statement BEST describes the PRINCE2 Agile guidance for change?

A.

The delivery team should be authorized to make changes at the detailed level

B.

The delivery team should quickly approve changes to the project baseline

C.

The executive should manage changes dynamically at the detailed level

D.

The executive should approve delivery level changes to harness the benefits of positive change

Full Access
Question # 10

When should PRINCE2 Agile be used?

A.

When a team is created to deliver a specific product

B.

When delivering an ongoing service to a customer

C.

When an established team performs product maintenance

D.

When simple requests to update a product are implemented

Full Access
Question # 11

How should product-based planning be used as part of PRINCE2 Agile?

A.

To track progress against the team plan

B.

To create the project plan using empiricism

C.

To enable team planning to be predictive

D.

To plan by focusing on the features required

Full Access
Question # 12

Which statement defines a PRINCE2 principle?

A.

A PRINCE2 project defines its quality management approach

B.

A PRINCE2 project is monitored and controlled on a stage-by-stage basis

C.

A PRINCE2 project ensures a consistent approach to risk management

D.

A PRINCE2 project is tailored to suit the competitor’s environment

Full Access
Question # 13

In which area is Agile strongest when blending with PRINCE2?

A.

Product delivery

B.

Project management

C.

Project direction

D.

Product management

Full Access
Question # 14

What does velocity typically measure?

A.

Work packages completed by the team

B.

The rate of progress the team is making

C.

The number of timeboxes completed

D.

The speed that a minimum viable product is created

Full Access
Question # 15

Which is a reason for releasing a product into a staging area?

A.

It enables the faster delivery of changes

B.

It supports regulatory compliance checking

C.

It enables a phased Waterfall approach

D.

It supports management by exception

Full Access
Question # 16

Which two statements are key responsibilities of supplier representative?

1. They highlight areas that the project may impact from a technical perspective.

2. They are partially assigned to the delivery team.

3. They create the project's specialist products.

4. They prioritize requirements.

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 17

How are user inputs FIRST gathered in the 'quality' practice?

A.

As user stories in the product backlog

B.

As epic user stories in the project backlog

C.

As the project Definition of Done in the quality management approach

D.

As a quality control activity in the quality register

Full Access
Question # 18

Which process can take place during a release review workshop?

A.

Controlling a stage

B.

Managing product delivery

C.

Managing a stage boundary

D.

Directing a project

Full Access
Question # 19

In Scrum, what answers the question ‘what can be done this sprint?’

A.

Daily scrum

B.

Sprint review

C.

Sprint planning

D.

Increment

Full Access
Question # 20

Which workshop enables participants to collaboratively define the Definition of Ready?

A.

Starting up workshop

B.

Project kickoff workshop

C.

Project initiation workshop

D.

Agile enablement workshop

Full Access
Question # 21

Which practice has the purpose of controlling uncertainties that would affect the project’s objectives?

A.

Plans

B.

Issues

C.

Quality

D.

Risk

Full Access
Question # 22

What is a good criterion to include in the Definition of Ready?

A.

The product is ready to hand over

B.

All components are complete

C.

Acceptance criteria are measurable

D.

The product has passed the quality checks

Full Access
Question # 23

Which statement about an epic is CORRECT?

A.

It can be broken down into user stories

B.

Its purpose is to document technical requirements

C.

It should appear at the top of a product backlog

D.

It contains sufficient granularity to allow work to start

Full Access
Question # 24

What is typically added to a user story as the understanding of the requirement evolves?

A.

An epic

B.

Acceptance criteria

C.

Definition of ‘ready’

D.

Effort actually expended

Full Access
Question # 25

Which role is responsible for facilitating the Agilometer assessment?

A.

Project board

B.

Project manager

C.

Team manager

D.

Customer subject matter expert

Full Access
Question # 26

How does the change theme regard change in PRINCE2 Agile?

A.

As disruptive

B.

As something to be avoided

C.

As a necessity

D.

As inevitable

Full Access
Question # 27

Which statement about velocity is CORRECT?

A.

It is based on the concept of rationalism

B.

It is shown by the ideal line on a bum-down chart

C.

It describes how much work is getting done

D.

It tracks the time and cost of a timebox

Full Access
Question # 28

Which statement describes how the PRINCE2 ‘starting up a project’ process can be applied in an agile environment?

A.

PRINCE2 is predictive, but not emergent

B.

PRINCE2 is predictive and can be emergent

C.

PRINCE2 requires a lengthy start to a project

D.

PRINCE2 requires a disruptive start to a project

Full Access
Question # 29

What should the business case state about the minimum viable product (MVP)?

A.

When the MVP will be defined

B.

That the MVP must go into operational use

C.

What the MVP is

D.

That the MVP is the same as project viability

Full Access
Question # 30

What is an epic?

A.

A detailed user story with high business value

B.

The set of products handed over to the users

C.

A high-level user story that is quite broad or vague

D.

A prioritized list of requirements to be delivered in a sprint

Full Access
Question # 31

Which of the following is a challenge when merging project management and agile?

A.

No common ground in terminology

B.

No clear processes to follow

C.

Lack of guidance at delivery level

D.

Lack of guidance on doing agile

Full Access
Question # 32

Which workshop focuses on team growth and improvements in working practices?

A.

Project kickoff workshop

B.

Team retrospective workshop

C.

Progress review workshop

D.

Team planning workshop

Full Access
Question # 33

Why are team working agreement produced?

A.

To create structure so that the team manager can assess individual performance

B.

To evolve the effectiveness and behaviors of the self-organizing team by agreeing values

C.

To make the team rules visible to the project manager for monitoring purposes

D.

To ensure that the delivery team members comply with company policy

Full Access
Question # 34

How should team working agreements be created?

A.

By the supplier subject matter expert agreeing what should be included

B.

By the customer representative deciding what should be included

C.

By team members agreeing on what should be included

D.

By the project manager deciding what should be included

Full Access
Question # 35

When tailoring PRINCE2, what does PRINCE2 Agile guidance cover?

A.

How to adapt the PRINCE2 management products

B.

How to select which Agile framework should be favoured

C.

How to decide whether PRINCE2 is appropriate

D.

How to calculate the project budget and cost tolerance

Full Access
Question # 36

Which is a purpose of the quality theme?

A.

To define the specific conditions that enable a product to be usable

B.

To determine how the means of delivering products is communicated

C.

To evaluate whether the project continues to be achievable

D.

To assess any potential improvements to a product

Full Access
Question # 37

Which of the following is a prioritized list of the requirements for a product?

A.

Project canvas

B.

Release map

C.

Project log

D.

Backlog

Full Access
Question # 38

Which PRINCE2 principle should be followed in order to engage the business, user and supplier stakeholder interests?

A.

Defined roles and responsibilities

B.

Continued business justification

C.

Learn from experience

D.

Tailor to suit the project

Full Access
Question # 39

What term is used to describe boards that display what work needs to be completed for people working on a project?

A.

Work in progress limit

B.

Information radiator

C.

Highlight report

D.

Glad! Sad! Mad!

Full Access