Pre-Summer Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: mxmas70

Home > PMI > Project-Management-Professional > PMP

PMP Project Management Professional (PMBOK 7th Version) Question and Answers

Question # 4

A project team is experiencing delays in completing a task that turned out to be more complex than initially estimated. This is a critical task that could impact current iteration goals

What two options will help the team initially address this obstacle? (Choose two)

A.

Escalate the issue to the project sponsor.

B.

Review and update dependencies

C.

Schedule a retrospective.

D.

Conduct a root cause analysis.

E.

Create a risk management plan.

Full Access
Question # 5

During a project review meeting, the project sponsor is worried that the protect may not be delivering results as planned Based on that the project manager is evaluating the project status. What information should the project manager use as an indicator that the project is actually delivering value?

A.

Stakeholders are satisfied with the current status.

B.

The project is under budget and on schedule

C.

The project is aligned with the project charter

D.

The protect is aligned with the benefits management plan

Full Access
Question # 6

While managing a project, the project manager has just noticed that the last several monthly invoices have been challenged by the client when they were clearly defined The actual invoice payments received have also been late and were outside of the contracted payment schedule Recent invoices have only been partially paid

What should the project manager do?

A.

Add nonpayment to the issue log and keep tracking payments

B.

Hold a meeting with the client to address the issue

C.

Review past projects for payment-related lessons learned

D.

Conduct a meeting with the project team to update the procurement management plan

Full Access
Question # 7

A project manager is working on a major construction project. Part of the

agreed-upon plan was to use a cloud-based system with a server that runs on high-speed

internet service since most of the team members work virtually. The company needs to

reduce operating costs as much as possible and management insists that the project will

now use a system running on a conventional dial-up service.

What should the project manager do next?

A.

Evaluate the impact of this decision and communicate with management.

B.

Agree with management and continue working the project management plan.

C.

Meet with management about their decision and ask them to get another project manager.

D.

Replace some of the team members that work virtually to help the company save money.

Full Access
Question # 8

A global company is executing a strategic project to upgrade a legacy enterprise system. The company uses a hybrid approach to project management and has just completed the first sprint A team member provided ideas to improve the testing process during the sprint retrospective.

What is the next step for the project manager?

A.

Document the lessons learned and implement improvements in the next sprint

B.

Facilitate a daily standup with the team to track the implementation of changes

C.

Organize a demonstration of the changes in the enterprise system

D.

Request that all team members think of ideas to improve processes.

Full Access
Question # 9

A project to add metro stations is being executed, with seven out of eight stations currently in place. Suddenly, a notification from the local community is received demanding the project be stopped. What should the project manager do first?

A.

Meet with project stakeholders to define a mitigation plan

B.

Register the issue and escalate it to the project sponsor

C.

Estimate the cost of changing the project location

D.

Execute the contingency plan defined in the risk management plan

Full Access
Question # 10

A product is facing performance issues that will significantly decrease the manufacturing yield expected, increasing the cost. This will be an issue as it will limit one of the high-margin contracted goals. Because it is a breakthrough development, the speed to market is key. What should the project manager do?

A.

Negotiate with operations to absorb the cost while the product is launched and remediate the issue.

B.

Engage with the sales team to increase the sales price since it is a breakthrough product.

C.

Evaluate the most cost-effective containment action and use their influence to implement it.

D.

Assess what corrective action is appropriate and use their influence to implement it.

Full Access
Question # 11

A project manager has been assigned to a project. The project deadline has been established but, based on the number of stakeholders to engage and interview, it will be difficult to complete the project within the timeline. How should the project manager address this challenge?

A.

Commit to completing the deliverables associated with only the engaged parties.

B.

Submit a change request to extend the time needed to engage all of the parties.

C.

Request that the product owner define which parties should be engaged first.

D.

Prioritize the engagement of parties who are most impacted to minimize project risk.

Full Access
Question # 12

A new team member joins the project and fails to apply the project-specific quality assurance (QA) processes. What should the project manager have done to avoid this issue?

A.

Obtained external training in QA for the new team member

B.

Delegated QA tasks to the team lead

C.

Made sure the new team member understood all requirements

D.

Ensured the new team member had access to the quality management plan

Full Access
Question # 13

A company started a project to create a new product that will be delivered in iterations. The artwork development plan included extensive consultation and validation before the build. The company changed the focus of the project to speed to market because one of their competitors announced the launch of a similar product. What should the project lead do?

A.

Work with the product owner to assess the impact and reprioritize the product backlog.

B.

Schedule a meeting with the project sponsor to identify and allocate additional resources.

C.

Submit a formal change request and obtain approval from the change control board (CCB).

D.

Meet with the Scrum Master to determine if the development cycle can be reduced.

Full Access
Question # 14

Due to delays on some activities one of the project team members has increased the scope without any approval What should the project manager do next?

A.

Remove the changes to match the original requirements.

B.

Add team members to the project to avoid more schedule delays.

C.

Evaluate the impacts of the changes that were made to the project

D.

Update project documentation with the new scope

Full Access
Question # 15

In an effort to modernize the technology for a project, the project manager has been discussing risk prioritization with the project team. The project manager determines that additional parameters are needed to iteratively assess and prioritize the project risks.

Match the project manager ' s goals on the left with the relevant risk parameter on the right.

Full Access
Question # 16

A project manager is leading a project in which the product requirements have not been fully met due to several uncertainties about customer acceptance. What should the project manager do?

A.

Gather a reduced number of approved requirements and add some extra features to fulfill the product specifications.

B.

Ask team members to research and collect data about the best features offered by similar products in the market.

C.

Stop all project activities until all requirements are set up front by the project sponsor and the key stakeholders.

D.

Gather enough requirements to produce a minimum viable product (MVP) with which to evaluate customer acceptance.

Full Access
Question # 17

A project manager has just been appointed to a project that has two major deliverables. Both deliverables have the same level of priority and are to be delivered at the same time. The members of the team are complaining about the lack of information regarding which deliverable needs to be finished first.

What should the project manager do?

A.

Ask key stakeholders to cancel the project due to the difficulty of executing both deliverables at the same time.

B.

Ask the team to start working on the easiest deliverable first so they gain experience to execute the second deliverable.

C.

Meet with the project sponsor and key stakeholders to assess each deliverable ' s value to the organization and set execution priorities.

D.

Require that the project team execute both deliverables at the same time, since this was requested and approved in the project charter.

Full Access
Question # 18

A typically high-performing team member has started to demonstrate a performance drop as well as some aggressive behaviors toward other team members in meetings.

The project manager has worked with this individual for many months on this project and has not seen this type of behavior before.

What should the project manager do?

A.

Discuss the project manager ' s observations with the individual to determine why they are behaving this way.

B.

Discuss the individual ' s behavior with the other team members to determine if they have noticed and know what is going on.

C.

Attend more team meetings to observe the team more closely to determine the root cause.

D.

Discuss their performance with the team member ' s functional manager as well as human resources (HR) and discuss next steps.

Full Access
Question # 19

A distributed project team has communication issues because of their collaboration tools. The team feels that efficiency could be improved by changing the collaboration platform.

What should the project manager do?

A.

Discuss this with the project team and select the appropriate tools.

B.

Inform the project team to continue using the current tools.

C.

Implement the communication tools used by other project teams.

D.

Escalate the issue to the sponsor and ask them to decide.

Full Access
Question # 20

A team member who is working on a critical project deliverable reported that their computer is not working. The IT department says that due to a high workload, they will not

be able to provide assistance for 1 week.

How should the project manager address this situation?

A.

Ask the team member to find an innovative solution or workaround to overcome the issue and avoid project delays.

B.

Schedule a meeting with the project sponsor to request a budget to buy or rent a new computer.

C.

Explore options with the IT department to expedite the necessary repairs based on criticality of the project.

D.

Use project reserves to buy new equipment to avoid an impact to the critical path of the project.

Full Access
Question # 21

A project manager brings in a new team member from an agile environment to work in a predictive environment The project manager expects to leverage the new team member ' s agile experience with the existing team members.

What should the project manager do to integrate the new team member effectively?

A.

Train the new team member in the predictive project management approach.

B.

Acknowledge that hiring this new employee is a risk to the existing team

C.

Set expectations with the new team member and explain what is needed

D.

Meet with all team members and explain the new employee ' s position.

Full Access
Question # 22

A project is delayed due to an undelivered component, which was caused by a conflict between the procurement lead and the contracts manager. The project manager

schedules a meeting with the two stakeholders to resolve the issue.

What role does the project manager play in this situation?

A.

Accommodator

B.

Mediator

C.

Arbitrator

D.

Conciliator

Full Access
Question # 23

In a construction project for a new building, the project manager decides to apply agile principles for the building foundation phase While evaluating the project schedule with the team, the project manager believes that the estimates are inaccurate. How should the project manager address this issue?

A.

Create a product backlog

B.

Perform sprint reviews with the team

C.

Assess the previous project velocity

D.

Reduce the story size by splitting stories

Full Access
Question # 24

An agile project has just started, and the backlog is being prioritized. The

customer wants to prioritize business value over identified risks.

How should the customer’s request be managed?

A.

Accept risks as they decrease over a period of time.

B.

Create a risk value profile to track the relative importance of risks.

C.

Log and track risks separately as only business value is important.

D.

Assess risks together with business value during prioritization.

Full Access
Question # 25

In a fixed time and budget project the customer wants the development of a core component to be based on agile practices, as the final scope of (he requirement has not yet been fully developed. The project manager is participating in contract development with the sales team and wants to ensure that development costs do not impact the profitability of the project.

Which two controls should the project manager incorporate into the contract to specifically address the development of the core component? (Choose two)

A.

Limit the number of iterations for development in the contract.

B.

Establish a governance committee to review the contract delivery

C.

Tier the contract for fixed and agile components

D.

Provide alternatives to scope change at specific project phases within the contract.

E.

Require that only internal resources be utilized for this project

Full Access
Question # 26

A project manager joins a startup and discovers that the chief technology officer (CTO) encourages the team to overlook some procedures in the interest of speed. What should the project manager do to ensure that all the procedures are followed in the future?

A.

Develop new procedures that are easy for the team to follow.

B.

Escalate the issue to the CEO and the board members.

C.

Instruct the team that the procedures should always be followed.

D.

Initiate a review of the procedures with the CTO and the team.

Full Access
Question # 27

A junior project manager with experience in predictive projects has joined a company that uses hybrid approaches for project delivery. A senior project manager with experience in hybrid approaches is assigned to be a coach. Match the activity descriptions on the left to the correct tools on the right.

Full Access
Question # 28

A project manager is leading a council ' s project that aims to ensure full compliance with health, ecological, and environmental standards.

At the same time, the project ' s goal is to remain fully adherent to the council ' s values, policies, and procedures.

How should the project manager ensure project success?

A.

Enforce the project manager ' s authority over the contracting partner delivering to the council. by

B.

Engage a third-party consulting firm to oversee the project ' s implementation.

C.

Develop the necessary implementation plan and ask the partners to adjust their plans to meet the project manager ' s objectives.

D.

Meet with the stakeholders regularly to share project objectives and mutually agree on common goals and plans.

Full Access
Question # 29

A project is nearing completion The contingency time has been consumed To ensure that the final deliverables are achieved fhin budget, the project manager has asked the team to follow a rigorous process This Is causing some resistance among the team members.

What should the project manager do to address the growing resistance?

A.

Crash the project schedule and ask project team members to work overtime to meet the new timeline

B.

Motivate project team members by offering incentives to complete the project on time

C.

Describe to the team members how specific tools and techniques can be used to finish on time

D.

Convince team members to use a specific methodology to complete the project on time

Full Access
Question # 30

A project manager is assigned to oversee the deployment of a new product that

will be used by the entire organization. A key success factor for the project is the timely

and successful adoption of the new solution by all entities.

What should the project manager do to ensure the success of this critical project?

A.

Considering the project scope and the multiple entities impacted by the solution,communicate with the stakeholders and ask them to adhere to the date.

B.

Ask the project sponsor to issue a directive requesting all business entities toaccept the date set for the new solution launch.

C.

Given the size of the organization and the multiple parties involved, discuss thelaunch date with the CEO and then communicate it to all entities.

D.

Engage in creative and iterative negotiations with the leaders of each entity toagree on the launch date.

Full Access
Question # 31

An ongoing project is facing a challenging situation where the customer is not satisfied. The team is new to agile development and frequently communicates with the customer and gives regular status reports. What should the project lead do to satisfy the customer?

A.

Reduce frequent communication and improve the status report format to include team progress

B.

Schedule a meeting with the customer and explain the team is new to agile and the situation will improve

C.

Review the situation with the customer and make the required adjustments with the team

D.

Review project progress with the customer and modify the frequency of sprint review

Full Access
Question # 32

A key team member shared confidential information about another team member with management, a practice that is against ethical standards. During a team meeting, some of the team members requested that the key team member be removed from the team.

What should the project manager do next?

A.

Contact the human resource (HR) department for a solution.

B.

Speak with the key team member to clarify the situation.

C.

Conduct a meeting with the team to deliberate on a decision.

D.

Suspend the team member until further notice.

Full Access
Question # 33

A project manager has taken over an existing project According to the previous project manager, the project is on track and within budget However, stakeholders are unhappy with the recent progress report since the metrics show that the project is delayed and the cost is higher than expected.

What should the project manager do?

A.

Schedule a meeting with the previous project manager

B.

Submit a change request to the change control board (CCB)

C.

Schedule training for project team members

D.

Conduct an earned value analysis (EVA)

Full Access
Question # 34

A project manager is assigned to a global project where, during the planning process, team members from different regions are not agreeing to collaborate with each other What should the project manager do?

A.

Review lessons learned from previous projects that used the same team

B.

Review the organizational culture, structure, and governance

C.

Coordinate a meeting to understand the situation and resolve any conflicts.

D.

Coordinate a meeting with regional managers to ask for support

Full Access
Question # 35

A project manager is worried that a key stakeholder is not participating in the project and has concluded that the final product is not as good as it could have been if the stakeholder had been more involved Drag the scenario on the left to the correct risk response strategy on the right

Full Access
Question # 36

According to the project contract the delivery date is approaching However one important material is still not on site The construction work will have to stop and wait for this special material, delaying the project.

What should the project manager do?

A.

Record it in the risk register

B.

Ask the client to help solve the problem

C.

Start procuring this material from another supplier.

D.

Engage the project team to look for alternatives to find a solution

Full Access
Question # 37

In a newly formed project team one experienced team member is overwhelmed by the complexity of the tasks and is not happy with the project team. What should the project manager do?

A.

Ask the team member to enter this potential schedule delay in the risk register.

B.

Explain that the tasks are unavoidable and ask the team member to find a solution to overcome the challenges

C.

Actively listen to the team member and identify ways to support their needs in completing the tasks.

D.

Set up team-building activities with the project team members to reduce tension

Full Access
Question # 38

A new team member inquires about how much they need to learn about the organizational process assets (OPAs) residing on the company intranet. Another team member states they only need to know the basics. However, the project manager believes the team member should know everything regarding the OPAs.

What should the project manager do?

A.

Create a training schedule for the new team member to follow over the next few weeks.

B.

Escalate the inquiry to the team member ' s functional manager.

C.

Clarify the relevance of reviewing the documentation on the intranet.

D.

Ask a senior team member to help the new team member navigate through all the documentation.

Full Access
Question # 39

In the middle of a project, a business unit manager who regularly interacts with the project manager ' s team is promoted to a higher management position. The replacement manager is from the same unit and is somewhat familiar with the project.

After getting more information about the new manager, what is the project manager ' s next step?

A.

Contact the previous business unit manager to learn more about the new manager.

B.

Update the stakeholder register and the stakeholder engagement plan to include the new manager.

C.

Send the new manager a copy of the project charter to ensure the project objectives are understood.

D.

Schedule a meeting with the new manager to discuss the business analysis team ' s plans.

Full Access
Question # 40

A project manager is approaching the end of a project, and several tasks are now practically complete and ready for handover to the client How should the project manager proceed?

A.

Update the quality management plan for the overall project

B.

Ask the client to verify and accept the tasks that have been completed

C.

Close out the project tasks that have been completed

D.

Update the communications management plan for the overall project

Full Access
Question # 41

For an agile pilot project, the sponsor arranged an early product demonstration for the customer. During the meeting, the customer realizes that a new feature will significantly improve the product

After collecting the new requirements, what should the project manager do?

A.

Assess the impact of the new requirements and initiate the change request process.

B.

Work with the product manager and the rest of the team to update the project backlog.

C.

Assess the impact and communicate the updated product roadmap to the stakeholders.

D.

Follow the change management plan to update the risk register so It accounts for the added scope.

Full Access
Question # 42

A company that is introducing a new product into the market by the end of the year requires a storage and distribution facility to be built. During the monthly stakeholder meeting, it is discovered that the location for implementation is a government-owned area

What should the project manager do first?

A.

Identify an alternative site.

B.

Update the issue log

C.

Issue a change request

D.

Update the risk register.

Full Access
Question # 43

Match the project situation on the left to the meeting on the right where the situation could occur.

Full Access
Question # 44

A project manager is working on a large project with a very difficult client. During

the course of the project, the project manager realizes that if the project team had a little more time and funding to make some minor changes, the client could realize the benefits of 25% of the project outcomes early.

How should the project manager approach this?

A.

Concentrate on the current project milestones.

B.

Update the project management plan for this new work.

C.

Develop a business case and submit it to the client.

D.

Make all the changes and then show the client the results.

Full Access
Question # 45

A year after implementing a policy change to improve diversity and inclusion within two teams, there is increasing conflict within the company What should have been done to prevent this conflict?

A.

The organization should have introduced the concept of diversity broadly

B.

The leadership team should have worked closely with the marketing team to get insight on diversity

C.

Organization-wide diversity training should have been provided to the workforce

D.

The critical departments in the organization should have been involved in this exercise

Full Access
Question # 46

Important projects in the portfolio backlog need to be delivered Budget estimates are needed to prioritize the projects How should the project budgets be estimated ' ?

A.

The project is decomposed into features and based on the feature value and the velocity of the team, the team provides the estimate

B.

Budget estimates are provided based on the experience of the sponsor, product owner and team facilitator

C.

The team facilitator uses historical data and arrives at an estimate based on the nature of the project.

D.

The product owner obtains all project details and based on the team ' s experience and velocity provides a budget estimate

Full Access
Question # 47

A new agile team is having trouble completing tasks. There are many disputes occurring in the team. What should the agile leader do in this situation?

A.

Escalate the issue to the team ' s manager.

B.

Remove some of the team members.

C.

Review the roles and responsibilities document.

D.

Develop working agreements with the team.

Full Access
Question # 48

A project manager has just started a new project for an organization that dislikes budget and schedule deviations. The project stakeholders are very engaged and want to ensure there is clear visibility of the project’s risks and progress. How should the project manager handle stakeholder expectations?

A.

Discuss the risk response strategies with the stakeholders

B.

Add buffers to the schedule to accommodate unforeseen changes

C.

Ensure the risk register includes all identified risks

D.

Develop a communications management plan to share updates with stakeholders

Full Access
Question # 49

During the implementation phase of a construction project the customer asked a key subcontractor to deliver a work package ahead of time The subcontractor was not prepared for it and asked the project manager for additional budget What should the project manager do first?

A.

Ask upper management for more funds and update the project budget

B.

Revise the project scope accordingly to cope with the budget changes

C.

Update the risk register and project log. and manage the budget closely.

D.

Submit a change request to accelerate the project as requested

Full Access
Question # 50

At a meeting to receive approval for the project management plan, a project manager realizes that there is so much detail in the presentation that many of the stakeholders are not actively engaged in the process. The stakeholders are agreeing to the scope, goals, and timelines without giving them substantial thought.

How should the project manager proceed?

A.

Stop the meeting and reschedule for another time with a more concise presentation.

B.

Set up information review sessions before reconvening another approval session.

C.

Get approval and promise to email more information to the stakeholders to clarify the technical details.

D.

Obtain approval as fast as possible and close the meeting.

Full Access
Question # 51

A project manager is managing an innovation project for a big corporation The project manager is planning to use email as the main communication channel, however, the product owner prefers to use another approved communication tool instead of email

What should the project manager do?

A.

Contact the sponsor to request direction regarding the communication tool to be used by the project team

B.

Update the communications management plan based on the product owner’spreferences and distribute to the team

C.

Suggest to the team to start using the communication tool suggested by the product owner

D.

Request the product owner to use email because using another tool will increase the workload

Full Access
Question # 52

A subcontracting company is presenting its feature release A key stakeholder is asking to add a new feature to the product How should the project manager deal with the new requirement?

A.

Follow the change management process and work with procurement if needed

B.

Engage an arbitrator to resolve any conflict while handling the new requirement

C.

Add the change to the next sprint to meet the customer ' s needs

D.

Allocate resources to work on the new feature immediately to complete the request

Full Access
Question # 53

As a member of an organizational change management team, a project manager must pass on any changes to the project team The project manager needs to avoid any misunderstandings or resistance to help ensure that the project team will support any organizational change

What should the project manager do?

A.

Conduct meetings with resistant members to facilitate smooth project implementation

B.

Meet with the team on a regular basis to ensure they are aware of changes.

C.

Influence the team to communicate any changes

D.

Check with the

Full Access
Question # 54

A global company hired a project manager for a new implementation at all of its sites After reviewing the business case and project charter, the project manager notes that the project team has different locations and regions to consider.

What should the project manager do to address this situation?

A.

Inform the steering committee of the situation and request additional resources.

B.

Coordinate virtual and face-to-face meetings at each site to improve communication

C.

Coordinate virtual meetings to assess the project team ' s communication needs

D.

Inform the project sponsor of this situation and request cultural orientation training.

Full Access
Question # 55

A senior management team member contacts an agile project lead and mentions

that certain features the senior manager thought would be in the current release were not

included. What should the agile project lead do?

A.

Assure the senior manager that these features will be queued up in the next sprint.

B.

Meet with the team to understand why the senior manager’s features were not included.

C.

Invite the senior manager to the next planning meeting.

D.

Send the product roadmap to the senior manager.

Full Access
Question # 56

A project manager is assigned to lead a team comprised of business executives. After several roadmaps were denied by the sponsor, the project manager asks to be removed from the project. The sponsor urges the project manager to find a solution as the sponsoring organization requested their assignment. What should the project manager do?

A.

Emphasize to the executives that the project manager was specifically requested for this project

B.

Schedule deliverables solely based on priorities and must-have-by dates, and gauge responses

C.

Hold a team meeting emphasizing existing governance policies and procedures

D.

Adopt a project framework aligned to the executives’ availabilities and then evaluate the risks

Full Access
Question # 57

A project manager has been assigned to an education project with the objective of training a workforce in application development One of the deliverables is to provide internships to the best students in the customer ' s active projects However the customer does not have enough projects in progress right now The project manager decides to create several internal projects in order to ensure the internships

Which three actions should the project manager take to fulfill this scenario without adding costs for the customer? (Choose three)

A.

Use the project ' s contingency budget

B.

Create a change request with the scope of the new internal projects.

C.

Influence the client to initiate a new project.

D.

Create a work breakdown structure (WBS) of the new scope with the internal projects

E.

Manage the quality of the delivery

Full Access
Question # 58

A business analyst on the project meets the customer in the elevator and says that due to constant changes in requirements the development of the product will take more time than expected What should the project manager do?

A.

Submit a change request to the change control board (CCB) in order to reflect the new requirements and longer timeline of the project

B.

Refer to the resource management plan to find out if more business analysts may be assigned to process the requirements changes

C.

Point out to the project team and the customer that all information concerning the timeline of the project should be communicated by the project manager.

D.

Explain that distribution of important news can only be done using traceable communication methods

Full Access
Question # 59

The project manager is having difficulty communicating with one of the team members The team member recently attended a training course and has been training other team members in a new agile technique However sometimes the team member is forceful in pushing ideas even if other team members are uncomfortable

What personality indicators should the project manager consider when determining what communication style to use with this team member?

Full Access
Question # 60

A project manager is managing a hybrid project After attending an iteration review, a stakeholder tells the project manager that they are very busy and asks why these reviews are held so frequently.

How should the project manager respond ' ?

A.

Negotiate a reduced review attendance with the stakeholder and update the stakeholder engagement plan to reflect this reduced attendance

B.

Discuss with the stakeholder the benefits of the hybrid project and how frequent reviews lead to greater value and less rework

C.

Record the issue in the issue log and escalate the conflict to the project sponsor for assistance

D.

Explain to the stakeholder that the stakeholder engagement plan requires theirattendance at all reviews

Full Access
Question # 61

A company that is heavily focused on delivering projects using predictive approaches on-boards a new project manager who uses hybrid approaches The scope of the project contains a number of unclear requirements.

How should the project manager plan the delivery of the project?

A.

Wait for the requirements to be more clear before any further action is taken on the project

B.

Ignore the unclear requirements and focus on the delivery plan of the project

C.

Escalate the issue of unclear requirements to the management team and wait for final authorization

D.

Break down the requirements and prioritize the requirements into iterative work packages

Full Access
Question # 62

During the implementation phase of a project, a new regulation affects the project, and a critical status meeting discussing the scope changes is required. The project manager discovers that a key stakeholder cannot attend the scheduled meeting

What should the project manager do?

A.

Call for a change control board (CCB) meeting, and inform the stakeholder about the outcome

B.

Update the communications management plan and implement the change

C.

Meet with the project sponsor to discuss how to address the situation.

D.

Meet with the stakeholder prior to the meeting to obtain their opinion

Full Access
Question # 63

A project manager is working on the implementation of new phases in the production process of a regulated industry. Which two stakeholders can help the project manager determine and address compliance requirements? (Choose two)

A.

Risk steering committee

B.

Functional managers

C.

Board of directors

D.

Advisory team panel

E.

Chief executive officer

Full Access
Question # 64

Stakeholders in some industries prefer to deal with programmers and system analysts directly, bypassing project managers. This complicates managing resources on projects

How should a project manager solve this issue?

A.

Propose implementing a new project management information system (PMIS).

B.

Request a meeting with senior management to escalate the situation

C.

Promote adoption of the communications management plan with the project team.

D.

Host a team-building event to develop team cohesion and improve communication

Full Access
Question # 65

A company is implementing a new system The project manager has identified that it is best to complete this project using a mix of Scrum and Kanban methodologies The product owner is confused as to how to start delivering the functionalities required

How should the project manager assist the product owner?

A.

Coach the product owner on how to create a product backlog

B.

Encourage the team to subdivide the project tasks

C.

Create a work breakdown structure (WBS) and explain the deliverables to the product owner

D.

Discuss the product owner ' s responsibilities within the project team

Full Access
Question # 66

A project manager finished reviewing the project deliverables for the current iteration with the customer A new key stakeholder who just joined the customer ' s team, complains that the results do not provide the capabilities the business anticipated

What should the project manager do to address this issue?

A.

Create a change request and update the scope management plan

B.

Conduct stakeholder identification and a project objectives review session

C.

Update the stakeholder list and fix the deliverables

D.

Update the project management plan and lessons learned

Full Access
Question # 67

A project manager notices that the team lacks a subject matter expert (SME) in a specific area. This expertise will be required for many future projects.

What should the project manager do?

A.

Seek help from the project sponsor to get an SME from another team in the organization.

B.

Provide an opportunity to one of the existing team members to become an SME.

C.

Hire a contractor from outside of the organization to continue with the project.

D.

Ask team members to document the issue and address it in the next project meeting.

Full Access
Question # 68

The following table shows the business value created and the development effort required to implement various features in a product

Which feature should the team prioritize first? Enter the feature name in the box below

Full Access
Question # 69

A project manager who is managing a critical project in a multinational company is conducting a progress meeting with all team members. During the meeting, one of the team members states that they are facing a critical problem that will prevent them from completing their assigned task

What should the project manager do?

A.

Ask the team member to follow the approved communications management plan to communicate their issue

B.

Schedule a meeting with the concerned team member to review and update the issue log together

C.

Review the risk register with the team member to find the proper response action for this issue.

D.

Ask the team member to raise a change request to assess the issue in detail

Full Access
Question # 70

A project manager is transferred to another country to perform a project within their organization. What should the project manager do first to ensure collaboration within the team for a successful delivery?

A.

Determine a leadership style that is suitable for that location.

B.

Check if resources from headquarters can also be assigned to the project.

C.

Mentor the team members to perform project management.

D.

Assign a local resource to manage communication with the team.

Full Access
Question # 71

A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The burndown chart is shown below. What should the team do next?

A.

Continue with the sprint as the progress shows buffers for potential interruptions.

B.

Ask the product owner if some low-priority stories could be cut from the sprint.

C.

Continue with the sprint work as planned and keep monitoring.

D.

Ask the project team to select any additional stories as they have additional capacity than planned.

Full Access
Question # 72

Two team members were recently released from a project because the customer reduced the budget. However, the agile team is still receiving the same, if not more, work requirements as before.

How should the agile project leader resolve this situation?

A.

Update the restriction log with the new team capacity.

B.

Explain the new project requirements to the team.

C.

Update the project budget with the released team members.

D.

Explain the new team velocity to the customer.

Full Access
Question # 73

Early in a project, a team member failed to effectively communicate the reason for their absence from three team meetings. How should the project manager handle this situation?

A.

Reaffirm the required project obligations directly with the team member. oy

B.

Ask the team member to explain the reason for the absences.

C.

Assess the impact of the team member ' s absence on the task involved.

D.

Send a formal letter to the team member stating that their absences are noted.

Full Access
Question # 74

In a weak matrix environment, two key team members are falling behind with their tasks, which will affect the success of the project.

Further investigation by the project manager reveals that they have unresolved issues with each other. The project manager asks them to find a way to resolve the issues, but this is unsuccessful. The project manager then holds a meeting with them to work outa permanent solution to the issues, but this is also unsuccessful.

What should the project manager do next?

A.

Escalate the issue to a higher authority.

B.

Suspend the two key team members immediately.

C.

Put the issue on the agenda for the next team meeting.

D.

Reassign one of the key team members to a different task.

Full Access
Question # 75

The portfolio management office wants to cut costs by suspending some ongoing

projects that do not directly support the organizational strategy. The project manager has invested too many resources into one of the projects to be suspended, but the portfolio

management office has not backed down on their plan.

What should the project manager do to continue the project?

A.

Meet with the project team and revise the project goals.

B.

Update the project charter to make it align with organizational strategy.

C.

Demonstrate the project alignment to the organizational strategy.

D.

Escalate the issue with the project sponsor to request support.

Full Access
Question # 76

During project implementation, a critical performance issue is identified by team members. What should the project manager do?

A.

Submit a change request to handle the performance issue

B.

Review the tender requirements related to the performance issue

C.

Pass the performance issue to subject matter experts (SMEs) to handle

D.

Work with the project stakeholders to address the performance issue

Full Access
Question # 77

The CEO has authorized the development of a complex financial product for a company to provide greater future benefits. The budget has been acquired through financing with global investors who expect all risks to be identified as soon as possible

What should the project manager use to identify the risks?

A.

An analysis of shared risks between parties

B.

Strengths, weaknesses, opportunities, and threats (SWOT) analysis

C.

Expert judgment

D.

A risk value assessment

Full Access
Question # 78

A project manager is appointed to simultaneously deploy a new solution to branches located in different countries Deployment teams in each country will integrate and deploy the solution The project manager discovers that the deployment teams each encounter similar issues However, each team addresses the issues separately

What should the project manager do to help ensure more collaboration between the teams?

A.

Organize regular meetings with all of the deployment teams to share issues and solutions

B.

Propose that some of the teams delay deployments in their countries

C.

Ask the project sponsor to appoint new managers for the deployment teams

D.

Ask each deployment team to provide a very detailed schedule and action plan

Full Access
Question # 79

An agile team member received certification on a new tool: however, this learn member is complaining that the rest of the team is not using the tool due to lack of knowledge How should the servant leader apply emotional intelligence to leverage this situation to benefit the project?

A.

Request budget to reward the team member so others will be motivated to obtain the same certification

B.

Promote the team member to product owner to leverage the new knowledge with the clients

C.

Provide an incentive to team members who begin using the new tool on this project.

D.

Ask the team member to use their recently acquired knowledge to develop and provide training to the team

Full Access
Question # 80

At the daily project meeting, team members are complaining about receiving emails from their functional managers to support other nonproject-related tasks. This is having a negative impact on the team ' s productivity.

What should the project manager do next?

A.

Ask the product owner to speak with the functional managers to ensure future requirements come through the product owner.

B.

Log this as a risk in the risk register and continue to monitor the issue at subsequent meetings.

C.

Address this concern with the functional managers to ensure there will be no further delays.

D.

Schedule a meeting with all of the functional managers to resolve the resource conflicts.

Full Access
Question # 81

A project manager is assigned to a project in a company that is transitioning to agile Not all stakeholders believe in the project, and some stakeholders would like the entire project defined and planned out early in the project However the project sponsor needs a quick win to ensure the continuation of the project.

What approach should the project manager use?

A.

An agile approach as this would provide working functionality earlier

B.

A predictive approach as this would please the senior stakeholders

C.

A hybrid project as this will mitigate stakeholders ' concerns.

D.

A predictive approach as this will show benefits for all stakeholders

Full Access
Question # 82

A project team is engaging a development team in another country to develop software. During progress reviews, the project manager identified completion date delays due to rework because there were different interpretations of the client ' s needs.

What should the project manager do?

A.

Set up a meeting with key stakeholders to clarify requirements

B.

Escalate to the project steering committee and request additional time

C.

Travel to the development team ' s office to push the schedule

D.

Create prototypes with the development team to confirm requirements

Full Access
Question # 83

A team member misses a project meeting without it being approved and has been penalized as defined in the ground rules. This team member, as well as other team members, insist that it is the first time they have seen this rule regarding the project and they do not agree with the penalty

What should the project manager have done to avoid this situation?

A.

Ensured the team charter was developed by the team members

B.

Ensured the team members are fully supportive of all decisions.

C.

Distributed the project charter to all team members.

D.

Used a charismatic leadership style

Full Access
Question # 84

A verbal announcement is made that the new team member joining the Scrum team has limited mobility The scrum master is aware that some team members are unsure how the dynamics of the team will change

What should the scrum master do?

A.

Create a stakeholder engagement plan

B.

Design a communications management plan

C.

Update the team charter accordingly.

D.

Set up a meeting to discuss accommodations the team will have to make

Full Access
Question # 85

During project execution, the risk owner is monitoring the critical speed rate of a power engine to eventually trigger the defined risk-response strategy. During the risk assessment and management process phase, it was defined that the power engine has the following characteristics

1,600 rpm (rate-per-minute) - > stops working and crashes the system

1.500 rpm (rate-per-minute) - > warns of max rate allowed

1.400pm (rate-per-minute) - > reduces the power and brakes the engine

Which of the following statements is correct?

A.

0 1,600 rpm is a project risk,1,500 rpm is an event that triggers a response strategy and 1,400 rpm is a project issue.

B.

1,600 rpm is a project issue,1,500 rpm is an event that triggers a response strategy and 1,400 rpm is a project risk

C.

1600 rpm is a project issue; 1,500 rpm is a project risk; and1,400 rpm is an event that triggers a response strategy

D.

1.600 rpm is an event that triggers a response strategy.1,500 rpm is a project issue and 1,400 rpm is a project risk.

Full Access
Question # 86

A new project manager learns the work assigned to the team has already been decomposed to its lowest level The project manager reviews the work and feels some additional useful information is missing

What should the project manager review?

A.

The project charter and scope statement

B.

The requirements traceability matrix

C.

The business requirement documents (BRD)

D.

The WBS dictionary

Full Access
Question # 87

At the closing phase of the project the project manager sends the completion reports to the client as a formal written document, indicating that the contract has been completed The client refuses to approve the document since the defect rate is 0.1%. The project manager insists that it is an acceptable rate as the standard defect rate of the industry is 0.15%.

What should have been done to avoid this situation?

A.

The acceptance criteria should have been properly defined in the contract

B.

The client requirements should have been clearly defined in the contract

C.

The Manage Quality process should have been appropriately conducted

D.

The project manager should have reviewed the standard industry defect rate

Full Access
Question # 88

A retail chain is evaluating a project to replace payment systems across all its stores in multiple locations The project does not pass the financial threshold but is also expected to increase market share, improve customer services and retain more customers The project is planned as a phased implementation building on learning from the retrospectives during each phase

How should the business increase the value of the project?

A.

Quantify the expected tangible and intangible benefits in the benefits management plan for each phase

B.

Ask the benefits owner to reassess the identified risks that are impacting the outcomes of the financial benefits.

C.

Consult with experts on methods to reduce costs and increase the financial value of the project

D.

Use a fishbone diagram to find the root cause of the lower financial benefits with the benefits owner

Full Access
Question # 89

A new project has been kicked off following a planning session. The project is under direct oversight of an executive in the organization After a review meeting, the project manager overhears an executive request a dashboard from one of the team members to show the overall project status

What should the project manager do?

A.

Update the stakeholder engagement assessment matrix

B.

Update the communications management plan to include informal requests

C.

Ask the team member to develop a dashboard to fulfill the request.

D.

Tell the team member to route the request through the project manager

Full Access
Question # 90

A project manager presented the project schedule to the mam stakeholders They have requested that the project be completed two months earlier than the scheduled date

What should the project manager do?

A.

Hold a stakeholder meeting to align timelines and scope expectations.

B.

Crash the schedule to shorten the timeline while keeping the scope unchanged

C.

Update the cost management plan to allocate more resources to the project to finish the scope earlier.

D.

Reduce the scope of the project by removing activities and shortening the timeline

Full Access
Question # 91

Drag the communication event on the left to the mam subject discussed during the event on the right.

Full Access
Question # 92

During the design phase, a project manager realizes that the project will benefit from using adaptive tools The effectiveness of this approach has been proven in past projects inside the organization

What should the project manager do first?

A.

Update project documents to include adaptive tools and artifacts and plan the first iterative session

B.

Contact the project sponsor and request new team members who are familiar with adaptive projects

C.

Confirm team capabilities before introducing adaptive tools and artifacts to the project

D.

Freeze the design stage and look for an external resource to run iterative design at extra cost

Full Access
Question # 93

A software project using an agile approach is facing quality issues with every release, generating many production problems. What should the project manager do to fix the problem and improve the quality?

A.

Seek extra funding approval with the sponsor to replace junior team members for more experienced ones

B.

Create a reward system granting incentives to the team members who are able to catch more defects

C.

Hire an external company to add an additional layer of testing, making sure that the final product is well inspected before releasing.

D.

Use the retrospective meeting to better understand the root cause of the quality problems and put together a plan with the team to address the problems

Full Access
Question # 94

How should the project manager develop the project management plan to ensure that the project continually delivers the expected benefits?

A.

Clarify project benefits with the sponsor.

B.

Identify the goal of each work product

C.

Perform integration testing of each release

D.

Include the entire project team in testing

Full Access
Question # 95

An agile project manager would like to convert the requirements document into epics, capabilities, features and stories In how many iterations should the project manager estimate the story duration?

A.

Four iterations

B.

One iteration

C.

Two iterations

D.

Three iterations

Full Access
Question # 96

A geographically distributed project team has development issues between the collocated and virtual teams causing productivity to decrease. What should the project manager do to address this issue?

A.

Force the team members to work from one location.

B.

Develop protocols for resolving conflicts between team members

C.

Obtain special expertise to advise the team members

D.

Set up face-to-face meetings with project team members

Full Access
Question # 97

A product owner presented the backlog to the team, and the team raised concerns over implementing some of the features due to various impediments What should the project manager suggest that the product owner do next?

A.

Ensure that the impediments are captured and prioritized based upon the highest valued features

B.

Estimate the financial impact of the impediments and request additional funding

C.

Begin to remove the impediments, starting with the easiest ones first, to foster team accomplishment

D.

Capture the impediments and inform management that their assistance is neededin resolving the impediments

Full Access
Question # 98

After reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months. Based on the new timeline, what should the project manager do?

A.

Plan for overtime apply crashing and fast tracking and share the risk of failure with project stakeholders

B.

Review the project backlog looking for high-priority items and come up with a minimum viable product (MVP) that fits the expected timeline

C.

Seek approval with the sponsor to triple the project budget, hiring more people to compensate for the compressed schedule

D.

Go over the critical path with stakeholders, explaining why it is not possible to deliver all the scope in the expected timeline

Full Access
Question # 99

A company has been following a predictive approach and always waits for the preceding phase to be completed before evaluating the quality of their products A new project manager with experience in hybrid approaches has been assigned to help increase the efficiency of the company ' s quality management process.

What should the new project manager do to address the process improvements?

A.

Understand the context and interdependencies of the process from the team members and then define improvements

B.

Continue with the process as is. and wait until the next phase to suggest any improvements

C.

Discuss the process improvement with the project management office (PMO) lead to update the project delivery framework

D.

Define a ground rule to comply with the quality standard and ask the team members to apply it.

Full Access
Question # 100

A company was awarded a project in a dangerous location that poses several high-level risks for employees Help is needed to tram the employees on major safety and health factors The project is ongoing and uses a hybrid approach The project will be conducted in multiple sites, with several development iterations running in parallel

How should the project manager handle this situation?

A.

Allocate and use part of the project ' s contingency reserves for training purposes.

B.

Negotiate a contract and form a partnership with a local authority for medical and security support services.

C.

Perform a retrospective and update the risk register and resource management plan regarding the necessary budget for training

D.

Hire only local resources who are aware of the terntory ' s hazards, providing employment to the local community

Full Access
Question # 101

A project manager is implementing a new software system Some department staff members are questioning the necessity of the change and feel the new system will impede their current processes

What should the project manager have done at the start of the project to prevent this resistance?

A.

Created a communications management plan that outlined the method of communicating to stakeholders.

B.

Ensured that the company culture encourages changes before accepting the project

C.

Encouraged leadership to discuss the change with departments that are typically resistant to change

D.

Involved stakeholders from all levels of the company so everyone understands the change

Full Access
Question # 102

Development team members are located in three different time zones It is difficult to find a suitable time to hold the daily standup for all team members

What should the project manager do?

A.

Encourage frequent small team meetings with two or three team members.

B.

Give up the daily standup and replace it with a daily report

C.

Let the team members decide themselves if they want to join the meeting.

D.

Require all team members to join the daily standup regardless of the meeting time

Full Access
Question # 103

While reviewing prototypes, the quality team found some deviations that do not affect the mam functionality but have the potential to be an issue in the future To avoid major problems in the future, the team recommends corrective actions that will require additional funds The project is already struggling to stay on budget and has even used some of the contingency reserves

What should the project manager do?

A.

Ask the product designer why the deviation was not considered in the design phase

B.

Report to the project sponsor that the product is working and the project is struggling with the budget.

C.

Evaluate and initiate the change request process with the stakeholders

D.

Ask the quality team to discard the sample and test again with a new sample

Full Access
Question # 104

A project manager is managing a hybrid project. After attending an iteration review, a stakeholder tells the project manager that they are very busy and asks why these reviews are held so frequently Record the issue in the issue log and escalate the conflict to the project sponsor for assistance.

How should the project manager respond’

A.

Negotiate a reduced review attendance with the stakeholder and update the stakeholder engagement plan to reflect this reduced

B.

Discuss with the stakeholder the benefits of the hybrid project and how frequent reviews lead to greater value and less rework

C.

Record the issue in the issue log and escalate the conflict to the project sponsor forassistance

D.

Explain to the stakeholder that the stakelrolder engagement plan requires their attendance at all reviews

Full Access
Question # 105

The rollout of a new finance system is in the execution phase. A number of issues have surfaced in the last month that are slowing the project down A new project sponsor has recently started with the company but has not had time to meet the project manager The project is at the point where the issues are significantly impacting delivery of the project

How should the project manager alert the new project sponsor about these concerns?

A.

Send an email invitation to the project sponsor to attend all of the project team ' s weekly meetings, and hope the sponsor will find time to attend

B.

Send an email to the project sponsor summarizing the project status and key concerns, and request an immediate face-to-face meeting to discuss them

C.

Continue emailing updated project status reports highlighting the key risks andissues, and wait for the project sponsor to request a meeting

D.

Complete a risk analysis outlining the delays and impacts, and email a copy of the risk register, urging the project sponsor to respond

Full Access
Question # 106

A company is initiating a project to enhance one of its existing products. All of its products are developed internally What should the project manager do?

A.

Ensure the stakeholder engagement plan is accurate and properly documented.

B.

Review the lessons learned from the previous project

C.

Identify the risk of implementing the new solution and evaluate the impact on the project.

D.

Create a lessons learned document for the initiation phase

Full Access
Question # 107

A project manager is assigned to a new project to deliver a product at the end of the year. The project manager was informed by the vendor that a core component could not be shipped on time, which will impact the schedule.

What should project manager to do next to minimize the impact on the project?

A.

Schedule a meeting with all stakeholders to extend the project deadline

B.

Replace the vendor with a new vendor who can offer the component on time

C.

Add an item to the next status review to make stakeholders aware of the vendor issue.

D.

Review and update the issue log and determine if any alternative components can be offered

Full Access
Question # 108

During the course of a project, the team develops negative group behaviors and becomes unmotivated and unproductive. What should the project manager do to improve the project team ' s performance?

A.

Define and analyze performance metrics

B.

Escalate poor performance to functional managers

C.

Update the stakeholder engagement plan

D.

Conduct a root cause analysis session

Full Access
Question # 109

A project manager realizes that a project is becoming delayed because some key decisions are affected by contradicting views between the organization ' s senior management and external stakeholders. What should the project manager do?

A.

Review the stakeholder register and ensure that communications are being followed in line with the communications management plan.

B.

Isolate the project team from external factors such as senior management and stakeholders so that decisions can be made more quickly

C.

Review the remaining scope and rebaseline the project’s schedule to take into account delays in decision making

D.

Review the adequacy of the project ' s governance and ensure that an appropriate structure is in place

Full Access
Question # 110

During the implementation of a project the project team discovered a new opportunity After an internal review the project team agreed that the opportunity is outside of the project scope The project manager decided to update the risk register and escalate the opportunity to a higher level

What should the project manager do next with this opportunity?

A.

Share this opportunity with another project

B.

Establish a contingency reserve to support the opportunity

C.

Further monitor the opportunity

D.

No more action is required

Full Access
Question # 111

The marketing team is transitioning to using hybrid approaches for their projects. The marketing director is not knowledgeable about hybrid methodologies and the project manager needs the director’s support as the marketing director is a key stakeholder.

What should the project manager do to obtain the support?

A.

Ask the marketing director to participate in daily meetings

B.

Mentor the marketing director on hybrid approaches

C.

Ask the marketing team members to coach the director

D.

Tram the marketing team and keep the director informed

Full Access
Question # 112

A learn has been working for two months and has consistently missed planned user stories How should the project manager address this issue?

A.

Ensure the sprint size is appropriate for the iteration duration.

B.

Promote changing the iteration duration in order to commit as planned.

C.

Engage in recruiting a highly skilled resource to reinforce the skills.

D.

Consider using a reward system to encourage timely delivery

Full Access
Question # 113

A project manager is working with a Scrum team that is continually missing deadlines The steering committee is concerned about the project as it is not clear that it will deliver the expected value After some analysis the project manager discovers there is a mismatch of competencies in one of the teams

What should the project manager do?

A.

Emphasize to the teams the importance of meeting the agreed deadlines

B.

Provide appropriate training to compensate for the mismatch.

C.

Update the project schedule to reflect the delay

D.

Accept the risk of the project missing deadlines due to the mismatch.

Full Access
Question # 114

During project execution, the project manager discovered that a key deliverable was missing from the scope of work After investigation, the project manager and the team discovered that the missing deliverable will impact the critical path

What should the project manager do to avoid future delays?

A.

Submit a change request.

B.

Add additional resources to the project

C.

Update the scope of work.

D.

Review the risk management plan

Full Access
Question # 115

During the development of a product, the project manager observes conflicts between project stakeholders, resulting in deliverable and output approval delays On which area should the project manager focus?

A.

Revisiting the project management plan to ensure deliverables are on time

B.

Increasing the frequency of project update meetings to keep stakeholders informed

C.

Revisiting the stakeholder engagement plan, focusing on specific overlooked stakeholders

D.

Reviewing the business case and identifying gaps within scope

Full Access
Question # 116

A food company is developing a new product using a predictive approach, and the product is currently in the testing phase Given the nature of the feedback of the tests, the project manager has decided to use an iterative approach At the end of one of the iterations, a new regulation related to the product is enacted.

What should the project manager do next?

A.

Make a change request regarding the project ' s scope to ensure compliance.

B.

Include an assessment to verfy compliance in the next iteration

C.

Conduct an iteration review to address the new regulation

D.

Start the tests over, adapting the trials to the new regulation

Full Access
Question # 117

A team member shares with their functional manager some negative details about the performance of another team member that was discussed during the retrospective. The project manager finds out about this discussion

What two actions should the project manager take? (Choose two)

A.

Contact the team member ' s functional manager and invite them to the next retrospective

B.

Meet with the entire team to review the ground rules about safe environments

C.

Meet with the product owner to talk about the situation.

D.

Contact the team member to explain what information can be shared outside the team

E.

Meet with the sponsor to review the situation.

Full Access
Question # 118

A project manager who is new to an organization observes that an approaching deadline is likely to be missed because there have been some delays on the project due to a lack of resources. What should the project manager do next?

A.

Review the milestone list to determine which tasks can be fast-tracked

B.

Review the risk management plan to identify the response strategy

C.

Escalate the issue to the sponsor and debrief them about the situation

D.

Organize a team meeting to discuss the next course of action

Full Access
Question # 119

Early in the execution phase, a project manager discovers that recent changes in enterprise environmental factors (EEFs) will severely reduce the implementation cost and shorten the project schedule. How should the project manager address this situation?

A.

Meet with the project team to decide how the remaining budget will be spent.

B.

Keep the extra budget as management reserve until project closeout

C.

Give the team extra time to finish tasks within the original timeline

D.

Follow the project escalation policy and communications management plan

Full Access
Question # 120

A project manager has just taken over a project that is halfway through its schedule. In a brief meeting with the client’s key project team, the project manager receives several requests from a specific client team member who was not at the project team meeting. The requests for information seem to be for trivial information that was previously submitted in project documents.

What should the project manager do first?

A.

Send an email to the client team member explaining that they have the information already.

B.

Review the stakeholder register to gain insight into the expectations of that team member.

C.

Inform the client project manager that they are sending too many trivial requests.

D.

Update the project risk register to include potential delays in answering these requests.

Full Access
Question # 121

A project manager has just finished initiating a project. While planning the project manager notes that several essential team members do not have the required skills for key tasks later in the project.

What should the project manager do first?

A.

Develop the resource management plan and ensure adequate training

B.

Replace the current project team members

C.

Outsource the task to be completed by a specialized vendor.

D.

Update the issue log to account for the lack of team member qualifications

Full Access
Question # 122

The client will not agree to closure, claiming that the project team has not performed the code inspections mandated in the development contract. The project team has performed the code inspections, however the records are not complete What should the project manager do?

A.

Seek expert legal advice on the interpretation of the clauses in the contract

B.

Hold a meeting with the project team project sponsor and the client to agree to the further work required to close the project and add to lessons learned

C.

Close the project and hand over the deliverables to the client

D.

Hold a lessons learned workshop with the project team and project sponsor to avoid contractual compliance issues arising in future projects

Full Access
Question # 123

During the implementation stage of a project. a newly appointed team leader approaches the project manager to verify the team ' s tasks and schedule. The work did not go as planned due to the team leader ' s lack of management experience. This could cause delays for the project.

What should the project manager do?

A.

Ask the human resources director to appoint a senior team leader

B.

Inform the project sponsor about the possible delay

C.

Directly manage the project team to avoid project delays

D.

Provide mentoring to the newly appointed team leader

Full Access
Question # 124

Some of the mote experienced members of a project team have complained about the project manager The senior project team members feel that the project manager is micromanaging them and preventing them from completing their work.

What should the project manager do when made aware of these issues?

A.

Ask for advice on how to be a better mentor to these team members.

B.

Set up a team building event to bring synergy back to the project team.

C.

Adjust the project manager ' s management style to better fit senior team members.

D.

Meet daily with each senior team member to monitor project status

Full Access
Question # 125

The programming activities of a project were planned to last 35 days per module but the programming of the first module has taken 45 days What should the project manager do?

A.

Ask the team to work overtime to complete the deliverable on time

B.

Evaluate the situation and identify ways to compress the schedule without impacting baselines

C.

Check the scope to verify if there is scope creep and get the project on schedule

D.

Submit a change request to the project sponsor to change the schedule

Full Access
Question # 126

During the last sprint review, the mam stakeholder complained that the product was missing many features they had been expecting The project team argued that every increment met the acceptance criteria and was approved by the mam stakeholder The cost performance index (CPI) of the project is 1 15 and the schedule performance index (SPI) is 1.43

What should the project manager do?

A.

Ask the project team to perform the modifications since the project budget and schedule can support them.

B.

Ask the stakeholder to submit a change request to increase the budget and time for the modifications requested

C.

Explain to the stakeholder that since the acceptance criteria for every increment were met the project can be closed.

D.

Analyze the reason for the gap in understanding with both sides and negotiate a solution

Full Access
Question # 127

The team is working on a critical project deliverable and the project manager is concerned about meeting the deadline There have been complaints from some stakeholders about some of the team members ' performance The project manager wants to understand the situation and provide feedback to the team as soon as possible

What three actions should the project manager take to address this situation? (Choose three)

A.

Define team ground rules

B.

Perform a retrospective session

C.

Implement daily team meetings.

D.

Request a manager performance review

E.

Conduct an annual review.

Full Access
Question # 128

During a retrospective meeting a project manager hears that stakeholders have been constantly complaining at iteration demos about product features not being delivered as requested. What advice should the project manager give to the Product owner to ensure that product features are always delivered as requested?

A.

Include stakeholders during daily standup meetings to monitor progress.

B.

Validate acceptance criteria with stakeholders prior to backlog refinement

C.

Avoid including stakeholders in iteration reviews.

D.

Create a requirements traceability matrix and distribute it accordingly

Full Access
Question # 129

A company ' s CEO has just returned from a conference on the use of artificial intelligence (Al) and would like the project manager to implement this technology in the organization What should the project manager do first?

A.

Start developing a business case.

B.

Start a strengths, weaknesses, opportunities and threats (SWOT).

C.

Engage stakeholders and allocate resources

D.

Gather requirements from stakeholders

Full Access
Question # 130

A project manager has team members around the world in many different time zones Project work frequently stalls because people in one office need to wait until another office is awake to have questions answered.

What should the project manager have done to avoid this?

A.

Used communication tools, such as video conferencing so different offices could communicate.

B.

Learned more about how each team member prefers to communicate before assigning project work

C.

Planned and scheduled tasks and work packages to overcome geographical and time zone challenges

D.

Ensured that the project would be the highest priority for all team members

Full Access
Question # 131

A project manager is appointed for the deployment of a new solution The solution will be integrated into the environment by a third-party vendor This vendor just announced a delay in delivering a key component, which will impact the project schedule.

What should the project manager do?

A.

Ask for expedited delivery of the component to mitigate the risk of schedule delays

B.

Ensure that relevant stakeholders and expectations are identified and assess the component delay

C.

Perform a detailed analysis of the release content for each component of the solution.

D.

Propose a new design of the solution to replace the external component with an internal one

Full Access
Question # 132

A project manager is managing a project to develop a new tool Because of the nature of the project, the project manager decides to use an agile approach One of the identified risks becomes an issue when the project manager finds out that another company patented a very similar tool.

What should the project manager do to address this issued

A.

Schedule a meeting with critical stakeholders to review the issue and decide on the next steps

B.

Put the project on hold and release the resources until the issue is resolved

C.

Inform the product owner and log the issue in the risk register to monitor closely for next steps.

D.

Contact the company that owns the patent of the similar tool to compare the similarities and differences with the current project.

Full Access
Question # 133

The sponsor is supportive in leveraging agile approaches The project manager is contemplating how to roll out the agile approach and gam buy-in from both project team members and stakeholders

What should the project manager do first?

A.

Determine which agile software tools will be required to support agile delivery within the organization

B.

Select a current predictive project define the approach, and provide agile training to execute the remainder of the project

C.

Start with a pilot project of appropriate complexity and provide agile training to those who are impacted

D.

Determine how to transform the organization using agile techniques, including organizational training and communications

Full Access
Question # 134

A project manager for a maintenance project has a contract that is renewed annually The project started 6 years ago After contract renewal this year the auditors reported that this version of the contract violates a new law that was passed last year

What has happened in this situation?

A.

The contract has not been appropriately reviewed by the project team

B.

The stakeholder engagement plan has not been correctly implemented

C.

The legal department has not disseminated the law correctly to all staff.

D.

The project manager does not have enough knowledge on this legal matter

Full Access
Question # 135

A Scrum team has committed to delivering a specific capability in their first release Multiple operational issues have prevented the developer from delivering key capabilities. The technical lead has also given notice that they are resigning from the company

What should the project manager have the Scrum team do to recover from these issues?

A.

Review constraints in the ongoing sprint planning and evaluate options for the release plan

B.

Stop the sprint and replan and prioritize the backlog to reduce resource levels

C.

Consult the resource management plan for an appropriate response

D.

Continue with existing sprint plans to ensure some of the scope will be delivered

Full Access
Question # 136

The tables show the requirements for an agile project with the anticipated return on investment (ROI) and identified project risks, along with the analysis details .

What should be the priority order in the product backlog?

A.

Risk3, Risk 1, Risk2, Requirements, Requirement 1. Requirement2

B.

Requirement 3, Risk 3, Requirement 1, Requirement 2, Risk 2

C.

Requirements, Requirement 1, Requirement2

D.

Requirement 3. Requirement 1, Risk 3, Requirement 2, Risk 1, Risk 2

Full Access
Question # 137

A project manager has taken over a project and realizes a number of the suppliers responsible for the delivery have not done an implementation as complex and large as this project. The project manager reviews the risk log and logs this as a risk. Three months later, two suppliers have missed key milestone dates and delivered substandard work.

What should the project manager do?

A.

Support the suppliers by providing them with additional resources.

B.

Execute the risk response plan and update the issue log.

C.

Ask suppliers to submit a revised plan and schedule.

D.

Execute the risk response plan and update the action register.

Full Access
Question # 138

A project manager for a large multiyear industrial project has a project with diversified stakeholders from various geographical areas. Recently, the project manager encountered an issue with stakeholder engagement

Which two tools should the project manager use to determine the underlying reason for why engagement is not having the planned effect? (Choose two)

A.

Five whys

B.

Communications management plan

C.

Ishikawa diagrams

D.

Issue log

E.

Open-space meetings

Full Access
Question # 139

A project manager has been managing a highly complex project. The project manager has ensured that all of the required tasks have been completed. During a recent external audit. The project manager was informed of a heavy penalty being levied on the project for the latest module that was implemented

What should the project manager have done to ensure that there were no liabilities arising from the recent implementation?

A.

Ensured that all defects identified during testing were resolved before implementation

B.

Ensured that all of the required tasks identified in the scope were completed successfully

C.

Ensured that all documentation was completed post implementation before closing the project

D.

Ensured that all the required approvals were received per the organizational procedures

Full Access
Question # 140

A project manager is approached by two new product owners who were instructed by their managers to join a new agile team. Both product owners were told they could start working with the new agile team immediately.

What should the project manager do to advise both product owners?

A.

Modify the communications management plan to integrate the new product owners into the teams effectively.

B.

Reiterate that having one product owner will improve clarity and accountability.

C.

Present the product owners ' product backlogs and prioritize the team ' s assigned requirements.

D.

Confirm that two product owners are necessary and that both will report to an overarching chief product owner.

Full Access
Question # 141

During a planning session, the development team and the product owner are arguing about the effort needed to deliver a specific feature in a software development project. The product owner says that the feature can be developed in one week, whereas the team estimates that it will take at least two weeks. After several hours of discussion, they have not reached an agreement.

What should the project lead do?

A.

Communicate to the stakeholders that the project has to be delayed for two weeks.

B.

Ask the project team to accept the shorter estimate as it is important to keep a good relationship with the product owner.

C.

Decide what should be the time estimate and proceed with the planning meeting.

D.

Educate the product owner that the project team members are the most appropriate group for assessing the effort.

Full Access
Question # 142

A transformation project that is composed of agile streams has come to an end.

How should the project manager collect the experience gained during this project?

A.

Organize a lessons learned session with the team.

B.

Create a document with the information from the last sprint retrospective.

C.

Ask for feedback during the next standup meeting.

D.

Conduct a session with the members of the project steering committee.

Full Access
Question # 143

An experienced team member has recently started performing at a slower pace and is no longer engaged in various team conversations. What should the project manager do?

A.

Incentivize the team with prizes for increased performance and engagement in order to persuade the team member to resume previous performance.

B.

Ask the direct manager to reach out and try to identify the problem, then provide that information back to the project manager.

C.

Inform the team member that a change in performance and engagement is noticed and work together to develop a solution for improvement.

D.

Meet with human resources (HR) to determine the problem and develop a recommendation based on the results.

Full Access
Question # 144

An agile team is struggling to successfully deliver what they have committed. During the daily status meetings, the project manager notices that the most senior engineer is doing all of the talking, leaving little time for the other members to share their status. The team ' s performance is not good, and some team members want to leave the team.

How should the project manager approach this situation?

A.

Measure the team ' s psychological safety.

B.

Reschedule the team ' s retrospective meeting.

C.

Coach the team to be more inclusive.

D.

Rotate the team ' s daily meeting roles frequently.

Full Access
Question # 145

A project manager notices that the project team is encountering product issues while coding client-specific developments. The project manager foresees delays to the project ' s timeline because of these product issues.

Which methods should the project manager use to communicate project delays and other difficult messages to stakeholders?

A.

Oral feedback, project meetings, and reporting

B.

Project meetings and reporting

C.

Project meetings and oral feedback

D.

Written feedback, project meetings, and reporting

Full Access
Question # 146

During execution of the third sprint in a project, a project team is uncertain about the frequent updates on the vendor ' s platform. The team is concerned about how the updates will impact the rest of the backlog.

What should the project manager do to minimize the uncertainty?

A.

Speak with the vendor and explain that constant updates are impacting the project and request an action plan to minimize the changes.

B.

Schedule a spike meeting, conduct risk assessments, and incorporate them into the backlog to help with risk mitigation.

C.

Explain to the project team that the vendor ' s updates are something unpredictable, and the team must continue working on the project.

D.

Schedule a retrospective meeting and conduct a risk assessment with the team, implementing mitigation tasks before the next sprint.

Full Access
Question # 147

A project team needs to create artifacts for an upcoming steering committee.

What should the project manager do first?

A.

Use templates from an existing project.

B.

Ask the project management office (PMO) for guidance.

C.

Surveying peers to understand what templates they have used.

D.

Lead the project team in finding the best templates.

Full Access
Question # 148

A project is delayed considerably from its original completion date for various reasons. The client attributes the delays to the contractor and is going to impose liquidated damages. The project manager of the contracting company reviews the schedule and observes that, though some activities were delayed by the contractor, the critical activity was delayed by the client.

What should the project manager of the contracting company do?

A.

Record that the delay is attributable to the client and request a meeting.

B.

Check the contractual terms about liquidated damages and reject if not applicable.

C.

Meet with the sponsor to analyze the delays and the associated liquidated damages.

D.

Schedule a detailed analysis of the delays using cause and effect.

Full Access
Question # 149

A sales director is upset that progress has been slow on the delivery of critical features to the customer. After consulting with the team, the project manager learns that a subject matter expert (SME) on the customer side is not cooperative in providing the input needed to complete the definition of ready (DoR).

What should the project manager do to avoid the same problem in future projects?

A.

Review the responsibility matrix at the customer kick-off meeting.

B.

Rely on internal SMEs for expert input on implementing the user stories.

C.

Include a contractual penalty for delays created by the customer.

D.

Require customer SMEs to attend at least half of the daily meetings.

Full Access
Question # 150

An important project to build a new airport was suddenly stopped because of the complaints from residents in the surrounding communities. The residents stated that they were not consulted and that the project would cause ecological and pollution damage.

What should that project manager have done first in order to avoid this situation?

A.

Identified the stakeholders and their expectations

B.

Presented the project to the community

C.

Added this situation to the risk register

D.

Added these requests to the project scope statement

Full Access
Question # 151

A work package to configure new computer hardware is received, and a list of related project activities have also been identified. What should the project manager do?

A.

Define the project management plan.

B.

Estimate the resources needed for the activities.

C.

Consult subject matter experts (SMEs) to review the schedule.

D.

Estimate the cost of each activity.

Full Access
Question # 152

A strategic project using international funds for a government agency is going through the execution phase. The government transition will take place in 1 month, and authorities will change. There is a risk that the project will be suspended or team members will be removed. The project manager wants to ensure that the project will continue despite these changes.

Which action should the project manager take to address this situation?

A.

Stop the project until the government transition has taken place.

B.

Ask the sponsor to send a communication to the president-elect team with the progress of the project.

C.

Ask the main stakeholders to document their progress on the project before the transition.

D.

Accept the risk as these changes are part of the organizational culture.

Full Access
Question # 153

A company is going through a large cost-cutting initiative. Senior management requests a report on the work remaining for outstanding projects.

Which tool should the project manager use for this purpose?

A.

Cumulative flow diagram

B.

Earned value (EV)

C.

Burndown chart

D.

Forecast estimation

Full Access
Question # 154

A project manager has been asked by the human resources (HR) review team to share information about how the project team members interact, communicate, and conduct themselves to reduce the risk of conflicts and improve overall team performance.

What should the project manager do next?

A.

Provide the HR review team with the team norms document.

B.

Invite the HR review team to attend one of the daily standup meetings.

C.

Discuss the resource management plan with the HR review team.

D.

Direct the HR review team to the communications management plan.

Full Access
Question # 155

A project manager has just started a project to build an external web application for customers to track their orders. The project is expected to take 2 years to complete. Customers are very dissatisfied with the time line and demand the project be completed in 1 year.

What should the project manager do to improve delivery?

A.

Review the work packages, schedule, and estimates with the team and consolidate tasks to shorten the schedule.

B.

Schedule more frequent design reviews with the customers and provide prototypes to demonstrate progress and gather feedback.

C.

Ask the sponsor for additional resources and funding to speed up the work and cover additional labor costs.

D.

Review work packages with the team to build a new incremental delivery plan with multiple releases and obtain the customers ' feedback.

Full Access
Question # 156

A project manager is facilitating meetings with a diverse team, considering that the team members come from different cultures and have different backgrounds. What should the project manager do to facilitate effective communication?

A.

Create incentives to promote better communication among team members.

B.

Assign the work packages based on geographical working groups.

C.

Understand and consider the emotions of each team member.

D.

Plan for communication training workshops for all team members.

Full Access
Question # 157

A virtual project team has members located on four continents. The project director is concerned about the declining motivational levels of team members and feelings of noninclusion by other team members. The project director has tasked the project manager with finding a solution.

What should the project manager do?

A.

Develop a plan for individual team members ' growth and organize more team-building events.

B.

Recommend that the project director appoint project managers for each continent.

C.

Set up ground rules for team engagement, taking into consideration different cultures.

D.

Take differences in time zones into consideration when scheduling team meetings.

Full Access
Question # 158

A project team is working on a critical release and the customer wants this feature to be made available as early as possible. The business owner suggests an enhancement during the product demo.

How should the project manager address this request?

A.

Determine the additional funding needed and seek the sponsor ' s guidance.

B.

Support value-based delivery that is aligned with the project objectives.

C.

Follow the project change control process to formalize the change.

D.

Estimate the additional funding needed and seek the client ' s approval.

Full Access
Question # 159

A customer complains that a software update project is failing to deliver value according to the original scope. What should the project manager do to resolve the problem?

A.

Ensure that the project issue log is up-to-date with the customer ' s issues related to the missed stories.

B.

Ensure that the project change log is up-to-date with the stories based on the missed requirements.

C.

Ensure that the project backlog has the features and stories prioritized correctly.

D.

Ensure that the project risk register is current and reflects the impacts posed by stories not delivered.

Full Access
Question # 160

A project is approaching the closing phase. While preparing for the final steps, the quality system is updated in accordance with new international quality standards, resulting in new deliverable/approval procedures.

Which action should the project manager take?

A.

Apply the new list of approval procedures.

B.

Escalate the issue to the project sponsor.

C.

Ask the project team if the scope can be changed.

D.

Inform the customer that the project will be late.

Full Access
Question # 161

A project manager is working in a constantly changing business environment. In order to address this situation, the project manager has decided to use a collaborative leadership style.

Which landscape describes the project environment?

A.

High accountability, little authority

B.

Available resources, bad roadmaps

C.

Good roadmaps, little accountability

D.

Enough authority, insufficient resources

Full Access
Question # 162

A project manager was assigned to lead a global project with a virtual team that is globally dispersed. The project manager has difficulties communicating with the team members and there seems to be frequent misunderstandings and conflicts.

What should the project manager do?

A.

Ask the team members to refamiliarize themselves with the communications management plan.

B.

Organize effective communication training for team members.

C.

Listen to team members actively and change the communication practices accordingly.

D.

Model servant leadership by adapting to team requirements.

Full Access
Question # 163

Three testers joined the project team just before the end of the build. During the project team meeting, the testers indicated that the project quality is poor, and they should not continue testing until all the defects are fixed.

Which three actions should the project manager do? (Choose 3)

A.

Stop the project and review the output.

B.

Ask the testers to provide additional information.

C.

Ask the sponsor for assistance and guidance.

D.

Continue with testing according to the plan.

E.

Brainstorm the issue with the project team.

Full Access
Question # 164

Two experienced team members in a hybrid project are having a conflict about a technical solution. The project manager has already spoken individually to the two team members without successfully resolving the conflict.

What should the project manager do next?

A.

Discuss the topic with the team members in a team meeting.

B.

Replace the two team members with other resources.

C.

Contact the functional managers of each team member.

D.

Schedule a meeting with both team members.

Full Access
Question # 165

A construction project is in its final stage when the owner of a private property where the pipeline is routed refuses to collaborate. The lack of collaboration causes a project delay, but the client insists that the project must be completed as per the contract. What should the project manager do next?

A.

Request additional budget from the project sponsor and raise a dispute with the property owner to force them to collaborate.

B.

Use the contingency reserve, add more resources, and reroute the pipeline to complete the project as per the contract timeline.

C.

Escalate the routing pipeline issue to the project change control board (CCB) and wait for a resolution to the conflict.

D.

Review the agreement with the property owner, schedule a meeting with them to discuss their concerns, and inform the client.

Full Access
Question # 166

A project manager is leading a hybrid project in which one technical team executes tasks using an agile approach, while a second team executes other tasks using a predictive framework. These teams are struggling to cooperate effectively, and several delays have occurred in transmitting information and coordinating activities.

What should the project manager do?

A.

Ask the agile team to establish the working rules for both project teams.

B.

Meet with senior team members of both project teams to establish the working rules for the project.

C.

Ask the predictive team to establish the working rules for both project teams.

D.

Meet with the project sponsor to establish the working rules for the project and inform both project teams.

Full Access
Question # 167

An agile project team is working on a large project involving multiple cross-functional teams in different geographical locations. Some team members are not clear on the next tasks.

Which strategy should the project lead implement to help the team?

A.

Review the prioritized backlog with the project team.

B.

Review the action items with the respective project team members.

C.

Review the project objectives at the next team meeting.

D.

Review the work scope with the functional managers and their teams.

Full Access
Question # 168

A company is involved in a mining project. There are some external stakeholders with no knowledge of the mining industry.

How should the project manager communicate the organizational culture and project goal to these stakeholders?

A.

Hire a company to advertise the project and company through a media outlet.

B.

Prepare a report outlining the organizational structure and project parameters.

C.

Take the stakeholders out informally and verbally brief them about the organization and project.

D.

Ask a team member to directly address the information needs of the stakeholders.

Full Access
Question # 169

A newly assigned team member immediately begins questioning operating procedures. This new team member wants the team to follow operating procedures that the team member had used previously. During assignments, the new team member begins using some of those processes and procedures and suggests these practices to other team members.

What action should the project manager take?

A.

Organize a training for the new team member on the processes the team is currently using.

B.

Speak with the new team member at the retrospective and discuss potential improvements.

C.

Formalize the new processes and implement the team member ' s proposed changes.

D.

Hold a team meeting on governance, operating policies, procedures, and practices.

Full Access
Question # 170

A project manager is working on a project that is using a hybrid approach. One key input for the deliverable will be from the outcome of another project that is using an agile approach.

What should the project manager do next?

A.

Ask the other project manager to change the delivery methodology.

B.

Request that the other project manager develop a work breakdown structure (WBS).

C.

Participate in the other project ' s daily standup meetings.

D.

Align with the other project manager ' s high-level project time lines.

Full Access
Question # 171

A new employee has joined the management team and wants to get a quick overview of all the agile team ' s projects. What should the agile team lead recommend to the employee as a first step to gain this understanding?

A.

Review the information radiators for each project.

B.

Connect with each project ' s scrum master to assess progress.

C.

Meet with each project ' s development team separately.

D.

Attend the daily standup meetings for each project.

Full Access
Question # 172

A project manager notices during project meetings that some team members repeatedly threaten to resign when they do not agree with something. Which phase of conflict escalation is the project in?

A.

Beginning

B.

Resolution

C.

Intensification

D.

Final

Full Access
Question # 173

The velocity of the team is decreasing at every iteration. The project team members are complaining that the user stories are being rejected by the quality assurance team.

Which three actions should the project manager take? (Choose three)

A.

Conduct a root cause analysis (RCA) and identify a solution.

B.

Elaborate on the plan to implement a solution and execute it.

C.

Increase the working time to recover the lost time.

D.

Negotiate with the teams involved to manage team dependencies.

E.

Evaluate the effectiveness of the proposed solution.

Full Access
Question # 174

A new project manager took over a project that has been ongoing for a while. Some project team members are not clear on when the project will end and feel the project has already transitioned into business as usual.

What should the new project manager do first?

A.

Meet with the team and gather their input on the completion rate.

B.

Revisit the timelines of the deliverables and the project.

C.

Consult the sponsor and secure approval to complete the project.

D.

Transition to an agile delivery so project closure will be faster.

Full Access
Question # 175

Before kicking off a high-priority and complex project, what should the project manager do to ensure all project stakeholders are aware of their role scope as it relates to project activities?

A.

Create a communications management plan.

B.

Create a responsible, accountable, consulted, informed (RACI) chart.

C.

Develop a kanban board.

D.

Send a copy of the project charter to all project stakeholders.

Full Access
Question # 176

A project manager is managing a project in a fast-paced environment. The project manager needs to empower the team to collaborate toward an expected outcome and enable high-team performance. The CEO has suggested that the project manager apply a servant leadership style.

What should the project manager do to demonstrate the capabilities of a servant leader?

A.

Encourage all team members to develop the perfect plan to achieve the desired results.

B.

Create an environment where all team members compete to achieve the desired results.

C.

Assess the business case and define the project priorities to motivate all team members.

D.

Define the project ' s objectives and create an environment where all team members can succeed in achieving them.

Full Access
Question # 177

A project is starting its first iteration out of six. During one of the daily meetings, the project manager realized that one of the team members does not have experience working in agile environments.

What should the project manager do?

A.

Give the team member some time to learn agile practices.

B.

Assign an agile mentor and follow the training process.

C.

Ask to increase the capacity of the team to finish on time.

D.

Ask the sponsor for additional budget for training.

Full Access
Question # 178

A team member on an important company project mistakenly caused significant cost overruns. The sponsor informed the project manager and expects the project manager to take action within 1 week. This team member has always been an outstanding performer.

What should the project manager do first to address the sponsor ' s concerns?

A.

Document the team member ' s mistake in the lessons learned.

B.

Train the team member to improve their performance to avoid future mistakes.

C.

Talk with the team member to identify the reason for the mistake.

D.

Relocate the team member to another project due to the mistake.

Full Access
Question # 179

A key stakeholder of a project wants to include additional work before completion.

What should the project manager do?

A.

Request the additional work through governance.

B.

Meet with the stakeholder and explain that additional work cannot be added.

C.

Prioritize the additional work in the backlog.

D.

Collaborate immediately with the stakeholder to complete the additional work.

Full Access
Question # 180

A project is nearing finalization and just released the final product to the customer. The assigned project manager left the company without notice and without sharing any information or documents for the remaining activities. A new project manager has just been assigned to the project.

What should the new project manager do next?

A.

Schedule a lessons learned meeting with the project team and close out the project.

B.

Use the contingency fund to extend the timeline and conduct a detailed review of past deliverables.

C.

Prepare a transition plan to hand over the operations and other closing documentation.

D.

Document the project manager ' s departure and the missing documents in the risk log.

Full Access
Question # 181

A project is in the start-up phase of the project life cycle. The project team consists of 20 people from five different countries. The project team is scheduled to have quarterly face-to-face meetings. However, due to unforeseen circumstances, no face-to-face meetings can occur. The project manager is concerned that the team may not be able to fulfill their individual roles without face-to-face meetings.

What should the project manager do in this situation?

A.

Review the risk register for this unforeseen circumstance.

B.

Utilize virtual teams for meetings and deliverables.

C.

Use the contingency reserve and subcontract the work.

D.

Ask for an extension of time on the project deliverables.

Full Access
Question # 182

To limit the amount of time and cost of using a contract programming firm, a product manager announces that the developers will not be paid for unrequested embellishments to the product. What should the development team and scrum master do to ensure they are paid for all their work?

A.

Have the product manager work with the scrum master to assign specialists to user stories to meet the requirement.

B.

Convert the story points on user stories to hours to provide estimates of the potential costs to the product manager.

C.

Ensure that the task board is used as an information radiator and all stories have enough detail to build the required feature or function.

D.

Refine the definition of done (DoD) for user stories to ensure that part of the completion is a verification review of the code.

Full Access
Question # 183

To ensure effective team communication and processes, a standard set of software including video conferencing is defined for a virtual scrum team. Several team members are reporting problems with their access and cannot adhere to team processes.

How should these issues be resolved?

A.

Individual team members should discuss solutions to resolve the issues after the Scrum is concluded.

B.

The scrum master should ensure the appropriate escalation to resolve the issues.

C.

The product owner owns the open issues until they are resolved.

D.

Individual team members need to submit service desk tickets to resolve the issues.

Full Access
Question # 184

A project manager is leading a software development project. At the start of the project, the project team decides that iterations are the best way to run the project and deliver value to the customer more quickly.

Which three actions should the project manager take? (Choose 3)

A.

Develop the project management plan based on the requirements requested by the customer.

B.

Develop the application as requested by the customer, based on the approved project requirements.

C.

Plan a minimum viable product (MVP) to get early feedback from the customer.

D.

Facilitate a focus group to assess the functionality before development.

E.

Use an agile approach to deliver the product based on sprints.

Full Access
Question # 185

A project lead is managing an agile project. The project activities, which have been placed in a backlog, still need to be refined and prioritized.

What should the project lead use for backlog refinement considering the sprints are 2 weeks long?

A.

Sixty minutes every sprint going through stories with higher story points.

B.

Ninety minutes every three sprints going through stories that are higher priority.

C.

Sixty minutes every sprint going through stories that are higher priority.

D.

Ninety minutes every three sprints going through stories with higher story points.

Full Access
Question # 186

A project manager who has been working on an ongoing volatile project is retiring. A new project manager is collaborating with the retiring project manager to ensure a smooth transition.

What should the new project manager first discuss, review, and clarify during the transition meetings?

A.

Resource management plan

B.

Change management plan

C.

Lessons learned log

D.

Risk register

Full Access
Question # 187

In an ongoing project, there is an argument between two subject matter experts (SMEs) on what the correct approach to design should be. The project manager suggests that the two SMEs meet and come to a consensus.

Which conflict resolution approach did the project manager use?

A.

Compromise

B.

Collaborate

C.

Synergy

D.

Force

Full Access
Question # 188

A project manager is confused when the operational results from previous iteration solutions have not been acceptable to the client. Team members have already delivered all previous solutions, which were accepted by the client as complete.

What should the project manager do?

A.

Recommend a change in the project methodology or the approach.

B.

Develop and execute a stakeholder engagement strategy.

C.

Determine the criteria and measuring systems for objective success.

D.

Allocate more time for mentoring project team members.

Full Access
Question # 189

An experienced project manager is in a meeting with project key stakeholders when they are informed that a senior manager with extensive experience on similar projects will join the project steering committee. The project kick-off meeting is scheduled for the following week.

What should the project manager do next?

A.

Have the kick-off meeting as scheduled and capture any new requirements raised in the meeting.

B.

Have a one-on-one interview with the new senior manager before the kick-off meeting.

C.

Ask the new senior manager to send any new requirements before the kick-off meeting.

D.

Ask the project sponsor to hold the kick-off meeting after the new senior manager has onboarded.

Full Access
Question # 190

A project manager works for an IT consulting firm that has submitted a bid during the request for proposal (RFP) process for a contract that focuses on data center migration and optimization. However, the consulting firm has little experience in data center optimization.

What should the project manager do?

A.

Send the team to a data center optimization training workshop.

B.

Partner with a company that is an expert in this area.

C.

Outsource the data center optimization work to a vendor.

D.

Request a budget to build this competency among project team members.

Full Access
Question # 191

A project sponsor is replaced during a hybrid project closure. The new project sponsor wants to change all of the project documentation to reflect a fully predictive approach.

What should the project manager do next?

A.

Review the key existing project documents with the new project sponsor.

B.

Ask the team to estimate the time it will take to update the documentation.

C.

Address the issue during the lessons learned session of the closing phase.

D.

Set up a meeting with the new project sponsor to understand their concerns.

Full Access
Question # 192

A project manager is preparing a large and complex international project. In order for the team to work well together in a virtual environment, the project manager needs to set up ground rules for good communication.

What should the project manager do first?

A.

Establish a communication channel.

B.

Create a communication protocol.

C.

Develop the stakeholder analysis.

D.

Distribute the risk register.

Full Access
Question # 193

A project manager assigned to an agile project realizes that after iteration demos, new user stories to fix issues reported by the product owner are not included in prioritization of the following sprint. This has led to a high number of unprioritized stories in the backlog and will lead to delay of the product release.

What should the project manager do?

A.

Review the minimum viable product (MVP) user stories and ensure all related stories are prioritized.

B.

Ask the team and product owner to reprioritize the user stories in the backlog for an updated iteration schedule.

C.

Ask the team to include the user stories as spikes in the next iteration to bring the project back on schedule.

D.

Add additional iterations to the schedule to accommodate for the work required on the stories.

Full Access
Question # 194

A software delivery project is in the execution phase. The project team has identified a need for an additional server as the software requires more data storage space than planned for. Without the additional server, the project delivery cannot continue.

What should the project manager do?

A.

Use the project budget and procure a new server before raising a change request.

B.

Request that the requirement is funded with the business operational expenses.

C.

Apply contingency reserves to procure a server that fits the requirement.

D.

Raise a change request and obtain approval from the project owner.

Full Access
Question # 195

A project manager is assigned to a research project. The project team has been selected and has worked together on other projects. Based on the project documentation, team members seem to be working at their own pace and have had little interaction with the project manager.

What should the project manager do to have a high-performing team?

A.

Set up regular project status meetings and invite all team members.

B.

Encourage the team to define the ground rules for performance.

C.

Set up individual calls to follow up on each team member ' s progress.

D.

Invite team members to an informal meeting to get to know one another.

Full Access
Question # 196

A project manager is leading a large-scale project to be deployed in another country, for an external company. After working with the project team, the project manager learns there are many stakeholders from the project manager ' s organization, the client organization, and the local community.

What should the project manager do after identifying the stakeholders?

A.

Prioritize stakeholders from the client ' s organization and the local community.

B.

Prioritize stakeholders from the project manager ' s own organization.

C.

Prioritize the stakeholders that are more interested in the success of the project.

D.

Prioritize the stakeholders that may have more impact on the development of the project.

Full Access
Question # 197

A project manager received several complaints from different project team members related to an unnecessary additional step the functional lead implemented as a preference. The project team members ' work has been affected by this and they have missed a few deadlines.

What should the project manager do to address this concern?

A.

Recommend the functional lead meet with the project team members to convince them to accept the change.

B.

Document the additional step from the functional lead and adjust the timelines to accommodate the change.

C.

Ask the functional lead to remove this additional step as it is not vital to the project.

D.

Advise the team that the functional lead ' s preference should be taken into consideration.

Full Access
Question # 198

The project team completed a demonstration of the main deliverable of the project. Although the project sponsor is happy with the outcome and is ready to sign the release to production, one of the business unit managers who attended the demo believes that the deliverable is not complete.

Which document should the project manager use to resolve this situation?

A.

Requirements traceability matrix

B.

Risk management plan

C.

Project scope statement

D.

Requirements management plan

Full Access
Question # 199

A project manager has developed a communications management plan. A junior team member asks why they are duplicating efforts by producing different versions of the same newsletter.

How should the project manager respond?

A.

Explain that each stakeholder expects a different customized newsletter, ensuring it complies to all of their requirements.

B.

Explain that to prepare for all situations and as part of risk mitigation, many different newsletters are created just in case they are needed.

C.

Explain that customized newsletters are part of the organizational culture and that following this step-by-step process is of utmost importance.

D.

Explain that each individual newsletter is based on specific categories of communication for the intended audience.

Full Access
Question # 200

A project manager ' s team has been working very hard to meet a critical deadline. Some project team members are experiencing burnout due to the high workload.

What should the project manager do first to manage the team ' s workload effectively?

A.

Add additional temporary resources to the project to achieve the next milestone.

B.

Encourage open communication and involve the team in task distribution decisions.

C.

Assign additional tasks to high-performing team members to decrease the burden on others.

D.

Renegotiate the scope of the next milestone with the stakeholders to align with the team ' s capacity.

Full Access
Question # 201

During a business review meeting, a key stakeholder raised a concern on the quality of deliverables and has now escalated the concern.

What should the project manager do first?

A.

Schedule a meeting with all team members to clarify and plan next steps.

B.

Discuss with the stakeholder and share a report on the deliverables.

C.

Discuss with the team and check all reports on the deliverables.

D.

Schedule a meeting with the stakeholder to clarify and plan next steps.

Full Access
Question # 202

A project lead has asked a project team to update a 200-page project report and send it to the project sponsor. The team mentioned that nobody reads the report and it takes time away from higher priority work. The project lead responded that they have to show all the work that they performed in every iteration.

What should the project lead do first?

A.

Summarize the project report so it can be more efficient to read and send it to the project sponsor.

B.

Ensure the communications methods, channels, frequency, and level of detail for the stakeholders are what is needed.

C.

Reinforce the need to document and provide updated information to make the process transparent.

D.

Include a task in every iteration to allocate time for the project team to complete the documentation updates.

Full Access
Question # 203

A project manager is new to an organization that typically follows a hybrid approach but is shifting to incorporate more agile. A dedicated project team has been provisionally assigned. The new project manager needs to review the internal environment in order to build a high-performing team.

To build a high-performing team, which three factors should the project manager evaluate? (Choose 3)

A.

Review the team ' s capability to determine if they have the skill set needed to proceed forward.

B.

Evaluate the infrastructure to determine if the team has the appropriate equipment and communication channels.

C.

Perform a benchmark analysis across similar sectors to determine if the structure can be followed.

D.

Review the customer governance documents so that they align with the set expectations.

E.

Assess the organizational culture to determine if more needs to be done to foster psychological safety.

Full Access
Question # 204

A scrum master is receiving conflicting status updates for the same task. How should an accurate status be obtained from the team?

A.

Encourage team members to work together.

B.

Establish a clear definition of done (DoD) for each task.

C.

Assign one person to be responsible for the task.

D.

Review the deliverable carefully and determine the right status.

Full Access
Question # 205

In the execution phase of a project, the development team is informed by the IT security department that one of the external platforms that the team is using will be uninstalled for the whole organization.

What should the project manager do first?

A.

Escalate the issue to the change control board (CCB).

B.

Ask the project team to analyze the impact.

C.

Register the risk and document the contingency plan.

D.

Have the project team brainstorm alternatives.

Full Access
Question # 206

A project manager is working on a software development project. Software development will be carried out through a partnership with a vendor based on a list of initial requirements not yet completely defined.

What type of contract and project approach should the project manager consider?

A.

Time and materials (T & M) with an agile approach

B.

Cost reimbursable contract with a predictive approach

C.

Fixed-price contract with a predictive approach

D.

Memorandum of understanding (MOU) with an agile approach

Full Access
Question # 207

An agile team is funded for a fixed 6-month period. The sponsor ' s request will take at least 12 months to complete.

What should the project manager do?

A.

Inform the sponsor that the team is unable to complete the requests due to a lack of funding, and defer the project.

B.

Prioritize the scope items to determine the duration needed for a minimal viable product (MVP) and adjust the funding request.

C.

Have the team work on the list of requests from the sponsor without modification until the 6-month period ends.

D.

Request the team complete all scope items, with the assumption of securing additional funding within 6 months.

Full Access
Question # 208

A key project stakeholder recently joined the project and is questioning some of the previously made decisions. This starts to impact project execution.

What should the project manager do?

A.

Reach out to the stakeholder via phone to explain that all decisions have been agreed upon with their predecessor.

B.

Provide the stakeholder with a link to a file-sharing site where the supporting documents for decisions are filed.

C.

Schedule a meeting with the stakeholder to provide an overview of the project, including the agreed-upon decisions.

D.

Update the risk register with a new risk of potential project changes as a result of stakeholder misalignment.

Full Access
Question # 209

The team ' s velocity is inconsistent, leading the product owner to believe the team is creating too many points in their user stories.

What should the scrum master do first?

A.

Remind the product owner that their role is to determine what the team should work on during the iteration.

B.

Meet with the product owner for planning and to resize the stories in the backlog.

C.

Invite the product owner to planning poker meetings and get their approval after each story is sized.

D.

Raise this concern with the team and review the performance of the past three sprints.

Full Access
Question # 210

A project was recently flagged as being noncompliant during an inspection. Several options were suggested on how to address the noncompliance, but each may have different impacts on the budget, schedule, and quality.

How should the project manager proceed?

A.

Review the risk register.

B.

Perform a cost-benefit analysis.

C.

Determine the cost of change.

D.

Conduct a root cause analysis (RCA).

Full Access
Question # 211

A project manager is working in a regulated industry. The minimum viable product (MVP) for the launch has been defined. The project manager learns that the regulatory body requires a prototype for inspection before the product can be launched; however, the prototype is not part of the MVP definition.

What should the project manager do next?

A.

Speak with the product manager to prioritize the compliance-related activities high enough in the backlog to submit a prototype to the regulatory body.

B.

Identify the missing requirements, prioritize the missing compliance work directly into the backlog, and assign the work to the team.

C.

Reschedule the launch of the product until the team can produce a prototype for inspection as required by the compliance team.

D.

Create an MVP that contains the scope for the prototype and that will be prioritized with the compliance team.

Full Access
Question # 212

A project team consisting of 13 people was set up three months ago. As part of the transition to agile, a scrum master was assigned to the project. The scrum master wants to know the status of the team ' s development stage. The project manager believes that the team has passed the " storming " stage.

Which indicators should be used to determine the team ' s development stage?

A.

Scrum ceremonies are held per the Scrum guide.

B.

Team members share information and experiences.

C.

Formal training courses have been completed by team members.

D.

Project deliverables are formally approved.

Full Access
Question # 213

A project manager is leading a complicated project that requires integrating several components from different suppliers. During execution, the project team indicates that some components are not being delivered to the site on time, affecting the project schedule.

What should the project manager do to address this concern?

A.

Register the issue as a risk with the project team members.

B.

Review the project schedule with project team members and the suppliers.

C.

Advise the procurement department to develop a new supplier strategy.

D.

Use the procurement and risk management plans to manage this issue.

Full Access
Question # 214

Due to scope changes, some of the risks identified during the initiation phase have materialized into issues. What should the project manager do next?

A.

Submit a request to access contingency reserves and accept the changes.

B.

Submit a change request for additional resources and accept the changes.

C.

Ask the project sponsor to reject high-risk scope changes.

D.

Closely monitor scope changes and implement corrective actions.

Full Access
Question # 215

A project manager has an engineering team mostly comprised of new hires. The project manager has to carefully predict in which stage of the project they will need to spend most of their time to ensure the team is properly integrated and performing well.

In which stage of the project would the project manager need a greater effort to lead them?

A.

Performing

B.

Storming

C.

Norming

D.

Forming

Full Access
Question # 216

A project team is using a vendor solution. The project team has been notified that the vendor solution will no longer be on the premises, but in the cloud. The cloud transition will require additional infrastructure resources and adherence to new security standards.

What should the project manager do first?

A.

Initiate a change request for covering additional security scope.

B.

Research alternative vendor solutions for on-premise security.

C.

Ask the sponsor to provide security training for the project team.

D.

Schedule a meeting with security to understand the standards.

Full Access
Question # 217

A project manager is in the process of authoring the communications management plan for a new project. One of the project ' s stakeholders has a habit of posting work updates on social media, which may include confidential project status updates.

What should the project manager do?

A.

Ensure that social media posts related to the project are removed.

B.

Ensure that sensitive information is not included in stakeholder updates.

C.

Review social media access and restrict it to ensure confidentiality.

D.

Review the protocols and security measures to ensure confidentiality.

Full Access
Question # 218

A global and complex project is in the execution phase. Recently, there were executive board changes, and the executive sponsor is transitioning to a new role. The outgoing sponsor asked the project manager to speed up project completion of the current phase to ensure successful onboarding of the new sponsor.

What should the project manager do?

A.

Use the contingency budget to implement compression techniques to finish the current project phase early.

B.

Review the stakeholder engagement plan and determine the best course of action to take.

C.

Notify the outgoing sponsor that the project needs to be put on hold until the new sponsor is onboarded.

D.

Submit a change request to the change control board (CCB) to modify the end date of the current phase.

Full Access
Question # 219

Construction work is preventing the project team members from entering the building where their offices are located.

What should the project manager do next?

A.

Inform the authorities so that they are aware of the situation and can take appropriate action.

B.

Continue business as usual since the construction work is not related to the project.

C.

Select the next action to be taken according to the risk management plan.

D.

Communicate with the stakeholders about the construction and ask for direction.

Full Access
Question # 220

Presented with flowcharts of the organization ' s operations, stakeholders are unfamiliar with several recorded processes, and others note that some recorded processes were discontinued. The project sponsor notices that the chart is several years old and wants an updated version immediately.

What should the project manager do?

A.

Assemble the entire project team to produce new flowcharts from current versions.

B.

Assemble and create teams of experts and stakeholders to update flowcharts to reflect current conditions.

C.

Raise a change request and ask the project sponsor to approve it so the flowcharts can be updated.

D.

Work with a consultant and the project sponsor to produce new flowcharts.

Full Access
Question # 221

A project manager leads an agile development project. During the sprint planning meeting, the development team expresses concerns that the proposed scope of the next sprint is much larger than expected given the current resource allocation. The project manager believes the scope is essential to meet the project milestones.

How should the project manager approach negotiating an agreement with the team to ensure the project remains on track?

A.

Allocate additional resources to the development team to ensure the original scope can be completed on time.

B.

Suggest prioritizing the most critical features for the next sprint as well as reevaluating the remaining scope.

C.

Agree on reducing the scope to match the team ' s resources and plan to add the removed items to future sprints.

D.

Insist on keeping the original scope and explain the importance of meeting all the project milestones on time.

Full Access
Question # 222

A team member mentions to the scrum master that the user stories are too long. The team member believes this may be the cause of the team ' s inability to deliver value for stakeholders.

What should the scrum master do?

A.

Review the user stories with the team and ask the product owner to break them down into more manageable units.

B.

Review the user stories with the stakeholders and ask the product owner to break them down into more manageable units.

C.

Ask the team member to suggest using shorter user stories to the product owner so that the next sprint can move faster.

D.

Ask all the team members for their views about using shorter user stories so that value can be created for stakeholders.

Full Access
Question # 223

A project lead was asked to support the team by subdividing the project tasks as necessary to help define the minimum viable product (MVP).

Which two steps should the project lead take to define the MVP? (Choose 2)

A.

Hold a team meeting to generate a work breakdown structure (WBS).

B.

Create a responsible, accountable, consulted, informed (RACI) chart.

C.

Develop a project management plan, including subtasks, to meet the requirements.

D.

Conduct an information gathering session to determine the project value.

E.

Refer to the stakeholder register to determine who should be consulted.

Full Access
Question # 224

A project manager has been assigned to a project where collaboration with the business is a critical key factor. The project manager is not sure about which approach to use. A senior project manager has been assigned to help the project manager.

What advice should the senior project manager provide?

A.

Provide a project management template for the project manager to follow as a guide.

B.

Suggest using an agile approach since customer and team collaboration is critical for project success.

C.

Work with the project manager to develop a new approach that will bring benefits to the project.

D.

Establish a project management methodology that requires the customer to provide daily updates to the team.

Full Access
Question # 225

A project manager gas been asked by the project manager office (PMO) to select the appropriate project management approach for three upcoming projects. Match the projects on the left with the approach that should be used on the right.

Full Access
Question # 226

After reviewing the lessons learned database, a project manager realizes that the current team may not be knowledgeable enough about organizational processes for the needs of a new project. What should the project manager do?

A.

Develop the team members to work as a cross-functional team.

B.

Ask a functional manager to provide the right team members.

C.

Review the project charter to see if the scope can be modified.

D.

Ask the portfolio manager to reassign the project to another team.

Full Access
Question # 227

A project manager just took over a construction project which was already in its execution phase. Labor union representatives of the construction workers ask to revise the overtime per hour rate, as wage per hour have increased across the industry.

What should the project manager do first?

A.

Obtain approval from sponsors to increase the rates because it can affect project due to lack of resources.

B.

Carefully read the agreements and see if there was any clause if the per hour rate could be increased.

C.

Assign a team member to negotiate the increased wage per hour with the labor union representatives.

D.

Negotiate with the labor union representatives if the clause about increased wage per hour meets their requirements.

Full Access
Question # 228

A company is transitioning from using a predictive approach to using an agile framework on a project. The project sponsor is concerned about the level of uncertainty and how to determine the time and budget required to complete the scope.

What should the project manager do to address this situation?

A.

Communicate to the key stakeholders that the project baseline could not be estimated due to the new framework being used.

B.

Ask the project team to create a high-level budget baseline for the project and provide more detail only for the first project stages.

C.

Review organizational process assets (OPAs) for similar projects to determine the schedule, costs, and resources required to execute them.

D.

Refine the amount of work required for the project with the project team and perform a detailed project baseline accordingly.

Full Access
Question # 229

A project manager Is working on a project using a hybrid approach. The project Is scheduled to be completed in three more sprints. One of the team members notifies the project manager that they are leaving the company which was approved by their functional manager

What should the project manager do first in this situation ' ?

A.

Ask the functional manager why a decision was made without consulting them

B.

Use soft skills to influence the team member to slay until the project is completed

C.

Ask the functional manager for an immediate replacement for the team member.

D.

Review the risk management plan and mitigation plan to understand the impact of this issue

Full Access
Question # 230

A project manager is leading a new project that is in the initiation phase, The project will build a new type of software technology service that has never existed at the organization before and will reenginger the business process for several operations teams. The project manager needs to determine the project management approach to be used, and there are many team

members and stakeholders who have contradictory opinions.

What should the project manager do?

A.

Meet with the stakeholders to determine the approach using the project goals and desired outcomes.

B.

Leverage agile methods only as the project pertains to software implementation, which can be broken into increments.

C.

Leverage hybrid methods as the project has a blend of work that needs to bring in both agile and predictive methods,

D.

Determine what methods the team has been trained on and utilize those methods for the project.

Full Access
Question # 231

The product backlog has been completed and prioritized. and the first sprint has begun A team member advised that during the daily standup there is a delay in having an external vendor contract signed.

What is the project manager ' s priority in this situation?

A.

Request that the team member gel the contract signed as soon as possible

B.

Determine a mitigation strategy to move the project forward

C.

Take over contract negotiations for the team member to speed up the process

D.

Assist with the removal of impediments and blockers so that the project can continue

Full Access
Question # 232

A project manager is reviewing the requirements of a large program. Which requirements should the project team prioritize to avoid getting fines?

A.

Developing new product lines

B.

Complying with new regulations

C.

Establishing company processes

D.

Certifying sustainable products

Full Access
Question # 233

A project manager finds an unexpected issue halfway through a customer ' s protect After analysis the project team determines that the issue will affect the timeline unless more resources are allocated to the project.

What should the project manager do?

A.

Meet with the project team to discuss internally whether they think cost is more important to the customer than the timeline

B.

Adjust the timeline since in the past the customer would not pay any additional costs then inform the customer of the change

C.

Inform the customer of the issue and discuss the options so that they are able to make a decision on cost versus timeline

D.

Absorb the additional cost for the additional resources internally so that the project completes within the timeline

Full Access
Question # 234

A project manager needs the team to define the steps and identify the risks of migrating data to a new system.

What type of leadership should the project manager use to accomplish this?

A.

Laissez-faire

B.

Transformational

C.

Dynamic

D.

Servant

Full Access
Question # 235

A project manager working on a software development project asked the software development about the status of a task. The developer responded that the task was delivered 1 week ago and mentioned that the delivery was reported via a specific project management software.

What should the project manager do next?

A.

Review the stakeholder engagement plan and communicate which technology is available to develop, transmit, and store project artifacts.

B.

Engage the software developer, let them work with this project management software, and then conduct a train-the-trainer activity to ensure everyone can use it.

C.

Research the project management software to understand how it works, and establish it as the acceptable software to hold the project artifacts.

D.

Review the communications management plan and communicate which technology is to be used to develop, transmit, and store project artifacts,

Full Access
Question # 236

A project manager works in a startup company and is in charge of a key project that has critical and time-sensitive delivery objectives. One of the project team members missed completing an assigned deliverable on time, despite repeated assurances from the team member that it would be completed on time

What should the project manager do next?

A.

Record the issue then refocus the team ' s efforts on delivering the next set of deliverables

B.

Give the team member a formal warning for the negative impact due to failure to delrver and not meet deadlines

C.

Hold a team meeting to discuss team member commitments and communications

D.

Meet with the team member and work on a development plan for them to avoid missed deliverables in the future

Full Access
Question # 237

A project manager is leading a project to modemize the information technology of a bank. The project manager needs to determine how the project stakeholders should communicate, and has discussed the various options with the project team.

What should the project manager do to communicate with the stakeholders?

A.

Provide updates to the project sponsor to review and distribute to each stakeholder.

B.

Use a single communication medium such as video teleconferencing to limit confusion.

C.

Use a variety of communication methods that respect cultural, practical, and personal preferences.

D.

Send frequent updates via email to each stakeholder because this is an information technology project.

Full Access
Question # 238

A global program is being kicked off, and various distributed teams are Involved in delivering the initiative. Besides planning and executing the scope for the initiative, team interactions must be considered.

How should the project teams interact in their meetings?

A.

Phone conversations

B.

Encrypted emails

C.

Videoconferencing

D.

Chat conversations

Full Access
Question # 239

A project manager for a large software delivery project is in the process of finalizing the project governance, The project manager would like to implement procedures that do not align with several policies required by the organization ' s project management office (PMO). The project manager

believes that the procedures outlined in the project governance will be necessary for this particular project due to the unique nature of the

technology.

What should the project manager do?

A.

Engage stakeholders to modify policies outlined by the PMO.

B.

Move forward with the project governance and inform the PMO.

C.

Discuss the proposed changes with the PMO.

D.

Disregard the initial procedures and follow the policies outlined by the PMO,

Full Access
Question # 240

A new project manager is assigned to a project that will deliver a new and optimized credit system. The project manager is allowed to use a hybrid approach which is new to the organization to manage the project and new tools

In order to deliver the project successfully, what should the project manager focus on as part of the plan?

A.

Align with the organization ' s project management office (PMO) to inform and make them aware of the new approach

B.

Explain and communicate the new approach to the project sponsor and key stakeholders

C.

Develop a detailed schedule for the entire project m the planning phase and communicate that to the stakeholders

D.

Communicate with other project managers to see how they manage hybrid projects

Full Access
Question # 241

A procurement team lead has been reported as getting into conflicts with other project team members on a weekly basis, The project manager engages with the team lead and discovers that other team members do not believe the team lead is right for this position.

What should the project manager do to resolve these recurring conflicts between the team lead and the other team members?

A.

Receive details of the conflicts from all involved, issue all a warning notice, and send all to leadership training.

B.

Organize a meeting to discuss emotional intelligence with the team, and establish a rule of respect and special treatment for the team lead.

C.

Issue the team lead a warning, and consider recommending the team lead for emotional intelligence training.

D.

Find ways to reduce the tension, increase cooperation, and understand the emotions of all team members involved.

Full Access
Question # 242

Anew systems project requires feedback from the accounting manager at the beginning of solution discussions and before meeting with other functional managers. The project manager knows the accounting manager will not be available until a few days before the deadline for the solution

document.

What should the project manager do to avoid a delay in the project?

A.

Ask the accounting manager to delegate a team member who can support the project.

B.

Wait for the accounting manager to be available while identifying subsequent tasks that can be compressed,

C.

Request that the sponsor direct the accounting manager ' s supervisor to provide a replacement resource,

D.

Begin discussions with other functional managers and meet with the accounting manager later.

Full Access
Question # 243

At the end of a third planning meeting, the client and a functional manager requested additional meetings to add more features to the product.

What should the project manager do to start building the product faster?

A.

Allow the sponsor to determine how long the planning phase should last.

B.

Allow the client ta determine how long the planning phase should last.

C.

Ask the functional manager to work with the team to finalize planning and begin building the product.

D.

Explain that more features can be planned in upcoming Iterations and begin building the product.

Full Access
Question # 244

project manager for a defense software application has a culturally and gender-diverse team with a short project time line Considering the project will be stressful what skill should the project manager use to monitor the team ' s performance?

A.

Coercion

B.

Conflict resolution

C.

Emotional intelligence

D.

Negotiating

Full Access
Question # 245

A project manager is working toward a deadline to prepare a client report. The project manager prepared a meeting agenda but not a single meeting has gone according to plan True, meetings always end in arguments and no action items come out of it. The project manager is very frustrated and seeks help from the project sponsor

What should the project manager have created to prevent this situation1?

A.

Resource breakdown structure

B.

Work breakdown structure (WBS)

C.

Team charter

D.

Project charter

Full Access
Question # 246

A scrum master is receiving conflicting status updates for the same task How should an accurate status be obtained from the team?

A.

Review the deliverable carefully and determine the right status

B.

Assign one person to be responsible for the task

C.

Establish a clear definition of done (DoD) for each task

D.

Encourage team members to work together

Full Access
Question # 247

A protect is going through its iterative design stage One of the team members has been performing poorly. This is a critical project for the company and execution is about to start What should the project manager do?

A.

Request action from the functional manager regarding the team members poor performance

B.

Avoid selecting the team member to the next project that has an iterative design stage

C.

Provide feedback and coach the team member during the iterative design stage

D.

Escalate the issue to the human resources manager and request that the team member be replaced

Full Access
Question # 248

A software development provider reports an issue that is blocking the other remaining deliverables What should the project manager do?

A.

Ask the provider to seek options to solve the issue

B.

Add the issue to the issue log and report it at the next review meeting

C.

Review the current plan and consolidate if necessary

D.

Schedule a meeting with the provider to collaborate on the options

Full Access
Question # 249

One deliverable for a project is to translate and print materials for students every 2 weeks Printing services are available but without guaranteed time lines because other projects make a significantly higher profit and have a higher priority

What should the project manager do to mitigate the risk of not having the materials printed on time?

A.

Meet with the manager to set a high priority for printing the materials

B.

Create a change request to modify the print requirements

C.

Include a risk response in the resource management plan

D.

Purchase a high-volume printer specifically for this project.

Full Access
Question # 250

A sales team working on an IT deployment project approached the project manager on several occasions and complained about nonpayment of their overtime pay. The project manager realized that other team members are receiving their overtime pay

What should the project manager do next?

A.

Have a discussion with the sales team to find a solution to the issue

B.

Validate the reason and add n as an issue m the issue log

C.

Escalate the issue to the functional manager

D.

Direct the sales team to speak with accounting to resolve the issue

Full Access
Question # 251

A bank has decided to initiate a project to transition from serving small businesses and entrepreneurs to mid- and large-scale businesses The country ' s economy is struggling, and some stakeholders cannot agree on this transformation need

What should the project manager do ' ?

A.

Escalate the issue to the sponsor and ask for stakeholder engagement

B.

Review the project business case and update it periodically

C.

Plan for strategic program management

D.

Implement a communications management plan

Full Access
Question # 252

A project manager is a part of the project management office (PMO) and Is tasked with finding a reputable vendor to provide on-site support for their project. The project sponsor stresses the urgency of the need and suggests using a vendor they know to provide the support.

What should the project manager do given the urgency?

A.

Consult preferred vendors from the company.

B.

Perform research on experienced vendors in the market.

C.

Source vendors with extensive experience.

D.

Follow the company ' s standard vendor selection criteria process,

Full Access
Question # 253

A project manager is working on a construction project. The company owner asks the project manager to provide cost estimates for the new decoration project within 4 hours.

How will the project manager be able to complete this task?

A.

Tell the owner that a rough order of magnitude will be provided.

B.

Contact a subject matter expert (SME) for advice and consultation.

C.

Call a meeting with the project team to identify the most appropriate approach.

D.

Tell the owner that the task requires more time and expertise

Full Access
Question # 254

A supplier, who was tasked with providing an important component for a project, is unable to deliver the materials due to a large-scale labor problem. What document should the project manager use to update the details and communicate to relevant stakeholders?

A.

Risk register

B.

Project schedule

C.

Change request

D.

Issue log

Full Access
Question # 255

An agile project team is tasked with a new project After multiple discussions with me customer it appears that there is a lack of clarity on the requirements which resulted in delays in the architecture and design phase

What should the team do next?

A.

Start with the end user documentation review with the customer and gather feedback

B.

Start with design of the prototype review with the customer and gather feedback

C.

Start with the product prototype development, review with the customer, and gather feedback

D.

Start with the product architecture review with the customer and gather feedback

Full Access
Question # 256

A project manager has been assigned to lead a major project in a government organization. There are no policies and procedures for project management since there is no project management office (PMO) The managers involved are unaware of their responsibilities for the project

What should the project manager do?

A.

Start planning the project and then request that a PMO be implemented in the organization

B.

Request that the implementation of a PMO be executed in parallel with the project

C.

Provide project management training to only the internal team involved m the project

D.

Provide project management training to the stakeholders and explain their responsibilities

Full Access
Question # 257

A project manager for a technology project is informed by the cybersecurity team that

there are changes in the government ' s cybersecurity requirements. The project manager calls a team meeting to discuss the requirements, and the team learns that the design changes can be made at no additional cost.

What should the project manager direct the team to do?

A.

Update the scope management plan to track the new government requirements.

B.

Accept the cybersecurity team’s request as the security of the company is at risk ofbeing noncompliant.

C.

Ask the project sponsor to increase funds in the contingency reserve as a risk mitigation.

D.

Request a change through the change control process to manage the new cybersecurityrequirements.

Full Access
Question # 258

A project manager is consolidating information tor all the workstreams within a data center and IT service transition project To ensure the project delivers value quickly the project manager will assess a large number of consolidated project schedules

Which two actions should the project manager take with regard to schedule analysis? (Choose two)

A.

Review with subject matter experts (SMEs) to ensure they have contributed to the schedule development

B.

Evaluate the master schedule and perform fast tracking and task crashing

C.

Look (or gaps in the different schedules to determine which major risks might evolve over time

D.

Review the project schedules to ensure that all tasks end with milestones

E.

Evaluate the schedules for interdependencies to establish the critical path

Full Access
Question # 259

In a geographically distributed project team, the project team members continue to email status reports and update schedules after their weekly meeting discussions. However, the team is having difficulty tracking the changes and progress made.

What should the project manager do?

A.

Maintain a central repository of artifacts with a version control system.

B.

Maintain separate document control via regions to avoid discrepancies.

C.

Develop a document management software for version control.

D.

Facilitate training on version control and project artifacts,

Full Access
Question # 260

During a project to develop a new pharmaceutical product, the project manager was informed that there has been a change in government regulations regarding the materials of the project.

What should the project manager do?

A.

Review the procurement documentation and modify requirements as needed.

B.

Study the new regulations with the team and evaluate if there is any impact on theproject variables.

C.

Update the contingency plan to take this issue into account.

D.

Meet with the stakeholders to update the risk register and risk management plan.

Full Access
Question # 261

An agile team has completed 9 out of 10 stones tor the sprint. During the retrospective a few team members pointed out that they finished a of their stories However one team member tailed to finish a story

What should the agile leader do1?

A.

Emphasize to the team that each member is responsible for their story but the team is collectively responsible for finishing the sprint

B.

Ask the team to address this at the next sprint planning instead of at the retrospective

C.

Suggest that the team assign stones at the beginning of the sprint based on each person ' s strengths to maximize performance

D.

Work with the product owner to remove the story from the sprint because the points cannot be splits

Full Access
Question # 262

A company is transitioning its projects from a predictive to an iterative approach. The protect team is complaining because they are unsure of what needs to be done due to all of the changes requested by the product owner for features already developed since the beginning of the project.

How should the project manager handle this situation?

A.

Ask the product owner to create a new entry in the risk management plan regarding likelihood and imped

B.

Review the backlogs from similar projects and understand how change requests were implemented

C.

Ask the product owner to follow the change request process to formalize new requirements

D.

Make sure that the product and sprint backlogs have the required level of documentation and both are visible to the team

Full Access
Question # 263

A company is launching a new product and decides to transition from a predictive to an agile approach. During the third sprint the project manager notices that the team is not working as a cohesive unit

Which two rules are appropriate tor the project manager to instill in the team? (Choose two)

A.

Strive toward continuous improvement

B.

Work together daily as a team

C.

Only share suggestions at the end of the sprint

D.

Follow the sprint planning

E.

Send communications to the entire team

Full Access
Question # 264

During a standup meeting, a team member raises the issue that they have blockers and impediments preventing them from moving on to the next task. How should the project lead

handle this situation?

A.

Support the team member by removing the blockers and impediments.

B.

Allocate the blockers and impediments to the product owner to resolve.

C.

Insist that the person who raised the blockers and impediments take ownership.

D.

Add any blockers or impediments to the risk register,

Full Access
Question # 265

During a project meeting, the project manager asks risk owners to present issues that may affect the backlog. During their presentation, the project manager realizes that some risk owners did not implement the already agreed-upon risk responses.

What should the project manager do to reduce exposure?

A.

Report the risk owners to the project management office (PMO) with the recommendation to remove them from the team.

B.

Reassign the outstanding risk tasks to other team members who have implemented their risk responses.

C.

Ask the risk owners to implement the risk responses before the next meeting and present the results in the meeting.

D.

Meet privately with the risk owners and work with them to address any impediments to the risk responses.

Full Access
Question # 266

A project is nearing completion. The sponsor is already asking the project management office (PMO) when the project manager will be assigned to host a planning session for a new initiative.

What should the project manager do next?

A.

Review organizational process assets (OPAs) for clarity.

B.

Document lessons learned before closing.

C.

Consult the project charter for next steps.

D.

Confirm the definition of done (DoD) has been met.

Full Access
Question # 267

A project manager is working on a project to modernize the information technology of a bank, The project manager is facing challenges with the project sponsor regarding how to proceed with implementation of a key piece of technology.

How should the project manager resolve this conflict?

A.

Meet with all project stakeholders to identify how to implement the technology.

B.

Identify the disagreement in the risk register and develop a contingency plan.

C.

Update the project charter to align with the desires of the project sponsor.

D.

Negotiate with the project sponsor to develop a mutually beneficial solution.

Full Access
Question # 268

A client comes to the company asking to copy a project that was executed 2 years ago

in the same city, with the expectation that the new project will have the same cost and duration.

While finalizing the project management plan, the project manager realizes that the baseline

costs are much higher than the original project.

What could the project manager have done to avoid this?

A.

Verified applicable budget inputs related to this project

B.

Assigned the same project resources to this project

C.

Estimated a budget for the project ' s quality management

D.

Determined a budget reserve for this project

Full Access
Question # 269

A project manager for a software technology project works in a matrixed organization with virtual teams. Unfortunately, the functional manager informs the project manager that there may not be any resources available to test the software.

What should the project manager do next?

A.

Engage with the functional manager to discuss details to obtain the required support.

B.

Request a teleconference meeting with the sponsor to submit a change request to allow the development team to conduct testing.

C.

Discuss testing requirements at the weekly project meeting to negotiate the best approach to test software.

D.

Send an email to the procurement specialist to negotiate with a company that specializes in software testing.

Full Access
Question # 270

A company has undertaken a large transformation project using agile practices. The project sponsor has asked the project manager to promote the new values identified in the intended transformation to the project team

What should the project manager do?

A.

Add a user story during sprint planning that gives recognition to behaviors that are aligned with the new values

B.

Send a standard email to the team prior to every daily standup containing the new values

C.

Organize a team meeting focusing on the new values associated with the transformation

D.

Give recognition to team members ' behaviors that are aligned with the new values during the sprint retrospectives

Full Access
Question # 271

A company strictly uses an agile approach, and the backlogs are continuously updated. A new project lead is hired and feels uncomfortable sharing some of the product ' s vital information with the team and the product owner.

What does the project lead need to do to prevent a risky situation in the next iterations?

A.

Keep the project focused and executed in silos for better outcomes.

B.

Report the concern to the agile project management office (PMO),

C.

Inform the product owner of the concern so that i can be addressed.

D.

Open up to the team to work collaboratively to achieve the outcomes.

Full Access
Question # 272

A construction services company has influence within the local community with the potential to derail a project site establishment. Their build was unsuccessful but they continue to communicate with the hope that their influence will persuade the project manager to reconsider their offer.

What is the appropriate course of action for the project manager to pursue?

A.

Do not communicate with the unsuccessful bidder as they do not have any further influence on the project

B.

Meet with the unsuccessful bidder to review their submission and the areas that led to the bid being unsuccessful

C.

Reassess the bid to establish areas for improvement with the intention to assign work to this contractor

D.

Report the unsuccessful bidder to the local community leadership who have been supportive of the project

Full Access
Question # 273

A senior developer working on a large artificial intelligence (Al) project has worked hard and shown excellent results. The project manager is very happy with the developer ' s contribution and thinks that the developer deserves a reward.

What should the project manager do?

A.

Create an opportunity (or the project team to recognize this developer

B.

Send a recognition email to the team and copy management

C.

Reward the developer according to their motivations and interests

D.

Print a recognition certificate and present it to the developer during a meeting

Full Access
Question # 274

A project manager for a construction site realizes the importance of stakeholder

relations, especially with the local community. The project manager and the project team strive to build effective relationships with these key stakeholders in order to prevent obstacles in the future.

What should the project manager do to customize the stakeholder engagement plan?

A.

Analyze stakeholder diversity in the community.

B.

Assess the need to collaborate with the community

C.

Analyze the need to negotiate with the community.

D.

Assess the information requirements of the community

Full Access
Question # 275

A quality Issue that requires a change to the quality standard Is encountered In a project Currently, there Is no budget available for the required changes. What should the project manager do?

A.

Check the change management plan

B.

Document the issue in the scope management plan.

C.

Conduct a team brainstorming session to resolve the issue

D.

Check the quality management plan

Full Access
Question # 276

A team is having a hard time completing work due to unclear requirements. They have not been able to complete an iteration successfully in several months.

In order to help the team, what should the project leader do?

A.

Recommend that the product owner reviews the backlog refinement processes.

B.

Recommend that the team reviews the length of the iteration with the stakeholders.

C.

Recommend limiting the work in progress to improve the team’s focus.

D.

Recommend a review of the team members’ individual performances.

Full Access
Question # 277

A project requires the installation of a call center to support operations. It is estimated that the call center will need 100 people working on

weekdays from 8:00 a.m. to 5:00 p.m. and weekends from 8:00 a.m. to 12:00 p.m.

What should the project manager do?

A.

Implement the call center with internal staff to ensure the work is performed according to the company’s culture.

B.

Work with 50% of the people internally and contract the other 50% to an outside company.

C.

Delegate the analysis to the human resources (HR) department in order to organize the call center operations.

D.

Conduct an alternative analysis to decide whether to hire people directly or contract with a company to do the job.

Full Access
Question # 278

A major national company known for quality products has just selected a small subcontracting firm to assist with a project. The project manager from the subcontracting firm is meeting with the project team to ensure that the project is delivered according to the customer ' s standards

in order to ensure this, what should the project manager define and document?

A.

Quality

B.

Estimates

C.

Objectives

D.

Requirements

Full Access
Question # 279

A large and complex program in an agile environment has experienced an increase in

escalations from the client side. The rates and responsibilities are unclear, and the client does not have any direction regarding the escalation process.

What should be done to resolve this issue?

A.

Invite the client and product owner to all planning, review, and retrospective meetings.

B.

Accept the escalations and manage them so the working relationship with the client isnot impacted.

C.

Review and clarify roles, responsibilities, and the governance model at the next sprintreview meeting.

D.

Invite the product owner to attend all Scrum meetings and define the governance modeland escalation path.

Full Access
Question # 280

During project execution for an innovative product, a project team has been working hard to meet the deadlines. However, one of the team members will be leaving in 3 weeks and will be replaced with a new team member.

How should the team share tacit knowledge?

A.

Provide the new member with access to the knowledge database so all of the project documentation Is available.

B.

Have the team meet on a regular basis and share their experiences, challenges, and lessons learned.

C.

Ask the new member to document all of the requirements so a better understanding of the project objective is acquired,

D.

Provide the new member with the project documentation repository to allow the new member to review previous lessons learned, Owner

Full Access
Question # 281

A project is delayed. The project manager added extra resources to some activities and approved overtime for several team members.

What technique is the project manager applying?

A.

Fast tracking

B.

Resource leveling

C.

Critical chain method

D.

Schedule crashing

Full Access
Question # 282

A project manager has just completed a fixed-price project and the stakeholder is unhappy with the result What should the project manager do?

A.

Explain to the stakeholder that any modifications require additional budget

B.

Review the missed program deliverables with the project team

C.

Review the project charter for the project approval criteria

D.

Speak with the team ' s manager to get extra hours from the team

Full Access
Question # 283

One phase of a project took much longer than initially anticipated The key stakeholders expressed their concern regarding a potential project delay. What should the project manager do?

A.

Expedite the next phase to reduce slippage

B.

Add more float to the overall project schedule

C.

Request additional contingency from the sponsor.

D.

Organize a root cause analysis (RCA) workshop.

Full Access
Question # 284

A project team has finished participating in an iterative product increment planning session. After the planning session, the team returns with a list of features to deliver.

How should the project manager ensure the product increments deliver the anticipated requirements?

A.

Appoint a dedicated product manager for the duration of the release

B.

Have the customer approve the product increment features.

C.

Ensure every user story has acceptance criteria.

D.

Track business outcomes for planned user stories.

Full Access
Question # 285

A project manager received the project charter for a new product. The project is expected to have two main deliveries: the hardware part that has detailed specifications already defined, including a sample machine, and the user interface software that has only a basic specification and a

requirement for a user experience design approach.

Which project management approach should the project manager use?

A.

The software development has a high uncertainty level, so an agile approach is recommended for the project.

B.

The scope is well defined; therefore, a predictive approach is straightforward and the hardware and software can by synchronized on the gates.

C.

The deliverables are significantly different, so the project should be split into two projects that are driven by a program.

D.

A hybrid approach will work, using agile for software development and a predictive approach for the hardware deliveries.

Full Access
Question # 286

An agile project is in the seventh iteration with multiple changes being accommodated from the project start due such as regulatory changes technological innovations market competition and other changes What should the project manager do to manage these continuous changes coming into the project?

A.

Ask the product owner to stop accommodating further changes to the scope

B.

Leverage the product owner to monitor the external environment

C.

Accommodate the critical and urgent changes in the current iteration

D.

Suggest to the product owner to execute the changes in a separate project

Full Access
Question # 287

A project is being delayed due to a large amount of rework caused by a quality problem that is impacting the critical path. What should the project manager do?

A.

Rebaseline the project schedule to absorb the delay.

B.

Report the delay with rectifying actions to the project management office (PMO).

C.

Notify the project steering committee about the cause of the delay.

D.

Report the delay with rectifying actions to the change control board (CCB) for review,

Full Access
Question # 288

A team averages 100 story points per iteration. The team estimates there are about another 2,000 points remaining and about 20 iterations remaining. One of the team members suggests estimating by feature because the large stories are difficult to break up.

What should the project manager do?

A.

Meet with this team member.

B.

Review this method with the team.

C.

Accept this task-based estimation.

D.

Reject this task-based estimation.

Full Access
Question # 289

An agile team completes a deliverable that is to be certified by another expert team The second team does not take the deliverable for many months What should the servant leader do?

A.

Review the process and remove the impediment

B.

Escalate this to the project director for a resolution

C.

Remove the certification need from the project scope

D.

Escalate this to the agile lead of the second team

Full Access
Question # 290

A project manager /s planning a project and identifies that legislation requirements for specific project tasks will be changing. This will occur half way through the project execution

phase and will affect a few key workers’ licenses, which will become noncompliant.

What should the project manager do?

A.

Start scheduling the training for key workers now to ensure compliance.

B.

Maintain the current key workers since the project has already started.

C.

Update the project charter to ensure the new legislation is addressed,

D.

Start a recruitment drive for new workers with the licenses required.

Full Access
Question # 291

Due to a statewide emergency, a project team for a global insurance company is being forced to complete a project virtually, The project manager is tasked with conducting meetings where confidential patient information will be presented.

What tool should the project manager use to conduct meetings with the project team and clients?

A.

Use a third-party instant messaging tool.

B.

Use a password-enabled audio/video product,

C.

Use a popular social media platform.

D.

Use a collaborative electronic whiteboard,

Full Access
Question # 292

During the execution of a project, a company decides that everybody will need to take vacation time before the end of the year. This may cause a change in the project time line.

How should the project manager address the situation?

A.

Discuss the vacation plan and include scheduling changes in the change log database.

B.

Submit a formal request to senior management asking them not to proceed with this decision based on the impact it will have on the project.

C.

Agree with functional management and team members on a vacation schedule that would minimally impact the project schedule.

D.

Push out the project timeline according to the vacation plan in place based on the recent company policy.

Full Access
Question # 293

A project engineer in country A is complaining about the sample received from the supplier in country B because the sample is not the correct length. During a telephone conference, the supplier checked the drawings and insisted that the measurement was accurate.

What should the project manager do next?

A.

Escalate the issue to the purchasing department for review.

B.

Evaluate the procurement contract to determine the agreed-upon specifications.

C.

Hire a company in country B to perform a quality check before shipment.

D.

Add an additional task to cut the received part according to the specifications,

Full Access
Question # 294

An agile project is in its early iterations, but the project manager already realizes that

more resources will be needed to achieve the expected time lines. There are no internal

resources. available.

What vendor strategy should the project manager use to maximize project delivery?

A.

Use compression techniques to break down the scope and assign the scope pieces todifferent vendors with a fixed-price contract.

B.

Use the contingency budget for hiring additional vendor resources to mitigate any projectrisk.

C.

Engage in a time and materials (T & M) contract and hire a local vendor to supportdevelopment.

D.

Establish a solid view of the scope and requirements and engage a vendor with a fixed price contract.

Full Access
Question # 295

A new project manager has been assigned to a project that is in its second phase The product created in the first phase was transferred to operations During a meeting, the project sponsor complained that some of the reports contain conflicting data on the product value

What should the new project manager do next?

A.

Review the benefits management plan

B.

Refer to the lessons learned from the first phase

C.

Consult the project reports from the previous project manager

D.

Collect information from related departments

Full Access
Question # 296

During protect execution the project manager observes lower velocity and a high volume of tasks m the testing queue. The project is using a hybrid approach and there are only a few sprints remaining

What should the project manager do?

A.

Work with the team to understand and solve the issues

B.

Provide testing training to all the project team members

C.

Increase the sprint duration so the testing can be completed

D.

Add a new resource with testing skills to the team

Full Access
Question # 297

A predictive project team come across a scenario where they need to use some agile tools and methods. However, they did not feel this was appropriate since their organizational project management processes did not mention this.

What should the project manager do in this scenario?

A.

Ensure the project team follows the organizational project management processes.

B.

Create a change request to include the agile methods and proceed to implementation,

C.

Work with the team to determine appropriate project methods and practices and implement them.

D.

Prepare a summary and escalate this issue to the project ' s change control board (CCB),

Full Access
Question # 298

A project team has missed the delivery date for the West milestone of a large software development project protect governance dictates that formal communication be sent to project stakeholders including the project manager ' s supervisor when a milestone is missed. The project manager is concerned that this wilt reflect poorly on the team

What should the project manager do?

A.

Send a formal communication regarding the missed milestone

B.

Delay sending a formal communication until the project team catches up

C.

Ask for a meeting with the sponsor to decide whether to send the formal communication

D.

Forego the formal communication and have a conversation with the supervisor

Full Access
Question # 299

A project is coming to a close, and the experienced project team members will be moving on to the next project. Who is responsible for ensuring that the appropriate knowledge transfer is done prior to project closure?

A.

The project manager must ensure that the knowledge transfer occurred and that this is also included in the organizational process assets (OPAs),

B.

The project team members need to ensure they have supplied sufficient knowledge transfer.

C.

The project sponsor must ensure all knowledge transfer is completed before project closure.

D.

The stakeholders need to ensure they have received sufficient knowledge transfer for ongoing support after the project handover.

Full Access
Question # 300

A healthcare company requires all new employees to attend mandatory computer-based training courses, Because some of the employees work with highly sensitive patient data, the training covers various aspects of data security. In spite of this training, data breaches continue to occur in

one of the project teams.

What should the project manager do?

A.

Apply a root-cause analysis on the data breaches.

B.

Ensure that all team members complete the training.

C.

Redesign the training courseware to make it interesting.

D.

Retrain the team members responsible for the breaches.

Full Access
Question # 301

Due to a tight schedule, a project team member suggests skipping the quality check of a minor deliverable. What should the project manager do?

A.

Evaluate the impact of skipping the quality check for the deliverable.

B.

Seek approval from the sponsor on an extension of the project schedule,

C.

Seek approval from the quality board to skip the quality check.

D.

Ask the team member to work overtime to complete the quality check.

Full Access
Question # 302

A project manager is building a team that will be comprised of subject matter experts (SMEs) from two different divisions of the same company.

The project team will be virtual and will include members from different countries around the world.

What should the project manager do to ensure effective team building occurs?

A.

Coordinate with team members to define and communicate ways of working, roles and responsibilities, scheduling, time zone, and culturalobservance information.

B.

Explain to the team that since they are all SMEs and know one another, they are expected to immediately collaborate and deliver effectively.

C.

Update the communications management plan and determine an issue resolution process for when furture conflicts arise.

D.

Colocate the team members at the beginning of the project to explain the expectations for team interaction, meeting schedules, and overallproject governance.

Full Access
Question # 303

A project manager has been assigned a low-priority project that includes new team members with no previous formal project experience. The project team has requested deadline extensions for the first development increment twice already.

What should the project manager do to support the team?

A.

Create a change request to extend the project ' s duration and costs.

B.

Provide feedback to the team using project performance evaluations.

C.

Escalate the impact on the schedule to the project sponsor.

D.

Include buffer time in the schedule to absorb future delays.

Full Access
Question # 304

A sales learn working on an IT deployment project approached the project manager on several occasions and complained about nonpayment of their overtime pay The project manager realized that other team members are receiving their overtime pay

What should the project manager do next?

A.

Have a discussion with the sales team to find a solution to the issue

B.

Validate the reason and add it as an issue in the issue log

C.

Direct the sales team to speak with accounting to resolve the issue

D.

Escalate the issue to the functional manager

Full Access
Question # 305

A project manager became aware of misunderstandings between a key stakeholder

and a team member with regard to some of the features defined in the project scope. What

should the project manager do?

A.

Reconcile the key stakeholder to the team member ' s recommendation.

B.

Reconcile the team member to the key stakeholder ' s recommendation.

C.

Escalate the communication concerns to the project management office (PMO) andrequest that they take action

D.

Work with both the team member and the key stakeholder to reach a consensus.

Full Access
Question # 306

During the development of a product, multiple identified risks have now become issues, which is hindering the team ' s velocity. What should the project manager do in this situation?

A.

Document the issues and extend the project delivery timeline.

B.

Convene the steering committee and inform them of the impact to the project.

C.

Prioritize the user stories with issues and have the team resolve them

D.

Update the project management plan and risk management plan.

Full Access
Question # 307

A company is transitioning from a predictive to an agile approach. During the last two sprint reviews, the product owner complained about the development team, indicating that the increments do not meet the acceptance criteria defined in the user stories. The development team complained about the product owner, who is defining sprint backlog items, because the backlog items cannot be delivered during the 2-week sprints agreed to at the beginning of the project.

How should the project manager resolve this situation in their new role as servant leader?

A.

Review the organizational process assets (OPAs) to find similar situations and review the resolution actions taken,

B.

Request that the team use the next sprint to complete all technical debt remaining from the previous sprints.

C.

Extend the sprints to 3 weeks to allow the work requested by the product owner to be completed.

D.

Encourage the whole team to be empowered and accountable for the decisions made according to their roles,

Full Access
Question # 308

A customer is meeting with an agile team at regular intervals and keeps changing priorities for the team members. What should the project manager do to remove this impediment?

A.

Escalate the situation to the customer management team.

B.

Ask the customer to discuss these changes with the product owner.

C.

Request that the customer to meet with the team only at the weekly meeting.

D.

Ask the customer to discuss these changes with the management team.

Full Access
Question # 309

Near the closing stage, a project is delayed due to staff shortages. In order to meet the mandatory deadline, additional resources are necessary, but there is no additional budget.

What should the project manager do first to obtain the funding to hire the needed resources?

A.

Introduce a change request.

B.

Update baselines to accommodate the delay.

C.

Use management reserves.

D.

Ask the sponsor for additional financial resources.

Full Access
Question # 310

A project manager is leading a project with a risk management plan detailing strategy and actions if any of the identified risks become an issue. One of the identified risks becomes an issue, but the project manager acknowledges that the response considered in the risk management plan may not be the best.

What should the project manager do?

A.

Adopt the action prescribed in the risk management plan since it was agreed to beforehand.

B.

Submit a change request to perform a different issue response than what is registered in the risk management plan.

C.

Escalate the issue to the project sponsor and register the new risk response in the project documents.

D.

Meet with the project team and sponsor to reevaluate all issue responses registered in the risk management plan.

Full Access
Question # 311

The project team embraces and encourages open communication and collaboration. However, the project manager is used to an approach based on the chain of command and formal hierarchy.

What should the project manager do?

A.

Allow the team members to pick the model they are most comfortable with.

B.

Understand team concerns, organizational culture, and previous lessons learned.

C.

Discuss the situation with senior team members and make a collective decision.

D.

Obtain direction from the senior executive team and file a change request.

Full Access
Question # 312

During the team’s daily meetings, the project manager notices that some team members are consistently experiencing blockers due to communication issues and misunderstanding process directions.

How should the project manager proceed in this situation?

A.

Hold coaching sessions to further educate these team members.

B.

Take the current velocity into account for the next iteration planning.

C.

Request that these team members improve their performance.

D.

Instruct the team members on how to remove project obstacles.

Full Access
Question # 313

An agile team of specialized engineers has completed some tasks later than planned and with a lower quality than expected. The situation is limiting the value the team is creating for the business. What should the project manager do next?

A.

Execute the next iteration planning considering the quality issues.

B.

Schedule quality reviews to obtain stakeholder approvals and feedback.

C.

Confirm the right quality tests are applied before moving to the next iteration.

D.

Include all the quality problems found in the technical debt backlog.

Full Access
Question # 314

A project is almost complete when a key stakeholder raises a concern because the functionality of their preferred requirement was not showcased in the prototype. The prototype has already been approved, and the developers have started work on the final application.

What should the project manager do next?

A.

Document the stakeholder’s requirements and validate those requirements by engaging stakeholders more often.

B.

Inform the stakeholder that little can be done at this time, since core development has begun and the project must be delivered on time.

C.

Be firm with the stakeholder, since they would push through any unreasonable requirement.

D.

Inform the stakeholder that the requirement will be included in the next deliverable cycle.

Full Access
Question # 315

A project manager is leading a software development project with agile practices and has outsourced work to three well-qualified subcontractors. Over time, problems arise related to supply-chain management, and the project manager considers replacing the subcontractors with new suppliers. What should the project manager have done to avoid this problem?

A.

Hired more Scrum Masters so every Scrum Master manages one supplier.

B.

Escalated the issue to the product owner to seek possible solutions.

C.

Engaged the suppliers by category and validated the strategy with stakeholders.

D.

Created user stories for the suppliers and saved their qualification records to the backlog.

Full Access
Question # 316

During a blueprint review meeting, the finance department representative is not comfortable with a proposed solution that favors another department. As a result, document approval is delayed and impacts the project schedule. What should the project manager do?

A.

Work with the project team to find a compromise solution that suits both departments

B.

Schedule a meeting with the project sponsor to seek advice on the approach of both departments

C.

Arrange a meeting with the two departments to understand their differences and address their needs

D.

Assess the risk of postponing this specific solution and advise both departments of the delay

Full Access
Question # 317

During a sprint planning meeting, a project team analyzes the effort required to complete some of the tasks before aligning on a sprint commitment. The project team faces issues when trying to estimate the testing effort for the tasks. What should the project manager do first?

A.

Obtain the acceptance criteria from the product owner.

B.

Encourage the team to do pair programming to reduce testing.

C.

Ensure the definition of done (DoD) is understood by all team members.

D.

Involve a quality assurance (QA) expert to support the testing estimation.

Full Access
Question # 318

A project manager is executing a project on time and on budget. Before a stage gate review, the project manager receives the regular business management report, but this time it entails a negative impact on the project success factors.

What should the project manager do?

A.

Request a delay to the stage gate until business development provides the next update.

B.

Call for business development to revalidate inputs at the next stage gate.

C.

Provide the necessary analysis to enable examination of the business value.

D.

Continue with execution since the project was successful up to this phase.

Full Access
Question # 319

A project team member finishes all assigned tasks in the middle of a sprint. The team member wants to plan tasks for the next sprint to deliver business value earlier. The team member has the abilities and knowledge to execute tasks not yet started by other team members in the current sprint. What should the project manager do?

A.

Validate completeness of the tasks delivered in the current sprint

B.

Increase team velocity to execute tasks for the next sprints

C.

Reassign the team member to other tasks in the current sprint

D.

Encourage the team member to execute the next sprint tasks

Full Access
Question # 320

One member of the project team has the necessary skills to execute a critical feature of the product. However, another team member wants to take on the challenging task.

What should the project manager do?

A.

Assign the task to the less experienced member to help improve their skills, with the support of the experienced member.

B.

Schedule a meeting with both team members to let them discuss the best course of action.

C.

Encourage both team members to collaborate and work using their respective strengths to deliver the project.

D.

Negotiate with the customer to postpone the particular feature to resolve the situation between the team members.

Full Access
Question # 321

Three months after creating a project schedule, the scope of a project significantly changed, resulting in a schedule rebaselining. One month after rebaselining, the project is two weeks behind schedule with a cost performance index (CPI) of 0.93. What should the project manager do to help get the project back on schedule?

A.

Crash the project with two additional contract resources for the newly identified tasks.

B.

Meet with the project stakeholders and inform them that the project is going to be delayed.

C.

Manage the schedule’s critical path, as this was an approved scheduling change.

D.

Review the project schedule and find ways to fast-track the overall project schedule.

Full Access
Question # 322

One of the main deliverables of a project is delayed due to a problem with a key provider. What should the project manager do?

A.

Create a change request to replace the provider with a more responsible one from the provider list

B.

Schedule a meeting with all relevant stakeholders to determine the best approach to resolve the issue

C.

Discuss with the sponsor and seek guidance to impose the penalty stipulated in the agreement

D.

Schedule a meeting with the provider to review impacts to the project timeline and deliverables

Full Access
Question # 323

Just as a team reaches a mutual consensus on a preferred design, a stakeholder submits a request to add new features that enhance the company’s competitive advantage.

What should the project manager do?

A.

Start the process to include the new features of the product in the next iteration.

B.

Reject all requested changes and bypass the company’s change control process.

C.

Encourage the project team to add premium features to impress the client.

D.

Allow all requested changes and bypass the company’s change control process.

Full Access
Question # 324

A new stakeholder is unaware of the existence of the project a few weeks before the final deliverable and project completion. What should the project manager do first?

A.

Escalate this issue to the project sponsor.

B.

Communicate the full details of the project activities to the stakeholder and solicit input.

C.

Analyze this stakeholder’s interest and impact.

D.

Share the summary of the project activities with the stakeholder and conclude the project.

Full Access
Question # 325

A project manager has recently been assigned to a construction project. The project has hundreds of stakeholders and three stages. The project manager recognizes that many steps have already been started, including risk identification. The project sponsor asks the project manager to rank the risks contained in the register. How should the project manager respond to the request?

A.

Execute a qualitative analysis to provide identified risks prioritization.

B.

Inform that a quantitative risk prioritization was completed using Monte Carlo simulation.

C.

Inform that a qualitative analysis has already been completed.

D.

Perform a quantitative analysis to provide identified risks prioritization.

Full Access
Question # 326

A project manager is leading a highly visible project initiative. A few weeks after kickoff, the project manager starts receiving requests for updates from various stakeholders. What should the project manager do?

A.

Remove those stakeholders from the project since they may negatively affect project goals

B.

Invite all project stakeholders to join the daily standup meeting to ensure they are informed

C.

Schedule a meeting with relevant stakeholders to review the project communications plan

D.

Explain to the stakeholders that they must request project updates from the project sponsor

Full Access
Question # 327

Halfway through the execution of a project, a key team member resigns from the company and will leave in 2 weeks.

What should the project manager do next?

A.

Persuade the team member to delay their resignation until the project is completed.

B.

Plan for the team member to finalize their assigned project tasks before leaving.

C.

Work together on the knowledge transfer plan for the remaining team members.

D.

Ask human resources (HR) to start looking for the team member’s replacement.

Full Access
Question # 328

A project is in its first of six iterations. The project team realizes that a key deliverable is dependent on the acquisition of a new device. The vendor is new to the organization and does not have a long history in the market. What should the project manager do first?

A.

Register the risk and provide appropriate response options.

B.

Register the risk and prioritize the implementation strategy.

C.

Register the risk and escalate it to the procurement team.

D.

Register the risk and escalate it to the project sponsor.

Full Access
Question # 329

A project manager is struggling to provide timely updates to the project team because team members are spread across multiple time zones.

Which communication method should the project manager utilize in this situation?

A.

Interactive communication

B.

Push communication

C.

Public communication

D.

Pull communication

Full Access
Question # 330

A project to add metro stations is being executed, with seven out of eight stations currently in place. Suddenly, a notification from the local community is received, demanding that the project be stopped.

What should the project manager do first?

A.

Register the issue and escalate it to the project sponsor.

B.

Execute the contingency plan defined in the risk management plan.

C.

Meet with the project stakeholders to define a mitigation plan.

D.

Estimate the cost of changing the project location.

Full Access
Question # 331

During the project planning phase, the customer explained the importance of delivering the project results proposed in the scope as soon as possible.

What should the project manager do first to address this issue?

A.

Gather all of the requirements details and schedule a refinement meeting.

B.

Prepare a project management plan for the full scope using an agile approach.

C.

Assess the opportunities to deliver project value incrementally.

D.

Approve a change request to change the project approach to agile.

Full Access
Question # 332

During the initial phase of a construction project, the team is confused about the safety requirements it needs to consider during implementation. The project manager recently met with the client to define the project scope.

How should the project manager share this information?

A.

Meet with the team and present the scope of the safety requirements.

B.

Distribute the security requirements during the project execution phase.

C.

Modify the project charter by including the safety requirements.

D.

Send an email to the team with the details of the safety requirements.

Full Access
Question # 333

A project manager is leading the construction of a high-rise mall for a customer in an emerging competitive market. Some customers want to move in as soon as the ground floor is completed.

What should the project manager do to deliver business value to the client?

A.

Request to use the management reserve and crash the project schedule.

B.

Adopt an incremental project delivery approach.

C.

Explain the need to follow the quality assurance (QA) schedule to the customer.

D.

Implement an agile project delivery approach.

Full Access
Question # 334

A project manager has recently been appointed to lead a critical software development project in a hybrid environment. What should the project manager do first to understand the project quickly and manage the project effectively?

A.

Identify key stakeholders and hold a project kickoff meeting to engage the stakeholders and obtain commitment.

B.

Assess the project management plan for dependencies and possible risks then validate stakeholder understanding.

C.

Review the project charter to understand the objectives, high-level scope, and business need.

D.

Share project objectives and scope with the team to ensure it understands the project value.

Full Access
Question # 335

A project manager has been assigned to a new agile project with rapidly changing knowledge areas. How should the project manager manage knowledge transfers on this project?

A.

Require stakeholders to fully document all domain knowledge before starting

B.

Mentor the team and stakeholders to ensure domain knowledge is exchanged during sprints

C.

Ask the team to set up initial sprints for knowledge transfer before focusing on deliverables

D.

Work with QA to ensure domain knowledge is transferred properly among stakeholders

Full Access
Question # 336

A project manager is leading a contract for a new market that was awarded to their company. The client has the desire to jump-start the market with informal sector traders. What should the project manager do?

A.

Plan the project in phases, starting with the informal sector, to deliver business value quickly

B.

Divide the project team into groups to execute as small parallel projects, including the informal sector

C.

Gather requirements and convert them into backlog items to quickly deliver value

D.

Execute the projects simultaneously following the project schedule and the communications management plan

Full Access
Question # 337

The execution stage of a construction project is beginning. There are many areas and phases to be built. The project team wants to review the relationships between the most important tasks to ensure that major items are executed properly during this stage. What project artifact should the project manager review with the team?

A.

Project milestone chart

B.

Project schedule management plan

C.

Project statement of work (SOW)

D.

Project program evaluation review technique (PERT)

Full Access
Question # 338

Five vendors are contributing to a project with an impending deadline. Two vendors are behind on their deliverables and rarely provide status updates. What should the project manager do?

A.

Begin daily check-ins with the two vendors to recover time at their own expense

B.

Extend the project schedule and inform the vendors it was due to their poor performance

C.

Find replacements for the two vendors to complete the project in a timely manner

D.

Reduce the two vendors’ pay due to poor performance and lack of communication

Full Access
Question # 339

An experienced project manager has recently joined a jeopardized project. The project is being impacted by multiple delays caused by a vendor’s late delivery of new servers. Due to budget restrictions, the project manager cannot add a new vendor, and the project must be completed within a maximum of 90 days as agreed.

What should the project manager do?

A.

Reach out to the vendor to determine a plan to get the project back on track.

B.

Review lessons learned from previous projects and take action accordingly.

C.

Request that the vendor provide the servers on time, as penalties may be applied.

D.

Wait until the project deadline is reached in order to use the contingency funds.

Full Access
Question # 340

A new team member joins the project and fails to apply the project-specific quality assurance (QA) processes.

What should the project manager have done to avoid this issue?

A.

Delegated the quality assurance (QA) tasks to the team lead.

B.

Ensured that the new team member had access to the quality management plan.

C.

Obtained external training in quality assurance (QA) for the new team member.

D.

Made sure that the new team member understood all of the requirements.

Full Access
Question # 341

A project manager notices that a product owner has been unresponsive over the last few weeks. During one-on-one sessions, the product owner is unable to provide complete information, leading to rework of the project stories.

What should the project manager do first?

A.

Escalate the issue to the stakeholder’s functional manager.

B.

Increase the sprint duration to accommodate the additional work.

C.

Conduct a root cause analysis before addressing the issue.

D.

Cancel the one-on-one sessions and obtain the information via email.

Full Access
Question # 342

A project manager has been tasked with developing a project schedule with fully detailed requirements. The project manager reaches out to subject matter experts (SMEs) for their initial thoughts on task duration. The project manager is concerned when these estimates appear to differ significantly. What should the project manager do to help with the estimate development?

A.

Ask the SMEs to hold up cards that show their estimate, discuss the highest and lowest estimates, and then estimate again.

B.

Recommend using an iterative approach, with a focus on estimates, that the SMEs agree with.

C.

Use historical information to help guide the estimates that were proposed by the SMEs.

D.

Escalate to the project sponsor and explain the differences in the estimations coming from the SMEs.

Full Access
Question # 343

A project team has been tasked with delivering robotics to automate a manufacturing line. The technical teams are all in place and have the technical information needed to build and install the robots. What other factors should be considered when planning this project?

A.

Software, security, and infrastructure.

B.

Industry standards and research.

C.

Safety and organizational culture.

D.

Financial and market conditions.

Full Access
Question # 344

A project team has deployed an email marketing campaign across different countries. In one country, the end users have been opting out of the campaign because they think the email is spam. What should the project manager do first?

A.

Conduct a retrospective meeting to identify what went well and what went wrong.

B.

Review the email marketing standards of that country with the stakeholders.

C.

Schedule a meeting with project team members to identify the root cause.

D.

Schedule additional country-specific user testing to reduce email opt out.

Full Access
Question # 345

A project manager is working on a multinational project with stakeholders from different regions. What should the project manager do first to ensure there is effective stakeholder collaboration?

A.

Review the stakeholder engagement plan with all of the stakeholders.

B.

Schedule regular virtual coordination meetings and invite all stakeholders.

C.

Request budget to invite all stakeholders to in-person team meetings.

D.

Analyze stakeholder interest levels to develop an engagement strategy.

Full Access
Question # 346

A major issue regarding conflicting priorities has been highlighted by the project team with respect to a few stakeholder requirements.

What should the project manager do?

A.

Escalate to the project management office (PMO) and request a solution for the requirements.

B.

Prioritize other items for the team and deal with the conflicting requirements later.

C.

Allow the project team to decide which requirement is the most appropriate to follow.

D.

Negotiate a common agreement with the involved stakeholders regarding the requirements.

Full Access
Question # 347

A project team member tells the project lead that expecting a similar delivery output for every day of the sprint is not realistic. The project lead reports this to the project management office (PMO).

What should the project lead do?

A.

Discuss this with the PMO manager.

B.

Discuss the issue with the product owner.

C.

Discuss this with the project team in the next sprint retrospective meeting.

D.

Discuss this with the project team in the next sprint planning meeting.

Full Access
Question # 348

A project manager is leading a project with a risk management plan detailing strategy and actions if any identified risks become an issue. One of the identified risks becomes an issue, but the project manager believes the planned response may not be the best. What should the project manager do?

A.

Meet with the project team and sponsor to reevaluate all issue responses registered in the risk management plan

B.

Escalate the issue to the sponsor and register the new risk response in the project documents

C.

Adopt the action prescribed in the risk management plan since it was agreed to beforehand

D.

Submit a change request to perform a different issue response than what is registered in the risk management plan

Full Access
Question # 349

The project team has reviewed the requirements and identified some concerns. The project sponsor has asked the team how they will handle each concern. What should the project manager do next?

A.

Work with the project team to assess the severity of each risk.

B.

Collaborate with the stakeholders on the communications management plan.

C.

Consult with team members to produce a Monte Carlo simulation diagram.

D.

Develop a mitigation strategy for each risk and update the risk register.

Full Access
Question # 350

A complex project is being developed in phases as per the original plan. Half of the systems have been handed over to the customer for operational use. There is no delay in the schedule. However, the customer is still not happy because some of the systems handed over are no longer useful due to changes in the environment. What should the project manager have done to avoid this?

A.

Asked the customer to participate in project status meetings to better understand the progress

B.

Informed the project team to closely monitor the deliverables and keep the customer informed

C.

Reviewed benefits realization with the customer regularly and constantly aligned expectations

D.

Explained to the customer that the project is in good shape as the system is operational

Full Access
Question # 351

There are several dependent work streams in a project. Some project stakeholders feel that coordination among team members and progress visibility are lacking. What should the project manager do?

A.

Discuss the concerns with the project sponsor

B.

Organize a team meeting to review the project status

C.

Review and update the communications management plan

D.

Escalate the concerns to the project steering committee

Full Access
Question # 352

A project manager is assigned to an IT project to deliver a new accounting system. Some managers at the company do not see the value of this project and say they will not use the new system. What two actions should the project manager take? (Choose 2)

A.

Review the list of stakeholders that will be affected by starting this business initiative.

B.

Continue with the project the way it was planned and validated by the sponsor.

C.

Describe the outcome of the project and business value to all company stakeholders.

D.

Add this issue to the risk register and monitor stakeholder engagement at the next milestone.

E.

Modify the project management plan and scope of work to avoid future difficulties.

Full Access
Question # 353

A project manager is assigned to a large complex project with cross-functional dependencies. The project enters a new phase requiring new stakeholders to be added with conflicting priorities. How should the project manager ensure successful engagement with the stakeholders?

A.

Invite all stakeholders to status meetings.

B.

Identify and categorize the stakeholders.

C.

Interact individually with the stakeholders.

D.

Recognize the diversity of the stakeholders.

Full Access
Question # 354

A project manager is leading a project and is asked to negotiate on behalf of their organization. The organization requires that three quotes from different suppliers be acquired prior to submitting a purchase request to the finance department. What should the project manager do to align with this requirement?

A.

Perform a make-or-buy analysis

B.

Review the statement of work (SOW)

C.

Leverage the enterprise environmental factors (EEFs)

D.

Refer to the organizational process assets (OPAs)

Full Access
Question # 355

Two project managers are competing to assign a key subject matter expert (SME) to their concurrently scheduled projects. Work requiring constant physical presence means the SME can serve on only one project at a time. What should the project managers do first to facilitate allocation of the resource?

A.

Calculate the schedule performance index (SPI) based on the SME assignment

B.

Assess both projects to determine the business benefits based on the SME assignment

C.

Evaluate the associated budget and schedule based on the SME assignment

D.

Determine the cost performance index (CPI) based on the SME assignment

Full Access
Question # 356

A project manager is leading a complex project with stakeholders from different countries, cultures, and languages. What can the project manager do to manage this diverse group of stakeholders?

A.

Assign team members to deliverables according to their cultures and languages

B.

Ask the PMO to assign a cultural manager to oversee relations between diverse groups

C.

Perform an analysis to better understand the communication needs and preferences of each group

D.

Establish one language as the main language for communications and one official time zone for the project

Full Access
Question # 357

A project manager faces a major conflict within their project team that should be resolved as soon as possible. Which form of communication should the project manager use to deal with the conflict?

A.

Schedule a conference call with the project team.

B.

Schedule meetings with individual members.

C.

Send email communications to all members.

D.

Distribute the progress report and risk register.

Full Access
Question # 358

An increment was delivered to the customer at the end of a sprint. The customer complains that the product does not meet the expected quality and will require some rework. What should the project manager do next?

A.

Review the evidence of the quality assurance (QA) activities performed.

B.

Perform an analysis of the impact caused by the required rework.

C.

Include time in the next increment for quality assurance (QA) inspections.

D.

Confirm with the customer the expected quality in the next increment.

Full Access
Question # 359

An organization that is running several simultaneous projects suddenly experiences a surge of resignations, leading to a lack of talent. Consequently, some of the projects have been missing key milestones. What should the project manager do to recover from the delays?

A.

Reduce the projects’ scope to meet the upcoming target dates.

B.

Crash the schedule from the delayed projects to meet upcoming target dates.

C.

Fast-track the delayed projects so they can meet upcoming target dates.

D.

Ask for project sponsor approval to revise the upcoming target dates.

Full Access
Question # 360

A project sponsor is transitioning their division to an agile environment and has emphasized that project team members and stakeholders should collaborate to achieve deliverables. On a few occasions, progress has been interrupted by one stakeholder who is unfamiliar with agile approaches. What should the project manager do first?

A.

Report the behavior to the project sponsor and find a replacement.

B.

Note the stakeholder’s attitude as a risk and continue development according to the plan to deliver value.

C.

Consider using a predictive project management framework and report the results to the project sponsor.

D.

Address the stakeholder’s behavior directly and provide feedback.

Full Access
Question # 361

A project manager is leading a hybrid project. A project team member has not been delivering on time; as a result, the project is about to be delayed.

What should the project manager do?

A.

Negotiate revised timelines with the project sponsor.

B.

Revise the project schedule with the customer.

C.

Discuss the situation with the project team member.

D.

Schedule a meeting with the project team to address timelines.

Full Access
Question # 362

A project manager is leading a complex project. The project stakeholders include individuals from different countries, cultures, and languages.

What can the project manager do to manage this diverse group of stakeholders?

A.

Establish one language as the main language for communications and an official time zone for the project.

B.

Perform an analysis to better understand the communication needs and preferences of each group.

C.

Organize and assign the team members to the project deliverables according to their cultures and languages.

D.

Ask the project management office (PMO) to assign a cultural manager to oversee relations between diverse groups.

Full Access
Question # 363

A project manager recently took over an ongoing project. Within a few weeks on the project, the project manager discovers that there are continuous change requests from different project end users. What is the probable cause for this?

A.

Undefined change control process

B.

Unidentified project risks

C.

Improper work breakdown structure (WBS)

D.

Incomplete requirements

Full Access
Question # 364

A project manager is hired to work on a very large, complex project that requires the team to complete a significant number of specialized tasks. What strategy should the project manager incorporate to help organize, assign, and monitor these tasks?

A.

Create a list of the tasks and send it to the project sponsor for review and approval.

B.

Develop a work breakdown structure (WBS) that decomposes the project deliverables into work packages.

C.

Schedule a meeting with the stakeholders to determine which tasks can be eliminated.

D.

Prepare a resource management plan that details all the resources needed to complete the tasks.

Full Access
Question # 365

A project manager is leading a highly visible project initiative. A few weeks after the kickoff, the project manager starts to receive requests for updates from various stakeholders.

What should the project manager do?

A.

Explain to the stakeholders that they must request project updates from the project sponsor.

B.

Schedule a meeting with relevant stakeholders to review the project communications plan.

C.

Invite all project stakeholders to join the daily standup meeting to ensure they are informed.

D.

Remove those stakeholders from the project since they may negatively affect the goals of the project.

Full Access
Question # 366

A project manager is working on an agile project. The organization does not have experience with agile delivery. During business case development, the new product owner asks when the project deliverables are considered complete.

How should the project manager respond?

A.

Items are considered complete when they satisfy the definition of done (DoD).

B.

The scrum master will approve the user stories that are complete.

C.

Backlog items are considered complete when the product owner approves the demo.

D.

At the end of each sprint, the outcome is considered ready for production.

Full Access
Question # 367

An organization is about to start a time-critical project and has decided to use an agile approach for the first time. However, stakeholders are worried they will not be able to verify project status because they believe their usual governance model will not work for an agile project. What should the project manager do?

A.

Discuss using a hybrid governance structure with stakeholders

B.

Meet with stakeholders to discuss and review the governance structure

C.

Recommend following the existing governance structure with the project team

D.

Review the governance structure to reflect scope changes

Full Access
Question # 368

A project management plan needs to be updated due to recent product requirements changes, but the latest version of the document is missing. What should the project manager do to prevent this from happening again?

A.

Improve the configuration management process

B.

Register an issue for the missing documents

C.

Ensure the lessons learned register is up to date

D.

Review the quality assurance (QA) processes

Full Access
Question # 369

A project manager is leading a contract for a new market that was awarded to their company. The client wants to jump-start the market with the informal sector traders.

What should the project manager do?

A.

Plan the project in phases, starting with the informal sector, to deliver business value to the client quickly.

B.

Divide the project team into groups to execute the project as small parallel projects, including the informal sector.

C.

Execute the projects simultaneously following the project schedule and the communications management plan.

D.

Gather requirements and convert them into backlog items to quickly deliver value to the client.

Full Access
Question # 370

A project has a very demanding and sensitive business stakeholder who functions as a subject matter expert (SME). The project manager has assigned two different team members to work with the stakeholder. However, both team members have complained that the stakeholder is difficult to work with.

What should the project manager do first?

A.

Evaluate the situation and look for alternatives to improve communication with the stakeholder.

B.

Speak with the team members to collect details and write an email to the stakeholder requesting that they collaborate with the team.

C.

Raise the issue during a steering committee meeting and ask that the stakeholder change their attitude.

D.

Escalate the issue to the sponsor and request that they speak with the stakeholder.

Full Access
Question # 371

Near the closing stage, a project is delayed due to staff shortages. In order to meet the mandatory deadline, additional resources are necessary, but there is no additional budget. What should the project manager do first to obtain the funding to hire the needed resources?

A.

Ask the sponsor for additional financial resources

B.

Introduce a change request

C.

Use management reserves

D.

Update baselines to accommodate the delay

Full Access
Question # 372

A project manager has been informed by a vendor that a shipment with supplies needed for the project will be delayed by six weeks. What should the project manager do first?

A.

Find another vendor to deliver the required supplies on time

B.

Ask the procurement manager to resolve the issue with the vendor

C.

Document this as a risk and define a risk response plan

D.

Treat the risk as an issue and launch the risk response plan

Full Access
Question # 373

A project lead accepted an assignment for a project that is still in the feasibility study phase. There are many uncertainties about project specifications, including poor alignment among the project sponsors on the final targets of the project.

Which approach should the project lead choose to deliver business value?

A.

Subdivide project tasks to find the minimum viable product (MVP).

B.

Ensure commitment from sponsors on executing the project until it ends.

C.

Identify and communicate clear risk mitigation plans.

D.

Recommend predictive project management to the sponsors.

Full Access
Question # 374

A project team is working on an agile software development project. The project manager is concerned that the virtual team may not be as effective as a colocated team at headquarters.

Which two actions should the project manager leverage to ensure the team is meeting performance expectations?

(Choose two)

A.

Hold daily virtual meetings to review progress.

B.

Implement time-keeping software for team members.

C.

Task functional managers to drive accountability.

D.

Utilize a web-based kanban board.

E.

Require a monthly individual status report.

Full Access
Question # 375

During daily team coordination meetings, team members constantly ask which tasks they should focus on first.

How should the project manager ensure the team is fully productive?

A.

Encourage project team members to prioritize the product backlog.

B.

Work with the product owner to ensure the project backlog is prioritized.

C.

Ensure team members are working according to the project management plan.

D.

Review the project backlog during the team’s coordination meeting.

Full Access
Question # 376

A project is behind schedule because of a delayed equipment installation. This is affecting many other activities. The manager responsible for the

equipment delivery notified the project manager that there is a capacity issue for the team doing the installation.

What should the project manager have done to prevent this situation from happening?

A.

Defined the skill requirements more clearly in the scope statement.

B.

Asked the manager to follow the agreed-upon resource management plan.

C.

Conducted periodic reviews with the manager on resource availability.

D.

Consulted with the installation team on a regular basis to check for conflicts.

Full Access
Question # 377

After the demo on a software project, one of the key stakeholders contacted the scrum master and complained that they were unaware of changes made to the project. After checking, the scrum master learned that the stakeholder ' s details were incorrectly entered into the register.

What should the scrum master do?

A.

Ask the product owner to update the stakeholders ' contact information at every meeting to address any changes.

B.

Update the stakeholder ' s information and inform them that they must make the team aware of any changes.

C.

Consider it a loss since the stakeholder should have ensured the contact information was up to date.

D.

Check the stakeholder register and ensure that every stakeholder ' s information is correct and current.

Full Access
Question # 378

After signing an agreement with a vendor, the project manager notices that the vendor is continuously asking for changes on the procurement statement of work (SOW).

These changes would improve the project outcome.

What should the project manager do next?

A.

Conduct an audit on the procurement process and inform the vendor about the audit ' s observations.

B.

Assess the situation as an opportunity for improvement and perform a risk analysis.

C.

Consult the list of selected vendors for the bid and evaluate a possible change of vendor.

D.

Revise the procurement control process to avoid undesired changes that might affect the schedule.

Full Access
Question # 379

A project management office (PMO) is currently stretched for project control resources. Specifically, the cost control resources are short of the staff required for this activity level. A new project is about to start soon.

What should the project lead do to obtain the needed resources?

A.

Evaluate running the project without the required resources and depend on the lessons learned from similar past projects.

B.

Prepare to perform the duties of the cost controller for the duration of the project.

C.

Meet with the PMO team and review the resource management plan ahead of the project kickoff to ensure resource availability.

D.

Inform the project sponsor and initiate a recruitment exercise outside of the PMO.

Full Access
Question # 380

A project manager joins an existing project. One project stakeholder is unhappy with the frequency and types of project updates received and has made a request for more What should the project manager do next?

information to be shared.

A.

Inform the stakeholder to wait for the annual stakeholder review meeting

B.

Schedule a meeting with the stakeholder to better understand their request

C.

Update the project communications management plan immediately

D.

Consult the scope baseline document to track project updates

Full Access
Question # 381

A project manager is working on a financial system implementation project for a government company. One of the key stakeholders, who uses

predictive approaches, does not like virtual tools such as chats, task trackers, and so forth. They prefer email, telephone calls, and face-to-face

meetings.

How should the project manager approach this situation?

A.

Use regular screen-sharing sessions to show the progress to the stakeholder.

B.

Align and agree with the stakeholder on the communication approach.

C.

Ask the manager to use virtual communication tools and online dashboards.

D.

Create a digital dashboard to meet the manager ' s information needs.

Full Access
Question # 382

A project manager is working on a large IT project. During a review for one of the deliverables, a stakeholder raised a concern about the final product.

What should the project manager do first?

A.

Set up a meeting with the product owner to discuss the stakeholder ' s concern.

B.

Discuss this with the team and review the project requirements documentation.

C.

Set up a meeting with the sponsor to discuss the details of the deliverable.

D.

Discuss this with the team and put the stakeholder ' s concern in the issue log.

Full Access
Question # 383

A client from the travel and hospitality industry is building software for an ongoing project. The project sponsor and key project stakeholders ask to add four new functionalities to the upcoming sprint.

What should the product owner do next?

A.

Ask the team to start implementing the new tasks.

B.

Add the new tasks to the current sprint backlog.

C.

Request a change control to expand the scope with the new tasks.

D.

Prioritize the new tasks in the planning of the upcoming sprint.

Full Access
Question # 384

A company plans to initiate a project involving a new technology. Approval for the project is required. What should the project manager do?

A.

Review the cost and schedule baselines for execution.

B.

Define change management for the new technology.

C.

Analyze the cost and identify the project benefits.

D.

Identify the risks in implementing the new technology.

Full Access
Question # 385

Several components of an expensive manufacturing project have been returned by the customer. The customer is complaining that the quality of

the components is poor and is concerned that, as a result, their products will be returned due to quality issues. The project manager is certain that

quality has been maintained.

How should the project manager communicate with the customer to help assure them that the project has produced quality products?

A.

Show the customer the tolerance and control limits.

B.

Show the customer sample results from the current batch.

C.

Show the customer a sample history of quality.

D.

Show the customer the quality control measurements.

Full Access
Question # 386

A project manager is working on a multinational project that has more than 100 stakeholders. The project manager is concerned about the

appropriate stakeholder participation and involvement level required for successful project delivery.

What should the project manager do?

A.

Communicate with the stakeholders to find a solution.

B.

Review the issue log with the project stakeholders.

C.

Evaluate the stakeholder engagement assessment matrix.

D.

Perform a stakeholder assumption and constraint analysis.

Full Access
Question # 387

A project team created user stories after understanding the customer requirements. As the project progresses, the project manager observes that

there are too many change requests. The team feels that the outcomes they are working on are not aligned with the customer requirements.

What should the project manager do?

A.

Refer to the configuration management knowledge base for similar projects delivered in the past.

B.

Arrange for a workshop with the customer to understand the business values expected from the outcomes.

C.

Include a representative from the customer to work collaboratively with the team.

D.

Acknowledge that the current team needs improvement and hire more qualified team members.

Full Access
Question # 388

A project manager is newly appointed to lead a project team that will be working remotely. The project manager decided to use a set of tools that

worked well for previous projects. However, a few team members are not happy with this plan.

What should the project manager have done to avoid this?

A.

Delegated the responsibility of selecting the collaboration tools to the project ' s technical lead.

B.

Met with the project team to determine their collaboration needs and identified tools that will work best.

C.

Allowed the project team members to use the tools that will work best for them for this project.

D.

Asked the project sponsor for approval to purchase the newest collaboration tool on the market.

Full Access
Question # 389

A project is starting its second iteration out of six. During the daily meeting, a team member asks for help. In order to finish a deliverable, an

approval from the design department will be needed.

What should the project manager do?

A.

Meet with the design manager to ask for the necessary approval.

B.

Invite a design team member to the next daily meeting.

C.

Update the issue log and escalate it to the project sponsor.

D.

Replace this iteration deliverable for one without any blockers.

Full Access
Question # 390

An agile project is running its third iteration with a duration of 2 weeks. A new operations director, who only has a predictive background, started

working at the company. In the first meeting with the project manager, the director demands a weekly project status report.

What should the project manager do?

A.

Invite the director to attend the daily standup meetings.

B.

Share this with the team and ask them to develop reports for the director.

C.

Introduce the agile aspect to the director and agree on a solution.

D.

Explain to the director that agile projects have live reports.

Full Access
Question # 391

After the merger of two large companies, a project manager is assigned to a project. The company hires a consultant to ensure best practices are

being used in information security. During an iteration, the consultant requests changes to a software component, claiming that it is not meeting

market requirements.

What should the project manager do?

A.

Continue the iteration and add the requested changes.

B.

Continue the iteration and review the change with the customer.

C.

Cancel the iteration and meet with the product owner.

D.

Cancel the iteration and add the requested changes.

Full Access
Question # 392

A project manager is acting as a servant leader and is struggling to make deadlines on a critical roadway construction project that is falling behind schedule due to a lowperforming team. In order to get the project back on track, what should the project manager do first?

A.

Empower the team members to conduct their job activities and hold each person accountable to improve the schedule.

B.

Notify the project sponsor that the team is underperforming and request additional resources to compress the schedule,

C.

Contact each team member to inform them that further schedule slips will not be tolerated by the project sponsor.

D.

Begin holding daily meetings to assign each team member discrete tasks with specific due dates.

Full Access
Question # 393

A subject matter expert (SME) external to the project team provides a suggestion that will save the project delivery time. This SME has available

time to support the project, but was not planned to be involved in the current agile iteration.

What should the project manager do?

A.

Bring the SME on board immediately and discuss the implications later.

B.

Ask the existing team members to collaborate with the SME and complete the activity.

C.

Ask the SME to complete all of the necessary changes, which will save time.

D.

Direct the team member to ignore the SME ' s changes as they were not planned.

Full Access
Question # 394

During a monthly review meeting, a high-performing team member raised a concern about the quality feedback mechanism. The team member expressed that they are not able to deliver high-quality output.

What should the project manager do first?

A.

Assign the work based on the skill sets of team members.

B.

Request feedback from stakeholders about the quality delivery.

C.

Assign the work in consultation with the functional manager.

D.

Discuss this with the team and review the quality process.

Full Access
Question # 395

A project manager has completed an assessment of the project team ' s performance. Some team members have performed poorly on their assigned tasks.

What should the project manager do?

A.

Develop different approaches based on team members’ motivation and ability.

B.

Develop a standard approach to provide feedback to all team members.

C.

Provide intensive oversight to the team members who performed poorly.

D.

Create a new standard performance measure based on project requirements.

Full Access
Question # 396

A multicultural team is working on a project. After a few months of observation, the project manager realizes that two team members are not responding to the construction manager properly. The project manager spoke to the team members individually and found that both had cultural differences with the construction manager.

What should the project manager do to improve the situation?

A.

Ask the team members to tolerate the cultural differences as they have a different cultural background.

B.

Ask the construction manager to meet with the two team members to resolve the situation.

C.

Provide the construction manager with instructions on how to resolve the situation.

D.

Discuss the team members ' concern with the construction manager and seek solutions.

Full Access
Question # 397

A project is ending its fifth out of six iterations. During the iteration review, a customer adds a new regulatory feature that exceeds the capacity of the remaining iteration.

What should the project lead do?

A.

Register an issue and escalate it to the project sponsor.

B.

Invite the stakeholders to discuss a new prioritization.

C.

Estimate the management to replace the customer service manager.

D.

Increase the team capacity to finish the project on time.

Full Access
Question # 398

A project team is executing a megaproject, and several contract requirements have been identified. In the planning phase, the project team agreed that a contract would be

required 3 months prior to the project ' s finish date. During project execution, it was determined that the contract was required immediately.

What should project manager do?

A.

Seek management ' s approval for executing the contract earlier than planned.

B.

Request the team to initiate a change request to execute the contract.

C.

Support the team ' s request and allow for early contract execution.

D.

Challenge the project team to identify the reasons for early contract execution.

Full Access
Question # 399

A project charter has been approved and the project manager has been assigned to the project. The project manager is currently working with the project team to subdivide the project work packages.

What is the project manager doing?

A.

Network diagram

B.

Decomposition

C.

Work breakdown structure (WBS)

D.

Resource leveling

Full Access
Question # 400

A critical project milestone was missed because one of the team members did not complete their tasks on time. This resulted in a heated discussion during a demonstration for the end users.

What should the project manager do next?

A.

Discuss the issue with the team member in a one-on-one meeting.

B.

Ask the team member to justify the delay during a team meeting.

C.

Review the human resources (HR) policies for relevant corrective actions.

D.

Escalate the performance issue to the team member ' s functional manager.

Full Access
Question # 401

A project manager is part of an organization that is assessing the use of agile delivery approaches. A new project management office (PMO) manager who had a bad experience with a Scrum approach recommended that the project board replace Scrum with a predictive approach.

What should the project manager do?

A.

Define a risk management plan (or the new approach, as needed.

B.

Review the benefits realization plan to include the cost of the change.

C.

Define a project management plan for the new approach, as needed.

D.

Review the communications management plan to identity new stakeholders.

Full Access
Question # 402

Due to contractual issues, a key team member cannot travel to the project location for a design review meeting.

What should the project manager do?

A.

Consider setting up a virtual meeting with the team for the design review.

B.

Ask the project sponsor if another team member can participate instead.

C.

Solve the contractual issues before continuing with the design review meeting.

D.

Inform the stakeholders and demand an immediate solution from the project sponsor.

Full Access
Question # 403

After meeting with stakeholders, a project manager working at a computer gaming company is creating a project management plan for the company ' s newest offering. The project manager learns that the company ' s main competitor is scheduled to release a similar offering leveraging the newest technology. The project manager fears that the competitor ' s offering is better in multiple ways compared to the project manager ' s project.

What should the project manager do?

A.

Perform a Kano analysis factoring in the competitor ' s offering and present it to the stakeholders.

B.

Meet with the development team to see what changes will improve the project compared to the competition ' s deliverable.

C.

Meet with the project team to discuss the concerns and determine how to ensure the project ' s deliverable can compete with the competitor ' s.

D.

Note this concern in the risk register and meet with the sales team to identify mitigation options factoring in the competitor ' s offerings.

Full Access
Question # 404

An updated schedule for work delivered by a subcontractor is a condition for a milestone payment. The subcontractor completed the work but does not have a schedule, claiming that work was already agreed upon with the client.

What should the project manager do?

A.

Negotiate a contract change with the subcontractor.

B.

Meet with the client to discuss the issue with the subcontractor.

C.

Inform the subcontractor that they must send the schedule.

D.

Tell the subcontractor to submit a draft schedule.

Full Access
Question # 405

During the execution of a project, a key stakeholder complains to the project manager about recent communications.

The key stakeholder explains that the relevant information from the project team was incomplete and late. As a result, the key stakeholder is beginning to disengage from the project.

What should the project manager do?

A.

Explain to the key stakeholder the way in which the project team communicates information.

B.

Ask the project sponsor to hold a meeting with the key stakeholder to ensure that the stakeholder is engaged in the project.

C.

Send relevant information to all key stakeholders simultaneously to ensure consistent communication.

D.

Update the communications management plan to fulfill the key stakeholder ' s expectations about relevant information.

Full Access
Question # 406

The project sponsor reports that a key stakeholder is complaining about performance differences in the metrics reported by the project manager,

which gives the impression that the project is out of control. The project manager has been providing the project ' s status according to the agreedupon communications management plan. This key stakeholder, however, seldom attends the status report meetings.

What should the project manager do first to address this situation?

A.

Evaluate the communication needs to discover the gaps and adjust the original plan if needed.

B.

Use the contingency reserves to implement fast tracking and improve the schedule key performance indicators (KPIs).

C.

Review the resource breakdown structure (RBS) to request the main stakeholder ' s manager to replace the stakeholder.

D.

Provide evidence to the project sponsor that the project is on track and the communications have been sent.

Full Access
Question # 407

A multinational company is rolling out a new software platform within its subsidiaries. However, the distributed project team struggles to meet regularly. As a result, the project milestones are not being achieved.

What should the project manager do first?

A.

Inform the project sponsor and request additional team members to crash the project schedule to meet the target

B.

Introduce an award system to promote member participation and establish some competition between the subteams

C.

Evaluate the effectiveness of the virtual teams and support them with the necessary technology and equipment

D.

Propose to roll out the new software in one subsidiary and then use the lessons learned to improve the project

Full Access
Question # 408

A project manager is leading a hybrid project that is building an app for a travel industry startup. Due to unforeseen events, the features and the overall solution will not be useable by many customers due to new travel restrictions.

What should the project manager do first?

A.

Release the team and help them achieve their potential on a new project.

B.

Ask the organization ' s management for advice regarding the project ' s direction.

C.

Assess the environmental changes and recommend a pivot for the project.

D.

Pause the project if business value cannot be reached and collect lessons learned.

Full Access
Question # 409

A project manager is starting a new project, and the project team is located in different countries. The team was going to use a specific tool to hold virtual meetings.

However, that tool is not available in one team member ' s country.

How should the project manager deal with this situation?

A.

Contact the project sponsor to have the team member removed from the project.

B.

Ask the team member to move to another location where the tool is available.

C.

Start the project and use email to communicate with the team member until the tool is available.

D.

Investigate alternative tools for virtual meetings that are available to all team members.

Full Access
Question # 410

A software development project completed the initiation phase. The technical design was approved by the project steering committee. Later, it was discovered that the design will impact the company’s production system. A new technical design must be found and this could delay the project by 3 months.

What should the project manager do first?

A.

Log the technical design delay as a risk in the project risk log.

B.

Set up a steering committee session to review the project delay.

C.

Continue with the approved design so that the project is not delayed.

D.

Ask the steering committee to approve a new technical design.

Full Access
Question # 411

A new agile project is starting. The project manager is asked to confirm the scope to address the concerns of one of the stakeholders.

What should the project manager use to explain the project scope?

A.

Product roadmap

B.

User stories

C.

Business requirements document

D.

Product backlog

Full Access
Question # 412

A project manager is preparing a budget estimation for an international construction project. They decide to consult the project team members who are experienced in this type of project and are familiar with the local laws of the country.

Which budgeting approach would be the least risky for the project team to apply?

A.

Review historical data and provide parametric estimations for the activities, including local law restrictions.

B.

Use a top-down estimation and add contingencies to cover any future impacts regarding the legal context.

C.

Make a general estimation using a standard legal approach and then look to include early definitions.

D.

Discuss and compile the local information about laws to develop bottom-up estimations.

Full Access
Question # 413

A project manager is leading a project when a key stakeholder requests additional work that is not in the scope. The stakeholder is also concerned that the project sponsors may not approve and fund the additional change in scope.

What should the project manager do first?

A.

Evaluate the cost of the additional requested work.

B.

Evaluate the impact and submit a change request.

C.

Discuss the requested change with the sponsor.

D.

Discuss the requested change with the team.

Full Access
Question # 414

In the middle of a software development project, the lead design programmer accepted an offer from a competitor. The project manager needs to find a replacement to meet an upcoming milestone.

What should the project manager do?

A.

Consult the risk response plan.

B.

Assign the tasks to another team member.

C.

Update the resource calendar.

D.

Issue a request to the change control board (CCB).

Full Access
Question # 415

A project manager is looking for ways to keep the budget on track throughout the project life cycle.

What should the project manager do to ensure that happens?

A.

Evaluate and test all budget variances.

B.

Baseline the project budget and schedule.

C.

Prioritize high-cost tasks and monitor them.

D.

Use metrics to track the cost performance.

Full Access
Question # 416

An internal virtual team is meeting daily to review iteration progress, as well as to conduct other technical and followup calls with key stakeholders. The team seems to be disengaged.

How should the project manager approach this situation?

A.

Give the team members a few days off to reduce stress.

B.

Reduce the number of internal and external meetings.

C.

Review team assignments and reduce the workload.

D.

Schedule one-to-one meetings and team-building meetings.

Full Access
Question # 417

A project manager works with a multifunctional team. During a review meeting, two team members disagree on the development approach.

What should the project manager do?

A.

Identify the best-fit approach and ask the team members to follow.

B.

Create goodwill among the team members for smooth operations.

C.

Review lessons learned and balance them within the team members ' opinions.

D.

Consult the functional team manager for their guidance on best practices.

Full Access
Question # 418

How can agile measurements improve upon predictive measurements in cases where the final 10% of a project takes longer than planned?

A.

By scheduling iterative meetings with the product owner to improve project tracking

B.

By focusing on the delivery of incremental working products lo the customer

C.

By reviewing burnup charts to determine the effort required against estimated earned value

D.

By conducting daily standups to more accurately track project deliverables

Full Access
Question # 419

A state-of-the-art product was delivered at the end of a project life cycle. However, the customer claims the product was not designed to specifications.

What should the project manager have done to avoid this issue?

A.

The customer ' s requirements should have been captured in order to meet the customer ' s standards.

B.

The iteration review planning meeting should have been planned accordingly.

C.

The sprint retrospective meeting should have included necessary stakeholders.

D.

The customer ' s requirements should have been captured and modified to meet the supplier’s standards.

Full Access
Question # 420

A mid-size capital project has shared resources from the company ' s contract department. During the execution phase, the project team observed

a delay in contracting. After communicating with the contract department, the project manager found the contract team is prioritizing other

contracting jobs because they are not part of the project team.

What should the project manager do first in this situation?

A.

Report the issue to higher management and seek their direct involvement to complete the job from the contract department.

B.

Arrange a meeting with the contract department to build trust and commitment by recognizing their critical support to the project.

C.

Arrange several meetings with the contract department and ask them to contract the project as it is critical for project success.

D.

Communicate with the contract manager to commit a budget for the resources required for project execution.

Full Access
Question # 421

A senior project manager is working for a company that is not yet making a profit. However, the company has many innovative projects in development. Most of the project

time lines have slipped, and the staff is overwhelmed .

What should the project manager do to help the company meet their financial objectives?

A.

Prioritize the projects, giving higher priority to projects that will increase profit.

B.

Make sure the project is fast tracked so that slipped time lines are recovered.

C.

Request that upper management hire additional staff to support the projects.

D.

Ensure that all of the projects are of high quality and are delivered on time.

Full Access
Question # 422

A project to construct an electricity generation plant is on site near a nature reserve. An environmental activist group is questioning the need for

the project. The customer has informed the project manager to disregard the group as they are not in support of the project.

What should the project manager do next?

A.

Ask the customer to contact the activist group and let them know the project status and completion date.

B.

Add the activist group to the list of stakeholders and analyze the impact they may have on project delivery.

C.

Obey the directive from the customer since they are funding the project and are the most important stakeholder.

D.

Request the project team disregard all communication from the activist group and continue with their project work.

Full Access
Question # 423

A project team is implementing an enterprise notification tool with a vendor. The project manager noticed that this vendor ' s developer has been reporting the same status for

several weeks in a row. A few days later, the vendor communicates that the deliverable will not be completed on time due to resource constraints within their company.

What should the project manager do next?

A.

Update the risk register to reflect the delay, communicate the impact to the schedule, and escalate to management for assistance.

B.

Conduct a project review with the project sponsor to explain the delay and add a developer to work with the vendor.

C.

Review the contract with the vendor to go over the financial penalty that is applicable to this situation.

D.

Add the delay to the issue log and work with the vendor for a resolution that will bring the schedule back on track.

Full Access
Question # 424

A project manager wants to assign a junior engineer to a new project. In past projects, the engineer showed initiative to take on complex tasks and solve problems in

innovative ways without any need for encouragement. However, the engineer declines the project manager ' s invitation to join the new project.

What is the most likely reason for the engineer ' s refusal to work on the project?

A.

The engineer did not feel welcome or enjoy working with the other project team members.

B.

The project manager did not follow the normal hiring process with the engineer ' s functional manager.

C.

The engineer has “project burnout " from working long hours and solving difficult problems.

D.

The project manager did not sufficiently support and recognize the engineer ' s professional growth.

Full Access
Question # 425

A project that is using an incremental approach has colocated team members and is using a kanban board to visualize the work in progress

(WIP). A key external stakeholder requests that all project activities be placed on hold until a status report is distributed.

What should the project manager have done to avoid this situation?

A.

Stored project documentation in a shared folder.

B.

Organized monthly meetings with the external stakeholders.

C.

Invited all of the stakeholders to daily standup meetings.

D.

Sent weekly status update reports to all of the stakeholders.

Full Access
Question # 426

A project manager noticed that the functional manager is not cooperating with staff assignment schedules and is always finding excuses not fo release the requested staff.

What should the project manager do first?

A.

Ask the leadership team for help obtaining the needed staff.

B.

Check with human resources (HR) regarding the availability of staff.

C.

Have a direct talk with the functional manager to understand the reasons behind their attitude.

D.

Evaluate the impact caused by the delay of forming the team and confront the functional manager.

Full Access
Question # 427

A feature has been added to the iteration backlog that has been prioritized by the project sponsor over other critical security patches. What should the project manager do?

A.

Perform a risk analysis and then meet with the project sponsor to discuss it.

B.

Meet with the project sponsor to discuss the feature with the product owner.

C.

Push back on the feature because it is not an immediate priority.

D.

Give all the work packages parallel priority and continue activities.

Full Access
Question # 428

A project manager assigned to an education project needs to train a workforce in application development. The customer is responsible for

providing the training center, and the deadline to start the first training is in 2 weeks. The customer calls to say that the center will not be available

in 2 weeks due to some unforeseen problems.

What should the project manager do next?

A.

Apply the terms and conditions of the contract with penalties.

B.

Issue a change request to reflect the anticipated date for training.

C.

Help the customer find an alternative location to start the training.

D.

Update the project schedule with the new date for training.

Full Access
Question # 429

A project team ' s performance is being impacted by impeding internal procedures that are affecting the progress of activities and team autonomy. What should the project

manager do first to address this situation?

A.

Try to remove the barriers and empower team members.

B.

Ask the organization to improve the internal procedures.

C.

Train the team members on the organization ' s procedures.

D.

Discuss the issue in the next sprint review meeting.

Full Access
Question # 430

An organization with a new project management office (PMO) team is now undergoing a restructuring. Additionally, there is a lack of communication from the PMO to the team members.

How should the project manager handle this situation?

A.

Meet the PMO team and explain the importance of communicating with the team members for project success.

B.

Request the PMO team share updates on the restructuring with the team members on an immediate basis.

C.

Set up a meeting with the PMO and project team to discuss and clarify questions related to restructuring.

D.

Inform the team that despite the new PMO and restructuring, the team will not change.

Full Access
Question # 431

A project manager is leading a cross-departmental project that involves many stakeholders. During the project, the project manager observes that the stakeholders are diverse and have different expectations about how the project should be handled. This leads to frequent confusion and misunderstandings among the stakeholders.

What should the project manager do to integrate the diverse stakeholder groups?

A.

Advise the team members to focus on project work and avoid getting distracted by the stakeholders’ disagreements.

B.

Hold separate meetings with the individual stakeholders and escalate their concerns to the project sponsor.

C.

Develop a joint quality policy for the project and seek a commitment by all of the departments.

D.

Analyze the probability and impact of the risks linked with the situation and implement the proper response plan.

Full Access
Question # 432

A large construction project is progressing well as per the project objectives. The project manager would like to report the project ' s value to the project sponsor and seek the

next phase of funding closure.

What should the project manager do?

A.

Ensure a measurement system is in place like earned value analysis (EVA) to track project value for the project sponsor.

B.

Submit a detailed report on the cost budget vs. the cost actuals as the project sponsor will want to know more about finances.

C.

Create a detailed project report on successes and challenges for the project sponsor.

D.

Arrange a site visit to show the project sponsor the construction progress in person.

Full Access
Question # 433

A project is about to start with a global project team. Travel is not a viable option for project team members, so most will participate virtually.

What should the project manager do to engage the team?

A.

Have one-on-one meetings with team members to improve communication.

B.

Ask human resources (HR) for team-building recommendations.

C.

Schedule weekly team meetings to encourage collaboration.

D.

Invest in a virtual collaboration/colocation environment.

Full Access
Question # 434

A website application project is underway and the agile team has reached a stable velocity. After eight iterations, they complete 20 story points per sprint. The project lead and team plan to maintain the same velocity for the next 2 months. After this period, the team completed 100 story points. The project sponsor asks for the project status.

How should the project lead respond?

A.

The cost performance index (CPI) is below average with a 25% reduction.

B.

The schedule performance index (SPI) is 25% less than expected.

C.

The team ' s performance indicator is higher than expected.

D.

The cost and schedule performance indicators are equivalent.

Full Access
Question # 435

A company is working on a project to develop an integration of their existing systems. There are known issues in production.

What should the project manager do?

A.

Identify and remove impediments and mitigate the risks.

B.

Ensure the product owner reviews requirements with the team.

C.

Include acceptance criteria in the definition of done (DoD).

D.

Review the quality control processes and procedures.

Full Access
Question # 436

A project manager is preparing to start a new project in which the team members are distributed geographically across different countries. The project manager is using the communications management plan to engage the team members and find a communication method that suits everyone.

How should the project manager continually evaluate the effectiveness of the virtual team ' s engagement?

A.

Collect feedback from the team to discuss alternatives to enhance the communication.

B.

Conduct individual meetings to create a trusting environment with team members.

C.

Establish periodic face-to-face meetings and address the communication topic.

D.

Hold meetings in accordance with the team members’ preferences and availability.

Full Access
Question # 437

A project manager has just received communication from an operational functional manager to complete an additional scope item for a project that was formally closed a few weeks ago. The scope looks relatively small and simple to handle as part of the daily operations activity.

How should the project manager deal with this request?

A.

Submit a change request and allocate the budget and resources needed for execution.

B.

Confirm that the budget and resources are available to execute the work request.

C.

Check the alternative resources available in the organization for the request.

D.

Evaluate the nature of the request and plan communication accordingly.

Full Access
Question # 438

In a geographically distributed team, a developer continues to delay a coding activity. This activity is on the critical path. The project manager

found out that the delay is due to the developer ' s lack of understanding of the customer requirements shared by the off-site team.

What should the project manager do?

A.

Replace the developer with a skilled resource.

B.

Perform a root cause analysis (RCA) with the team members.

C.

Facilitate communication to ensure clarification of the requirements.

D.

Conduct frequent performance reviews.

Full Access
Question # 439

A company was acquired, and the new company management asked the project manager to begin using a specific set of metrics immediately to measure team performance. The project manager is working on a predictive project and thinks this request will distract the team and delay the project.

What should the project manager do first?

A.

Assess and analyze the impact of using these metrics.

B.

Involve the team in reviewing the proposed metrics.

C.

Request an extension to implement the new metrics.

D.

Support the required metrics during the next project phase.

Full Access
Question # 440

All project team members refer to the project manager for various decisions. This causes delays for some tasks, as the project manager is usually preoccupied in meetings throughout the day.

What should the project manager do to prevent these delays?

A.

Review the Pareto diagram to identify the source of delays.

B.

Meet with the team in 2 weeks to respond to all of the open tasks.

C.

Consolidate the decision-making authority to remain with the project manager.

D.

Delegate the decision-making authority of some tasks to the team.

Full Access
Question # 441

A project manager is leading a long-term project, executed in stages, to set up a complex communications network in many rural areas. The project is being executed in stages.

What should the project manager do to ensure that monetized business value is generated as planned?

A.

Compare the estimate to complete (ETC) benefits against the project business plan

B.

Compare the benefits of the throughput analysis against the project business plan

C.

Evaluate the net promoter score (NPS) benefits against the project business plan

D.

Evaluate the generated benefits at project milestones against the project business plan

Full Access
Question # 442

A project team has finished its first iteration out of six. The iteration ' s delivery performance (velocity) was 50%.

During the iteration retrospective, the team realizes that the complexity of the work was underestimated.

What should the project manager do?

A.

Update the issue log and escalate it to the project sponsor.

B.

Meet with the team to review internal actions to resolve the situation.

C.

Ask the technical manager to help the team with the issue.

D.

Ask to replace some team members with more experienced ones.

Full Access
Question # 443

A project manager is leading a large public project that will have a high impact on the town ' s citizens. How should the project manager define the different requirements?

A.

Include only the common requirements of each stakeholder group in the project goals.

B.

Include only the key requirements and keep the stakeholders informed about scope decisions.

C.

Analyze the interests and influence of stakeholders and evaluate their requirements.

D.

Add only the opinions of the team, because they know the objectives of the project.

Full Access
Question # 444

An agile team is required to address a technical, complex requirement that has no visual deliverable to show the customer. What guidance should the product manager provide to improve the requirement development?

A.

Discuss this with the team and reprioritize the backlog to deliver maximum value by including a portion of the complex work.

B.

Reprioritize the product backlog by lowering the priority of the complex activity, so it will be worked on later in the project.

C.

Allow the team to focus and complete the complex work because it will reduce the risk of finding issues later in the project.

D.

Inform the customer that there will not be any deliverable due to the complexity involved in the requirement.

Full Access
Question # 445

A team is finishing the third release to present to the stakeholder as part of a demonstration. The company that subcontracts the developers has communicated that there is a cash flow problem and the company will not be able to provide the same resources for the next iterations.

What should the project manager do next?

A.

Create a risk register to track the risks and request additional budget.

B.

Analyze the impact against the release plan if the blocker is not addressed.

C.

Work with the project owner to prioritize the product backlog.

D.

Escalate the situation to the project sponsor for a possible resolution.

Full Access
Question # 446

A project manager has received feedback from stakeholders regarding poor communication about project progress. Weekly status reports were provided to the project management office (PMO), and the standard communications management plan was followed.

What should the project manager do?

A.

Perform a root cause analysis (RCA) of the existing communication approach.

B.

Ensure that all of the complaining stakeholders are on the distribution list.

C.

Create a change request for implementing an online collaboration tool.

D.

Distribute hard copies of status reports and confirm that messages were read.

Full Access
Question # 447

A startup company has just appointed a CEO that has no prior project experience. The CEO wants to execute projects with their own resources

and has appointed a project manager.

What should the project manager recommend that the CEO do first?

A.

Create a framework to justify project execution.

B.

Utilize an agile approach for all upcoming projects.

C.

Create a framework to support project success.

D.

Utilize a predictive approach for all upcoming projects.

Full Access
Question # 448

A project team member identified a procurement risk and sent an email to the project sponsor highlighting the risk.

The sponsor forwarded the email to the project manager asking for further details. After speaking with the sponsor, the project manager decided to take preventive action.

Which document should the project manager review with their team?

A.

Risk management plan

B.

Quality management plan

C.

Communications management plan

D.

Procurement management plan

Full Access
Question # 449

Anew major road project is starting, and the contractor has contractually committed to submitting regular status reports and participating in integration meetings. Halfway through the project life cycle, the contractor stops participating in meetings and submitting reports, stating these items consume too much time.

What should the project manager do first?

A.

Assess the risk of the contractor not attending meetings and submitting reports for the rest of the project and escalate it to the project sponsor.

B.

Submit a claim for not fulfilling the contract terms and handle the claim in accordance with the alternative dispute resolution.

C.

Remind the contractor that they committed to attending meetings and submitting reports per the contract.

D.

Speak with the company’s lawyer and request that they demand the contractor fulfill their contractual commitments.

Full Access
Question # 450

A project team is transitioning to agile. During the sprint retrospective, a new member of the team proposed a more structured approach for capturing requirements that would improve clarity and reduce rework. Although the team members are happy to use it, changing the way business requirements are described requires agreement from an influential business manager.

What should the project manager do?

A.

Contact the business manager and discuss the benefits of the new approach.

B.

Contact the project management office (PMO) and ask them to endorse the new approach.

C.

Ask the team member to wait until the business is ready for the new approach.

D.

Ask the team to describe the requirements using the more structured approach.

Full Access
Question # 451

A mandatory compliance requirement that will impact the project software is introduced during the execution phase of an iterative project. The team is aware of the compliance requirement.

What should the project manager do next?

A.

Update the product backlog item with this new requirement.

B.

Escalate the issue of project impact to the project sponsor.

C.

Escalate the issue of project impact to the product owner.

D.

Update the stakeholder register to include the requirement owner.

Full Access
Question # 452

A project manager is leading an agile team. The daily standups and iteration meetings are currently facilitated by the product owner. A team member contacts the project manager and mentions that they are looking to improve their facilitation skills.

How should the project manager respond to this request?

A.

Ask the team member to review the lessons learned on facilitation from previous projects.

B.

Suggest that the team member facilitate an upcoming iteration and review the outcomes in the iteration retrospective.

C.

Engage their functional manager to determine if there is alignment to their development plan before agreeing.

D.

Add new elements to the project backlog to account for the training needs of the team member.

Full Access
Question # 453

A project manager works in an organization that embraces using different project approaches. The project manager ' s current project uses a

predictive approach with clear requirements. A few months following the kickoff, the project manager notices that the virtual development teams

are not communicating enough, and coordination is becoming an issue. The teams are not aligned on the tasks being done or the current

impediments.

What should the project manager do?

A.

Ask the members to be more proactive and share ideas with each other.

B.

Set up a daily virtual meeting with the development team.

C.

Plan a monthly virtual meeting to align and to review the plans.

D.

Review the issue with the project sponsor and ask for support.

Full Access
Question # 454

In an agile project, the project owner has repeatedly called for ad hoc meetings with team members. What should the project manager do?

A.

Ask the team to focus only on the goal, not on ad hoc meetings.

B.

Coach the project owner about the implications of unplanned meetings.

C.

Discuss the issue with the project owner at the retrospective meeting.

D.

Escalate the situation to management because it is affecting the team.

Full Access
Question # 455

A newly formed project team includes team members who have been working in the company for a long time as well as team members who are new to the company. The

project team members discovered that there is a gap in communication between these two groups, and they are finding it hard to collaborate with one another.

What should the project manager do?

A.

Ask the experienced members to lead the junior members to facilitate skill transfer.

B.

Encourage team members to focus on delivering results with their specialized skills.

C.

Organize networking sessions to allow the team members to get to know one another.

D.

Ask the team to self-organize and escalate any issues to the project manager.

Full Access
Question # 456

A project manager is in the middle of handling a major upgrade to an existing product. The project manager learns that the resources initially promised as part of the project are being moved to another priority project.

What should the project manager do?

A.

Retrieve the documentation that shows the resource allocation.

B.

Examine ways of modifying the scope of the project.

C.

Adopt a resource leveling procedure to level the resources.

D.

Perform an impact analysis to see the effect on the project.

Full Access
Question # 457

An organization is transitioning to agile. The project manager is discussing how to manage risks with the development team in light of the transition for a particular project.

The team estimates the risk level as low.

What should the project manager do?

A.

Capture all the backlog entries assessed by the development team to have evidence that risk management has been completed

B.

Create a risk register to identify, capture, review, and manage risks using a risk management process.

C.

Trust the development team ' s risk estimation and inform the project sponsor that the risks will be evaluated at a later time.

D.

Create a risk register and include a single generic risk, set the level to low, and then close the risk at the end of the project.

Full Access
Question # 458

A project manager has been assigned to a hybrid project that must receive approval from a government regulator. During the daily standups, one

member reported an impediment that requires collaboration from an expert who is assigned to another project.

What should the project manager do first in this situation?

A.

Review the project ' s key performance indicators (KPIs) to determine the impact of this assignment.

B.

Check the expert ' s availability within the organization on an as-needed basis.

C.

Develop the team member ' s capacities through mentoring and training.

D.

Ask the project sponsor to assign a new resource with the necessary expertise to the team.

Full Access
Question # 459

A project is about to start. The project manager has found that the client does not have an appropriate knowledge management system and does

not have a requirement for it.

What should the project manager do?

A.

Ask the team to collect the knowledge locally and share it at the end of the project.

B.

Utilize the cloud wiki to collect the necessary knowledge.

C.

Coordinate with the team and the project stakeholders to collect the knowledge.

D.

Provide just-in-time knowledge to the client, upon request.

Full Access
Question # 460

A company is transitioning from a predictive approach to an agile approach. A project manager is assigned to the first pilot with an inexperienced team. Due to an unexpected event, the whole team is asked to work remotely. During the second sprint, the project manager starts to notice a lack of commitment from the team members.

What should the project manager do in this situation as a servant leader?

A.

Request an exception to allow the team to return to work on-site

B.

Allow the team to address the problem as a self-organized team

C.

Coach team members to increase their engagement and collaboration

D.

Force the team to attend the daily standups to gather the project status

Full Access
Question # 461

A project manager has recently moved to an organization to lead a key project. The project manager notices that team performance is below the target, and the tasks assigned are not delivered on time. Team commitment is also not as appropriate as it should be.

What should the project manager do?

A.

Study and determine the appropriate leadership style suitable for the team.

B.

Hire a project team leader who can influence the project team members.

C.

Schedule a meeting and communicate the performance concern to the team.

D.

Apply an agile approach to help improve team performance.

Full Access
Question # 462

A multimillion-dollar project has started and is in the execution phase. A local regulatory authority has just announced changes to the requirements that will need to be implemented in 6 months, prior to completing the project execution phase.

What should the project manager do next?

A.

Add the new requirements to the project scope immediately since they are mandatory changes.

B.

Review the new requirements with the compliance department to determine if a change request is needed.

C.

Ignore the new requirements as the current budget and schedule do not allow for any changes.

D.

Proceed with the defined project requirements and delay implementing the new requirements.

Full Access
Question # 463

An agile project team is working on an infrastructure product to be delivered incrementally over several iterations. Midway through the third iteration, the whole company is

informed that the operating systems supported by the infrastructure will be terminated in the upcoming quarter. Several thousand machines will be impacted by this change.

What should the project manager do first?

A.

Prioritize the upgrade of project machines with the IT department.

B.

Inform the product owner and request more project resources.

C.

Schedule a session with stakeholders to understand the impact.

D.

Add product backlog items to prioritize operating system stories.

Full Access
Question # 464

A project manager has been assigned to manage multiple agile project teams. The project manager wants to empower the teams and make them self-organizing.

What should the project manager do to create a positive environment?

A.

Establish the team ground rules and share them with the team for strict adherence.

B.

Copy the ground rules established by another project and provide them to the teams.

C.

Extract the organization ' s policies and processes, customize them, and give them to the teams to adhere to.

D.

Help the teams in establishing and adhering to their ground rules and revisit after regular intervals.

Full Access
Question # 465

A project manager is managing a project that has a new sponsor who is cutting the budget As a servant leader how should the project manager handle the budget cuts with the team?

A.

Notify the project sponsor that the budget reduction will require a schedule slip and scope reduction.

B.

Inform each team member that they must release a portion of their budget but must remain on schedule with no change to the scope

C.

Meet with the schedule coordinator and financial analyst to tell them which budget lines to reduce and where to release slack

D.

Collaborate with the team to assess the impact of the change on the project and recommend an updated project plan

Full Access
Question # 466

An experienced project team member always points out the issues of other team members during meetings. The other team members feel that

the experienced team member is deflecting their own issues in meetings.

What should the project manager do?

A.

Arrange separated group meetings to allow everyone to express their opinions.

B.

Review the communications management plan with the team and enforce its implementation.

C.

Prepare an agenda for all future team meetings and facilitate the discussion.

D.

Speak with the experienced team member to discuss the issues in a supportive way.

Full Access
Question # 467

A project manager is working on a time and materials (T & M) project using a hybrid approach. The milestones and outcomes are defined for the first 6 months with

incremental releases every month. After the first 2 months, the client communicates their dissatisfaction with the results and asks to change the course of the project. The project manager held a face-to-face meeting with the client and now has a better understanding of the newly desired milestones and outcomes.

What should the project manager do first?

A.

Forward the client ' s request to management as a change request to get formal approval.

B.

Document the information in the meeting minutes and share it with the project stakeholders.

C.

Draft a contract change with the desired scope changes and send it to the client for approval.

D.

Finish the current monthly release as it was planned and replan for the future months.

Full Access
Question # 468

A defect is identified during user acceptance testing that could significantly impact the system ' s performance. The project team has advised that this defect puts the delivery date at risk.

Which risk management process should be performed?

A.

Plan Risk Responses, to outline the possible options to bypass the system performance issue

B.

Perform Qualitative Risk Analysis, to assess the extent of the system performance impact

C.

Monitor Risks, to install system performance monitoring tools and update the risk register

D.

Perform Quantitative Risk Analysis, to outline the details of the system performance issues

Full Access
Question # 469

In a highly politicized organizational environment, the stakeholders are driven by their own operational or business goals, which results in

conflicting interests regarding the project. What should the project manager do to steer the stakeholders toward the collective project goal?

A.

Anticipate, alert, and follow the risk management process.

B.

Detect, track, and follow the issue management process.

C.

Promote, inspire, and follow the stakeholder engagement process.

D.

Discuss, educate, and follow the communications management process.

Full Access
Question # 470

A product owner is invited to a sprint review meeting. At the end of the review, the product owner says that the increment is ready to be delivered to the customer.

What conclusion should the project manager come to with regard to the product owner ' s statement?

A.

The product owner does not have visibility into what the team has done in the product increment.

B.

The product owner trusts the team and is marking the product as complete.

C.

The product owner has evaluated the product against the definition of done (DoD).

D.

The product owner will release the product to customers without showing them a demo.

Full Access
Question # 471

In the planning phase of a software implementation project, two of the team members disagree on how to approach end-user training. The

discussion has intensified and the team members are not able to agree.

What should the project manager do next?

A.

Remove one of the team members from the project to improve team dynamics.

B.

Make a decision based on expert judgment as a project manager.

C.

Consider the view of each team member about the issue in order to reach consensus.

D.

Remove both team members since they are not productively adding to the team.

Full Access
Question # 472

An organization initiated a project in a complex program. The project lead notices that the team is demotivated because the current project framework implemented by the project management office (PMO) is not compatible with agile delivery

What should the project lead do?

A.

Escalate the problem to the product owner.

B.

Ask the PMO to review the framework

C.

Request the PMO to define a new framework.

D.

Plan a brainstorming session with the project team

Full Access
Question # 473

A company is engaged in a transformation journey, and the project manager for this endeavor is new to this project. During one of the project status update meetings, a key stakeholder, the project manager ' s functional manager, is dissatisfied with the work in progress, and points to the project manager.

What should the project manager do?

A.

Schedule a one-on-one meeting with the functional manager to prove the project is on time

B.

Listen carefully and show understanding of the growing needs of the functional manager.

C.

Admit that the functional manager is right and promise to rectify the situation immediately.

D.

Show the functional manager that the progress is on time based on the schedule.

Full Access
Question # 474

A company has undertaken a large transformation project in preparation for the changing economy. During the planning of the transformation project, the key resource from human resources (HR) refuses to approve the proposed project plan.

What should the project manager do to gain an understanding of the cause for the resource ' s refusal?

A.

Speak directly with the resource.

B.

Communicate with their supervisor.

C.

Organize a team meeting.

D.

Speak with their colleague.

Full Access
Question # 475

A project manager has been managing an agile project for 6 months. Over the last two iterations, the team velocity has decreased due to a new technology that was needed

for the product.

What should the project manager do to continue with the delivery plan and return to the expected velocity?

A.

Use retrospectives to better understand the new technology ' s impact on the schedule, map the skill gaps, and adjust the team accordingly.

B.

Reevaluate the backlog by looking for high-value/low-effort items, and negotiate a new minimum viable product (MVP) strategy with key stakeholders.

C.

Seek sponsor approval for additional funding to hire new team members, increasing the capacity of the team and compensating for the productivity lost with the new technology.

D.

Replace poorly performing team members with more experienced members, setting an example of accountability for the team.

Full Access
Question # 476

A project manager is managing an agile project that is part of a program with many interconnected projects. Dependency management is fundamental because there will be many milestones for different projects that are dependent upon each other during the program duration.

What should the project manager do?

A.

Assign a development team member to have the responsibility of managing dependencies.

B.

Suggest that each project develops a high-level plan to monitor the dependencies

C.

Recommend switching to a predictive approach to have detailed plans to manage the dependencies

D.

Continue the project with 2-week iterations as dependencies will be managed individually

Full Access
Question # 477

A company has created a cross-functional team to drive the digital transformation project for the business. The team is expected to deliver the minimum viable product (MVP) that addresses market need in the shortest possible time.

Match the roles for the team on the left to their corresponding responsibilities on the right.

Full Access
Question # 478

A project manager has been assigned to a new project that is similar to a project that was closed last year. There is no schedule baseline, but the project manager received the activity list and wants to prepare a reasonable schedule.

What should the project manager do?

A.

Adopt the same timeframe as the closed project for the current project.

B.

inform the sponsor that the activity list is not adequate for creating a schedule baseline.

C.

Create a draft schedule based on the activity list and the historical data from the closed project.

D.

Evaluate each activity duration and build a new project schedule.

Full Access
Question # 479

A scrum team ' s daily meetings are conducted by teleconference between three teams, each located in different countries. The meetings typically

last 45 minutes with many misunderstandings due to language barriers.

How should the project manager resolve this issue for the next iteration?

A.

Transfer half of the backlog items to the next iteration to allow more time to complete the meetings.

B.

Extend the meeting to 1 hour and request that all of the participants bring up all of the issues.

C.

Instruct the meeting participants to speak only about blockers during the meeting.

D.

Train the three team leads to conduct a local meeting, then run an overall status meeting.

Full Access
Question # 480

A project manager is managing a national rollout for an innovative product in a regulated environment that is expected to change. The project management office (PMO)

needs visibility of the regulatory constraints while maintaining a degree of flexibility.

Which tool can the project manager use?

A.

Use a burndown chart to provide transparency.

B.

Use a kanban board to increase accountability.

C.

Use a product backlog to manage changes.

D.

Use a burnup chart to provide transparency.

Full Access
Question # 481

In an agile project, the learn planned to complete 40 story points in an iteration, but only completed 30 story points. What is the schedule performance index (SPI)?

A.

30/40

B.

40/70

C.

30/70

D.

40/30

Full Access
Question # 482

A project manager is managing a few innovation projects with a high level of uncertainty. The project manager is experiencing challenges with the large number of change

requests issued due to the nature of the project.

What should the project manager do?

A.

Add a fixed number of change requests allowed by the client on the project baseline.

B.

Request sponsor approval for all change requests to reduce the number of changes.

C.

Initiate the number of iterations to reduce the number of change requests.

D.

Reduce the number of approvers required to implement a change request.

Full Access
Question # 483

An organization is transitioning to an agile approach. At the project ' s first sprint review, the product owner did not accept the result of the sprint and has some concerns.

What should the project manager do?

A.

Organize a sprint retrospective and discuss the issues and how they can be avoided in the next sprint.

B.

Ask the project team to address the product owner ' s issues since the product owner is responsible for the scope in agile.

C.

Ask the product owner to accept the outcome since the team delivered what was agreed in the sprint planning.

D.

Create a record in the issue register and escalate the issue to the project steering committee.

Full Access
Question # 484

A project manager is assigned to a multiyear enterprise resource planning (ERP) solution project. During planning, the business sponsor emphasizes the importance of demonstrating value along the way, while maintaining the integrity of the final product.

How should the project manager establish the delivery model for this project?

A.

Organize the project into multiple subsets based on business functions and deliver each subset as a component of the final product.

B.

Reestablish the project as a program with multiple small projects, as each project will be delivered as a product of its own.

C.

Communicate the latest status to the steering committee and provide a demo of the features completed.

D.

Schedule routine demos on features completed and deliver a single product once all features are completed.

Full Access
Question # 485

After assigning tasks to a project team, a project manager discovers that some team members are uncomfortable. Same team members are having 4 difficult time understanding their assigned tasks, whereas other team members are challenging the schedule based on that allocation to the project.

Which phase of the Tuckman ladder of team formation is occurring?

A.

Forming

B.

Mourning

C.

Storming

D.

Norming

Full Access
Question # 486

A project manager is reviewing the lessons learned for an historical project. The review identifies that the client ' s engineer was adamant that they review all changes, even those not identified in the contract.

How should the project manager deal with this when planning the project?

A.

Ensure the change management plan highlights this requirement to prevent future issues.

B.

Update the project charter with this information regarding change management.

C.

Update the project risk register to identify this risk and describe how to mitigate the issue.

D.

Talk with the client to ensure they are aware of the change management procedure.

Full Access
Question # 487

A senior employee with experience relevant to a highly complex project is seeking a promotion to be able to join the project. The employee has made a recommendation regarding the project. The project charter was recently approved.

How should the project manager address the employee ' s request?

A.

Evaluate the employee ' s recommendation by reviewing the lessons learned from a similar project.

B.

Create a salience model to determine if the employee will have influence on the project.

C.

Ask the project sponsor to revisit the project charter to consider the employee ' s recommendation.

D.

Assess the influence and power of the employee to see if the employee will add value.

Full Access
Question # 488

Halfway through project execution, stakeholders ask for equipment that was expected to be procured. The project manager explains that the equipment was purchased, but differs from what the stakeholders are currently asking for. This is because the initial requirements were changed during a previous meeting.

What should the project manager have done to avoid this situation?

A.

Ensured that communications were sent to all stakeholders when requirements change

B.

Ensured procurement contracts were able be canceled when situations like this arise

C.

Ensured project requirements were validated and communicated with the procurement team

D.

Ensured changing stakeholder needs and requests were properly monitored

Full Access
Question # 489

A project manager for an iterative project noticed that retrospective items indicate that the team is not fully conversant with the principles of iterative development. The team meets to analyze the gaps in the training that recently concluded with a third-party trainer.

What should the project manager do next?

A.

Initiate hybrid development as an interim approach.

B.

Let the project team self-organize and develop their skills.

C.

Mentor and coach the team to meet the project needs.

D.

Review the training contract to determine the next steps,

Full Access
Question # 490

A project manager has established daily standup meetings with the team during the execution phase of the project. The project manager has been successful in removing 75% of the

obstacles reported, but the timeline continues to deviate further each day with no signs of improvement.

What should the project manager have done to avoid this issue?

A.

Prioritized blockers on the critical path

B.

Distributed the daily standup meeting agenda beforehand

C.

Followed the quality control measurements

D.

Developed the team members’ competences:

Full Access
Question # 491

During the daily standup meeting that is assessing progress against the current sprint, a team member reports some delays due to a component

managed by an external vendor. How should the project manager address the team member ' s concern?

A.

Ask the team member to resolve the issue independently to minimize further delays.

B.

Ask the team member to provide details to address the issue with the vendor.

C.

Implement fast tracking to reduce the impact of the delay on the sprint.

D.

Update the communications management plan to prevent future reoccurrence.

Full Access
Question # 492

A project manager manages multiple information technology (IT) projects in a matrix organization. The project manager schedules a meeting with one of the functional

managers to coordinate testing support for two software development projects. Unfortunately, the functional manager is not able to attend the meeting and informs the project manager that there may not be any resources available to test the software.

What should the project manager do?

A.

Discuss the testing requirements with a test engineer and negotiate the best approach to test the newly developed software.

B.

Meet with the project team to collaboratively determine how the project manager can ensure the needed testing assistance is obtained.

C.

Request a meeting with the sponsor to change the scope to allow the development team to conduct testing.

D.

Meet with a procurement specialist to negotiate with a company that specializes in software testing to test the software.

Full Access
Question # 493

A company wants to be a pioneer in its industry and has announced the launch date of a new innovative product. After the first sprint planning, the

team realizes that it is not possible to deliver all the features in the required time.

What should the project manager do to ensure success?

A.

Increase the capacity of the team to deliver the completed backlog on time.

B.

Ask the customer to reduce the backlog to meet the launch date.

C.

Assist the team in defining a minimum viable product (MVP) by the launch date.

D.

Schedule a meeting with the stakeholders to review the contingency plan.

Full Access
Question # 494

A project manager is made aware that there are defects in the parts provided by a supplier, which are causing delays in the testing phase. The supplier claims that all parts have been delivered as per the contract. If the defects are not fixed by the supplier within one week, the product release will be impacted.

What should the project manager do?

A.

Escalate this issue to senior management, as the supplier is not following the procurement contract.

B.

Request a revision of the procurement contract to include specifications for the parts.

C.

Request a cancellation of the procurement contract with the supplier and impose a penalty.

D.

Review the procurement contract and ask the supplier to negotiate a solution.

Full Access
Question # 495

At a meeting, the project manager for an agile project indicates that the sprint goals were not met. The product owner leaves the meeting early. and the team discusses how the meeting went. Team members are confused as there were no defects for the new user stories and no new requirements were discussed.

What should the project manager do in the future to avoid this situation?

A.

Create better plans to test the functionality in more detail.

B.

Review the definition of done (DoD) with the product owner.

C.

Include previous sprint defects and close them in the actual sprint.

D.

Get approval from the product owner on the user stories.

Full Access
Question # 496

In the middle of the execution phase for a big project a new stakeholder who was unfamiliar with the project joined the board of directors and is influencing the decisions made in the project. This change is impacting the project ' s progress

What should the project manager do first?

A.

Revise the project schedule

B.

Present the project to the stakeholder

C.

Inform the client about the change

D.

Update the risk register with a new risk

Full Access
Question # 497

A project manager in one country is reporting to a lead project manager for a new software development project in another country. The lead project manager constantly

requests updates from the project manager, often demanding information via multiple communication channels if the project manager does not respond within a few minutes

of a request. Both of them are equal in seniority and both report to the same functional manager.

How should the project manager proceed?

A.

Update the communications management plan and the stakeholder engagement plan.

B.

Escalate the issue to the functional manager and explain the situation to them.

C.

Negotiate a mutually agreeable feedback cycle with acceptable timelines.

D.

Refer the lead project manager to the communications management plan.

Full Access
Question # 498

A project manager is leading three projects in a program focused on starting product commercialization. Once the three projects fareket, the project manager stops attending the recurring team meetings. The program manager asks the project manager to continue attending these meetings to maintain those team touchpoints.

This request does not match the project manager ' s expectation, since a program manager is overseeing the remaining work

How should the project manager approach the situation?

A.

Attend only the program meetings where the market launch is being monitored

B.

Provide an answer via email recommending a division of tasks between both roles.

C.

Politely inform the program manager that attending these meetings is no longer required.

D.

Schedule a meeting to discuss the different perspectives and agree on a decision.

Full Access
Question # 499

A project manager receives information in preparation for reporting the project ' s monthly performance to the project steering committee,

* Actual progress = 2 units

* Planned progress = 3 units

* Actual cost (AC) = 2 units

* Budgeted cost = 3 units

What statement should the project manager make to the project steering committee?

A.

The project is currently behind schedule with a corresponding lower cost, and every effort is being made to expedite the delayed activities.

B.

The project is currently behind schedule with a corresponding cost savings, and no further actions should be taken.

C.

The project is currently behind schedule but at a lower cost, and an application for a time and budget extension will be submitted.

D.

The project is currently behind schedule but is under the planned expenditure, and the project manager is pleased to declare a project cost savings,

Full Access
Question # 500

A project manager has been assigned a project to build a new solar farm that will provide clean energy to a new housing complex. The government has decided to reduce

the tax on renewable energy products starting 1 January. The supplier has reached out and stated that the order placed for solar panels to be delivered on 20 December

might be delayed until early January. On the other hand, the project will face similar constraints due to the December holidays.

What should the project manager do about this risk?

A.

Update the risk register and take advantage of the opportunity.

B.

Review the supplier ' s contract to understand the terms of sale.

C.

Accept the risk and update the risk register.

D.

Insist that the supplier deliver the goods on the agreed date.

Full Access
Question # 501

An organization is struggling to start an important project. The project manager has identified that the scope definition is the main item preventing

the project from starting. Although most of the scope items are defined and agreed upon among the stakeholders, there are a few items that are hard to grasp and very complex to define at this stage.

What should the project manager do?

A.

Recommend splitting the project into two smaller projects in order to work exclusively in an agile environment without interference from a predictive approach.

B.

Propose that the well-defined scope items be delivered using a predictive approach and use an agile approach to deal with the complexitems.

C.

Maintain stakeholder momentum in working on the scope definition until a full detailed scope is achieved prior to starting the project.

D.

Update the risk register and escalate the issue to the project management office (PMO), requesting more resources be added to help definethe project scope.

Full Access
Question # 502

A technical team for a project is managed by the lead who was recently promoted to this role. Inside the team, a mature and experienced engineer is constantly questioning the actions of the team lead and is currently ignoring part of the team lead ' s decisions. The team lead asks the project manager for help.

What should the project manager do?

A.

Suggest to the team lead how to deal with this team member and discuss the situation with the engineer.

B.

Organize a meeting with all of the project stakeholders and inform them about the new risk and its impact on the project.

C.

Organize a meeting with the project team and discuss the situation and its impact on project delivery.

D.

Suggest to the engineer how to work efficiently with the lead and discuss the situation with the lead ' s functional manager.

Full Access
Question # 503

A project manager is assigned to a project that is in the execution phase that has different types of stakeholders. Some of the stakeholders are very interested in the project, whereas other do not show the same level of interest.

What should the project manager do to assure the project finishes correctly?

A.

Look at the stakeholder assessment matrix to find stakeholders ' interests and make updates if necessary.

B.

Invite the most interested stakeholders to risk assessment sessions and assure the less interested stakeholders agree with the requirements.

C.

Review the user person definitions to find the interests of the stakeholders and make updates if necessary.

D.

Create a stakeholder assessment plan to manage stakeholder engagement and took at stakeholders ' approvals.

Full Access
Question # 504

A risk was identified at the beginning of a project, and a response plan was established. Unforeseen consequences resulted in a higher level of

risk. The project manager has an idea that could address the new risk in an efficient way, but the response is different from the original risk

mitigation plan.

What should the project manager do?

A.

Submit the new response plan to the stakeholders for their review.

B.

Obtain management approval prior to implementing the new risk response.

C.

Use the management reserve to mitigate the risk.

D.

Implement the new response to address the risk.

Full Access
Question # 505

Midway into a project, the project manager is concerned with the lack of responsiveness from a vendor. What should the project manager do to

ensure the project is delivered successfully?

A.

Ask the vendor to communicate via the established channels.

B.

Invite the vendor to a meeting to discuss the concerns.

C.

Escalate the vendor ' s lack of responsiveness to the project sponsor.

D.

Proceed with other tasks while awaiting a response from the vendor.

Full Access
Question # 506

A product owner has added new high-priority work to the backlog, A project manager is working with a dedicated agile team that does not specialize in this specific area of work. The team reviewed the work and wants to accept it but acknowledges it may not have the same level of efficiency as another team having specialization in this area.

What should the project manager do In this scenario?

A.

Add temporary members with the specialized skill set to the team to accomplish the work with a high level of confidence.

B.

Assess the impact of a possible delay to the project and encourage the team to take the work if the impact is tolerable.

C.

Accept the work and outsource it to another team that has the specialized skill set; then integrate the solution,

D.

Reject the work from this team ' s backlog and ask the product owner to add It to another team ' s backlog.

Full Access
Question # 507

A project manager is presented with a roadmap that excludes most of their recommendations. The content source of the roadmap is an influential stakeholder who disagrees with the use of specific procedures and practices. The project sponsor deems the roadmap acceptable. Which two actions should the project manager take first? (Choose 2)

A.

Align the roadmap within the project framework and perform a risk analysis.

B.

Align deliverables based on the roadmap and documented results.

C.

Request to have the roadmap reviewed by the project management office (PMO).

D.

Request reassignment to another project to avoid conflict with the stakeholder.

E.

Discuss the reasoning behind the roadmap with the stakeholder.

Full Access
Question # 508

A company has decided to initiate a project to eliminate a sales channel that has been unprofitable for the past 3 years. Some members of the project team are pessimistic about the project.

What should the project manager do in this situation?

A.

Engage the functional managers to describe the project ' s impact to the team members directly.

B.

Provide team members with specific and clear instructions on the project objectives and tasks.

C.

Communicate the project ' s impact and plans to engage the project team throughout the project.

D.

Escalate the team ' s concerns and ask the project sponsor to change the team ' s composition.

Full Access
Question # 509

A project has come to the closing stage. The work is generally finished, and the project manager wants to commence the closure process for the project. What should the project manager ensure is in place prior to the closing process?

A.

The organizational process assets (OPAs) have been updated.

B.

The contractual deliverables of the project have been accepted.

C.

It The handover and deliverable acceptance have been completed.

D.

The lessons learned sessions have been conducted.

Full Access
Question # 510

A project manager identifies a risk that has a high probability of occurring. How should the project manager manage this risk?

A.

Submit a change request to transfer the risk to a third party in case it becomes an issue.

B.

Remove the user stories associated to that risk and avoid the impact to the project deliverables.

C.

Assign a qualified team member to be the risk manager for the project.

D.

Ask the team to monitor the risk and provide an alert if it becomes an issue.

Full Access
Question # 511

The project manager ' s firm is executing a construction project. The project is stalled due to reemerging conflicts and misunderstandings among stakeholders.

What should the project manager do to ensure a smooth start and completion of the project?

A.

Conduct an on-site survey, start the project to avoid any undue delays, and ensure costs are under control

B.

Invite all the stakeholders to a change control board (CCB) meeting, share feedback and facts, and come to a consensus.

C.

Advise the firm to cancel the project due to misunderstandings among the stakeholders and the associated risks.

D.

Determine the root cause of the misunderstandings, get all parties to reach a consensus, and help to implement the outcome.

Full Access
Question # 512

A project manager is managing an internal project with a tight budget and schedule. While executing the project, the project manager realizes that

some stakeholders are working against the success targets of the project.

What should the project manager do to ensure successful project delivery? (Choose two)

A.

Update the project stakeholder analysis and methods to satisfy the stakeholders’ requirements.

B.

Escalate the issue to the functional manager and ask for support.

C.

Involve all stakeholders in the project by distributing status reports.

D.

Focus on the supportive stakeholders and minimize involvement of unsupportive stakeholders.

E.

Engage all stakeholders in the project including the unsupportive stakeholders.

Full Access
Question # 513

During a project ' s initiation phase a lessons learned sharing session was held with the team from another project Low construction productivity was discussed as a potential delay to project completion

What should the project manager do next?

A.

Discuss this issue with the project sponsor to request additional funding to implement mitigation

B.

Hire a construction management consultant to develop a comprehensive site execution plan

C.

Prequalify contractors with proven track records to eliminate productivity concerns

D.

Add construction productivity to the risk register and develop a mitigation strategy for site execution

Full Access
Question # 514

A project team member was unhappy with a new change in project governance and complained to one of the project sponsors. The project sponsor challenged the project manager.

How should the project manager resolve this conflict?

A.

Arrange a meeting with the project team member and project sponsor to discuss the change and obtain consensus.

B.

Discuss how to manage this conflict with the project management office (PMO) and let them decide how to resolve the issue.

C.

Explain to the sponsor why the change is required and get their support in forcing the project team member to accept the new change.

D.

Schedule a meeting with the project team member ' s functional manager and request the functional manager ' s support.

Full Access
Question # 515

While following up on a deliverable, a team member expresses concern to the project manager about working with another team member. This team member states that the other team member, who is a functional manager, is often defensive and aggressive during meetings.

How should the project manager handle this situation?

A.

Suggest that the team member ignore the disruptive team member and focus only on the work.

B.

Encourage both team members to meet as soon as possible and resolve the problem

C.

Monitor the situation for a few weeks to determine if the disruptive team member ' s attitude changes.

D.

Report the disruptive team member to the human resource (HR) department.

Full Access
Question # 516

A key team member informs the project manager that they have been accepted to a master’s degree program. The team member explains that the first semester of the master ' s program will coincide with the last phase of the project.

What should the project manager do?

A.

Ask the team member to delegate some of their tasks to another colleague during the last phase of the project.

B.

Suggest the team member postpone their enrollment in the master ' s program until the project is completed.

C.

Ask the team member to inform human resources (HR) about their enrollment in the master ' s program.

D.

Assess the team member ' s commitment to the master ' s program and its impact on project performance.

Full Access
Question # 517

A company is running a project to eliminate a sales channel that has been unprofitable for the past 3 years. A key stakeholder from another area, who has legacy ties to that sales channel, objects to the project.

What should the project manager do in this situation?

A.

Assess the impact of the stakeholder and engage properly.

B.

Escalate the stakeholder issue to the project sponsor.

C.

Develop a specific communications strategy for this stakeholder.

D.

Use interpersonal skills to gain stakeholder engagement.

Full Access
Question # 518

A project manager is assigned to a project to develop a mobile app. The sponsor explains that the application should do better than their closest competitor ' s app. The sponsor ' s expectation is that the team can be put together and start work immediately.

What should the project manager do?

A.

Start working on the resource management plan in order to identify the best team for the project.

B.

Utilize expert judgment and organizational process assets (OPAs) to estimate the effort and budget.

C.

Review the competitor ' s app to understand the functionalities that the project scope should consider.

D.

Define the project scope with the stakeholders and determine how formal acceptance will be obtained.

Full Access
Question # 519

In a marine construction project, the project manager is informed by the marine authority that the work permit will not be issued until certain environmental reinforcement work has been completed. After reviewing the project management plan, the reinforcement work is not included in the project scope.

What should the project manager do?

A.

Organize a meeting with the team and update the work breakdown structure (WBS).

B.

Raise this issue, and review and update the progress report for the next monthly project meeting.

C.

Start the organization ' s change control process via a change request.

D.

Communicate with an officer in the environmental protection department to check if it is necessary.

Full Access
Question # 520

An agile team is facing a challenge with the quality of its deliverables. Every time a feature is promoted to production, many defects arise, preventing the customers from properly using the solution.

What should the project manager do to avoid this situation in the future?

A.

Create a team incentive program with prizes, allowing the team members to work overtime to find defects.

B.

Reduce the release cycle and invest more time on stabilizing the current features instead of releasing new ones.

C.

Hire a quality assurance specialist and integrate a second phase of testing into the current project life cycle.

D.

Use the next retrospective to understand the root cause of the quality issues and have the team come up with an action plan.

Full Access
Question # 521

The testing backlog for a hybrid project has increased significantly and is becoming a bottleneck. The team has researched a tool that could

resolve the bottleneck, and the project manager has been informed.

What should the project manager do next?

A.

Add developers to remove the backlog.

B.

Escalate the issue with the product owner.

C.

Reduce the testing scope of the backlog.

D.

Enroll team members in training on the tool.

Full Access
Question # 522

During an agile team retrospective, a project team member mentions that the code quality is degrading, which might result in future rework that

could become unmanageable with time. What should the project manager do?

A.

Help the team create the definition of done (DoD) to improve delivery quality.

B.

Add testing items to the backlog to assess quality periodically.

C.

Expand the team in order to improve the quality of the project.

D.

Compare the cost of improving quality against the cost of failure and adjust the budget.

Full Access
Question # 523

A project team member informs the project manager that a stakeholder is contacting the team member to request status updates. The team member is being distracted by these repeated requests, which are interfering with the completion of assigned tasks.

What should the project manager do?

A.

Increase the frequency of updates given to this stakeholder.

B.

Inform the team member to stop sending any further updates to the stakeholder.

C.

Raise this issue to the project sponsor in the next project status review meeting.

D.

Review this stakeholder ' s communication requirements.

Full Access
Question # 524

A sales manager submitted a new feature request to the product owner, and the request was added to the product backlog. During the sprint planning meeting, the team struggles over which algorithm is the most efficient one to use. The team thinks that some development work is needed to decide.

What should the project manager do?

A.

Invite the sales manager to the next sprint meeting to clarify requirements.

B.

Create a new item in the sprint backlog to determine the appropriate algorithm.

C.

Ask the scrum master to choose an algorithm based on the pros and cons of each option.

D.

Request a meeting with the product owner to help clarify the user story.

Full Access
Question # 525

A project manager is working on an agile project. The organization decided to implement the Scrum framework. The project manager organized a workshop to explain the differences between traditional project artifacts and the Scrum approach. The most frequent question raised is what artifact will replace the project schedule.

What should be me project manager ' s response?

A.

Sprint plan and product roadmap

B.

Product roadmap and sprint backlog

C.

Product backlog and scrum board

D.

Sprint backlog and scrum board

Full Access
Question # 526

A project manager is leading a fast-moving project with strict deadlines and minimal time to deliver each milestone. The project manager

discovers that one of the remote team members, who puts alot of effort into delivering the project, has confided in an on-site team member. The

remote team member feels they are not being adequately rewarded and recognized for their job.

What should the project manager do?

A.

Inform the human resource (HR) manager of this situation and ensure this news does not spread.

B.

Make arrangements with the resource ' s functional manager to relocate the team member to another existing project.

C.

Send a copy of the engagement contract to the remote team member and indicate that the team member is entitled to what is included in thecontract.

D.

Engage the remote team member, empathize with them, and let them know their contribution is appreciated regardless of their remote work status.

Full Access
Question # 527

A project manager is facilitating a project steering committee meeting where the prioritization of work items in the backlog is being discussed. The

engineering executive wants to prioritize features based on level of effort, completing the smallest items first. The quality executive wants to

complete the most complex tasks first to have adequate time to ensure a quality product is delivered. The compliance officer wants to complete

items with associated regulatory components as they are essential items.

How should the project manager prioritize the work items?

A.

Complete tasks associated with regulatory components as the team cannot deliver business value that does not adhere to complianceregulations.

B.

Ensure that the team assesses opportunities to deliver the highest business value items incrementally.

C.

Ensure that the project value is within the quality guidelines by prioritizing and completing intricate tasks earlier in the project.

D.

Complete the smaller tasks first to allow the team opportunities to prototype and evaluate development processes.

Full Access
Question # 528

In an organization with good work-life balance, one team was continuously overloaded, thereby delivering the product ft quality. What should the project

manager do?

A.

Request the team to work more for on-time delivery.

B.

Request the team to focus on doing better planning.

C.

Request the replacement of certain team members.

D.

Request management for a high-performing team.

Full Access
Question # 529

A project manager ' s new employer decided to use an agile delivery approach to implement a new accounting system. The chief financial officer (CFO), who is also the

project sponsor, is committed to a new way of working but does not have experience as a product owner. The project manager ' s background includes a couple of years’

experience as an agile practitioner working as a scrum master.

What should the project manager do at the start of the project?

A.

Collaborate with the development team to help the project sponsor acquire the relevant skills.

B.

Assume the product owner role until the project sponsor is ready to take over the product owner role.

C.

Delay the build of the system until the project sponsor is ready to take over the product owner role.

D.

Work with and assist the project sponsor in building and prioritizing the product backlog.

Full Access
Question # 530

In a project, one core team member tends to do all the work and ensures all tasks are completed. This core team member is soon leaving the project, which may make the project vulnerable.

What should the project manager do?

A.

Ensure the activities of this team member are distributed across the project team.

B.

Assess a mechanism for knowledge transfer among the team members.

C.

Motivate the team member to stay by providing them with incentives.

D.

Ask human resources (HR) to counsel the team member to balance the workload.

Full Access
Question # 531

A project manager is assigned to a new project team that has several stakeholders who can have significant influence over the project outcomes.

The project manager categorized the stakeholders into four different groups and wants to define the communication strategy.

How should the project manager handle communication?

A.

Utilize a uniform communication structure across all groups.

B.

Define and direct communication to influential stakeholders.

C.

Describe the four groups in the project stakeholder matrix.

D.

Develop and define a communication strategy for stakeholders.

Full Access
Question # 532

An organization is undergoing an agile transformation. The executive leadership team is concerned that they will lose control over the scope of the project.

What should the project manager, who is responsible for this project, do to mitigate this risk?

A.

Ensure that the executive leadership team approves all scope that is being proposed by the multiple agile teams to avoid misalignment.

B.

Propose a governance model that empowers the teams while providing the necessary oversight to the executive leadership team.

C.

Propose a multilayered gate system based on risks and financial expenditures, involving the executive leadership team as needed.

D.

Assure the executive leadership team that the current governance model will not be affected by the agile approach.

Full Access
Question # 533

A project manager is working on a project to release a new version of a key product, The product strategy and marketing areas are still working on defining the final details for the products appearance, but the team is clear about the main features. During the last sprint review, the project sponser expressed concerns about the low quality of the product,

What should the project manager, as a servant leader, do to address this situation?

A.

Dedicate the next sprint to completing the missing details.

B.

Apply fast-track techniques to work on the missing details in parallel,

C.

Continue iterating and monitoring quality aspects sprint by sprint.

D.

Create a new risk entry for the delay in the risk management plan.

Full Access
Question # 534

An innovation project with a budget of over US$30 million is expected to have a large impact on the technology industry. The business area is concerned if the project will meet stakeholder expectations and raised this concern with the project manager.

What should the project manager do to manage business concerns and expectations before starting the project?

A.

Meet with the project finance team to measure market variations and product impact.

B.

Direct the project team to estimate user stories in greater detail.

C.

Ask the product owner to prioritize the backlog items based on the return on investment (ROI).

D.

Request that the project team develop a release plan and roadmap for the project.

Full Access
Question # 535

During the execution of a hybrid project, one developer had to be replaced. The new resource is extremely competent in quality assurance tasks, but does not have much

experience in development.

What should the project manager do?

A.

Allow the team to reevaluate the tasks and determine how they should be allocated.

B.

Maintain the same task allocation structure to avoid any disruption in the project team.

C.

Move the developer to another team and look for a replacement developer.

D.

Request that all quality assurance tasks be allocated to the new resource.

Full Access
Question # 536

A project manager is in the beginning stages of delivering a project and is assessing and prioritizing identified risks. What should the project manager do next?

A.

Plan the risk responses and assign risk response owners.

B.

Start monitoring and controlling the identified risks.

C.

Proceed with executing the risk management plan.

D.

Spend the contingency budget on the identified risks.

Full Access
Question # 537

One-on-one interviews with members of an agile team reveal that they distrust an expert member. Their explanations seem to point to the expert’s communication style in daily coordination meetings, which team members interpret as avoiding accountability.

What two actions should the project manager take to address the situation? (Choose 2)

A.

Instruct the expert member to avoid phrases that make the team uncomfortable.

B.

Help the team gain trust in the expert by describing the expert’s experience.

C.

Encourage the team to respectfully ask questions to promote clear communication.

D.

Help the expert member feel secure enough to communicate more freely.

E.

Remind the team that all communications are valid and worthy of trust.

Full Access
Question # 538

A new project includes important product features that should be delivered as soon as they are completed during the following quarter. The project team consists of junior and senior technicians.

Which two actions should the project manager take to deliver product features as soon as possible? (Choose 2)

A.

Instruct the senior technicians to lead the junior technicians.

B.

Align on clear and proper accountability levels.

C.

Empower the team to self-organize.

D.

Conduct a detailed work review of the junior technicians.

E.

Review a detailed plan with the senior technicians.

Full Access
Question # 539

A project manager is leading the construction of a high-rise mall for a customer in an emerging competitive market. Some customers want to move in as soon as the ground floor is completed. What should the project manager do to deliver business value to the client?

A.

Use management reserve and crash the schedule

B.

Implement an agile project delivery approach

C.

Explain the need to follow the quality assurance (QA) schedule to the customer

D.

Adopt an incremental project delivery approach

Full Access
Question # 540

A project manager has been assigned to a long-term project. The project manager came across a government debate over a new law that may affect the project.

What are the first two actions the project manager should perform? (Choose two)

A.

Create a change request to discuss with the change control board (CCB).

B.

Request additional budget for contingency.

C.

Perform a risk identification process with the project team.

D.

Consult with the project stakeholders.

E.

Discuss the possible impacts with subject matter experts (SMEs).

Full Access
Question # 541

A project team was established for a community impacted by oil and gas exploration activities. The team is required to interact with several external stakeholders. The local council authority has requested a meeting with the project team to discuss the impact of the project on the community. The project manager was not available at the time of the meeting, and the team was in disagreement regarding who should attend the meeting.

What should the project manager have done to prevent this conflict?

A.

Provided copies of the stakeholder engagement plan to all team members.

B.

Defined the roles and responsibilities of the team members.

C.

Updated the communications management plan.

D.

Established ground rules for the team

Full Access
Question # 542

Two key team members suggest different options to prevent time overruns and delays. There is a conflict between these two team members because of their divergent views.

What should the project manager do next?

A.

Schedule a meeting between the team members to find a solution.

B.

Refer the team members to the project charter to resolve the conflict.

C.

Issue a new change request to evaluate this situation and communicate the result.

D.

Document the facts explained by the team members in the issue log.

Full Access
Question # 543

In the past, the project manager and the project team performed well using

predictive methodology. However, the organization recently decided to adopt agile

approaches, and the project sponsor wants to use an agile approach in an upcoming project.

Before initiating the project, what should the project manager do?

A.

Prepare a risk report that captures the probability and impact of risks, and then shareit with the project sponsor.

B.

Share the organization ' s decision with the team and make plans to adopt an agileapproach in the upcoming project.

C.

Make a request to human resources for new team members who have agileexperience.

D.

Ask the project sponsor to change the approach back to predictive as that is theteam’s strength.

Full Access
Question # 544

An agile team is making infrastructure changes to the human resources (HR) application system. Conflicting requirements are being submitted by various stakeholders.

What should the project manager do to help move the project forward?

A.

Review documents provided by other teams, such as lessons learned and the risk matrix.

B.

Attend the Scrum of Scrums to identify roadblocks and manage dependencies.

C.

Study the technology to assist the team in decision-making if progress slows.

D.

Encourage the stakeholders to collaborate by facilitating meetings and sharing knowledge.

Full Access
Question # 545

A project manager is using a hybrid approach for project delivery. The

development team was sized, but is not yet fully resourced. The project manager is working

on defining the project schedule.

What should the project manager do to address the issue of developer availability?

A.

Organize a planning session with the development team and use their estimations to complete the schedule.

B.

Ask the resource manager when the new contractor is available to start and change the delivery date for the project schedule.

C.

Ask the sponsor to provide the desired completion date for project activities and complete the schedule.

D.

Use expert judgment to estimate all of the tasks and complete the schedule in the allocated time.

Full Access
Question # 546

Due to organizational changes: several key stakeholders are replaced by new ones in the middle of a project. As a result, numerous new requirements are raised What should the project manager do to ensure success of the project?

A.

Review and prioritize new requirements with stakeholders to determine which change requests are needed.

B.

Escalate the issue to the project sponsor and seek support to keep the original requirements.

C.

Seek immediate approval to amend the project timeline and budget in order to deliver all new requirements

D.

Emphasize to the new stakeholders that new requirements are not allowed at this stage of the project

Full Access
Question # 547

A project manager was recently appointed to an agile project. The project will have a lot of visibility and impact for the company, so the project management office (PMO) manager wants to ensure that the project manager manages the risks correctly.

What should the project manager do?

A.

Implement the agile risk manifesto to ensure the proper tracking, analysis, and remediation of the project risks.

B.

Ask the product owner to act as a risk manager to assist with the remediation of risks.

C.

Implement the role of an agile risk manager to take care of the risk management process.

D.

Follow the risk management process while ensuring that risks are identified, analyzed, and managed during each iteration.

Full Access
Question # 548

A project manager is managing a megaproject. The project stakeholders are from different geographical areas and have diverse cultural and social backgrounds. The project manager wants to improve team productivity to realize more effective and efficient results.

Which action should the project manager take?

A.

Empower team members to participate in decision-making and take ownership of actions.

B.

Implement a flexible work schedule policy to eliminate the time zone problems among stakeholders.

C.

Encourage team members to network so that they know each other ' s cultural backgrounds.

D.

Provide a relaxed work schedule policy and encourage team members to work from home.

Full Access
Question # 549

A highly skilled team resource received a job offer and is leaving the project soon What should the project manager do to maintain project performance while a new team member is being onboarded?

A.

Log a risk in the risk register and work with the new team member to mitigate it

B.

Motivate the new team member to perform.

C.

Share project documents with the new team member.

D.

Offer cross-training and mentoring to the new team member

Full Access
Question # 550

A project manager is working to create a product that can be released to the market as soon as it passes rigorous quality standards.

Historically, the company has used a predictive methodology, but the company is exploring the implementation of agile methodologies.

The company asked the project manager to explain the value gained by using an agile process.

How should the project manager respond?

A.

Early value cannot be achieved until the product is fully released.

B.

Early value can be gained by testing the most important features in the initial stages to fix deviations.

C.

Early value will be gained only if beta products can be released to the market.

D.

Early value will be gained only if the speed can be increased to release the product to the market.

Full Access
Question # 551

A company has agreed to run a transformation project using agile approaches.

During the implementation, there is pushback from the functional groups that the project is moving too fast.

What should the project manager have done at the beginning of the project to prevent this from happening?

A.

Circulated the project charter

B.

Assessed the organizational culture

C.

Determined the level of maturity of the employees

D.

Communicated the project schedule

Full Access
Question # 552

A large company has agreed on a business case for an environmental project. The

project will cause some major changes in their operations, such as reduction in paper use,

which will obviously affect all of the users.

What is the first thing the appointed project manager should do?

A.

Evaluate the impact to the users and create a plan to address it.

B.

Inform users about the new changes and ask for their collaboration.

C.

Ask all managers to collaborate implementing this change to users.

D.

Start implementing the change so that users will eventually get used to it.

Full Access
Question # 553

A few developers have submitted their resignation after completing their annual review and receiving their annual bonus. The project manager cannot find replacements for all of the developers in time to meet the project ' s deadline.

What should the project manager do?

A.

Request additional budget to recruit more developers.

B.

Lower the recruitment criteria.

C.

Log the issue in the issue log.

D.

Analyze the impact and inform the stakeholders.

Full Access
Question # 554

During a project status update by the project management office (PMO), the CEO is concerned that the status of all projects suddenly changed from green to red, without warning. Upper management is used to reading traditional reports related to progress and cost, and they want to continue viewing this information.

How should the PMO implement a better way to report the project ' s health?

A.

Perform a root cause analysis (RCA) to find out why the status of projects is deteriorating so fast.

B.

Explore reporting the earned value (EV) key performance indicators (KPls) using agile progress as an input.

C.

Ask the project managers to report on their projects using a Kanban board format.

D.

Request the program managers to be more accurate when presenting status reports.

Full Access
Question # 555

During the third iteration of a project, the main sponsor retired from the company, and a new sponsor was appointed. The new sponsor is not familiar with the agile approach for project delivery, which leads them to request more control over the project team.

What should the project manager do?

A.

Schedule a meeting with the new sponsor in order to explain the agile approach and how teams are supposed to be self-organized.

B.

Schedule an emergency meeting with the project team so they fulfill every request that comes from the sponsor.

C.

Review the sponsor ' s request with the project team during the next daily review meeting in order to provide the requested control.

D.

Review the sponsor ' s request with the project team during the next iteration review meeting in order to obtain a team decision.

Full Access
Question # 556

An agile senior project team member suddenly resigns from the organization. Following this departure, the remaining team members are having difficulty accessing information and are unable to complete a deliverable.

What should the project manager have done to avoid this situation?

A.

Ensured the project repository is up to date.

B.

Updated the job descriptions for all team roles.

C.

Provided specialist training for all team members.

D.

Made an effort to reemploy the senior project team member.

Full Access
Question # 557

The business manager and the product owner are requesting a more flexible way to incorporate changes into the product baseline They are concerned about losing time to market with respect to other vendors

What should the project manager do?

A.

Review the assumption log and project management plan for changes.

B.

Identify adequate change management tools to conduct the project

C.

Establish a change control board (CCB) with key stakeholders.

D.

Allow key stakeholders to make some changes to deliver the product faster

Full Access
Question # 558

A project manager is managing a project with a hybrid approach and has requested a senior team member to perform a quantitative risk analysis The team member responds that they do not have the knowledge to perform such an analysis.

What should the project manager do?

A.

Contact the project management office (PMO) and request them to assign another team member who has the knowledge to perform this task to the team

B.

Escalate the issue to the functional manager

C.

Help the team member to perform the quantitative risk analysis through coaching, mentoring and training

D.

Perform the quantitative risk analysis for the team member.

Full Access
Question # 559

A Scrum team working in an aircraft manufacturing company has completed Its first iteration for a critical project. It is very Important for the project sponsor to complete the project on time and under budget A burndown chart indicates that the project is behind schedule

Which two actions should the project manager take to manage Impediments and improve the team ' s velocity? (Choose two)

A.

Look for processes that cause bottlenecks and slow down the team ' s agility

B.

Assign the items with high complexity lo senior developers

C.

Empower the learn to make decisions to remove impediments

D.

Work with the team to remove impediments as quickly as possible

E.

Move the items with high complexity to the last iterations

Full Access
Question # 560

An organization has recently decided to switch from a predictive to an agile delivery approach. The one ongoing project will still be led by a project manager. The agile teams for that project have not produced any documentation.

What should the project manager of the ongoing project do?

A.

Submit new user stories to the product owner in order to put documentation in the product backlog.

B.

Introduce a document management tool to support the agile teams in preparing the documentation.

C.

Check with the agile teams to see if the project manager ' s understanding of the Agile Manifesto is correct.

D.

Add an additional team member to take up the role of scribe for the required documentation.

Full Access
Question # 561

During the initiating phase of a project, a key stakeholder requests frequent changes to the project scope What should the project manager do to improve the stakeholder ' s engagement?

A.

Discuss the work breakdown structure (WBS) with the key stakeholder and refine the requirements

B.

Update the project backlog and discuss it with the key stakeholder

C.

Update the project charter and discuss it with the key stakeholder.

D.

Discuss the project scope statement with the key stakeholder and build prototypes

Full Access
Question # 562

An agile project is starting its seventh out of eight iterations In a planning meeting, the team realizes that an unidentified risk became an issue and the contingency reserve has to be used.

What should the project manager do?

A.

Ask the sponsor to approve inclusion of an additional iteration to the project

B.

Ask the team to include the contingency plan in the iteration backlog

C.

Help the team review the project approach to initiate the corrective actions

D.

Ask the sponsor for money to implement the contingency plan.

Full Access
Question # 563

A project manager has just been assigned to a project to build new software for a client. All the requirements have been gathered.

What should the project manager tell the team members to focus on?

A.

Reducing cost for the customer

B.

Delivering value to the customer

C.

Working together as a team

D.

Finishing the project on schedule

Full Access
Question # 564

A company has hired a vendor to deliver a scope of work and assigned a project

manager to oversee the project. The vendor advised that they completed the scope

successfully and is asking for approval.

What should the project manager do in response to this request?

A.

Obtain approval from the project sponsor.

B.

Update the project management plan and mark the milestone as completed.

C.

Ask the vendor to validate the agreement for any deviations.

D.

Set up a meeting with stakeholders to validate and confirm acceptance of the deliverables.

Full Access
Question # 565

A project manager is managing a project aimed at providing incremental deliveries to the market every three months. The team has been assigned, and the product backlog was created and prioritized by the product owner. After four iterations, the product owner escalates complaints to the CEO because the product does not meet the product owner ' s expectations.

What should the project manager have done to prevent this situation from happening?

A.

Implemented sprint reviews with the product owner and retrospectives with the team to minimize gaps

B.

Performed risk management analysis during daily scrums

C.

Reviewed the organizational process assets (OPAs) and lessons learned from similar projects

D.

Performed backlog grooming to ensure that acceptance criteria were being met

Full Access
Question # 566

A project manager receives feedback from the customer ' s leadership team regarding their annoyance about the frequency of email updates. What should the project manager have done first to prevent this?

A.

Understood the customer ' s company culture

B.

Updated the communications management plan

C.

Analyzed customer interest and engagement

D.

Scheduled weekly update meetings

Full Access
Question # 567

During project execution, a project manager discovers that the budget at completion has shifted significantly and is higher than expected.

What should the project manager do?

A.

Adjust the original budget estimates with the current cost variance.

B.

Negotiate the project changes and adjust stakeholder expectations.

C.

Perform a root cause analysis of the project performance.

D.

Review the activity duration to reforecast the project completion date.

Full Access
Question # 568

After a project learn has been working on a project for several months, the project Is cancelled The project sponsor Is putting pressure on the project manager to perform closeout duties as fast as possible so that the project team can move on to other work. The project sponsor has instructed the team not to waste time archiving the project artifacts for the cancelled project.

How should the project manager handle this situation?

A.

Comply with the project sponsor ' s request to not archive the project artifacts.

B.

Document the project sponsor ' s instructions as the archived project artifacts.

C.

Archive the project artifacts on the project manager ' s local computer for future reference

D.

Consult with the project management office (PMO) for guidance on project artifacts.

Full Access
Question # 569

A project manager is appointed for the deployment of a new solution. The solution will be integrated into the environment by a third-party vendor. This vendor just announced a delay in delivering a key component, which will impact the project schedule.

What should the project manager do?

A.

Ensure that relevant stakeholders and expectations are identified and assess the component delay.

B.

Perform a detailed analysis of the release content for each component of the solution.

C.

Propose a new design of the solution to replace the external component with an internal one.

D.

Ask for expedited delivery of the component to mitigate the risk of schedule delays.

Full Access
Question # 570

A project is delayed due to multiple problems discovered during the quality review. Every time the team addresses one problem, additional problems are encountered. This is

frustrating for both the project team and the project sponsor, who are driven to meet the dates and results expected by the organization.

What should the project manager do?

A.

Request that the team identifies, documents, and registers the issues to locate the source of the problems.

B.

Evaluate the cost and schedule variance in order to determine how much the project is off track.

C.

Ask the team to commit to a new date to fix all the problems and proceed with a change request to adjust the baseline.

D.

Request that a senior subject matter expert (SME) be hired to analyze and solve the problems.

Full Access
Question # 571

Close to the end of a project, a customer claims that some deliverables have not

been met and starts initiating change requests. What should the project manager do next?

A.

Refer to the requirements traceability matrix.

B.

Revise the project scope baseline.

C.

Escalate the change request to the project sponsor.

D.

Review the approved project charter.

Full Access
Question # 572

A major project is unable to access the US$12 million funding allocated for the project. This prevents the start of the procurement process and is already leading to costly delays.

What should the project manager do?

A.

Escalate to the project steering committee.

B.

Invite the finance department to the next project demo.

C.

Review the project requirements.

D.

Use the currently available resources.

Full Access
Question # 573

An organization is transitioning to an agile environment. The project manager finds that most of the team members are not familiar with an agile environment.

What should the project manager do to address this concern?

A.

Change the approach with the team.

B.

Meet with an agile coach to handle this issue.

C.

Analyze the level of the team ' s agile maturity.

D.

Support the team members ' growth and development.

Full Access
Question # 574

During a regular review, the project manager of an agile project realizes that a key stakeholder is missing critical information about some features being developed. In order to improve communications and reduce the risk of deploying the wrong features, what should the project manager do?

A.

Assess the stakeholder ' s needs and communication style and propose a tailored approach with regular status reports and progress meetings.

B.

Invite the stakeholder to the regular " show and tell " sessions so the stakeholder is aware of project progress and feedback can be gathered.

C.

Conduct stakeholder remapping, evaluate stakeholders by their level of influence and interest on the project, and communicate accordingly.

D.

Include the stakeholder on regular project communications so that decisions can be followed up closely.

Full Access
Question # 575

After a performance review, a team member approaches the project manager and asks for feedback. The project manager mentions anecdotal information about this team member being a positive team player and generally getting their work done on time, even though they have been late with work once or twice. The team member expresses frustration at not having better information included in the annual performance review.

What should the project manager do to prevent this frustration going forward?

A.

Request the human resource (HR) department to provide the key performance indicators (KPls) that were defined for this project.

B.

Set team performance goals and explain how the team receives the same performance scores.

C.

Review the key performance indicators (KPIs) for this team member and remind the team member how they are determined.

D.

Provide the team member with velocity tracking tools and explain how the team member can see and track performance.

Full Access
Question # 576

An agile team is working on a product deliverable in an organization that is transforming itself to quickly respond to change. The finance

team is requesting a project budget for the new product.

What should the team do to address this request?

A.

Work with the finance team to transition to incremental budgeting.

B.

Request the finance team to allocate a budget based on historical data.

C.

Provide the budget to the finance team for only the planned increments.

D.

Extrapolate the budget based on the current cost performance index (CPI).

Full Access
Question # 577

A team member has indicated their user story will not be finished until the end of the iteration as their functional manager has requested they assist in resolving a high-priority production issue. What should the project manager do?

A.

Discuss with the product owner that the user story will not be completed this iteration.

B.

Meet with the team member ' s functional manager to try to remove the impediment.

C.

Tell the project team member not to work on the production issue and to inform their manager.

D.

Escalate the issue to the project sponsor to resolve and adjust the project burndown chart.

Full Access
Question # 578

During a project review meeting, several project team members expressed that they did not have an understanding of the benefits of certain features for the project What should the project manager do next?

A.

Review the project scope statement

B.

Confirm ownership for ongoing value realization

C.

Escalate the issue to the project sponsor

D.

Appraise the stakeholders of value gain progress

Full Access
Question # 579

A contractor delivering construction services to a company is using agile principles

to manage the project tasks. Engineers are producing frequent design changes due to new legislation. There is a risk the contractor may lose money due to resources waiting on design

changes or performing rework.

What should the project manager do to minimize the cost?

A.

Put the project on hold until all definitions are ready in order to avoid rework.

B.

Review the backlog with the product owner and prioritize the tasks that are least likely to be affected by a change in legislation.

C.

Capture the engineers ' feedback at the daily meeting and communicate it to the product owner.

D.

Cancel the project release resources, then start again when all the definitions are ready.

Full Access
Question # 580

An agile project is starting and the assigned team is new to agile During the first daily meetings, the project manager observes that the team is having problems meeting goals What should the project manager do?

A.

Plan an outdoor activity tor the team to get to know each other

B.

Ask the team to review agile protect management approaches.

C.

Ask the human resources department for an experienced agile team

D.

Conduct a meeting to help the team define the team charter

Full Access
Question # 581

A project manager is meeting with the project sponsor regarding a new project.

The project manager tells the sponsor that, as part of the communications management

plan, a weekly email will be sent with the status of the project, so the sponsor can be

informed of the progress. The sponsor indicates that the email is not necessary because

they will ask for a status update whenever it is needed.

What should the project manager do next?

A.

Advise the project sponsor to request a 15-minute meeting, whenever necessary, with prior notification.

B.

Agree to the project sponsor ' s request, but continue to copy them on the weekly email so they can be informed of progress in case it is needed.

C.

Tell the project sponsor that if they prefer to not receive the communication, there is no problem in removing them from the email distribution.

D.

Ask the project sponsor what sort of information is needed and agree on a frequency for the communication.

Full Access
Question # 582

A system migration project is in its closing stage. The project manager is being pressured to close the project The project manager communicated to all stakeholders; however, the last department to migrate indicated that they have not received the notification

What should the project manager do?

A.

Report the issue during the next status meeting at the end of the week

B.

Escalate the issue to the project sponsor and upper management

C.

Close out the project and tell the manager to open a service desk ticket

D.

Log the issue and assign it to the project team member(s).

Full Access
Question # 583

A leader from project B consistently reaches out to a team member in project A for

assistance. What should project A ' s project manager do?

A.

Allow project B ' s leader to continue building relationships.

B.

Talk with project B ' s leader to discuss possible impacts to both projects.

C.

Tell project A ' s team member to ignore project B ' s leader.

D.

Ensure project A ' s team member can finish the work committed to project A.

Full Access
Question # 584

A concerned project team member complains to the project manager that another team member is being disruptive and argumentative during team meetings. The project manager received some information that the team member recently overcame a difficult personal situation.

What should the project manager do to address the concem9

A.

Provide team-building activities so that the team can learn how to overcome disruptive behavior

B.

Inform the disruptive team member ' s functional manager that the disruptive behavior should be stopped immediately

C.

Request a meeting with the disruptive team member and help to resolve the issue

D.

Encourage self-governance and ask the concerned team member to speak to the disruptive team member directly

Full Access
Question # 585

During the executing phase, a project manager is reviewing the issue log and finds

there are outstanding high-priority issues that are still open. Most of the open issues require

effort from external domain experts who are not on the project team.

What should the project manager do?

A.

Ask the issue reporter to close the issues, because there are no project team memberswho have the required domain knowledge.

B.

Review the open issues with the issue reporter and issue a change request to hire anexternal domain expert.

C.

Request that the project team members learn the required domain knowledge andresolve the open issues in a short time.

D.

Reduce the project scope to ensure that the project team has the knowledge to deliverthe system on schedule.

Full Access
Question # 586

A project manager is appointed to manage an infrastructure project that spans

across several countries, including different time zones within a subregion. It is likely that most of the project team members will never meet, but they will have to collaborate to ensure deliverables are met.

What should the project manager do to ensure good collaboration between the remote project team members?

A.

Discuss the concerns with the project sponsor and modify the project charter to includemore budget for interactions.

B.

Plan a communication method and allow the project team members to virtually interact.

C.

Create a social media group platform for the team to create a supportive environment.

D.

Set the ground rules and identify a contingency plan in the risk register.

Full Access
Question # 587

In a hybrid project, 100 new base stations are being added to a 4G mobile network

every month. At the end of the first month, the team is behind the target and the operator is

losing money. The stakeholders are requesting information on when the base stations can go

live and begin to bill.

What should the project manager do to take the schedule back and accelerate the return on

investment (ROI) of the project?

A.

Change the project approach to predictive.

B.

Increase reporting to the business.

C.

Clarify the agile and predictive modules.

D.

Reconsider necessary schedule reserves.

Full Access
Question # 588

A subcontractor informs the project manager that they are unable to supply a key

component to the project. What should the project manager do?

A.

Discuss the issue with the project sponsor and request extra time and budget to obtainthe component from a different supplier.

B.

Raise a new risk in the risk register, perform a risk assessment, and convene SMEs and relevant stakeholders to plan a risk response

C.

Submit a change request to the change control board (CCB) for changes to theperformance measurement baseline to obtain the component from a different supplier.

D.

Raise a new issue in the issue log and convene subject matter experts (SMEs) andrelevant stakeholders to identify alternatives to address the problem.

Full Access
Question # 589

A project team member has lost enthusiasm and is experiencing low morale for a

project they were once excited about. What should the project manager do?

A.

Escalate the issue to the team member ' s functional manager and request a responseas soon as possible.

B.

Meet with the team member to understand what the issues are and to provide support.

C.

Leverage other team members who are contributing and making the project a success.

D.

Have the team member transferred to another project and add other resources to theproject.

Full Access
Question # 590

A project manager is working on a complex project and is unsure about planning, executing, monitoring and controlling the project. Match the phrase on the left with the correct statement on the right.

Full Access
Question # 591

A project team has transitioned to full-time remote working. The project manager

started noticing that some team members have not been completing their assigned tasks by

the planned dates despite reminders during weekly team meetings. This has the potential for

delaying the project delivery.

How should the project manager resolve this situation?

A.

Communicate the delivery dates twice a week to the team members to ensure timelydelivery.

B.

Set up review sessions with each of the team members to identify the root cause ofdelays.

C.

Mentor the team members to work in a remote work environment to ensureproductivity.

D.

Talk to the resource managers regarding the delay and request additional resources

Full Access
Question # 592

There is a problem with a project because some features are not in compliance with

regulations. Some stakeholders do not believe compliance is a priority, while others disagree.

What should the project manager do?

A.

Review the stakeholder engagement assessment matrix to determine next steps.

B.

Set up some time with the stakeholders to explain the importance of compliance.

C.

Meet with the sponsor to discuss how to handle the stakeholders ' differing opinions.

D.

Send out documentation to align stakeholder expectations and project objectives.

Full Access
Question # 593

A supplier is hired to provide information security services for a project. The supplier has decided not to provide this service any longer since they have not been paid on time. Their services are critical and this decision will affect the outcome of the project.

What should the project manager do to address this issue?

A.

Negotiate the payments with the supplier and remind them of their long-term association

B.

Penalize the supplier according to the contract ' s service level agreement (SLA)

C.

Hire another information security supplier and incentivize them for speedy delivery

D.

inform the relevant stakeholders of this challenge and seek their support

Full Access
Question # 594

A developer who has almost completed a required product feature for a prototype

leaves the company in the middle of an iteration. What should the project manager do?

A.

Review the backlog to reschedule the deliverable for a later iteration.

B.

Engage with stakeholders directly to review the iteration process.

C.

Determine whether other cross-functional team members are able to take over thework.

D.

Go to management and ask to hire a new external developer.

Full Access
Question # 595

A project manager is leading a project that is on time and under budget. In the

weekly meeting with the team, the project manager finds out that one of the tasks due next

week does not have an assigned resource available for it. The resource is currently assigned

to another project.

What should the project manager do to manage the situation?

A.

Ask the procurement department to supply a different resource.

B.

Change the schedule according to the availability of the resource.

C.

Ask the sponsor to obtain the resource as originally planned.

D.

Contact the other project manager to request the resource.

Full Access
Question # 596

A project manager is asked to implement a hybrid approach that will replace a predictive approach on an upcoming project How should the project manager adjust their responsibilities accordingly?

A.

Become a servant leader by supporting team collaboration and removing impediments

B.

Delegate coordination activities to the product owner so the project manager can locus on managing collaboration

C.

Request a scrum master to focus on the collaboration while the project manager focuses on the coordination

D.

introduce new communication tools to the project team members

Full Access
Question # 597

A project manager is in the process of creating a strengths-based team and is

organizing a series of workshops to identify and document the strengths of each project team

member. During this session, there are multiple team members who are not actively

participating. These meetings are becoming futile due to a lack of participation.

What should the project manager do?

A.

Have a one-on-one discussion with each team member to emphasize their individualtalents.

B.

Document the behavior of the team members and highlight it during their performancereviews.

C.

Identify the team members who are not participating and reprimand them.

D.

Explain the benefits of the approach and the effects of positive psychology.

Full Access
Question # 598

A new privacy law will go into effect at the beginning of the next calendar year. The project manager realizes the project needs to be compliant with the new law. What should the project manager do next?

A.

Inform the project steering committee of this constraint.

B.

Inform the project team and create a spike for the next Iteration.

C.

Inform the legal department that the project scope will be updated.

D.

Inform the product owner that the project will continue as planned.

Full Access
Question # 599

A hybrid project manager has taken over a large-scale software development project m a highly regulated environment. During a handover session the outgoing project manager explains that they devised their own status reports which is different from the project management office ' s (PMO ' s) status report style. The project stakeholders are extremely particular about the information they receive in updates and do not believe the PMO ' s status reports have sufficient enough information

How should the new project manager proceed*?

A.

Continue using the outgoing project manager ' s status reports as well as their approach for schedule reporting

B.

Explain to the PMO that the hybrid project team needs to keep an agile approach for reporting and will not be complying with the organizational standard

C.

Change the status reports according to the template supplied by the PMO and proceed with scheduled reporting

D.

Meet with the project stakeholders to explain the need to comply with the PMO standards and update the status report format accordingly

Full Access
Question # 600

A few key stakeholders are concerned about how the prefect team is planning to develop some features tor a new product. They know that the requirements associated with these features are unstable but are also highly strategic for adding value to the product and the customer.

What should the project manager do?

A.

Suggest an agile approach to refine these requirements and prioritize them according to the project objectives

B.

Validate the prioritization of all requirements with the sponsor and share the results with the stakeholders

C.

Review the project governance to validate the policies procedures and guidelines used to prioritize the project

D.

Ask the stakeholders to refine these requirements at a level of detail that becomes more stable and measurable

Full Access
Question # 601

The sponsor approaches the project manager with new features they want added to

the project. The project is 95% complete, but the sponsor insists that continued support for the

project relies on the addition of the new features.

What should the project manager do?

A.

Assess the impact of the features and refer it to the change control board (CCB).

B.

Implement the new features after assessing the impact.

C.

Reject the new features since it amounts to gold plating.

D.

Add the new features to avoid losing the sponsor ' s support for the project.

Full Access
Question # 602

A team is the first team m the company to use agile methods for a traditional project. The team ' s manager is concerned that the risks are not being managed. What should the team do to assess and manage risks regularly?

A.

Identify and escalate any identified risks to the facilitator to handle

B.

Update the risk register during every iteration with any open concerns

C.

Use regular feedback loops through daily standups iteration demos and retrospectives

D.

Focus on developing a working deliverable instead of documenting risks

Full Access
Question # 603

After 1 year Into the life cycle of an ongoing residential project, an announcement was received from the municipality regarding a new regulation that will greatly impact the project ' s schedule and budget. What should the project manager do next?

A.

Perform a qualitative risk analysis and update the risk register.

B.

Submit a change request through the Integrated change control process.

C.

Update the issue log and discuss It in the next steering committee meeting.

D.

Estimate the associated costs and increase the project budget accordingly.

Full Access
Question # 604

An agile project manager is evaluating the method that will be used to display the

value of the work performed to date. Which method will they select to display to the project stakeholder?

Full Access
Question # 605

A project team is facing challenges understanding how to deliver a project ' s scope.

A senior subject matter expert (SME) from the organization ' s global office is in town for 1 week.

What should the project manager do to benefit from the SME ' s presence?

A.

Ask the SME to review the scope for alignment with the project charter.

B.

Organize a mentoring session with the team and the SME.

C.

Meet with the SME to discuss the current challenges the team is facing.

D.

Review the project scope statement with the SME.

Full Access
Question # 606

Eight people have been working on a project for an extended period of time. The

scope has changed significantly and the product owner has been replaced multiple times. The

team members are feeling disassociated from the project.

What should the project manager do to ensure team alignment with the goals?

A.

Ask the new product owner to explain the importance of the project.

B.

Email the team a detailed outline of the business requirements.

C.

Review the project charter with the team.

D.

Facilitate a discussion of the vision for the project.

Full Access
Question # 607

A project has recently Kicked off. The project manager observes that thete are different expectations among the project team members. These growing misunderstandings are affecting team productivity.

Which document should the project managefve?

A.

Project charter

B.

Stakeholder register

C.

Team charter

D.

Project organization charts

Full Access
Question # 608

A project manager primarily works on implementation projects Depending on the deliverable, the project manager is able to estimate the time line based on previous projects. The project manager now receives a project that is different from the previous implementation projects.

What should the project manager do next?

A.

Refer to the previous protect they worked on and base the estimate on that

B.

Use expert judgment to estimate the schedule and then adjust the schedule as the project progresses

C.

Ask the project management office (PMO) by when the project can be completed and use that date as the project time line

D.

Break down the project into smaller tasks and estimate the durations of the activities

Full Access
Question # 609

A project manager is managing a government project that targets the development of

small businesses in remote towns. The project team is having difficulty conducting

entrepreneurship training in some of the targeted towns because the local municipal

governments will not authorize the training. As a result of the delay, project implementation is at risk.

What is a probable reason for this?

A.

The project should have constructed training centers in the remote towns.

B.

The project did not identify and engage the correct stakeholders.

C.

The project should have representatives in all the remote towns.

D.

The project did not fully engage the project sponsor.

Full Access
Question # 610

A key import supply has suffered a delay of 6 months. The delay affects a functionality that is needed to complete the project on time. The project manager learns from the project te«... that another team is working on a product that could work as a solution, but it is still a prototype

What should the project manager do to accelerate this solution?

A.

Contact the other project team and ask them to organize a demo of the prototype

B.

Perform iterative planning with the team to use the prototype

C.

Check the burnup charts to see what progress has been made to integrate the solution

D.

Prioritize the backlog with the customer to remove the feature

Full Access
Question # 611

A complex, high-value agile project includes sprint demonstrations with the customer

every four weeks. Executive management is concerned about the project ' s progress and

wants more frequent updates on the project status.

What should the project manager do?

A.

Inform executive management that the customer is made aware of the status duringthe sprint demo.

B.

Prepare a weekly status report and share it with executive management every week.

C.

Inform executive management about agile principles and processes that are followedin the project.

D.

Ask the team to prepare and share the status report with executive management everyweek.

Full Access
Question # 612

A sponsor and project manager found out that a vendor in a different time zone has delayed the delivery of its products and needs close supervision until the project gets back on track. The only option is to relocate three key members of the project team to spend 6 months abroad

What should the project manager do next?

A.

Communicate to the whole team the decision to relocate team members abroad and the implications of doing so in the next project status meeting

B.

Communicate individually with the affected team members to negotiate the decision and confirm their willingness to relocate

C.

Communicate the decision to the human resources (HR) department so they can direct the project team members to be sent abroad

D.

Communicate to the affected team members ' manager and schedule a meeting to discuss the details of this assignment

Full Access
Question # 613

A company has decided to investigate the feasibility of a new product. The project manager is in charge of validating the customer requirements. What should the project manager do to gam customer feedback?

A.

Have the product owner create product documentation

B.

Have the team create a minimum viable product (MVP).

C.

Have the marketing department create a survey

D.

Have the team create a prototype with all features

Full Access
Question # 614

A project manager who is working with a virtual team needs to mentor an entry-level colleague. This team member informs the project manager that they feel demotivated and excluded from the team

What should the project manager do first to solve the situation?

A.

Speak with the team member about their engagement and contributions

B.

Perform an assessment of each member of the project team

C.

Assign the team member to a team where they can contribute more

D.

Conduct a team building event to involve the team member

Full Access
Question # 615

A key resource is newly assigned to a project. The project manager and the resource

did not get along well in a previous project. This resource is needed to ensure the completion

of a major component for the project.

What should the project manager do?

A.

Work on resolving the differences with the key resource and building a good workingrelationship to ensure project success.

B.

Monitor the key resource closely throughout the project, but do not let the projectsponsor know about the conflict.

C.

Request that the key resource ' s functional manager work directly with the resourceduring the project.

D.

Discuss this with the project sponsor and request that this key resource be replaced onthe project.

Full Access
Question # 616

A project manager notices that a project participant seems frustrated and expresses themselves loudly at status meetings and later discovers that the participant is hearing impaired. Which process should the project manager have used at the start of the protect that would have identified this situation?

A.

Stakeholder analysis

B.

Resource needs analysis

C.

Accommodations assessment

D.

Team member assessment

Full Access
Question # 617

A project manager is assigned to an automotive product development project in me middle of the pilot phase. According to the test lab. a durability test was completed with good results 6 weeks ago but there were no reports left behind by the test engineer who left the organization the previous month.

What should the previous project manager have done to prevent this issue?

A.

Built a pair-engineering environment so that experienced engineers always work with junior engineers to assist in knowledge transfer

B.

Contracted with a third-party test lab to outsource all testing processes and required that they produce all test reports

C.

Led a technical benchmark workshop every month to share state-of-the-art technology trends and ask all team members to attend the workshop

D.

Built a shared repository for the project in the internal server and asked the team to create record and save all project deliverables to the server

Full Access
Question # 618

A project manager is working on a project that has strict deadlines and budget restrictions. The project manager realizes that in order to win the bid the company submitted a significantly tower bid than their local competitors leaving a thin profit margin. The client is constantly submitting change requests and. unfortunately, these change requests are stretching both the schedule and the budget

What should the project manager do?

A.

Instruct the team to accommodate the changes to the project

B.

Review the project charter to identify the agreed scope

C.

Negotiate the impact of these changes with the client

D.

Escalate the issue to senior management

Full Access
Question # 619

A project manager submits a version of the software that the project team created. During the review meeting, a team member informs the project manager of a recent regulation that requires a dual verification process in the software. However, the product sponsor strongly insists there should be no updates to the software.

What should the project manager do?

A.

Include the new requirement in the next iteration of the software without informing the sponsor.

B.

Inform the team that the sponsor decided to reject any changes and release the software as is.

C.

Release the software as is and start a new project to deliver the new requirements.

D.

Collect the requirements of the regulation and follow the change control process.

Full Access
Question # 620

A project manager acquired information from the market that would reduce the business value being delivered by an ongoing protect Based on that information, the project manager believes the project should be stopped

How should the project manager handle the situation?

A.

Remove the items no longer applicable from the backlog and present the backlog to the project team

B.

Continue working on the defined scope and review the risk matrix

C.

Have a discussion with the project sponsor and cancel the project

D.

Have a discussion with the sponsor and recommend the project business value be reassessed

Full Access
Question # 621

During project execution, an important stakeholder threatens to withdraw support

for the project, citing a lack of transparency and accountability in the way the project is being

executed. What should the project manager do to handle this situation?

A.

Approach the stakeholder to address the concerns.

B.

Consult the risk management plan.

C.

Escalate the issue to the project management office (PMO).

D.

Refer the stakeholder to the project sponsor.

Full Access
Question # 622

A project manager recognizes that a key stakeholder is not engaged in the project and does not seem interested in the project status. The project manager is concerned that the project may go off track if the stakeholder expectations are not met

How should the project manager approach the stakeholder?

A.

Analyze the stakeholder ' s expectations and emphasize the topics of interest that may influence the project ' s success

B.

Post regular updates to the project teams board and email the stakeholder when they are posted so the stakeholder can review at their convenience

C.

Schedule regular review sessions with the stakeholder and the project team so the stakeholder can understand the status and engage with team members

D.

Continue to send status reports by email and schedule one-on-one sessions with the stakeholder so they are regularly debriefed on the project status

Full Access
Question # 623

During a network upgrade for a company, the client informs the project manager that a government representative notified the client about a separate project that will affect the network upgrade. Any change in the upgrade will impact the project ' s cost and schedule.

What should the project manager do first?

A.

Perform an impact analysis with subject matter experts (SMEs).

B.

Inform the government representative about the impact of the separate project.

C.

Implement a change request to increase the budget and schedule.

D.

Consult and update the risk register with the project stakeholders.

Full Access
Question # 624

During the project planning phase, a project manager called a meeting to discuss the

product backlog with multiple stakeholders who represent the end users in various capacities.

Only one executive manager attended the meeting.

What should the project manager do?

A.

Meet with each stakeholder individually to gather input to the product backlog andbegin project planning.

B.

Proceed with prioritization of the product backlog based on previous lessons learnedand complete the project planning phase.

C.

Reschedule the meeting to ensure the majority of stakeholders are present for theproduct backlog discussions.

D.

Proceed with the meeting in order to keep the project on track and start prioritizing the product backlog.

Full Access
Question # 625

A project manager writes to the receiving organization to inform them that all

acceptance activities are completed with success and it is time to initiate handover. The

receiving manager replies that the team will not be ready for the handover procedure for

another two weeks.

What should the project manager do?

A.

Deliver to the receiving manager on time, who can then make a knowledge transfer totheir team.

B.

Inform the project sponsor of the two-week delay and replan activities to minimizedelays.

C.

Request that the receiving manager issue a change request to prolong the project bytwo weeks.

D.

Issue an internal change request to secure the resources for an additional two weeks.

Full Access
Question # 626

A project manager is working on a critical path activity and notices a delay in product delivery due to an anticipated event What should the project manager do first?

A.

Follow the risk response plan

B.

Use the contingency fund

C.

Prepare a change request

D.

Update the risk register

Full Access
Question # 627

An agile project manager has just been given a sizeable software development project to implement. Early in the initiation stage, the project sponsor requests an indication of time lines for delivery of the initial release.

What tools should the agile project manager use to do these estimates?

A.

Product backlog, budget, resource management plan

B.

Budget, minimum viable product (MVP), retrospective notes

C.

Resource management plan, retrospective notes, backlog grooming

D.

Backlog grooming, product backlog, minimum viable product (MVP)

Full Access
Question # 628

A project with multiple teams recently transitioned from a predictive approach to agile

as requested by the product owner. Midway through implementation, a team member noticed

there was no technical capability to support the current business requirement; therefore, the

project will need to be reworked and the issue needs to be communicated to all stakeholders.

What should the agile project lead have done to avoid this situation?

A.

Assessed the technical and organizational readiness for the project and identified risksat the beginning of the first iteration

B.

Requested the product owner ' s approval to add an external expert to define theacceptance criteria

C.

Defined a clear acceptance criteria at the initiation phase and continued with theproject

D.

Increased the communications between the team member and the product owner

Full Access
Question # 629

An engineer working on a project team has tasks that require an additional skill that the engineer does not have a designer on the team is experienced with this skill from previous jobs and is willing to teach this skill even though it is not part of the current work

What should the project manager do?

A.

Escalate the situation to the engineer ' s manager

B.

Request external training for the engineer

C.

Request external training for the engineer and designer

D.

Allow the engineer and designer to cross-train with each other

Full Access
Question # 630

A project manager receives a serious complaint from a functional manager about a

team member. What should the project manager do?

A.

Replace the team member immediately to maintain a good relationship with thefunctional manager.

B.

Discuss the issue with the functional manager to understand the reason for thecomplaint.

C.

Support the team member and provide documentation to the functional managerproving their performance.

D.

Protect the team member and ask the project sponsor to minimize any externalinterruptions.

Full Access
Question # 631

A project manager is leading a project that is implementing an assembly line.

During the quality review meeting, a team member reports an issue stating that the product

being developed has discrepancies with the one requested by the customer.

What should the project manager do?

A.

Ensure the current solution is in place to enable future usability.

B.

Run a root cause analysis to identify the quality breach and update the qualitymanagement plan.

C.

Check that the product meets the requirements established by the customer.

D.

Make a proposal of new specifications and submit it to the customer for approval.

Full Access
Question # 632

An agile team was hired to work on a public service project. The team received a

list of vague ideas about the business and now needs to understand, develop, and prioritize a

list of functionalities.

Who will be responsible for this task?

A.

Project owner

B.

Agile leader

C.

Agile team

D.

Product owner

Full Access
Question # 633

An organization is adopting an agile mindset. On the first agile project, the project

manager faced an issue because the team was unable to make decisions on time.

What should the project manager do to address the problem?

A.

Define clear guidelines on how decisions should be made under the neworganizational policy and reinforce them with the team on every occasion.

B.

Invite senior leadership to a team-building workshop and restate the importance ofaccountability and leadership under the new company direction.

C.

Assess the situation to understand how the organization ' s culture impacts the decisionmaking process, and coach the team toward a new model.

D.

Adopt an autocratic leadership style and dictate all decisions in order to speed up theteam ' s velocity.

Full Access
Question # 634

A company has always acquired very specialized services from local companies for

its projects. During the planning stage for a regulatory project, the project manager is informed

that local vendors would not be able to operate due to an unexpected major event. There is an

option to hire the same services from companies in other countries.

What should the project manager do in this situation?

A.

Plan to execute the procurement tasks in a virtual environment.

B.

Review organizational process assets (OPAs) for similar projects.

C.

Create a change request to extend the duration of the project.

D.

Ask the project sponsor to put the project on hold.

Full Access
Question # 635

A regulatory branch of an environmental government agency has recently placed a ban on the manufacturing of a specified thickness of plastic packaging products. This ban will take effect in 12 months. The project manager for a startup firm working in alternative packaging has been monitoring the progress of this law for a while and. as part of the risk management, has identified new products that can support a growing customer base.

What should the project manager do next?

A.

Continue production processes and plan to discuss changes at the next annual target review meeting.

B.

Begin a marketing campaign to sell alternative packaging after the 12-month period ends.

C.

Inform management of the new law as an opportunity to expand market share and share the proposed products

D.

Organize a meeting with all stakeholders and review the stakeholder engagement plan

Full Access
Question # 636

A project manager is managing the development of a dental wire bending machine. The machine is compatible with the three most popular dental wires in the market which covers 90°.© of the market The prototype is now under testing for certification. The manufacturer of one of the three wires announced they will be producing a different wire mat will be incompatible with the machine. This will result in a 25% loss of market coverage from the initially predicted 90% coverage

What should the project manager do?

A.

Investigate the impact of this issue with the team and survey the market for alternative wires with similar characteristics

B.

Stop the project and kick off another project to apply alternative wires for the machine

C.

Meet with the sales and marketing representatives and ask them to convince the manufacturer to reconsider

D.

Meet with the wire manufacturer to secure enough of the existing stock for the machine

Full Access
Question # 637

An equipment vendor will implement a new production line for a client company. The year-long project will include 2- to 4-month long iterations; however, the client ' s project manager has no agile experience.

How should the project manager ensure that the client is effectively represented in the daily meetings?

A.

Recommend agile training programs that best suit the client project manager ' s schedule.

B.

Realign the project to a predictive approach to ensure optimal collaboration between the teams.

C.

Propose a session tor essential agile Knowledge transfer for the client team to align with the daily meeting goals

D.

Provide the client project manager with agile best practice documents and web resources.

Full Access
Question # 638

On a project with multiple international locations, a trend for delays has been

flagged. When looking into the issue, the project manager realized that some of the key

activities were scheduled over the holiday periods in the overseas offices.

What should the project manager do next?

A.

Update the schedule to reflect the holidays and share the workload among offices tomitigate schedule slippage.

B.

Hire additional personnel on a temporary basis to cover the extra workload during theholiday seasons.

C.

Request that the offices in overseas locations work overtime to mitigate scheduleslippages.

D.

Update the schedule to reflect the holidays and notify the project sponsor of thedelayed completion.

Full Access
Question # 639

A project manager is leading a project at a contracting company, and the project

team just completed an iteration. The product passed inspection, but an additional feature was added to the product. The customer notices the additional feature and thinks it will introduce new risks to the product.

What should the project manager do to avoid this situation in the future?

A.

Manage the scope baseline to influence the factors that drive change.

B.

Follow the proper change control process and evaluate the change for further impact.

C.

Work with the customer to ensure the feature adds value.

D.

Perform frequent reviews with the customer to ensure that the product is working asexpected.

Full Access
Question # 640

A new project manager has been assigned to an environmental project. After

reviewing the project plan, the project manager notices that health and safety requirements have not been properly addressed. This is a serious concern, and the project manager wants to fix this issue immediately.

Why is this situation problematic?

A.

Injury or loss incidents could delay project deliverables.

B.

It is imperative that established performance metrics are met.

C.

The project manager is obligated to comply with the project location ' s regulatoryrequirements.

D.

The project manager must follow their employer ' s organizational process assets(OPAs).

Full Access
Question # 641

A project stakeholder has expressed concern that the established success criteria for

the project are not being met. What should the project manager do next?

A.

Review the established project benefits tracking metrics.

B.

Update the project business case document.

C.

Document the agreed-upon ownership of benefits realization.

D.

Create a project benefits management plan.

Full Access
Question # 642

A project manager is managing a hybrid project. There is software in place to access the repository of project artifacts However a few stakeholders are reporting that they are unable to find the latest project schedule

What should the project manager do?

A.

Advise the project management office (PMO) that there is a resource gap for sharing project artifacts effectively

B.

Escalate the issue to the steering committee and ask them to deal with the stakeholders ' lack of training

C.

Make sure all stakeholders have access to the system and know where to find project artifacts

D.

Send the project schedule via email to the stakeholders who need that information

Full Access
Question # 643

The marketing team is moving from predictive to hybrid approaches for their projects. The marketing director is not familiar with hybrid approaches and does not support the new direction. What should the project manager do?

A.

Advise the marketing director to receive formal training.

B.

Ask the marketing team members to coach their director.

C.

Train the marketing team and keep their director informed.

D.

Mentor the marketing director on the approaches.

Full Access
Question # 644

A project team is experiencing conflict between two team members. Team member A feels that team member B is always talking over team member. A and does not listen to any advice Team member B is not willing to listen to feedback

What should the project manager do to resolve the issue?

A.

Move one of the team members to a different protect team

B.

Review the ground rules for collaboration within the team

C.

Report the performance issue to both of the team members ' supervisors

D.

Modify the communications management plan and resend it to the team

Full Access
Question # 645

A project manager is leading a software development project. Recently, team members have complained that during the last few dally standup meetings, a key stakeholder frequently interrupts, requests explanations, and proposes unplanned changes. This issue is frustrating the project team and slowing down me work.

What should the project manager do?

A.

Instruct the team to work as planned and Ignore the stakeholder ' s requests.

B.

Escalate the situation to upper management.

C.

Add more team members to make up for any project delays.

D.

Address the issue with the stakeholder and explain the situation.

Full Access
Question # 646

Throughout an entire project, the project manager took notes at every meeting with

team members. These notes provided useful insights from key stakeholders, which later

resulted in increased value to the project. The project manager thought it would be helpful to

keep these notes as a future reference for other project managers within the organization.

Where should the notes be located?

A.

Lessons learned

B.

Organizational process assets (OPAs)

C.

Enterprise environmental factors (EEFs)

D.

Project management plan

Full Access
Question # 647

The customer wants to show their stakeholders a tangible outcome faster. This requires advancing a milestone.

Which two things should the project manager do? (Choose two)

A.

Inform the customer that moving the milestone has a very high impact on project cost.

B.

Escalate the Issue to senior management so they can impose a solution on the customer.

C.

Convince the customer to keep the requirements as is and not move the milestone.

D.

Review the customer ' s priorities regarding the desired requirements for the milestones.

E.

Discuss which requirements can be delivered faster with the project team.

Full Access
Question # 648

A project requires testing of the final product to be done at another department ' s

testing facility, which is known for having low availability. This situation could potentially

impact the project schedule.

What should the project manager do next?

A.

Update the risk register.

B.

Update the issue log.

C.

Update the lessons learned register.

D.

Update the project schedule.

Full Access
Question # 649

During a documentation audit of an international company it was identified that the last version of the protect schedule was from one month ago even though the project manager kr. it was recently updated How should the project manager have handled documentation for the project?

A.

Reviewed the risk register to identify a response plan for the audit

B.

Assigned a project team member to ensure all project documentation was updated

C.

Updated the project management plan regularly and had it securely shared with all stakeholders

D.

Kept documentation in the project management information system (PMIS) and shared it with appropriate stakeholders

Full Access
Question # 650

A project manager has experience working with a specific provider that has been

requested for an upcoming project. This provider often fails to meet deliverable dates; however, it is the only company with the specific experience required for the project.

What should the project manager do during the planning phase?

A.

A. Hire resources to obtain knowledge about the provider ' s specific capabilities.

B.

B. Add penalty clauses to the contract and update the risk register.

C.

C. Encourage the provider to work overtime with no additional costs to the project.

D.

D. Contract another provider with less experience and give them a chance to provide the deliverables.

Full Access
Question # 651

A project manager has been assigned with initiating a large project to deliver

complex equipment. Part of the project will be the result of a long research process, but once

this is completed, the other part of the project must be incrementally delivered to the

customer.

Which approach should the project manager choose for this project?

A.

Agile

B.

Waterfall

C.

Predictive

D.

Hybrid

Full Access
Question # 652

In a hybrid project a stakeholder requests some feature modifications directly to one of the team members. When investigating further the project manager finds this to be a common practice m the business, which is different from what is stated in the project management plan

What should the project manager do?

A.

Update the risk register including noncompliance with the change process as a probable cause for scope creep

B.

Make sure that all stakeholders are aware and in agreement with the project governance structure m place

C.

Advise the team not to engage in modifications unless it follows the proper change approval process

D.

Escalate to the project management office (PMO) and request that the team member who accepted the request be replaced

Full Access
Question # 653

A project manager is assigned to an ongoing complex project. The team is delivering value each iteration However, the deliverables are internal and the customers are unaware of the deliverables.

Which action should the project manager take?

A.

Ask the internal sales team to keep the customer informed of the delivered value

B.

Evaluate various delivery options in order to immediately demonstrate value to the customer

C.

Inform the customer about the progress and update them on the final deliverables

D.

Wait for an important milestone to complete and then inform the customer of the progress

Full Access
Question # 654

A project manager is working on a cost-reimbursable contract from the client ' s side. During project execution the project manager notices a major deliverable is missing. The project manager raises this with the seller but the seller advises the project manager that the subject deliverable is not part of the contract. The project manager remembers negotiating and agreeing to this deliverable during the tender process but cannot find it in the contract

What should the project manager do?

A.

Request a change in the contract in order to add the deliverable

B.

Add this deliverable to the requirements traceability matrix

C.

Terminate the contract and commence the closeout process

D.

Look to see if the deliverable is described in the statement of work (SOW)

Full Access
Question # 655

A project manager is assigned to an important company project. While reviewing the lessons learned from a similar, previous project, the project manager finds that the biggest challenges were related to learn motivation.

What should the project manager do to avoid these challenges?

A.

Increase the project budget by 10% for team-related activities and awards.

B.

Plan to implement team-building strategies throughout the project.

C.

Ask the functional manager to motivate the team outside of the project.

D.

Colocate the team to encourage more motivational team activities.

Full Access
Question # 656

A project manager who works for a company involved in several industries is asked

to lead a software development project for a government agency. The company attempted to

execute similar projects for other industries before but was unsuccessful.

What should the project manager do to ensure project success?

A.

Document this information in the risk management plan.

B.

Develop a contingency plan to prepare for possible risks.

C.

Continue executing the project using expert judgment.

D.

Review the lessons learned registers from the previous projects.

Full Access
Question # 657

A project manager is leading a project in which key performance Indicators (KPls) are measured through earned value management (EVM). Match each measurement on the left with the correct category on the right.

Full Access
Question # 658

A globally distributed project team is running behind schedule due to the lack ol team commitment and low morale. In order to bring the schedule back on track, what should the project manager do first?

A.

Seek the sponsor ' s approval to extend the project schedule.

B.

Set up a meeting to perform a root cause analysis.

C.

Update the issue log and communicate it to the team.

D.

Permanently colocate the team for better performance.

Full Access