Summer Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: myex65

Home > PMI > Project-Management-Professional > PMP

PMP Project Management Professional (2025 Version) Question and Answers

Question # 4

A project team is executing a project to replace an existing system with a new one.

A new project manager has been hired and observes that the team consist of professionals

who have worked with the older system, and others who have little previous experience.

What should the project manager do to ensure project success?

A.

Request a performance assessment for the team from the functional manager.

B.

Evaluate the current effectiveness of the team and define development needs.

C.

Allow each team member to use their individual strengths for project success.

D.

Assign team member roles and responsibilities based on past experience.

Full Access
Question # 5

A project manager is working with an agile team to enhance a product. Due to a

tight deadline, the team is trying to crash the schedule by engaging multiple resources to work

on the project simultaneously. However, the technical environment is configured to allow only

one resource to work on a feature at a time. The team plans to upgrade the technical

environment but is unable to agree on a way forward.

What should the project manager do first?

A.

Conduct a consensus-building session to decide how to approach the next set of work.

B.

Escalate the issue to the product owner for resolution.

C.

Add this conflict to the agenda for discussion at the next daily standup meeting.

D.

Conduct a planning session to decide how to approach the next set of work.

Full Access
Question # 6

A project is about to close and the project manager is p Set up a meeting to perform a root cause analy reparing a draft of the project closure report. The project sponsor has approached the project manager to stay on longer to ensure the benefits in the charter are tracked as completed However, some of the benefits will not be realized until 1year after project implementation.

What should the project manager do?

A.

Explain to the project sponsor that the project manager is only accountable for managing the project scope budget quality and schedule

B.

Document who will be tracking benefits realization what will be tracked and when it will be tracked in the project closure report

C.

Explain to the project sponsor that they are accountable for tracking benefits realization after project completion

D.

Discuss extending the project manager's allocation to the project until all benefits are realized with the project management office (PMO)

Full Access
Question # 7

A project manager is leading a project at a contracting company, and the project

team just completed an iteration. The product passed inspection, but an additional feature was added to the product. The customer notices the additional feature and thinks it will introduce new risks to the product.

What should the project manager do to avoid this situation in the future?

A.

Manage the scope baseline to influence the factors that drive change.

B.

Follow the proper change control process and evaluate the change for further impact.

C.

Work with the customer to ensure the feature adds value.

D.

Perform frequent reviews with the customer to ensure that the product is working as

expected.

Full Access
Question # 8

A hybrid project is experiencing several issues with both the agile delivery of the

product as well as the predictive development of a marketing strategy. What should the project manager do to receive feedback from stakeholders located in different time zones?

A.

Refer to the stakeholder engagement plan.

B.

Set up a conference call for all stakeholders.

C.

Refer to the communications management plan.

D.

Send an email to all stakeholders.

Full Access
Question # 9

A project manager works at an organization that is transitioning to agile The development team has recommended using a burndown chart to provide visibility on project progress to all stakeholders.

What should the project manager do to ensure effective communication throughout the project?

A.

Advise the project management office (PMO) to use the burndown chart as the single communication channel.

B.

Develop a communications management plan for each category in the stakeholder register.

C.

Include the burndown chart in a monthly report that is distributed to all stakeholders.

D.

Postpone the recommendation since the organization does not currently have a defined agile methodology.

Full Access
Question # 10

A project selection committee is shortlisting projects for the coming year. Which selection criteria should the project manager recommend?

A.

Projects with the least duration

B.

Projects that maximize the business value

C.

Projects with maximum revenue generation

D.

Projects with the least associated risks

Full Access
Question # 11

In an ongoing project, stakeholders have been approaching team members for status

reports and changes without consulting the project manager. What should the project

manager do to ensure a successful project?

A.

Send the project charter to all stakeholders for information.

B.

Send an email to all stakeholders directing them to approach the project manager

directly.

C.

Review the stakeholder engagement plan and inform the stakeholders.

D.

Review the change management plan and ask the change control board (CCB) to be

involved.

Full Access
Question # 12

Two team members are arguing about which technology they should use when implementing iteration tasks. The predictive approach was broken into several legations that need to be completed on time so as not to jeopardize the projects timely completion.

What should the project manager do to resolve this issue and help the team move on to the next iteration?

A.

Postpone the selection of the technology used until more information is gathered

B.

Suggest their own approach to solve the issue and ask the team to follow it

C.

Call for an open dialogue which the team will arrive at through consensus

D.

Allow the team to decide since the teams should be autonomous

Full Access
Question # 13

During a project kick-off meeting the project manager tells team members that they can attend a weekly progress meeting either from home or the office. Which intangible stakeholder engagement quality is the project manager embracing to manage relationships?

A.

Asking and listening

B.

Being collaborative

C.

Managing expectations

D.

Building trust

Full Access
Question # 14

A customer asks the project manager about opportunities to create business value.

What should the project manager do first in order to provide the customer with an appropriate

response?

A.

Examine the business value throughout the project.

B.

Ask the team to organize a spike to identify more value.

C.

Meet with the product owner to review the backlog.

D.

Meet with the sponsor to review the business case.

Full Access
Question # 15

A project manager is in the process of creating a strengths-based team and is

organizing a series of workshops to identify and document the strengths of each project team

member. During this session, there are multiple team members who are not actively

participating. These meetings are becoming futile due to a lack of participation.

What should the project manager do?

A.

Have a one-on-one discussion with each team member to emphasize their individual

talents.

B.

Document the behavior of the team members and highlight it during their performance

reviews.

C.

Identify the team members who are not participating and reprimand them.

D.

Explain the benefits of the approach and the effects of positive psychology.

Full Access
Question # 16

The start of a 12-month project has been delayed by 2 months The project has a fixed budget, deadline and product specifications. What should the project manager do next?

A.

Schedule a time to negotiate a trade-off regarding the quality of the product with the customer

B.

Meet with the risk manager to identify potential threats related to the schedule delay.

C.

Set up a meeting with the project sponsor and submit a change request to the scope of the product

D.

Start the project plan for the scope and quality and identify options to deliver and meet stakeholders expectations

Full Access
Question # 17

A project manager is working on a project that has strict deadlines and budget restrictions. The project manager realizes that in order to win the bid the company submitted a significantly tower bid than their local competitors leaving a thin profit margin. The client is constantly submitting change requests and. unfortunately, these change requests are stretching both the schedule and the budget

What should the project manager do?

A.

Instruct the team to accommodate the changes to the project

B.

Review the project charter to identify the agreed scope

C.

Negotiate the impact of these changes with the client

D.

Escalate the issue to senior management

Full Access
Question # 18

A project manager has been assigned with initiating a large project to deliver complex equipment Part of the project will be the result of a long research process, but once this is completed, the other part of the project must be incrementally delivered to the customer.

Which approach should the project manager choose for this project?

A.

Agile

B.

Waterfall

C.

Hybrid

D.

Predictive

Full Access
Question # 19

An organization started the process of a digital transformation and is trying to change

its culture from a predictive to a more agile approach. The project manager leading the

change management process identified some knowledge gaps of key team members, which

could prevent the transformation from happening as planned.

What should the project manager do?

A.

Provide mentoring for the key team members on agile practices and support the team

with training and encouragement.

B.

Create an agile conduct guideline and ensure that all team members follow the rules

stated in the document.

C.

Replace the key team members with new resources who are already aware of the agile

mindset.

D.

Provide directions to the team members on how to accelerate the company's

transformation, bringing the project back on track.

Full Access
Question # 20

Throughout an entire project, the project manager took notes at every meeting with

team members. These notes provided useful insights from key stakeholders, which later

resulted in increased value to the project. The project manager thought it would be helpful to

keep these notes as a future reference for other project managers within the organization.

Where should the notes be located?

A.

Lessons learned

B.

Organizational process assets (OPAs)

C.

Enterprise environmental factors (EEFs)

D.

Project management plan

Full Access
Question # 21

A project manager is assigned to a project related to taxes, which will be managed

using an agile approach. By reviewing lessons learned from a previous project, the project

manager discovers that a key stakeholder is an expert on taxes and is willing to help.

How should the project manager leverage this information?

A.

Recognize the stakeholder's skills are important for the project and evaluate the

possibility of the stakeholder supporting the project team.

B.

Request the functional manager to assign the team from the lessons learned project to

the current project to avoid a learning curve.

C.

Ask the project team to review the lessons learned and have the team contact the

stakeholder directly if there are any questions.

D.

Send a request to the project sponsor to hire the stakeholder and have them become

part of the project team.

Full Access
Question # 22

A leader from project B consistently reaches out to a team member in project A for

assistance. What should project A's project manager do?

A.

Allow project B's leader to continue building relationships.

B.

Talk with project B's leader to discuss possible impacts to both projects.

C.

Tell project A's team member to ignore project B's leader.

D.

Ensure project A's team member can finish the work committed to project A.

Full Access
Question # 23

A project manager is managing two integrated projects in a program A key integration point is misaligned, which has resulted in delays. One of the team's integration leads is a subject matter expert (SME) m this integration area. The other team's integration lead is not a SME but is more senior and has worked on the project longer Both team leads are blaming each other

What should the project manager do first to resolve this situation?

A.

Assign the resolution of the issue to the senior integration lead who has worked on the project longer

B.

Meet with both integration leads to understand the root cause and determine a resolution

C.

Escalate the issue to the program architect who developed the integration plan

D.

Assign the resolution of this issue to the integration lead who is a SME

Full Access
Question # 24

A new manufacturing line project is planned to be delivered in iterations tor the equipment installation phase. During one of the iterations the vendor communicates to the project manager that they will not be able to deliver some of the equipment at the agreed dates.

What should the project manager do next?

A.

Replan the remaining iterations according to the new installation dates

B.

Update the product backlog m order to address the delays

C.

Review the procurement agreements to address the situation

D.

Find another vendor who can fulfill the delivery dates

Full Access
Question # 25

A project team delivered a critical deliverable to the customer. The customer

complained that the maintenance manual was not included.

What should the project manager do next?

A.

Submit a change request to include the manual.

B.

Add the needed manual and update the risk log.

C.

Review the stakeholder engagement plan.

D.

Review the terms and conditions of the contract.

Full Access
Question # 26

A project manager is leading a project that is implementing an assembly line.

During the quality review meeting, a team member reports an issue stating that the product

being developed has discrepancies with the one requested by the customer.

What should the project manager do?

A.

Ensure the current solution is in place to enable future usability.

B.

Run a root cause analysis to identify the quality breach and update the quality

management plan.

C.

Check that the product meets the requirements established by the customer.

D.

Make a proposal of new specifications and submit it to the customer for approval.

Full Access
Question # 27

A company is moving to a hybrid approach and conducted capacity activities for all of the project managers. During these capacity-building activities, the focus was on agile approaches and team facilitation skills. When starting the implementation phase, the project managers faced issues motivating the newly hired agile staff.

Why are the project managers having issues motivating the agile staff?

A.

The capacity building activities missed the servant leadership concept transfer.

B.

Transitional periods normally cause this type of problem.

C.

The agile staff is not used to being led by a project manager.

D.

Project managers are expected to become coaches in agile teams.

Full Access
Question # 28

A project team that is very experienced in enterprise resource planning (ERP)

systems implementation is currently planning the delivery of a new ERP project. There is a

requirement to reuse the client's security subsystem developed by a third party. The client

states that integration with the security subsystem must be done by the client's team. The

project manager does not want to have such an external dependency.

What should the project manager do first?

A.

Plan the implementation of this integration in the first iteration to help reduce risks.

B.

Record the issue in the issue log and closely manage this dependency.

C.

Inform the client that the project team will take care of the integration.

D.

Document the client's responsibility for the integration with the security subsystem.

Full Access
Question # 29

A project manager who is working with a virtual team needs to mentor an entry-level colleague. This team member informs the project manager that they feel demotivated and excluded from the team

What should the project manager do first to solve the situation?

A.

Speak with the team member about their engagement and contributions

B.

Perform an assessment of each member of the project team

C.

Assign the team member to a team where they can contribute more

D.

Conduct a team building event to involve the team member

Full Access
Question # 30

A project manager working on a large-scale network implementation is frustrated

with the hardware supplier. Their deliveries have been consistently late and frequently do not have vital components. The project manager's company has decided to cancel the contract and move to a new supplier, but the only other option is an overseas company.

What should the project manager do first to proceed with this change?

A.

Engage the services of an interpreter who understands the project domain.

B.

Check social media to determine if there are any common connections that use the new supplier.

C.

Request assistance from the procurement department on the next steps.

D.

Become aware of any cultural characteristics of the new supplier that could impact

negotiation.

Full Access
Question # 31

An organization's management system is being upgraded by an agile team. Although the project was scoped thoroughly, the functional requirements were handed over to the project team and there is no subject matter expert (SME) available to work on the project continuously. The project manager is concerned that the team's progress will be hindered by their lack of knowledge.

Which two project events will assist the project manager to ascertain if this is the case? (Choose two)

A.

Requirements analysis

B.

Retrospective

C.

Sprint planning

D.

Standup

E.

Backlog refinement

Full Access
Question # 32

In an iteration-based marketing project, a product is scheduled to be launched at the sixth iteration In the third iteration demo the marketing team expressed that they need five iterations to launch the product and they have not started yet

What should the project team have done to avoid this issue?

A.

Held a touchpoint with marketing before the demo to discuss any impediments

B.

Scheduled a demo presentation of the product during the first reason

C.

Asked the marketing team to start working on the product immediately

D.

Confirmed marketing requirements and constraints when adding to the backlog

Full Access
Question # 33

A project manager is defining the sprint goals with the team, A team member who is responsible for acceptance testing starts criticizing the goals and cannot come to an agreement with the other team members.

How should the project manager handle this situation?

A.

Request to meet with the team member and ask that any issues be escalated separately.

B.

Reprimand the team member and provide immediate coaching on goal alignment.

C.

Proceed with defining the goals with the team members given the majority approval from the team.

D.

Approach the team member with empathy and obtain agreement through collaboration.

Full Access
Question # 34

A company made several changes recently, which resulted in a positive change in

the company culture. A project manager was just assigned to report to a new project

supervisor whose leadership style is about getting things done quickly regardless of employee

and operational impacts. Some employees are complaining about this.

What should the project manager do?

A.

Clarify expectations by explaining the company culture with the supervisor.

B.

Ask senior management to move the supervisor to a different project.

C.

Revisit the company's organizational culture.

D.

Instruct the employees to listen to the supervisor.

Full Access
Question # 35

While working on a poorly defined internal project, a project manager receives

multiple change requests from senior management. What should the project manager do first?

A.

Identify how the proposed changes will benefit the project in relation to the business

case.

B.

Ask for a temporary budget increase to avoid cost overruns.

C.

Keep the team motivated and incentivized to avoid exhaustion from working on a

lengthy project.

D.

Assess the schedule delay and begin implementation to avoid additional lags

Full Access
Question # 36

A regulatory branch of an environmental government agency has recently placed a ban on the manufacturing of a specified thickness of plastic packaging products. This ban will take effect in 12 months. The project manager for a startup firm working in alternative packaging has been monitoring the progress of this law for a while and. as part of the risk management, has identified new products that can support a growing customer base.

What should the project manager do next?

A.

Continue production processes and plan to discuss changes at the next annual target review meeting.

B.

Begin a marketing campaign to sell alternative packaging after the 12-month period ends.

C.

Inform management of the new law as an opportunity to expand market share and share the proposed products

D.

Organize a meeting with all stakeholders and review the stakeholder engagement plan

Full Access
Question # 37

A project to implement a new online landing platform has started After the first sprint, the project sponsor requested a change. What should the project manager do next?

A.

Escalate the change request to the sponsor

B.

Validate the work completed

C.

Inform the stakeholders of the change

D.

Facilitate the update of the product backlog

Full Access
Question # 38

A supplier is hired to provide information security services for a project. The supplier has decided not to provide this service any longer since they have not been paid on time. Their services are critical and this decision will affect the outcome of the project.

What should the project manager do to address this issue?

A.

Negotiate the payments with the supplier and remind them of their long-term association

B.

Penalize the supplier according to the contract's service level agreement (SLA)

C.

Hire another information security supplier and incentivize them for speedy delivery

D.

inform the relevant stakeholders of this challenge and seek their support

Full Access
Question # 39

There is a problem with a project because some features are not in compliance with

regulations. Some stakeholders do not believe compliance is a priority, while others disagree.

What should the project manager do?

A.

Review the stakeholder engagement assessment matrix to determine next steps.

B.

Set up some time with the stakeholders to explain the importance of compliance.

C.

Meet with the sponsor to discuss how to handle the stakeholders' differing opinions.

D.

Send out documentation to align stakeholder expectations and project objectives.

Full Access
Question # 40

Ai the start of a project, the sponsor declares that demonstrating benefits from the product will be extremely important. The project sponsor calls a meeting with the project manager and the project leadership team to discuss the best approach because the project has a high degree of uncertainty and many changes are expected.

What should the project manager propose?

A.

Develop requirements and designs to support a faster product release.

B.

Emphasize the adoption of a predictive approach to minimize ambiguity.

C.

Recommend an agile approach so the project can be delivered iteratively.

D.

Outsource development of the product to a third party with more experience.

Full Access
Question # 41

A hybrid project manager has taken over a large-scale software development project m a highly regulated environment. During a handover session the outgoing project manager explains that they devised their own status reports which is different from the project management office's (PMO's) status report style. The project stakeholders are extremely particular about the information they receive in updates and do not believe the PMO's status reports have sufficient enough information

How should the new project manager proceed*?

A.

Continue using the outgoing project manager's status reports as well as their approach for schedule reporting

B.

Explain to the PMO that the hybrid project team needs to keep an agile approach for reporting and will not be complying with the organizational standard

C.

Change the status reports according to the template supplied by the PMO and proceed with scheduled reporting

D.

Meet with the project stakeholders to explain the need to comply with the PMO standards and update the status report format accordingly

Full Access
Question # 42

A project manager has been assigned to a project that is in progress. The project

manager is looking for information regarding why the project is being completed.

What should the project manager do first?

A.

Evaluate the project exit criteria in the project charter.

B.

Reach out to the senior executive sponsor for the project.

C.

Understand the project success criteria and objectives.

D.

Review the project status reporting for the latest information.

Full Access
Question # 43

During the project quality control process, the project manager realizes that the quality management plan does not include how the final user will perceive the benefits of the new product compared with the actual product. What should the project manager do first?

A.

Let the product go to market and wait for customer feedback regarding quality

B.

Ask the quality manager to include the final user tests in the quality management plan.

C.

Submit a change request to analyze a new set of quality tests

D.

Ask the product manager to include the final user tests in the quality management plan

Full Access
Question # 44

A financial company is developing a new application for mobile banking using a hybrid approach The project is delayed as the product concept has not yet been developed to the key stakeholder s satisfaction despite multiple design iterations. The key stakeholder has now started participating in all daily standups. The project manager has observed that the key stakeholder's presence has had a negative impact on the team's morale, while also impacting productivity

How should the project manager ensure that the stakeholder s issues are addressed effectively without impacting the team?

A.

Set up a meeting with the stakeholder to address their concerns directly

B.

Move to a predictive design-and-requirements gathering approach

C.

Talk to the team separately to address the stakeholder's concerns

D.

Schedule a team retrospective and invite the stakeholder

Full Access
Question # 45

A company has decided to investigate the feasibility of a new product. The project manager is in charge of validating the customer requirements. What should the project manager do to gam customer feedback?

A.

Have the product owner create product documentation

B.

Have the team create a minimum viable product (MVP).

C.

Have the marketing department create a survey

D.

Have the team create a prototype with all features

Full Access
Question # 46

A key project team member has exhibited high interest in a project. The input from

this person has been very useful, and the project is steadily progressing. Suddenly, this individual's participation decreases, and activities that they were responsible for are not being completed within the planned period.

What should the project manager do?

A.

Reallocate tasks for the team member of concern so that work is handled by another team member.

B.

Schedule a meeting to discuss recent observations with the team member.

C.

Organize a team-building session with all of the team members.

D.

Consult the resource allocation matrix to see if the team member is still required for the

project.

Full Access
Question # 47

A contract has fust been awarded for an automation project that was supported by the local community. The project manager was warned by the elected officials that the project cannot proceed.

Why did this action occur?

A.

Inadequate funds for the automation project

B.

Inadequate engagement of the political stakeholders

C.

Lack of competence to manage the automation project

D.

Lack of a proper legal framework in place

Full Access
Question # 48

A new sales software development project is underway The customer is still finalizing the requirements for the system when a new CEO is introduced. The new CEO is expected to make changes to the organization, which most likely will impact development. However, the most important criterion for the project is that the software must provide correct sales results. No intermediate results are required.

Which project approach should the project manager take?

A.

Incremental

B.

Predictive

C.

Hybrid

D.

iterative

Full Access
Question # 49

A project is on its sixth iteration out of seven. Select the two points where the team is

performing better than expected. (Choose two.)

Full Access
Question # 50

During project execution a project team member resigned and a new junior member joined the team To smooth the transition the project manager assigned a senior project team member to transfer knowledge and support the junior team member The project manager subsequently received feedback from the senior team member saying that the junior member submitted a poor-quality deliverable and should be removed from the team However the project manager checked that deliverable and found it met quality requirements

Which technique should the project manager use to resolve this issue?

A.

Smooth/accommodate

B.

Compromise/reconcile

C.

Force/direct

D.

Collaborate/problem solve

Full Access
Question # 51

A project manager is leading a software development project. Recently, team members have complained that during the last few dally standup meetings, a key stakeholder frequently interrupts, requests explanations, and proposes unplanned changes. This issue is frustrating the project team and slowing down me work.

What should the project manager do?

A.

Instruct the team to work as planned and Ignore the stakeholder's requests.

B.

Escalate the situation to upper management.

C.

Add more team members to make up for any project delays.

D.

Address the issue with the stakeholder and explain the situation.

Full Access
Question # 52

A project is in the execution phase During a few planning sessions the team brought up dependencies and risks based on their knowledge of other project. The project manager also received questions from the company in terms of how and when the team planned to perform acceptance testing and training activities

What should the project manager do next?

A.

Document the project management plans and share them with the company and all team members via email for review

B.

Create a log to track risks assumptions issues and dependencies and establish a periodic review with the stakeholders

C.

Add contingency m the schedule to account for dependencies and risks then review rt with the team

D.

Engage with the company and the project team to determine the best course of action

Full Access
Question # 53

A new project manager has been assigned to an environmental project. After

reviewing the project plan, the project manager notices that health and safety requirements have not been properly addressed. This is a serious concern, and the project manager wants to fix this issue immediately.

Why is this situation problematic?

A.

Injury or loss incidents could delay project deliverables.

B.

It is imperative that established performance metrics are met.

C.

The project manager is obligated to comply with the project location's regulatory

requirements.

D.

The project manager must follow their employer's organizational process assets

(OPAs).

Full Access
Question # 54

An agile team was hired to work on a public service project. The team received a

list of vague ideas about the business and now needs to understand, develop, and prioritize a

list of functionalities.

Who will be responsible for this task?

A.

Project owner

B.

Agile leader

C.

Agile team

D.

Product owner

Full Access
Question # 55

A customer interacts directly with a Scrum team and continually requests changes in

priorities. This causes confusion among the team members and they complain to the project

manager.

What should the project manager do?

A.

Advise the customer to discuss changes with the product owner.

B.

Document this issue in the sprint backlog for discussion at a team meeting.

C.

Ask the customer to submit a change request to the project sponsor.

D.

Encourage the team to clarify the requests with the customer.

Full Access
Question # 56

A project manager is instructed by the project sponsor to draft the project charter. The project sponsor asks the project manager to involve a particular stakeholder m order to provide necessary resources However, the stakeholder is refusing to get involved because the stakeholder thinks mat there is no benefit m using the project deliverable

What should the project manager do to resolve this?

A.

Meet with the stakeholder to discuss the impact of the deliverable

B.

Consider the stakeholder as a risk and evaluate possible solutions with the project team

C.

Improve communication with the stakeholder to obtain their assistance in the future

D.

Escalate to the project sponsor due to the political nature of the issue

Full Access
Question # 57

A project manager is leading a hybrid project. The self-organizing teams are

continually late in delivering their demos, resulting in low morale. The steering committee is

familiar with the reporting and planning associated with a predictive approach and is

concerned about the project because it is unclear if the expected value will be delivered.

What should the project manager do?

A.

Emphasize to the teams the importance of reaching the agreed deadlines and value.

B.

Request to coach the team to ensure motivated project team members are on board.

C.

Update the project schedule with a buffer to reflect the expected delays being incurred

by the team.

D.

Suggest to the teams to limit the scope of work per iteration so they will start to deliver

more reliably.

Full Access
Question # 58

A project involves exporting 150 packages to the customer. However, only 30 packages have been cleared by the customer for shipment. The logistics manager provided

details to the customer 2 weeks ago and set up a weekly conference call to effectively

communicate with them, but the customer has not been participating in the calls.

How should the project manager handle this situation?

A.

Request a change in the contract to include the shipment in the project management

plan.

B.

Find the root cause of the issue and discuss the customer's current engagement.

C.

Inform the customer that subsequent packages cannot be manufactured.

D.

Request a delivery date extension from the customer

Full Access
Question # 59

A company has always acquired very specialized services from local companies for

its projects. During the planning stage for a regulatory project, the project manager is informed

that local vendors would not be able to operate due to an unexpected major event. There is an

option to hire the same services from companies in other countries.

What should the project manager do in this situation?

A.

Plan to execute the procurement tasks in a virtual environment.

B.

Review organizational process assets (OPAs) for similar projects.

C.

Create a change request to extend the duration of the project.

D.

Ask the project sponsor to put the project on hold.

Full Access
Question # 60

A project manager is assigned to an ongoing complex project. The team is delivering value each iteration However, the deliverables are internal and the customers are unaware of the deliverables.

Which action should the project manager take?

A.

Ask the internal sales team to keep the customer informed of the delivered value

B.

Evaluate various delivery options in order to immediately demonstrate value to the customer

C.

Inform the customer about the progress and update them on the final deliverables

D.

Wait for an important milestone to complete and then inform the customer of the progress

Full Access
Question # 61

Eight people have been working on a project for an extended period of time. The

scope has changed significantly and the product owner has been replaced multiple times. The

team members are feeling disassociated from the project.

What should the project manager do to ensure team alignment with the goals?

A.

Ask the new product owner to explain the importance of the project.

B.

Email the team a detailed outline of the business requirements.

C.

Review the project charter with the team.

D.

Facilitate a discussion of the vision for the project.

Full Access
Question # 62

A project manager is assigned to an automotive product development project in me middle of the pilot phase. According to the test lab. a durability test was completed with good results 6 weeks ago but there were no reports left behind by the test engineer who left the organization the previous month.

What should the previous project manager have done to prevent this issue?

A.

Built a pair-engineering environment so that experienced engineers always work with junior engineers to assist in knowledge transfer

B.

Contracted with a third-party test lab to outsource all testing processes and required that they produce all test reports

C.

Led a technical benchmark workshop every month to share state-of-the-art technology trends and ask all team members to attend the workshop

D.

Built a shared repository for the project in the internal server and asked the team to create record and save all project deliverables to the server

Full Access
Question # 63

A concerned project team member complains to the project manager that another team member is being disruptive and argumentative during team meetings. The project manager received some information that the team member recently overcame a difficult personal situation.

What should the project manager do to address the concem9

A.

Provide team-building activities so that the team can learn how to overcome disruptive behavior

B.

Inform the disruptive team member's functional manager that the disruptive behavior should be stopped immediately

C.

Request a meeting with the disruptive team member and help to resolve the issue

D.

Encourage self-governance and ask the concerned team member to speak to the disruptive team member directly

Full Access
Question # 64

A project is nearing completion. The sponsor is already asking the project management office (PMO) when the project manager will be assigned to host a planning session for a new initiative.

What should the project manager do next?

A.

Review organizational process assets (OPAs) for clarity.

B.

Document lessons learned before closing.

C.

Consult the project charter for next steps.

D.

Confirm the definition of done (DoD) has been met.

Full Access
Question # 65

During the planning for a long project, the project manager recognized that several

members of the team are new to their roles. How should the project manager incorporate this

into planning?

A.

Increase the overall project duration to account for the inexperienced team members

on the project.

B.

Ensure planning has accounted for replacing team members in new project roles who

do not deliver on project goals.

C.

Assess the training requirements and ensure time for professional development

training by senior members.

D.

Revisit the project resource allocation to remove the inexperienced team members

assigned to the project.

Full Access
Question # 66

A team member is openly criticized by others during a standup meeting for failing to

complete yesterday's tasks. What should the agile coach do first to address the situation?

A.

Emphasize the ground rules and then focus on today's activities and impediments.

B.

Let the discussion go on as it is important that the team is clear on priorities for the

day.

C.

Address the team members involved during the next sprint retrospective.

D.

Avoid the discussion by referring to the team charter.

Full Access
Question # 67

A product team is comprised of consultants and staff members Most of the team members agree on risks and the defined risk actions. One consultant discovers a new risk and communicates it directly to management.

What should the project manager do?

A.

Reject the risk because the team is not in agreement on escalating it

B.

Include the risk in the risk assessment and evaluate it with the team

C.

Accept the risk and immediately enter the risk into the risk register

D.

Discuss with the consultant to understand why the risk was escalated

Full Access
Question # 68

As a result of updated external regulations a project manager has been asked to upgrade the operation system tor a call center The project manager is beginning to meet with and segment the stakeholders involved

How should the project manager categorize the call center staff? Click on the correct section of the power/interest grid.

Full Access
Question # 69

A high-tech borehole protect was initiated with the goal of providing water for a rural community of 1500 villagers located in an arid region. The project was completed with a cost performance index (CPi) of 1 09 and a schedule performance index (SPl) of 0.93 Six months after its completion it is determined that the villagers could not access water

What caused this situation to occur?

A.

The risk analysis was inadequate

B.

The project was completed behind schedule

C.

The requirements gathering was inadequate

D.

The project was delivered above budget

Full Access
Question # 70

A project manager is reviewing the requirements of a large program. Which requirements should the project team prioritize to avoid getting fines?

A.

Developing new product lines

B.

Complying with new regulations

C.

Establishing company processes

D.

Certifying sustainable products

Full Access
Question # 71

A CEO has requested that the project manager provide a budget estimate for a long-term project that will be executed over the span of 4 years What should the project manager do?

A.

Include enterprise environmental factors (EEFs)

B.

Conduct a bottom-up estimate

C.

Include projected inflation rates

D.

Conduct an analogous estimate

Full Access
Question # 72

A project team identified a low-cost software product available for purchase that would drastically reduce the scope of development. The development manager has confirmed that this tool would fulfill the business need.

What should the project manager do?

A.

Remind the team that their primary responsibility is software development.

B.

Add a user story to the product backlog to test the software product.

C.

Discuss the Option in the next daily standup meeting to finalize the decision.

D.

Recommend the option to the product owner for consideration.

Full Access
Question # 73

A project is approaching its project closure phase, and the project manager receives

an email from a key stakeholder who complains that the project documentation and artifacts have not been updated. The project manager assigns a project specialist to support the project management office's (PMO) effort to update the project documentation and artifacts.

Which three actions should the project manager ask the project specialist to take? (Choose

three)

A.

Create a quality assurance plan for the documentation.

B.

Identify the components of the project documentation.

C.

Archive only the initial and draft versions of the documents.

D.

Ensure that the documents are in an easily retrievable form.

E.

Collect the documents at the time of their creation.

Full Access
Question # 74

A senior-level executive approached the project manager of a highly visible project that is currently in the execution phase. The executive indicated that they do not support the project

and will be actively trying to prevent its success by reailocating key team members to another critical project.

What should the project manager do?

A.

Request help from human resources to keep the key team members on the project.

B.

Work with the project sponsor to determine an appropriate response.

C.

Ask to meet privately with the senior-level executive to discuss the matter further.

D.

Discuss the incident with the key project team members.

Full Access
Question # 75

A project manager for a digital transformation project has already received the business needs for the project. When gathering requirements, the project manager discovers that not all of the requirements can be delivered with the available resources, but that some of the requirements will be

enough to add business value.

With the project on a fixed budget, what should the project manager do next?

A.

Plan the project based on the available resources and submit a change request upon completion.

B.

Gather all stakeholders and provide recommendations on a smaller, more feasible project scope,

C.

Identify the technical requirements and request that management hire external resources,

D.

Document the problem in the issue log and suggest a change request to decrease the scope.

Full Access
Question # 76

A procurement team lead has been reported as getting into conflicts with other project team members on a weekly basis, The project manager engages with the team lead and discovers that other team members do not believe the team lead is right for this position.

What should the project manager do to resolve these recurring conflicts between the team lead and the other team members?

A.

Receive details of the conflicts from all involved, issue all a warning notice, and send all to leadership training.

B.

Organize a meeting to discuss emotional intelligence with the team, and establish a rule of respect and special treatment for the team lead.

C.

Issue the team lead a warning, and consider recommending the team lead for emotional intelligence training.

D.

Find ways to reduce the tension, increase cooperation, and understand the emotions of all team members involved.

Full Access
Question # 77

A project manager for a technology project is informed by the cybersecurity team that

there are changes in the government's cybersecurity requirements. The project manager calls a team meeting to discuss the requirements, and the team learns that the design changes can be made at no additional cost.

What should the project manager direct the team to do?

A.

Update the scope management plan to track the new government requirements.

B.

Accept the cybersecurity team’s request as the security of the company is at risk of

being noncompliant.

C.

Ask the project sponsor to increase funds in the contingency reserve as a risk mitigation.

D.

Request a change through the change control process to manage the new cybersecurity

requirements.

Full Access
Question # 78

A project manager is working on a project to modernize the information technology of a bank, The project manager is facing challenges with the project sponsor regarding how to proceed with implementation of a key piece of technology.

How should the project manager resolve this conflict?

A.

Meet with all project stakeholders to identify how to implement the technology.

B.

Identify the disagreement in the risk register and develop a contingency plan.

C.

Update the project charter to align with the desires of the project sponsor.

D.

Negotiate with the project sponsor to develop a mutually beneficial solution.

Full Access
Question # 79

A project team member is struggling to understand a specific requirement. How should a servant leader address this issue?

A.

Assess and evaluate the team member's skills to ensure alignment to the particular requirement and solution

B.

Reassign the requirement to another team member who may have ideas on how to meet the requirement

C.

Assist by connecting the product owner with the team member to discuss what problem is to be solved

D.

Deprioritize the requirement and assign a task tor it to be restated to provide the necessary clarity

Full Access
Question # 80

A project manager and project team have brought a project back on track after mapping and removing impediments During the current sprint the team reported that an impediment that previously caused major delays has appeared again. The team tried implementing the same mitigation tasks that worked previously However, the tasks are not having the same result with the impediment

What should the project manager do?

A.

Escalate the issue with an impediment to the project sponsor

B.

Use the contingency budget to implement schedule compression

C.

Implement the mitigation plans listed in the organizational process assets (OPAs)

D.

Reassess the issue as part of monitoring and controlling

Full Access
Question # 81

A software development provider reports an issue that is blocking the other remaining deliverables What should the project manager do?

A.

Ask the provider to seek options to solve the issue

B.

Add the issue to the issue log and report it at the next review meeting

C.

Review the current plan and consolidate if necessary

D.

Schedule a meeting with the provider to collaborate on the options

Full Access
Question # 82

An agile team completes a deliverable that is to be certified by another expert team The second team does not take the deliverable for many months What should the servant leader do?

A.

Review the process and remove the impediment

B.

Escalate this to the project director for a resolution

C.

Remove the certification need from the project scope

D.

Escalate this to the agile lead of the second team

Full Access
Question # 83

A project manager has been authorized to begin a project and realizes that an effective high-performing team is needed to finish the project successfully What should the project manager do next?

A.

Establish the project scope and set clear team objectives

B.

Set performance standards and direction

C.

Hold early kick-off meetings and regular weekly meetings

D.

Select members for their skill or potential

Full Access
Question # 84

An agile project is in its early iterations, but the project manager already realizes that

more resources will be needed to achieve the expected time lines. There are no internal

resources. available.

What vendor strategy should the project manager use to maximize project delivery?

A.

Use compression techniques to break down the scope and assign the scope pieces to

different vendors with a fixed-price contract.

B.

Use the contingency budget for hiring additional vendor resources to mitigate any project

risk.

C.

Engage in a time and materials (T&M) contract and hire a local vendor to support

development.

D.

Establish a solid view of the scope and requirements and engage a vendor with a fixed price contract.

Full Access
Question # 85

A company initiated a departmental transformation project improving the processes for the organization using a predictive approach, This is a critical project for the organization and, in the middle of the project, the project manager noticed that one of the deliverables cannot be produced due to a missing technical skill.

What should the project manager have done to avoid this?

A.

Planned all required training for the team during the onboarding process

B.

Identified all required skills after the kick-off of the project

C.

Identified all required skills during the planning of the project

D.

Asked the sponsor to identify all required skills during the planning of the project

Full Access
Question # 86

An agile team completes a deliverable that is to be certified by another expert team The second team does not take the deliverable for many months What should the servant leader do?

A.

Review the process and remove the impediment

B.

Escalate this to the project director for a resolution

C.

Remove the certification need from the project scope

D.

Escalate this to the agile lead of the second team

Full Access
Question # 87

An agile coach and technical writer for a globally distributed agile team are In a country with a 9-hour time zone difference from the agile team. The agile coach and project lead disagree on the timing for the daily standup. The project lead thinks the standup should be at 10:00 am local time, but

the agile coach and technical writer feel that is an inconvenient time for them.

How does the project lead ensure adherence to agile practices?

A.

Escalate to management that the agile process is not going to work and ask them to speak to the agile coach,

B.

Have two separate daily standups, one for the agile coach and technical writer and one for the agile development team.

C.

Have a discussion with the team on the approach and come to a decision on when the daily standups should be.

D.

Inform the agile coach that the daily standup will be at 10:00 am local time and ensure all parties can attend.

Full Access
Question # 88

A project manager became aware of misunderstandings between a key stakeholder

and a team member with regard to some of the features defined in the project scope. What

should the project manager do?

A.

Reconcile the key stakeholder to the team member's recommendation.

B.

Reconcile the team member to the key stakeholder's recommendation.

C.

Escalate the communication concerns to the project management office (PMO) and

request that they take action

D.

Work with both the team member and the key stakeholder to reach a consensus.

Full Access
Question # 89

A project manager is leading a project to modemize the information technology of a bank. The project manager needs to determine how the project stakeholders should communicate, and has discussed the various options with the project team.

What should the project manager do to communicate with the stakeholders?

A.

Provide updates to the project sponsor to review and distribute to each stakeholder.

B.

Use a single communication medium such as video teleconferencing to limit confusion.

C.

Use a variety of communication methods that respect cultural, practical, and personal preferences.

D.

Send frequent updates via email to each stakeholder because this is an information technology project.

Full Access
Question # 90

A project manager is managing an internal software development project that is on schedule to complete in 1 month. The project should begin seeing value once the system is online,

yet some stakeholders lack an understanding of how it will provide value to the organization.

What should the project manager do next?

A.

Ask the sponsor to identify requirements for a new project to monitor and report achievement of the benefits.

B.

Direct the team to implement the benefits management plan and track achievements before the end of the project.

C.

Coordinate with the stakeholders to ensure the benefits management plan is in alignment with the goals.

D.

Update the work breakdown structure (WBS) and project schedule with tasks and resources to track benefits realization.

Full Access
Question # 91

A new project manager is assigned to an ongoing agile innovation project that started 2 weeks ago. After reviewing the project, the new project manager discovered that the previous project manager was planning to use a predictive approach. The previous project manager planned to present the first major deliverable to the client when the project was completely finished in 8 months.

What should the new project manager do?

A.

Meet with the team to review the backlog and create small iterations that can deliver incremental value to the client,

B.

Continue working with the predictive approach to deliver the value at the end of the project.

C.

Use a hybrid approach in which agile practices are used but the value is provided to the client at the end of the project.

D.

Submit a change request to the project board to adjust the delivery date to 2 months earlier than planned.

Full Access
Question # 92

A company has rolled out the latest retail management system, and the project has been handed over to operations. The operations team finds that many of the day-to-day requirements are not covered in the system, and support for the project has limited hours, The project team has dissolved and the contract resources are no longer working on the project. As a result, the operations team has been facing numerous customer issues.

What should the project lead have done initially to avoid this situation?

A.

Reviewed the project management plan

B.

Created a detailed operations manual

C.

Increased support hours for the hours of operation

D.

Involved operations stakeholders during planning

Full Access
Question # 93

A lead project manager for an agile project needs to prioritize requirements define the scope of the initial product and deliver the approved scope in a series of multiple versions. What should the project manager do next?

A.

Work with the product owner to evaluate and prioritize the requirements

B.

Ask the lead developer to run a meeting with the stakeholders to agree on an ordered list

C.

Determine the expected benefits of each requirement to maximize the overall business value

D.

Prioritize the requirements based on the hierarchical level of the requesting stakeholders

Full Access
Question # 94

A new project manager has been assigned to a project that is in its second phase The product created in the first phase was transferred to operations During a meeting, the project sponsor complained that some of the reports contain conflicting data on the product value

What should the new project manager do next?

A.

Review the benefits management plan

B.

Refer to the lessons learned from the first phase

C.

Consult the project reports from the previous project manager

D.

Collect information from related departments

Full Access
Question # 95

A senior developer working on a large artificial intelligence (Al) project has worked hard and shown excellent results. The project manager is very happy with the developer's contribution and thinks that the developer deserves a reward.

What should the project manager do?

A.

Create an opportunity (or the project team to recognize this developer

B.

Send a recognition email to the team and copy management

C.

Reward the developer according to their motivations and interests

D.

Print a recognition certificate and present it to the developer during a meeting

Full Access
Question # 96

A project is being delayed due to a large amount of rework caused by a quality problem that is impacting the critical path. What should the project manager do?

A.

Rebaseline the project schedule to absorb the delay.

B.

Report the delay with rectifying actions to the project management office (PMO).

C.

Notify the project steering committee about the cause of the delay.

D.

Report the delay with rectifying actions to the change control board (CCB) for review,

Full Access
Question # 97

A sales learn working on an IT deployment project approached the project manager on several occasions and complained about nonpayment of their overtime pay The project manager realized that other team members are receiving their overtime pay

What should the project manager do next?

A.

Have a discussion with the sales team to find a solution to the issue

B.

Validate the reason and add it as an issue in the issue log

C.

Direct the sales team to speak with accounting to resolve the issue

D.

Escalate the issue to the functional manager

Full Access
Question # 98

A complex project is m its execution phase. The project is set up to produce both predictive and incremental deliverables. The agile team is running late on their tasks There is a resource on the agile team who is responsible for producing progress reports for the project manager This resource has the required skills to help other team members with their workload

What should the project manager do to optimize the time of the resource who produces the progress reports?

A.

Work more closely with the agile team to eliminate the need for progress reports

B.

Record this in the issue log and find a resource to produce the reports

C.

Produce the progress reports on their own

D.

Engage a new resource to produce the progress reports

Full Access
Question # 99

A project requires the installation of a call center to support operations. It is estimated that the call center will need 100 people working on

weekdays from 8:00 a.m. to 5:00 p.m. and weekends from 8:00 a.m. to 12:00 p.m.

What should the project manager do?

A.

Implement the call center with internal staff to ensure the work is performed according to the company’s culture.

B.

Work with 50% of the people internally and contract the other 50% to an outside company.

C.

Delegate the analysis to the human resources (HR) department in order to organize the call center operations.

D.

Conduct an alternative analysis to decide whether to hire people directly or contract with a company to do the job.

Full Access
Question # 100

One deliverable for a project is to translate and print materials for students every 2 weeks Printing services are available but without guaranteed time lines because other projects make a significantly higher profit and have a higher priority

What should the project manager do to mitigate the risk of not having the materials printed on time?

A.

Meet with the manager to set a high priority for printing the materials

B.

Create a change request to modify the print requirements

C.

Include a risk response in the resource management plan

D.

Purchase a high-volume printer specifically for this project.

Full Access
Question # 101

A new product is designed for a certain market. This product needs to adhere to the health and safety regulations for that region. What should the project manager do to ensure that the product complies with the regulations?

A.

Inform the design team to ensure compliance during the product design phase

B.

Inform the quality team that they need to ensure that the product is in compliance

C.

Ensure that compliance is explicitly mentioned in the relevant requirements

D.

Meet with the team and remind them of the compliance requirements

Full Access
Question # 102

A company is transitioning its projects from a predictive to an iterative approach. The protect team is complaining because they are unsure of what needs to be done due to all of the changes requested by the product owner for features already developed since the beginning of the project.

How should the project manager handle this situation?

A.

Ask the product owner to create a new entry in the risk management plan regarding likelihood and imped

B.

Review the backlogs from similar projects and understand how change requests were implemented

C.

Ask the product owner to follow the change request process to formalize new requirements

D.

Make sure that the product and sprint backlogs have the required level of documentation and both are visible to the team

Full Access
Question # 103

A customer wants to launch a new product in the market and an agile team is set up to work on this project for 9 months After 1 month the customer feels that it would be better to release the product 2 months earlier than the planned date. The task is now assigned to the most talented resource in the organization to this project tor an early finish.

Which risk management strategy has been adopted in this scenario?

A.

Shared

B.

Accepted

C.

Enhanced

D.

Exploited

Full Access
Question # 104

A project manager is leading a project with a predictive approach for a governmental body with strictly defined requirements. In the middle of the project, the sponsor requires a significant new feature to be included. This feature was not in the original plan, nor was it part of the planning process,

What should the project manager do?

A.

Descope low-priority features that were not explicitly requested and add this feature as a high priority.

B.

Inform the senior manager that they will need a new project management plan for this feature,

C.

Complete the most current feature and release the resources for the new feature.

D.

Analyze the impact of this change and present the options to the senior manager.

Full Access
Question # 105

During protect execution the project manager observes lower velocity and a high volume of tasks m the testing queue. The project is using a hybrid approach and there are only a few sprints remaining

What should the project manager do?

A.

Work with the team to understand and solve the issues

B.

Provide testing training to all the project team members

C.

Increase the sprint duration so the testing can be completed

D.

Add a new resource with testing skills to the team

Full Access
Question # 106

As the project progresses, the learns not performing at acceptable levels and in accordance with the key performance indicators (KPls) that were set at the beginning of the

project. How should the project manager resolve this?

A.

Escalate a schedule risk to the sponsor.

B.

Conduct team-building exercises.

C.

Stop the project and perform a team skill assessment.

D.

Make sure that the team has a full understanding of the scope.

Full Access
Question # 107

A protect team member is having difficulty delivering assigned tasks for a project that is at risk of being delayed The main issue is that the team member does not understand a new system that was recently implemented

What should the project manager do?

A.

Ask the team member to learn the new system as on-the-job training

B.

Issue a change request to extend the project schedule

C.

Escalate the team members performance to the project sponsor

D.

Assign an experienced resource to support the team member

Full Access
Question # 108

A major national company known for quality products has just selected a small subcontracting firm to assist with a project. The project manager from the subcontracting firm is meeting with the project team to ensure that the project is delivered according to the customer's standards

in order to ensure this, what should the project manager define and document?

A.

Quality

B.

Estimates

C.

Objectives

D.

Requirements

Full Access
Question # 109

An established project team with a good track record has been working on a project for one year The project manager trusts the team and the work they produce. Which term describes the project manager's management approach?

A.

Laissez-faire

B.

Transactional

C.

Transformational

D.

Charismatic

Full Access
Question # 110

At the end of a third planning meeting, the client and a functional manager requested additional meetings to add more features to the product.

What should the project manager do to start building the product faster?

A.

Allow the sponsor to determine how long the planning phase should last.

B.

Allow the client ta determine how long the planning phase should last.

C.

Ask the functional manager to work with the team to finalize planning and begin building the product.

D.

Explain that more features can be planned in upcoming Iterations and begin building the product.

Full Access
Question # 111

What should an agile lead do lo ensure their team is set up for success?

A.

Pay attention to team dynamics and understand that coaching is done simultaneously at an individual and whole-team level

B.

Schedule sprint meetings and coaching sessions to discuss project-related information

C.

Plan quarterly informal meetings or team bonding sessions to encourage the team to work together

D.

Document team tasks and challenges in order to understand when to step in and help a member of the team

Full Access
Question # 112

A project manager has recently joined an organization and notices that the engineering manager shouts at the project manager during project meetings Also the procurement manager will not return calls and the accountant always insists the project manager clears approved budget line items with them personally before expensing

Which three corrective actions should the project manager perform? (Choose three)

A.

Confront the people causing the stress directly with the aim of finding amicable solutions

B.

Seek support from the project management office (PMO) on addressing issues affecting the project

C.

Discuss the possible actions with the project sponsor

D.

Avoid the people causing stress and request a transfer as soon as possible

E.

Talk to the human resources (HR) manager about these concerns

Full Access
Question # 113

Due to a statewide emergency, a project team for a global insurance company is being forced to complete a project virtually, The project manager is tasked with conducting meetings where confidential patient information will be presented.

What tool should the project manager use to conduct meetings with the project team and clients?

A.

Use a third-party instant messaging tool.

B.

Use a password-enabled audio/video product,

C.

Use a popular social media platform.

D.

Use a collaborative electronic whiteboard,

Full Access
Question # 114

A project team has finished participating in an iterative product increment planning session. After the planning session, the team returns with a list of features to deliver.

How should the project manager ensure the product increments deliver the anticipated requirements?

A.

Appoint a dedicated product manager for the duration of the release

B.

Have the customer approve the product increment features.

C.

Ensure every user story has acceptance criteria.

D.

Track business outcomes for planned user stories.

Full Access
Question # 115

A project is delayed. The project manager added extra resources to some activities and approved overtime for several team members.

What technique is the project manager applying?

A.

Fast tracking

B.

Resource leveling

C.

Critical chain method

D.

Schedule crashing

Full Access
Question # 116

During the final iteration of the execution phase, the project has a cost performance

index (CP!) of 0.9 and a schedule performance index (SPI) of 1.0.

How should the project manager avoid a budget shortfall?

A.

Follow the risk management plan.

B.

Reduce the team effort utilization.

C.

Look for cost-saving opportunities.

D.

Submit a change request to add to the management reserve.

Full Access
Question # 117

A project manager is assigned to a time-bound internal project on quality improvement During project execution the project manager observes that a specific team member is being isolated by other team members

Which three actions should the project manager take? (Choose three)

A.

Allow team members to resolve personal issues without involving the project manager

B.

Arrange and conduct team-building sessions to improve team effectiveness

C.

Obtain feedback from the isolated team member to understand the situation

D.

Get feedback from other team members to understand what led to this situation

E.

Identify the isolated team member as a risk and document the situation in the risk register.

Full Access
Question # 118

A project manager is managing a project that is going to deliver a new risk platform. This platform will enable data-driven and new risk market models to ensure compliance with new regulations. The regulatory requirements for the models are released continuously and are not fully fixed yet. The project manager is reviewing the risk register and added a few new

Hems

Match the risks on the left lo the correct category on the right.

Full Access
Question # 119

A project manager notices that one of the marketing executives in the firm always appears stressed. The project manager observes that the executive's performance is gradually declining and is affecting the project deliverables.

What should the project manager do?

A.

Assign the marketing executive's tasks to another project team member

B.

Review the executive's declining performance with human resources (HR)

C.

Show empathy and praise the marketing executive's strengths

D.

Make the marketing executive accountable for their work and output

Full Access
Question # 120

Many issues have been encountered in a project due to the low competence of the team members. These issues might lead to poor project performance and potentially to project termination.

What should the project manager do?

A.

Organize a brainstorming session with the project team to address the issue.

B.

Advise the project team on the importance of team engagement,

C.

Invest in coaching and training for all project team members.

D.

Escalate the issue with the human resource (HR) department to take action,

Full Access
Question # 121

A new member was included on a project team in an ongoing software project. This team member was the only available resource but does not have the proper experience to accomplish the activities.

What should the project manager do to ensure this team member's lack of experience does not negatively impact the project?

A.

Schedule a training course for the new team member to fill in their gaps in experience.

B.

Log this as an issue in the project issue log and speak with the resource manager.

C.

Provide weekly feedback to all project team members, including the new member.

D.

Ensure that coaching meetings are in place for this team member within the project timeline.

Full Access
Question # 122

A protect is going through its iterative design stage One of the team members has been performing poorly. This is a critical project for the company and execution is about to start What should the project manager do?

A.

Request action from the functional manager regarding the team members poor performance

B.

Avoid selecting the team member to the next project that has an iterative design stage

C.

Provide feedback and coach the team member during the iterative design stage

D.

Escalate the issue to the human resources manager and request that the team member be replaced

Full Access
Question # 123

An agile team has completed 9 out of 10 stones tor the sprint. During the retrospective a few team members pointed out that they finished a of their stories However one team member tailed to finish a story

What should the agile leader do1?

A.

Emphasize to the team that each member is responsible for their story but the team is collectively responsible for finishing the sprint

B.

Ask the team to address this at the next sprint planning instead of at the retrospective

C.

Suggest that the team assign stones at the beginning of the sprint based on each person's strengths to maximize performance

D.

Work with the product owner to remove the story from the sprint because the points cannot be splits

Full Access
Question # 124

As a result of the first iteration review, the stakeholders' feedback indicated that they saw more technical features than business ones What should the project manager do?

A.

Include this topic in the next iteration retrospective

B.

Review this topic with the product owner before the next iteration planning

C.

Discuss this topic with the team in the next daily meeting

D.

Ask the product owner to review this topic in the next iteration planning

Full Access
Question # 125

A key challenge that a project manager is facing is the lack of discipline by various team members and their inability to harness energy to achieve the project objectives. What should the project manager do to overcome this challenge?

A.

Meet with each team member separately and apply an appropriate approach with each one.

B.

Approach the project sponsor and request help in discussing the project deliverables with team members.

C.

Explain to the team that the project manager is ultimately responsible for the delivery.

D.

Assign multiple managers to the various teams and delegate all of the tasks to them.

Full Access
Question # 126

A project manager is involved with a project to remodel a long-used product. There are no proper records for the original design and execution of the original product. The stakeholders doubt that the remodel can be accomplished without this information and are hesitant to provide support for the project.

What should the project manager do?

A.

Acknowledge the stakeholders’ concerns with open dialogues and realign the project with stakeholder requirements and past lessons learned.

B.

Solicit a larger reserve for cost and time and manage the stakeholders’ expectations.

C.

Create a plan to inform stakeholders on the progress so they are able to see that the project can succeed,

D.

Share the threats of not updating old solutions and ask stakeholders to be patient with any inconveniences.

Full Access
Question # 127

A project manager Is working on a project using a hybrid approach. The project Is scheduled to be completed in three more sprints. One of the team members notifies the project manager that they are leaving the company which was approved by their functional manager

What should the project manager do first in this situation'?

A.

Ask the functional manager why a decision was made without consulting them

B.

Use soft skills to influence the team member to slay until the project is completed

C.

Ask the functional manager for an immediate replacement for the team member.

D.

Review the risk management plan and mitigation plan to understand the impact of this issue

Full Access
Question # 128

Due to a tight schedule, a project team member suggests skipping the quality check of a minor deliverable. What should the project manager do?

A.

Evaluate the impact of skipping the quality check for the deliverable.

B.

Seek approval from the sponsor on an extension of the project schedule,

C.

Seek approval from the quality board to skip the quality check.

D.

Ask the team member to work overtime to complete the quality check.

Full Access
Question # 129

During the execution of a project, a company decides that everybody will need to take vacation time before the end of the year. This may cause a change in the project time line.

How should the project manager address the situation?

A.

Discuss the vacation plan and include scheduling changes in the change log database.

B.

Submit a formal request to senior management asking them not to proceed with this decision based on the impact it will have on the project.

C.

Agree with functional management and team members on a vacation schedule that would minimally impact the project schedule.

D.

Push out the project timeline according to the vacation plan in place based on the recent company policy.

Full Access
Question # 130

A project manager sent the first communication about the project management plan to the team. The next day. two field engineers were asking about their roles and the project schedule.

What should the project manager have done*?

A.

Confirmed that the communication was understood and solicited feedback from the team

B.

Sent the roles and responsibilities matrix along with the project management plan

C.

Discussed the roles with the managers to help explain them to their team members

D.

Briefed each team member on their roles before sending the project management plan

Full Access
Question # 131

A company has transitioned and is now delivering projects using a hybrid approach

instead of a predictive approach. The distributed project team's knowledge of agile is varied.

The project manager feels this new methodology will impact the timely delivery of the project.

What should the project manager do?

A.

Ask to execute the project with a predictive approach since there is a budget and schedule risk.

B.

Use crashing to reduce the critical path to ensure enough buffer to include the impact of the agile methodology update.

C.

Plan for training on agile tools and techniques used in the defined hybrid methodology

for consistent application by all team members.

D.

Use the predictive approach for team members who are not knowledgeable in agile project delivery practices.

Full Access
Question # 132

A company has undertaken a large transformation project using agile practices. The project sponsor has asked the project manager to promote the new values identified in the intended transformation to the project team

What should the project manager do?

A.

Add a user story during sprint planning that gives recognition to behaviors that are aligned with the new values

B.

Send a standard email to the team prior to every daily standup containing the new values

C.

Organize a team meeting focusing on the new values associated with the transformation

D.

Give recognition to team members' behaviors that are aligned with the new values during the sprint retrospectives

Full Access
Question # 133

A company's CEO complains about the frequency of project communications. The CEO receives five project reports each week by email but does not have enough time to review them. In addition, the information that the CEO receives is not relevant in that it does not explain the project status,

What should the project manager do first?

A.

Review the stakeholder engagement plan.

B.

Review the communications management plan.

C.

Send the CEO one executive summary per week instead of five reports per week.

D.

Meet with the team and decide the type and frequency of the reports to send to the CEO.

Full Access
Question # 134

One phase of a project took much longer than initially anticipated The key stakeholders expressed their concern regarding a potential project delay. What should the project manager do?

A.

Expedite the next phase to reduce slippage

B.

Add more float to the overall project schedule

C.

Request additional contingency from the sponsor.

D.

Organize a root cause analysis (RCA) workshop.

Full Access
Question # 135

During a kick-off meeting at the start of project execution, the vendor presents a

migration plan to client stakeholders. The director of the business unit that owns the solution being migrated demands the ability to make the final go/no-go decision about whether the systems go live.

What should the project manager do?

A.

Schedule a meeting with the director to provide proof of expertise so the client

stakeholders will trust the project team's decision.

B.

Schedule a meeting with the project sponsor to determine if it is appropriate to accept

the director's request to provide a decision.

C.

Confirm with the director that the client stakeholders will be made accountable for the

decision in the responsibility assignment matrix (RAM).

D.

Ask the client to initiate a change request to make the director accountable for the

decision.

Full Access
Question # 136

In an agile project, two key stakeholders disagree about a major new requirement. Recognizing that this could lead to potential issues, what should the project manager do next?

A.

Facilitate a meeting with the stakeholders and product owner to clarify the new need,

B.

Update the acceptance criteria documentation to clearly reflect what was approved.

C.

Review the new requirement and update all the stakeholders accordingly.

D.

Ask the two key stakeholders to agree on the requirement based on a Pareto analysis.

Full Access
Question # 137

A new project manager is assigned to a project that will deliver a new and optimized credit system. The project manager is allowed to use a hybrid approach which is new to the organization to manage the project and new tools

In order to deliver the project successfully, what should the project manager focus on as part of the plan?

A.

Align with the organization's project management office (PMO) to inform and make them aware of the new approach

B.

Explain and communicate the new approach to the project sponsor and key stakeholders

C.

Develop a detailed schedule for the entire project m the planning phase and communicate that to the stakeholders

D.

Communicate with other project managers to see how they manage hybrid projects

Full Access
Question # 138

A project manager is managing a hybrid project that is using a contractor for a few key deliverables. The contractor has been hired to perform an important delivery, but has not yet confirmed that they can meet the required schedule.

What should the project manager do?

A.

Escalate the issue to the procurement team as the final delivery date of the project will be impacted.

B.

Review the project scope with the stakeholders and remove the potentially delayed item from the scope.

C.

Plan the task delivery with the contractor or vendor, highlighting the criticality of the current situation,

D.

Check with procurement to see if there is another previously used contractor who can develop the task.

Full Access
Question # 139

A technical lead has complained to the project manager about a team member's performance. The team member has repeatedly missed tasks that have put sprint commitments at, What should the project manager do?

A.

Remove the learn member from the team and hue a more skilled one

B.

Ask the technical lead to provide more training to the team member

C.

Ask the technical lead to discuss performance directly with the team member

D.

Meet with the team member to understand the situation and provide feedback.

Full Access
Question # 140

Two companies recently merged. The team charter for a new initiative combines the best practices of both companies. One of the team members consistently ignores one of the rules.

What should the project manager do to address this concern?

A.

Schedule a dedicated session to review the team charter.

B.

Set up a meeting with the team member to review the team charter.

C.

Ask another team member to meet with this team member for a discussion.

D.

Send a reminder to the team member about the rule being violated.

Full Access
Question # 141

A project manager Is leading an agile software development project with strict deadlines The client complained that the last deployment did not meet the acceptance criteria The development team lead is arguing that the deployment met all specifications and has provided evidence of the client's specifications

What should the project manager do?

A.

Schedule a meeting with all stakeholders to understand what went wrong and who should be held responsible

B.

Review the requirements traceability matrix with the team lead and the client to adequately resolve the issue

C.

Meet with the client and discuss the project deadlines

D.

Seek approval for more time for rework and resolve the issue

Full Access
Question # 142

A project manager is working on a project that will transform the organization's operating model. The project manager reviewed the budget allocation for various phases and was informed that upper management will not approve any additional funds.

Knowing that there are no additional funds available, how should the project manager proceed?

A.

Allocate the budget to the phases of the project and meet with upper management to consolidate the final funds.

B.

Ensure that the budget is enough to cover the internal resources, since external supplies can be covered by procurement.

C.

Allocate the budget to the deliveries that have higher business value for the organization than those with lower business value.

D.

Decide to work on the small deliveries, leaving the big deliveries until the end of the project, and track critical expenses.

Full Access
Question # 143

During a project to develop a new pharmaceutical product, the project manager was informed that there has been a change in government regulations regarding the materials of the project.

What should the project manager do?

A.

Review the procurement documentation and modify requirements as needed.

B.

Study the new regulations with the team and evaluate if there is any impact on the

project variables.

C.

Update the contingency plan to take this issue into account.

D.

Meet with the stakeholders to update the risk register and risk management plan.

Full Access
Question # 144

A project is scheduled to end in 2 weeks. The team is expected to continue working long hours and is showing signs of weariness and fatigue What should the project manager do to encourage the team?

A.

Schedule training courses to enhance team performance

B.

Add new team members to help the project finalization

C.

Initiate rewards and incentives according to assessment results

D.

Schedule working lunch meetings until the project is complete

Full Access
Question # 145

An agile team is conducting a sprint retrospective and wants to focus on the practices that allowed them to recover after a bad start Please click on the area of the burndown chart that the team should focus on.

Full Access
Question # 146

A project manager finds an unexpected issue halfway through a customer's protect After analysis the project team determines that the issue will affect the timeline unless more resources are allocated to the project.

What should the project manager do?

A.

Meet with the project team to discuss internally whether they think cost is more important to the customer than the timeline

B.

Adjust the timeline since in the past the customer would not pay any additional costs then inform the customer of the change

C.

Inform the customer of the issue and discuss the options so that they are able to make a decision on cost versus timeline

D.

Absorb the additional cost for the additional resources internally so that the project completes within the timeline

Full Access
Question # 147

A project manager is building a team that will be comprised of subject matter experts (SMEs) from two different divisions of the same company.

The project team will be virtual and will include members from different countries around the world.

What should the project manager do to ensure effective team building occurs?

A.

Coordinate with team members to define and communicate ways of working, roles and responsibilities, scheduling, time zone, and cultural

observance information.

B.

Explain to the team that since they are all SMEs and know one another, they are expected to immediately collaborate and deliver effectively.

C.

Update the communications management plan and determine an issue resolution process for when furture conflicts arise.

D.

Colocate the team members at the beginning of the project to explain the expectations for team interaction, meeting schedules, and overall

project governance.

Full Access
Question # 148

A third-party supplier demands payment for the services provided for a project. The agreement was that payment would be made after the organization receives payment from the client. The third-party supplier lacks the capital to meet their payroll and has informed the project manager that if they do not receive payment quickly, they will withdraw team members from the project.

What should the project manager do?

A.

Process a bank loan to pay the payroll of the third-party supplier.

B.

Reassign resources from other projects to pay the third-party supplier.

C.

Explain the third-party supplier situation to the client and request payment.

D.

Inform the client that the project must be delayed until payment is received.

Full Access
Question # 149

A company is launching a new product and decides to transition from a predictive to an agile approach. During the third sprint the project manager notices that the team is not working as a cohesive unit

Which two rules are appropriate tor the project manager to instill in the team? (Choose two)

A.

Strive toward continuous improvement

B.

Work together daily as a team

C.

Only share suggestions at the end of the sprint

D.

Follow the sprint planning

E.

Send communications to the entire team

Full Access
Question # 150

A project manager works in a startup company and is in charge of a key project that has critical and time-sensitive delivery objectives. One of the project team members missed completing an assigned deliverable on time, despite repeated assurances from the team member that it would be completed on time

What should the project manager do next?

A.

Record the issue then refocus the team's efforts on delivering the next set of deliverables

B.

Give the team member a formal warning for the negative impact due to failure to delrver and not meet deadlines

C.

Hold a team meeting to discuss team member commitments and communications

D.

Meet with the team member and work on a development plan for them to avoid missed deliverables in the future

Full Access
Question # 151

During project execution for an innovative product, a project team has been working hard to meet the deadlines. However, one of the team members will be leaving in 3 weeks and will be replaced with a new team member.

How should the team share tacit knowledge?

A.

Provide the new member with access to the knowledge database so all of the project documentation Is available.

B.

Have the team meet on a regular basis and share their experiences, challenges, and lessons learned.

C.

Ask the new member to document all of the requirements so a better understanding of the project objective is acquired,

D.

Provide the new member with the project documentation repository to allow the new member to review previous lessons learned, Owner

Full Access
Question # 152

In a standup meeting a team member has been providing the same update for five consecutive days. The task which is on the critical path is now at risk tor delaying the schedule. What should the project manager do?

A.

Reassign the task to another member of the team

B.

Support the team member by providing one more resource to complete the task immediately

C.

Ask the team member if there is an impediment and help to remove the blockers

D.

Keep the project sponsor informed about the delay

Full Access
Question # 153

A construction services company has influence within the local community with the potential to derail a project site establishment. Their build was unsuccessful but they continue to communicate with the hope that their influence will persuade the project manager to reconsider their offer.

What is the appropriate course of action for the project manager to pursue?

A.

Do not communicate with the unsuccessful bidder as they do not have any further influence on the project

B.

Meet with the unsuccessful bidder to review their submission and the areas that led to the bid being unsuccessful

C.

Reassess the bid to establish areas for improvement with the intention to assign work to this contractor

D.

Report the unsuccessful bidder to the local community leadership who have been supportive of the project

Full Access
Question # 154

It is late at night on a weekend when a team member calls the project manager on the telephone. The team member Is crying about the pressures of an upcoming deadline.

What should the project manager do?

A.

Ask the team member to send their concerns in writing.

B.

Empathize with the team member and discuss next steps.

C.

Review the organization's human resources (HR) policy.

D.

Schedule a meeting with the team member for the next work day.

Full Access
Question # 155

A company wants to launch a new product for customers. The project for this new product is in the development phase. Due to an uncertain environment, the project manager has

doubts about the feasibility of the project.

What should the project manager do in this situation?

A.

Validate assumptions using appropriate tools to assess the risks.

B.

Refer to the lessons learned to determine the impact on the external environment.

C.

Recommend postponing the project until the uncertainty is resolved,

D.

Highlight the concern to the project sponsor in the next project review meeting,

Full Access
Question # 156

A project manager noticed that the functional manager is not cooperating with staff assignment schedules and is always finding excuses not to release the requested staff. What should the project manager do first?

A.

Ask the leadership team for help obtaining the needed staff.

B.

Have a direct talk with the functional manager to understand the reasons behind their attitude.

C.

Evaluate the impact caused by the delay of forming the team and confront the functional manager.

D.

Check with human resources (HR) regarding the availability of staff.

Full Access
Question # 157

A team averages 100 story points per iteration. The team estimates there are about another 2,000 points remaining and about 20 iterations remaining. One of the team members suggests estimating by feature because the large stories are difficult to break up.

What should the project manager do?

A.

Meet with this team member.

B.

Review this method with the team.

C.

Accept this task-based estimation.

D.

Reject this task-based estimation.

Full Access
Question # 158

A project learn member is having difficulty delivering assigned tasks for a project that is at risk of being delayed. The main issue is that the team member does not understand a new system that was recently implemented.

What should the project manager do?

A.

Assign an experienced resource to support the team member

B.

Escalate the team member's performance to the project sponsor

C.

Ask the team member to learn the new system as on-the-job training

D.

Issue a change request to extend the project schedule

Full Access
Question # 159

One of the risks identified during project planning activities is related to a component from a preferred vendor. The component utilizes new technology, and there is a possibility of incompatibility with other parts of the system that are being developed.

What should the project manager do?

A.

Create a risk probability matrix to address the incompatibility.

B.

identify an alternative component in case of incompatibility.

C.

Use the contingency fund to redesign the interface if it is incompatible,

D.

Require the vendor to redesign the incompatible component to fit the system.

Full Access
Question # 160

A Scrum team has committed to delivering a specific capability in their first release Multiple operational issues have prevented the developer from delivering key capabilities. The technical lead has also given notice that they are resigning from the company

What should the project manager have the Scrum team do to recover from these issues?

A.

Review constraints in the ongoing sprint planning and evaluate options for the release plan

B.

Stop the sprint and replan and prioritize the backlog to reduce resource levels

C.

Consult the resource management plan for an appropriate response

D.

Continue with existing sprint plans to ensure some of the scope will be delivered

Full Access
Question # 161

During the course of a project, the team develops negative group behaviors and becomes unmotivated and unproductive. What should the project manager do to improve the project team's performance?

A.

Define and analyze performance metrics

B.

Escalate poor performance to functional managers

C.

Update the stakeholder engagement plan

D.

Conduct a root cause analysis session

Full Access
Question # 162

A team member misses a project meeting without it being approved and has been penalized as defined in the ground rules. This team member, as well as other team members, insist that it is the first time they have seen this rule regarding the project and they do not agree with the penalty

What should the project manager have done to avoid this situation?

A.

Ensured the team charter was developed by the team members

B.

Ensured the team members are fully supportive of all decisions.

C.

Distributed the project charter to all team members.

D.

Used a charismatic leadership style

Full Access
Question # 163

During daily calls team members share task progress One team member does not usually communicate many details and has critical tasks to be completed All team members are located in different countries and critical work is about to start Which two options will help the project manager in this situation? (Choose two)

A.

Encourage all team members to use a virtual workspace

B.

Ask the team to send emails with detailed task progress

C.

Talk to the team member about their engagement and take appropriate action.

D.

Reassign the work to a resource who participates in the daily calls

E.

Report the team member’s poor performance to the functional manager

Full Access
Question # 164

A new project manager is planning an information security project for a company that resides in different countries. What is the first step the project manager should take to gather customer requirements?

A.

Conduct a stakeholder analysis to identify how regional policies may influence needs

B.

Request relevant stakeholders to conduct an analysis and reach consensus independently

C.

Conduct a project scope review workshop with relevant stakeholders.

D.

Conduct project planning meetings in one location with relevant stakeholders

Full Access
Question # 165

The project team finds that the latest delivery from a vendor is missing a critical component, which will likely delay the project in split of corrective measures. What should the project manager do to communicate this message?

A.

Ask the vendor to identify the stakeholders affected, create an action plan and determine an implementation date

B.

Draft a warning letter to the vendor ask internal stakeholders to comment, and solicit stakeholder support to hold the vendor accountable

C.

Identify the worst-case scenario, put it into the project risk register, share the register with all project stakeholders, and raise an alert.

D.

Contact department managers who are identified as stakeholders, solicit concern, and provide updates to the situation

Full Access
Question # 166

Drag the communication event on the left to the mam subject discussed during the event on the right.

Full Access
Question # 167

A company is implementing a new system The project manager has identified that it is best to complete this project using a mix of Scrum and Kanban methodologies The product owner is confused as to how to start delivering the functionalities required

How should the project manager assist the product owner?

A.

Coach the product owner on how to create a product backlog

B.

Encourage the team to subdivide the project tasks

C.

Create a work breakdown structure (WBS) and explain the deliverables to the product owner

D.

Discuss the product owner's responsibilities within the project team

Full Access
Question # 168

During the course of a project, the project manager wants to ensure that the work carried out and the product being created do not deviate from the prescribed business value.

What should the project manager pay special attention to in order to achieve this goal?

A.

Reviewing and updating the requirements management plan

B.

Carrying out quality audits and failure analyses

C.

Monitoring the work breakdown structure (WBS)

D.

Monitoring and updating the benefits realization plan

Full Access
Question # 169

The project manager is experiencing delays with two critical tasks that are to be executed by two different teams The project manager realizes that the functional managers of these two teams have an unsolved conflict and they are not communicating properly.

What should the project manager do?

A.

Arrange a meeting with the managers and try to reach an agreement.

B.

Communicate with the project sponsor regarding the need to resolve the conflict between the managers.

C.

Evaluate the impact of the delay on the project and look for alternatives to create a remediation plan

D.

Meet with both teams and their managers and try to figure out the root cause of the conflict

Full Access
Question # 170

A team is currently working on a mobile app solution. During sprint execution, one of the developers requires clarification about the acceptance criteria for a particular task

What should the project manager do to obtain the information required by the developer?

A.

Request direction from the project sponsor

B.

Write an email to the client requesting clarification

C.

Seek support from the development manager.

D.

Work with the product owner to clarify the requirement

Full Access
Question # 171

The change control board (CCB) rejects a change request submitted by a subject matter expert (SME) The SME refuses to accept this rejection and does not want to continue the project without the change

What should the project manager have done to avoid this situation?

A.

Requested that the sponsor approved the change request first.

B.

Assessed the change's overall impact to the project before submission

C.

Ensured that the change request was aligned with the project scope

D.

Submitted the change request directly to the CCB

Full Access
Question # 172

One team member is not as active as the rest of the team during a brainstorming session The project manager has a separate conversation with the team member and learns that the team member is slightly hearing impaired The team member appreciates the project manager's concern The project manager then decides to change the time and room for the meeting to ensure everyone can participate

What interpersonal skill did the project manager use?

A.

Networking

B.

Emotional intelligence

C.

Conflict management

D.

Influencing

Full Access
Question # 173

A project manager is managing a hybrid project After attending an iteration review, a stakeholder tells the project manager that they are very busy and asks why these reviews are held so frequently.

How should the project manager respond'?

A.

Negotiate a reduced review attendance with the stakeholder and update the stakeholder engagement plan to reflect this reduced attendance

B.

Discuss with the stakeholder the benefits of the hybrid project and how frequent reviews lead to greater value and less rework

C.

Record the issue in the issue log and escalate the conflict to the project sponsor for assistance

D.

Explain to the stakeholder that the stakeholder engagement plan requires their

attendance at all reviews

Full Access
Question # 174

A company's new communication system will include online dashboard reporting. The executive board might receive bi-weekly performance reports through the online dashboard What should the project manager do?

A.

Review the project management plan

B.

Update the stakeholder engagement plan.

C.

Update the communications management plan

D.

Review the configuration management plan.

Full Access
Question # 175

A company's project management office (PMO) has been trying to implement an adaptive approach in the project management framework and a project manager has been asked to use adaptive tools in their next project This is not the first time the request has been made and the previous project failed when adaptive tools were implemented

What should the project manager do?

A.

Prepare a change request and seek approval from the steering committee regarding the new project framework

B.

Conduct individual interviews with key stakeholders in order to understand all concerns, then prepare a communications management plan

C.

Bring in a third party company to develop and implement a hybrid framework for this specific project.

D.

Recommend to the PMO that it is not the right time to start implementing adaptive tools in projects

Full Access
Question # 176

A project manager who is new to an organization observes that an approaching deadline is likely to be missed because there have been some delays on the project due to a lack of resources. What should the project manager do next?

A.

Review the milestone list to determine which tasks can be fast-tracked

B.

Review the risk management plan to identify the response strategy

C.

Escalate the issue to the sponsor and debrief them about the situation

D.

Organize a team meeting to discuss the next course of action

Full Access
Question # 177

A company has decided to implement a new archiving system A data breach occurred during the implementation of the project

What should the project manager do first?

A.

Implement the planned risk response to handle the issue.

B.

Review possible alternative documentation methods with team

C.

Update the risk register with the risk and proposed impact.

D.

Ask the team to fix the system to resolve the issue

Full Access
Question # 178

A project has a very tight delivery schedule The project is approaching the delivery date and the project sponsor often sends the project manager alerts to avoid any schedule slippage The project team has performed at an acceptable level until now but the project manager wants to ensure the team's performance level is maintained until the end

What action should the project manager take to motivate the project team’s performance?

A.

Send a formal notice to team members instructing them to maintain performance

B.

Hire a few temporary team members to help with the additional work

C.

Award certificates of appreciation to encourage the team

D.

Inform the team about the delivery pressure from the project sponsor

Full Access
Question # 179

A new agile team is forming and the project manager notices that the team is struggling in many areas The team is experiencing both the inability to meet iteration commitments and team member conflicts

What should the project manager do next?

A.

Raise the issues in the retrospective and propose solutions

B.

Inform management that commitments will not be met.

C.

Involve management to help resolve the conflicts

D.

Coach the team both as a whole and individually

Full Access
Question # 180

Two functional managers disagree on key features of one deliverable during the planning of a project The project manager discovers that each manager included requirements that contradict each other The functional managers do not want to meet with each other to find a solution This situation has been escalated to the sponsor who requests a meeting with them

What strategy should the project manager use to resolve this conflict in the meeting?

A.

Explain to the managers that the contradicting requirements are being considered for implementation in the project

B.

Explain to the managers that only one of the two requirements can be implemented, and submit a change request,

C.

Ensure that both managers understand the requirements and search for a solution that best satisfies this deliverable

D.

Request that the managers explain why each requirement must be implemented and decide by considering the cost and benefits

Full Access
Question # 181

A project manager is appointed to simultaneously deploy a new solution to branches located in different countries Deployment teams in each country will integrate and deploy the solution The project manager discovers that the deployment teams each encounter similar issues However, each team addresses the issues separately

What should the project manager do to help ensure more collaboration between the teams?

A.

Organize regular meetings with all of the deployment teams to share issues and solutions

B.

Propose that some of the teams delay deployments in their countries

C.

Ask the project sponsor to appoint new managers for the deployment teams

D.

Ask each deployment team to provide a very detailed schedule and action plan

Full Access
Question # 182

The project manager is having difficulty communicating with one of the team members The team member recently attended a training course and has been training other team members in a new agile technique However sometimes the team member is forceful in pushing ideas even if other team members are uncomfortable

What personality indicators should the project manager consider when determining what communication style to use with this team member?

Full Access
Question # 183

After reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months. Based on the new timeline, what should the project manager do?

A.

Plan for overtime apply crashing and fast tracking and share the risk of failure with project stakeholders

B.

Review the project backlog looking for high-priority items and come up with a minimum viable product (MVP) that fits the expected timeline

C.

Seek approval with the sponsor to triple the project budget, hiring more people to compensate for the compressed schedule

D.

Go over the critical path with stakeholders, explaining why it is not possible to deliver all the scope in the expected timeline

Full Access
Question # 184

A few months into a project, several schedule issues have emerged Drag the schedule problems on the left to the specific tools on the right that if implemented during schedule development could have prevented the issues.

Full Access
Question # 185

A project manager for a maintenance project has a contract that is renewed annually The project started 6 years ago After contract renewal this year the auditors reported that this version of the contract violates a new law that was passed last year

What has happened in this situation?

A.

The contract has not been appropriately reviewed by the project team

B.

The stakeholder engagement plan has not been correctly implemented

C.

The legal department has not disseminated the law correctly to all staff.

D.

The project manager does not have enough knowledge on this legal matter

Full Access
Question # 186

The project sponsor on an agile project informed the project lead that an executive would like an update on the project’s progress What should the project lead do?

A.

Provide a link to the project's shared drive for the executive to search through for any artifacts that are of interest.

B.

Invite the executive to the project's meeting space to determine if the project information radiators meet their needs

C.

Reach out to the project management office (PMO) for status report templates and provide project updates in that format

D.

Ask the project sponsor or product owner to provide an update since the project lead should be trying to keep the team free from impediments

Full Access
Question # 187

A hospital is running a project for one of their internal critical systems to manage billing patient data and record management along with consultation reports and input from physicians The project manager now needs to categorize the identified risks

Drag each risk type on the left to its correct example on the right

Full Access
Question # 188

A project manager is struggling to figure out the performance of the project teams in an agile environment for the same scope of work, team A has calculated 100 story points and team B has calculated 125 story points

Which team is performing better?

A.

Team A as they have calculated fewer story points than team B.

B.

Team B as they have calculated more story points than team A

C.

The team that completes the most stories selected from the sprint backlog

D.

The team with the least amount of defects in their deliverables

Full Access
Question # 189

One of a project manager’s team members is continuously improving This team member has been a role model and mentor to others in the organization

How should the project manager acknowledge this team member’s commitment?

A.

Send this person to a meeting to negotiate the scope with the client

B.

Appreciate this team member’s performance throughout the project life cycle

C.

Promote this team member to a coaching role after this project is completed

D.

Document it in the team member’s end of year performance review

Full Access
Question # 190

A technical manager newly appointed by the client, visits the project site to verify the project deliverables The technical manager feels that the project manager has not been providing enough information

What should the project manager do first to resolve this situation?

A.

Update the issue log and escalate to the project sponsor

B.

Identify the lack of information as a risk and update the risk register

C.

Schedule more frequent meetings with the technical manager.

D.

Review and update the stakeholder engagement plan

Full Access
Question # 191

A company wants to increase the commercial value of one of its products in a highly competitive market In order to do this, the company commissions a project to create a prototype The team constructs the prototype incrementally Which action should the project manager take as a priority?

A.

Emphasize the use of Kanban methodology.

B.

Ensure the project sponsor is aware of the go-to market date

C.

Deliver business value as soon as possible

D.

Implement a plan-do-check-act (PDCA) cycle

Full Access
Question # 192

Team members are having a discussion with the project manager In the last retrospective meeting, the team realized that the obsolete equipment could affect the next iteration of the project The team recommends buying new equipment because it is critical to the success of the final deliverable

What should the project manager do next?

A.

Check the project budget to verify if there is enough contingency reserve

B.

Review the cost management plan to determine how to address this issue

C.

Tell the team members that more equipment is not part of the project's scope.

D.

Submit a change request to increase the budget and buy new equipment

Full Access
Question # 193

During a project’s third iteration, two of the existing team members were replaced As the project entered the next iteration, the team velocity dropped and the performance started to slip.

What should the project manager do?

A.

Guide the team to revert back to the forming and storming stages

B.

Escalate the issue to the project sponsor.

C.

Convene a team building event to address key performance indicators (KPIs).

D.

Discuss the decrease in productivity with human resources

Full Access
Question # 194

A project team with members from many different countries is struggling to cooperate The project manager accepted these difficulties during the storming phase of team development, but the team has not moved to the next phase The project is beginning to fall behind schedule

What can the project manager do to move the team to the norming phase?

A.

Plan social activities to help foster stronger interpersonal relationships and identify shared goals.

B.

Speak with the project sponsor about changing the team composition

C.

Figure out who is behind the issues and apply progressive disciplinary techniques.

D.

Show the team the schedule impact of their communication issues and encourage them to put their differences aside

Full Access
Question # 195

For the purposes of quality assurance a quality audit was conducted on the processes being used in the project execution plan. One of the nonconformance issues raised by the auditor was that attendance lists for the project risk review meetings were not available

Why is an attendance list important?

A.

It is standard practice on projects to conduct risk review meetings which should have records on meeting attendance

B.

The attendance list is evidence that risk review meetings were held with the appropriate project team members

C.

It is a record that shows the number of attendees in the meeting

D.

It is a document that is registered within the lessons learned register

Full Access
Question # 196

In analyzing a project for monthly status reporting, the project manager notices that the schedule performance index (SPI) is 0.75 and the cost performance index (CPI) is 1 25 The project manager must provide the first project status review soon and wants to emphasize that the project is under control

How should the project manager report the project status to key stakeholders?

A.

Prepare a detailed presentation for stakeholders on earned value including how it is calculated and the project's current earned value results

B.

Report that the project is behind schedule but that an additional experienced resource can be added to stay within schedule and maintain the budget.

C.

Perform a detailed root cause analysis utilizing a pareto chart and fishbone diagrams to demonstrate that the project is under control.

D.

Report that the project is not tracking as expected, but is still under control since the next project milestone is over a month away

Full Access
Question # 197

The team has reported the following impediments at the daily standup meeting Drag each impediment on the left to the action that the project manager needs to take on the right

Full Access
Question # 198

A project manager has been using predictive methodology for more than 10 years and is switching to an agile project. The team members have not previously worked together. After two sprints of work, the team has not achieved any outcome and there is a lot of pressure to get work done

What kind of leadership style should the project manager use at this stage?

A.

A directive style that makes decisions for the group to reach early outcomes

B.

A leadership style that coaches people who want help and fosters greater team collaboration

C.

A passive leadership style that allows the team to self-organize until the norming stage is reached

D.

A democratic style that uses techniques where majority opinion prevails

Full Access
Question # 199

A newly formed team has become accustomed to agile practices The project lead has noticed that while they are performing according to expectations, there is boredom with daily team practices among many of the team members.

What should the project lead do in this situation?

A.

Challenge the team to find new ways to achieve higher levels of performance to improve the situation.

B.

Speak with individual team members to determine what they would like to do to improve the situation in the team

C.

Have the team inform senior management of the situation and ask for recommendations.

D.

Allow the team to self-organize and have them analyze the situation in their retrospective session and self correct

Full Access
Question # 200

A company's project management office (PMO) has started to implement iterative tools A project manager is starting a new project and has identified an opportunity to use the iterative tools One of the senior managers is concerned about this modified framework as it is fairly new to the company

What should the project manager do first?

A.

Organize individual sessions with the stakeholders to build awareness and trust in the new framework

B.

Look for external training on the new framework to eliminate the risk of low engagement from stakeholders.

C.

Send documentation to the senior manager about the advantages of the new framework

D.

Escalate the senior manager's concern to the project sponsor and distribute the status to the team

Full Access
Question # 201

A project for Company A was successfully delivered within scope schedule, and budget by the end of the last iteration However during the project celebration ceremony, one of the business stakeholders says they perceive the project as a failure as it did not add any business value.

What should the project manager have done to avoid this perception?

A.

Involved the business stakeholders in the sprint review

B.

Defined product backlog priorities with the sponsor and key stakeholders to deliver business benefits

C.

Implemented a closing survey for key stakeholders

D.

Confirmed that there is a communications management plan in place to make business stakeholders aware of the success

Full Access
Question # 202

A project manager who is managing a critical project in a multinational company is conducting a progress meeting with all team members. During the meeting, one of the team members states that they are facing a critical problem that will prevent them from completing their assigned task

What should the project manager do?

A.

Ask the team member to follow the approved communications management plan to communicate their issue

B.

Schedule a meeting with the concerned team member to review and update the issue log together

C.

Review the risk register with the team member to find the proper response action for this issue.

D.

Ask the team member to raise a change request to assess the issue in detail

Full Access
Question # 203

A project manager is assigned to a project in a company that is transitioning to agile Not all stakeholders believe in the project, and some stakeholders would like the entire project defined and planned out early in the project However the project sponsor needs a quick win to ensure the continuation of the project.

What approach should the project manager use?

A.

An agile approach as this would provide working functionality earlier

B.

A predictive approach as this would please the senior stakeholders

C.

A hybrid project as this will mitigate stakeholders' concerns.

D.

A predictive approach as this will show benefits for all stakeholders

Full Access
Question # 204

A retail chain is evaluating a project to replace payment systems across all its stores in multiple locations The project does not pass the financial threshold but is also expected to increase market share, improve customer services and retain more customers The project is planned as a phased implementation building on learning from the retrospectives during each phase

How should the business increase the value of the project?

A.

Quantify the expected tangible and intangible benefits in the benefits management plan for each phase

B.

Ask the benefits owner to reassess the identified risks that are impacting the outcomes of the financial benefits.

C.

Consult with experts on methods to reduce costs and increase the financial value of the project

D.

Use a fishbone diagram to find the root cause of the lower financial benefits with the benefits owner

Full Access
Question # 205

In an industrial plant, the owner has decided to add more capacity to the plant by installing a new machine and updating the software used in production. This capacity enlargement will occur while the plant is still functioning and producing The software update will be accomplished using an agile approach in order to minimize risk The machine procurement, installation, and integration will be accomplished using predictive approaches

What types of communications will the project manager have to design into the schedule management plan to ensure the project will be on schedule'’

A.

Weekly colocated meetings with the relevant stakeholders

B.

Biweekly conference calls with the relevant stakeholders

C.

Weekly one-on-one meetings with each of the relevant stakeholders

D.

Biweekly written status reports from the relevant stakeholders

Full Access
Question # 206

An agile team is geographically separated across multiple continents, and the project manager of identifying the tools to manage the communication among the virtual teams Drag the appropriate tool on the left to each project task on the right

Full Access
Question # 207

A project manager is working on the implementation of new phases in the production process of a regulated industry. Which two stakeholders can help the project manager determine and address compliance requirements? (Choose two)

A.

Risk steering committee

B.

Functional managers

C.

Board of directors

D.

Advisory team panel

E.

Chief executive officer

Full Access
Question # 208

A project manager is managing a complex research project with a high level of uncertainty A request is made to implement a mechanism to measure the quality of the deliverables.

Using a hybrid approach, what techniques can be used to achieve this goal?

A.

Daily Scrum and product owner quality assessments.

B.

Scrum master reviews and the quality Kanban method

C.

Paired work and the customer role method.

D.

Time-boxed iterations and standup review meetings

Full Access
Question # 209

An agile project is in its eighth iteration out of 16 After the last iteration review, the team members receive feedback from the security department about regulations with which the project must comply

Which two actions should the project manager take? (Choose two)

A.

Ask the team members to analyze the impact of including this regulation

B.

Ask the stakeholders about the priority of this regulation

C.

Ask the product owner to include the requirements in the product backlog

D.

Ask the security department for details about regulations

E.

Ask the team members to include the requirements in the next iteration

Full Access
Question # 210

A project manager is assigned to a project within a program. The high-level requirements of the project are known, but the priorities of some of the requirements are uncertain as they are interdependent on some other pipeline projects within the program.

How should the project manager prepare for the next steps of the project?

A.

Escalate to the management team to increase the timeline based on the complexity of the project

B.

Wait for the other project estimates before planning the schedule

C.

Prioritize and estimate the milestones for the high-level requirements based on historical data

D.

Ask the project management office (PMO) to estimate the tasks for all the projects and share the project management plan

Full Access
Question # 211

The project manager has learned that the project sponsor is unhappy with the development of the project requirements In order to realign the project with the sponsor's expectations, what should the project manager do?

A.

Review the project goal diagram with the team.

B.

Perform a stakeholder evaluation

C.

Confirm which templates the team should be using

D.

Review the risk management plan

Full Access
Question # 212

Drag the characteristics of the stage on the left to the correct Tuckman Ladder stage on the right

Full Access
Question # 213

A project manager led the implementation of an electronic invoicing project that has just been completed. The financial manager communicated that the team discovered three invoices with errors.

Which two documents should the project manager update as soon as possible? (Choose two)

A.

Issue log

B.

Risk register

C.

Stakeholder register

D.

Change log

E.

Backlog register

Full Access
Question # 214

During project execution, a conflict occurs between the project manager and one of the team members at every project team meeting The ongoing conflict is preventing tasks and deliverables from being completed The project manager contemplates changing their leadership style

What should the project manager do?

A.

Review the set of responsibilities with the team member

B.

Avoid the team member to prevent further conflicts

C.

Escalate the situation to the project sponsor

D.

Review the personnel skill documents

Full Access
Question # 215

A new project manager is assigned to a project midway through its implementation During the first risk review meeting, the project manager notices that the version of the risk register used by the project team members is different from the one the project manager is using

What should the project manager have done to avoid this issue?

A.

Referred to the communications management plan

B.

Validated the issue log

C.

Validated the project artifacts

D.

Performed expert judgment

Full Access
Question # 216

The product owner decides to launch a product after a couple of releases knowing that the minimum viable product (MVP) lacks some features One of the key stakeholders the marketing vice president is not happy with the results and questioned the release decision.

What should the project manager do?

A.

Support the product owner's decision and seek better alignment with this stakeholder in order to avoid this type of issue in the future

B.

Coach the team on the decision-making process, assuming a risk-averse strategy towards product releasing

C.

Assume the responsibility for product releases making the final call on when something is ready for customer launch

D.

Escalate the issue to the sponsor questioning the authority of the key stakeholder regarding the product launch decision

Full Access
Question # 217

During the implementation phase of a project, a new regulation affects the project, and a critical status meeting discussing the scope changes is required. The project manager discovers that a key stakeholder cannot attend the scheduled meeting

What should the project manager do?

A.

Call for a change control board (CCB) meeting, and inform the stakeholder about the outcome

B.

Update the communications management plan and implement the change

C.

Meet with the project sponsor to discuss how to address the situation.

D.

Meet with the stakeholder prior to the meeting to obtain their opinion

Full Access
Question # 218

A project manager is acting as a scrum master in a hybrid project and is dealing with a conflict between team members What strategy should be used to handle this conflict?

A.

Sort conflicts into two groups: positive and negative

B.

Place conflicts into categories: structural and interpersonal.

C.

Place conflicts on a shared conflict list and ensure it is visible

D.

Review conflicts during daily Scrum so they are handled in a timely manner

Full Access
Question # 219

A project manager finished reviewing the project deliverables for the current iteration with the customer A new key stakeholder who just joined the customer's team, complains that the results do not provide the capabilities the business anticipated

What should the project manager do to address this issue?

A.

Create a change request and update the scope management plan

B.

Conduct stakeholder identification and a project objectives review session

C.

Update the stakeholder list and fix the deliverables

D.

Update the project management plan and lessons learned

Full Access
Question # 220

A project manager is assigned to lead a newly formed agile team. The functional manager has assigned tasks to team members, but the team members do not feel empowered.

How can the project manager promote empowerment and accountability among the team?

A.

Assign the tasks individually based on the role of the team member to ensure expertise on the subject.

B.

Encourage and assign the team to perform demos of their products or software with the customers

C.

Give the team autonomy to make their own decisions on how to perform the tasks.

D.

Encourage the team to keep the product owner involved when choosing ways to resolve the given task

Full Access
Question # 221

A project manager is working on a software development project. A team member complains that since the project tasks are very simple, there is no reason to perform quality control The project manager understands that removing the quality management plan from the project will also help to save money, which is important to the customer

What should the project manager do?

A.

Register starting the project without a quality management plan as a risk, and allocate the budget savings to the management reserve

B.

Develop the quality management plan, as quality is as equally important as cost and schedule management.

C.

Get confirmation from management that the team member has enough experience

to build software without quality control

D.

Ask the customer to order an external quality audit after accepting the project deliverable, and decrease the budget of the project

Full Access
Question # 222

A global petroleum crisis has affected the distribution of crude oil in the region where the construction project is underway Materials are not being delivered on time and this phase of construction is already behind for what was initially planned.

What should the project manager do first to prevent the project from going further off track?

A.

Perform a risk assessment and define a risk response action plan.

B.

Proceed with the project using management reserves to cover any delays or losses.

C.

Propose a pause in this phase to save labor costs and asset depreciation.

D.

Establish new partnerships with other suppliers in anticipation of any delays.

Full Access
Question # 223

While managing a project, the project manager has just noticed that the last several monthly invoices have been challenged by the client when they were clearly defined The actual invoice payments received have also been late and were outside of the contracted payment schedule Recent invoices have only been partially paid

What should the project manager do?

A.

Add nonpayment to the issue log and keep tracking payments

B.

Hold a meeting with the client to address the issue

C.

Review past projects for payment-related lessons learned

D.

Conduct a meeting with the project team to update the procurement management plan

Full Access
Question # 224

A project manager joins a team that is providing a customized enterprise resource planning (ERP) system to a client A potential design problem is identified by the development team After reviewing this issue with the project owner and team members, all agreed to revise the design to avoid a system defect when deployed The design is already approved.

What should be the project manager's next steps?

A.

Conduct a proof of concept to make sure there are no problems in the revised design

B.

Amend the design specifications and pass them to the development team for reprogramming

C.

Make a change request and get format approval from the project owner

D.

Inform the client of the problem and follow the change request process

Full Access
Question # 225

Important projects in the portfolio backlog need to be delivered Budget estimates are needed to prioritize the projects How should the project budgets be estimated'?

A.

The project is decomposed into features and based on the feature value and the velocity of the team, the team provides the estimate

B.

Budget estimates are provided based on the experience of the sponsor, product owner and team facilitator

C.

The team facilitator uses historical data and arrives at an estimate based on the nature of the project.

D.

The product owner obtains all project details and based on the team's experience and velocity provides a budget estimate

Full Access
Question # 226

After a couple of iterations the project manager decides to present the product to a key stakeholder The stakeholder's feedback is that the team missed the mark on many features

What should the project manager do to avoid this in the future?

A.

Set up requirements-gathering sessions with all key stakeholders to evaluate the scope once again and reprioritize the backlog based on the sessions.

B.

Schedule adequate sprint demos to gather early feedback from the stakeholders and adapt the plan accordingly

C.

Incorporate design thinking practices into the project life cycle to better understand the product's personas and be more effective to match their needs.

D.

Evaluate the team's skills to look for someone with experience in product design and assign that person the task of rebuilding the product interface

Full Access
Question # 227

A company was awarded a project in a dangerous location that poses several high-level risks for employees Help is needed to tram the employees on major safety and health factors The project is ongoing and uses a hybrid approach The project will be conducted in multiple sites, with several development iterations running in parallel

How should the project manager handle this situation?

A.

Allocate and use part of the project's contingency reserves for training purposes.

B.

Negotiate a contract and form a partnership with a local authority for medical and security support services.

C.

Perform a retrospective and update the risk register and resource management plan regarding the necessary budget for training

D.

Hire only local resources who are aware of the terntory's hazards, providing employment to the local community

Full Access
Question # 228

A new project manager for an agile project is reviewing with an established team, some of the roles to avoid confusion on what to expect. Drag the description on the left to the role on the right

Full Access
Question # 229

A project manager is worried that a key stakeholder is not participating in the project and has concluded that the final product is not as good as it could have been if the stakeholder had been more involved Drag the scenario on the left to the correct risk response strategy on the right

Full Access
Question # 230

A project team is engaging a development team in another country to develop software. During progress reviews, the project manager identified completion date delays due to rework because there were different interpretations of the client's needs.

What should the project manager do?

A.

Set up a meeting with key stakeholders to clarify requirements

B.

Escalate to the project steering committee and request additional time

C.

Travel to the development team's office to push the schedule

D.

Create prototypes with the development team to confirm requirements

Full Access
Question # 231

During the execution of a project the project manager notices that only one team member has one of the technical skills needed to build the product The project manager is afraid this might have a future impact on the quality and schedule because most of the upcoming activities will require at least three people with this specific skill.

What two actions should the project manager take to prevent the team from being unqualified? (Choose two)

A.

Exclude the activities from the roadmap

B.

Encourage working in pairs and knowledge sharing

C.

Teach the entire team the new skill.

D.

Facilitate a training event with an external trainer

E.

Increase the time estimates on the activities that require such abilities

Full Access
Question # 232

In an advanced stage of a project a stakeholder who is not receiving the project status report communicates this to the project manager After checking, the project manager determines that the person is registered as a stakeholder but was not included in the communications management plan.

What should the project manager do next1?

A.

Update the communications management plan to include the missed stakeholder, and send the current project status documentation to this stakeholder

B.

Inform the project sponsor that there are stakeholders who are not included in the communications management plan

C.

Inform the stakeholder that the project team cannot provide information to anyone who is not registered in the project's communications management plan

D.

Ask the stakeholder to get the project status report from another stakeholder listed in the communications management plan.

Full Access
Question # 233

A project team is having difficulties understanding technical details regarding requirements The information was not initially provided by the customer, but the information is critical in the current iteration for clarification on how tasks need to be accomplished

How should the project manager approach this situation?

A.

Request that the customer reviews and clarifies feature definitions for the current sprint

B.

Send a burndown chart of the current sprint to the customer and seek clarifications.

C.

Educate the customer and have them participate in daily standup meetings.

D.

Schedule weekly meetings and product reviews with the customer to clarify requirements

Full Access
Question # 234

After completion of a project with specific users in various countries, the project manager's supervisor asks if the project users are satisfied with the way the project was run. What two actions should the project manager take? (Choose two)

A.

Prepare the lessons learned from the project phase.

B.

Obtain official approval on the new process from the various countries

C.

Send a questionnaire to the project participants and seek their feedback.

D.

Refer to the communications management plan

E.

Deliver the project materials to the users and see if they have any comments

Full Access
Question # 235

A project manager at a company is considering a high-performing junior member of the organization to be the new project manager for a current project. What should the project manager do to prepare for a recommendation to senior management?

A.

Compile key highlights featuring the team member from the meeting minutes.

B.

Ask the team member to write a short biography listing their qualifications

C.

Gather project artifacts that demonstrate the team member's high performance

D.

Calculate the health of the projects on which the team member has worked

Full Access
Question # 236

During project execution, the project manager notices that the work performance reports have deteriorated drastically in less than two weeks The project team in country A is complaining about delays resulting from holidays occurring in country B that have impacted their project team

How should the project manager handle this situation?

A.

Implement crashing to compress the schedule and improve the schedule performance index (SRI).

B.

Implement fast-tracking to compress the schedule and improve the SPI

C.

Perform conflict management using the project's resource management plan.

D.

Review the risk management plan to evaluate the probability and impact of these delays

Full Access
Question # 237

Which two actions should a project manager consider while launching a new virtual team? (Choose two)

A.

Recruit the best resources within the organization to be part of the virtual team

B.

Evaluate the project manager’s own strengths and weaknesses as a virtual team leader to identify avoidable pitfalls

C.

Identify the types and quantities of resources required for each work package or activity

D.

Establish in the beginning, how progress will be monitored and the best means for communicating progress

E.

Verify if team members are on more than one team and cannot devote enough time to this team

Full Access
Question # 238

At the end of a meeting a functional manager takes the project manager aside to raise some concerns on behalf of a project team member who is unclear about their role and responsibilities for the project What should the project manager do in this situation?

A.

Develop a work plan for the project team member with the help of the resource manager

B.

Advise the functional manager and the project team member to review the resource management plan

C.

Tell the functional manager and the project team member to review the project

charter

D.

Ask the functional manager to create a specific responsible, accountable, consult, and inform (RACI) chart for the team member

Full Access
Question # 239

A company's project management office (PMO) is incorporating more adaptive technologies and has hired a new project manager with hybrid project management experience The team is slow in adopting the new methodology and has not been updating project artifacts in a timely manner.

Which action should the project manager take to improve the team's performance?

A.

Set up a training session for all project team members

B.

Reach out to the functional managers for support

C.

Speak individually with each project team member about making the needed updates

D.

Send an email asking all project team members to complete updates at the end of the day

Full Access
Question # 240

A learn has been working for two months and has consistently missed planned user stories How should the project manager address this issue?

A.

Ensure the sprint size is appropriate for the iteration duration.

B.

Promote changing the iteration duration in order to commit as planned.

C.

Engage in recruiting a highly skilled resource to reinforce the skills.

D.

Consider using a reward system to encourage timely delivery

Full Access
Question # 241

Stakeholders in some industries prefer to deal with programmers and system analysts directly, bypassing project managers. This complicates managing resources on projects

How should a project manager solve this issue?

A.

Propose implementing a new project management information system (PMIS).

B.

Request a meeting with senior management to escalate the situation

C.

Promote adoption of the communications management plan with the project team.

D.

Host a team-building event to develop team cohesion and improve communication

Full Access
Question # 242

A marketing team is planning for a multiyear initiative that will include a lot of cross-functional stakeholders The project manager has been assigned and is now in the project planning phase

What item(s) should the project manager develop first?

A.

A product backlog and identification of the features to be delivered

B.

A business case and scope document

C.

A communications management plan that addresses the team's needs

D.

A risk management plan to incorporate known risks

Full Access
Question # 243

A project manager is leading an in-house company project in its very early stages This current project is similar to another project that ended a year ago

What should the project manager do to analyze the involved stakeholders?

A.

Lower the priority of stakeholder engagement as the stakeholders already have knowledge of this kind of project

B.

Use lessons learned from the previous project as a guide for the current project's stakeholder register

C.

Refer to the stakeholder register from the previous project as it was similar to the current project

D.

Document in the risk register that the current project may have different

stakeholders than the previous project

Full Access
Question # 244

In a multinational multi location project with virtual teams a project manager has established a project baseline The project manager discovers that multiple risk elements have appeared. The project manager did not foresee these risks during the planning stage of the project.

What should the project manager calculate to address this critical budgetary situation? (Choose two)

A.

Contingency control in the project and rebaseline

B.

Mitigation control in the project

C.

Benefits management control in the project

D.

Integrated change control in the project

E.

Currency exchange rate

Full Access
Question # 245

A verbal announcement is made that the new team member joining the Scrum team has limited mobility The scrum master is aware that some team members are unsure how the dynamics of the team will change

What should the scrum master do?

A.

Create a stakeholder engagement plan

B.

Design a communications management plan

C.

Update the team charter accordingly.

D.

Set up a meeting to discuss accommodations the team will have to make

Full Access
Question # 246

A marketing team is developing ideas in order to revamp an existing product The marketing executive reaches out to the project manager to make sure that necessary measures are in place for a successful launch

On what should the project manager focus?

A.

Ensuring that the team is also focused on the overall change management plan

B.

Determining and aligning performance indicators that will help in assessing successful delivery

C.

Planning for regular project updates to cover the status of critical deliverables

D.

Ensuring that the scope management plan is in place to cover all related objectives

Full Access
Question # 247

During the last sprint review the product owner stated that the product does not deliver any value The project manager believes that the product meets all the provided specifications

The team is confused by the product owner's statement

What should the project manager do when using a hybrid approach?

A.

Escalate the matter to the executive board so they can decide on next steps

B.

Prioritize the project backlog and ask the development team to fix the issues

C.

Review the project's benefits management plan with the product owner.

D.

Ask the product owner to terminate the project as it is no longer aligned to the expected benefits

Full Access
Question # 248

During the closing process, the project manager learns that one deliverable is not meeting customer expectations How should the project manager proceed?

A.

Ask the customer to issue a change request with the information to analyze and provide a solution.

B.

Review the deliverable requirements, check the customer approval criteria, and proceed accordingly

C.

Meet with the customer to reach agreement on the scope of the deliverable that will satisfy both parties

D.

Contact the project sponsor and ask for help in negotiating the closing of the project with the customer

Full Access
Question # 249

A project manager has a team of shared resources from other projects who are working on a client project Three days before the project is due. The team informs the project manager that the project will be delayed because a component was not delivered on time Competing priorities of the shared resources are delaying delivery of the component

What should the project manager have done to prevent this delay from happening?

A.

Updated the risk management plan and registered lessons learned for the project

B.

Reorganized the team for the project based on the work breakdown structure (WBS)

C.

Maintained constant communication with the stakeholders of the other projects

D.

Used the resource management plan to identify the impacts of the other projects

Full Access
Question # 250

A project manager is assigned to a new project to deliver a product at the end of the year. The project manager was informed by the vendor that a core component could not be shipped on time, which will impact the schedule.

What should project manager to do next to minimize the impact on the project?

A.

Schedule a meeting with all stakeholders to extend the project deadline

B.

Replace the vendor with a new vendor who can offer the component on time

C.

Add an item to the next status review to make stakeholders aware of the vendor issue.

D.

Review and update the issue log and determine if any alternative components can be offered

Full Access
Question # 251

A project manager has just finished initiating a project. While planning the project manager notes that several essential team members do not have the required skills for key tasks later in the project.

What should the project manager do first?

A.

Develop the resource management plan and ensure adequate training

B.

Replace the current project team members

C.

Outsource the task to be completed by a specialized vendor.

D.

Update the issue log to account for the lack of team member qualifications

Full Access
Question # 252

A team is holding the first demonstration of the software built to date on a medium-sized project The product owner has uncovered a number of issues they would like to be addressed before providing approval

How should the project manager approach this problem?

A.

Plan to address the issues through backlog grooming and incorporate them into the next sprint

B.

Refer the product owner to the change management plan, then escalate to the steering committee

C.

Refer the product owner to the signed business requirement document and explain that the current plan cannot facilitate these changes

D.

Tell the product owner the issues will be addressed in the second version of the software

Full Access
Question # 253

Drag the to the correct scenario on the right

Full Access
Question # 254

An agile project started 6 months ago. Since the beginning of the project, there have been disagreements among team members regarding daily meetings since some of the team members are not available at the same time. The project manager is convinced an agile team should be self-organizing, and that meeting times should be worked out by the team.

What should the project manager do?

A.

Establish a project schedule

B.

Assign a team leader

C.

Recognize the team's contributions

D.

Establish a team charter

Full Access
Question # 255

By the end of the first sprint, a project lead notices that one of the team members is not performing very well. Which form of communication should the project lead use to handle the situation?

A.

Informal written communication, such as a friendly reminder

B.

Formal written communication, such as an email with a copy sent to the manager

C.

Informal verbal communication, such as a conversation

D.

Formal verbal communication, such as a conversation at the end of the sprint retrospective

Full Access
Question # 256

While finalizing project management plans, a customer provides the project manager with a new set of quality standards to which the final product must adhere. What

should the project manager do to ensure a smooth delivery of the product?

A.

Involve the client in risk identification.

B.

Agree with the client on acceptance criteria.

C.

Involve the client in a performance gap analysis.

D.

Agree with the client on a new project charter.

Full Access
Question # 257

A project manager is leading a technically complex project. The project is part of a strategic program of work and the first to use an agile approach. One of the board members is interested in attending a meeting to see how the delivery of the project scope is progressing.

What should the project lead do?

A.

Invite the board member to the next daily standup.

B.

Invite the board member to the next sprint retrospective.

C.

Invite the board member to a separate demo.

D.

Invite the board member to the next sprint review.

Full Access
Question # 258

A project lead is working on an agile project to build the team's vision, including the decision-making process. It was decided that the team will

vote on items, and if 90% of the team agrees on a decision, then it will be carried forward. At the very first technical design meeting, the team

makes a decision that the project lead strongly disagrees with.

How should the project lead proceed?

A.

Refuse to let the team proceed with the work based on their decision.

B.

Take the technical team lead aside and try to persuade them to change their vote.

C.

Note the reasons for the disagreement and let the team proceed.

D.

Set up a meeting with the project champion and ask them to intervene.

Full Access
Question # 259

A customer is concerned with the quality of the product delivery, as the production deployment is approaching. What should the project manager do next to ensure acceptance of the deliverables?

A.

Test product integration in accordance with the requirements.

B.

Evaluate the quality checklist for product compliance.

C.

Review the approved exit criteria for the product.

D.

Verify the production budget before advancing the product.

Full Access
Question # 260

In a geographically distributed team, a developer continues to delay a coding activity. This activity is on the critical path. The project manager

found out that the delay is due to the developer's lack of understanding of the customer requirements shared by the off-site team.

What should the project manager do?

A.

Replace the developer with a skilled resource.

B.

Perform a root cause analysis (RCA) with the team members.

C.

Facilitate communication to ensure clarification of the requirements.

D.

Conduct frequent performance reviews.

Full Access
Question # 261

A company has selected a cross-functional team to develop an innovative digital product to drive the digital transformation project for the business. What should the project

manager do to ensure business value is delivered early?

A.

Create a detailed project plan and escalate delays to the functional managers.

B.

Fast track the project and monitor tasks closely to ensure timely delivery.

C.

Create robust incentives to the team members to encourage speedy delivery.

D.

Break down the deliverables into sprints and deliver value incrementally.

Full Access
Question # 262

A project team is engaging a development team in another country to develop software. During progress reviews, the project manager identified completion date delays due to rework because there were different interpretations of the client's needs.

What should the project manager do?

A.

Travel to the development team's office to push the schedule.

B.

Set up a meeting with key stakeholders to clarify requirements.

C.

Escalate to the project steering committee and request additional time.

D.

Create prototypes with the development team to confirm requirements.

Full Access
Question # 263

Two members of a new project team disagree on the best approach to solve a problem. The conflict has been going on for 1 week. The two

members are tense around each other and are taking everything personally.

What should the project manager do?

A.

Help the team members to resolve the conflict in a way that results in the best team performance.

B.

Offer a compromise that is acceptable to both team members, even if it may not be the best solution.

C.

Understand each team member's argument and select the one that results in less risk to the project.

D.

Send both team members to the human resources (HR) department for an acceptable resolution.

Full Access
Question # 264

A project manager is working on a software development project for an oil and gas client using an agile approach. The project manager is having difficulty preparing the schedule because the project has various unknowns.

Which scheduling method should the project manager use to develop the schedule?

A.

Iterative scheduling

B.

Three-point scheduling

C.

Parametric scheduling

D.

Analogous scheduling

Full Access
Question # 265

A project manager has been assigned to an existing infrastructure project. The current project manager, who is retiring, and the project sponsor have had a good working relationship for many years. The project sponsor has expressed dissatisfaction with having a new project manager assigned to the project.

What should the project manager do?

A.

Set up a new communication plan and stakeholder engagement plan and submit to the project sponsor.

B.

Discuss the strategic benefits of the project and schedule communication with the project sponsor.

C.

Send weekly project reports to the project sponsor to provide an opportunity for engagement and feedback.

D.

Set up a detailed meeting with the project sponsor and brief them about the project's progress.

Full Access
Question # 266

A software delivery project is in the execution phase. The project team has identified a need for an additional server as the software requires more data storage space than planned for. Without the additional server, the project delivery cannot continue.

What should the project manager do?

A.

Use the project budget and procure a new server before raising a change request.

B.

Request that the requirement is funded with the business operational expenses.

C.

Apply contingency reserves to procure a server that fits the requirement.

D.

Raise a change request and obtain approval from the project owner.

Full Access
Question # 267

In an effort to modernize the technology for a project, the project manager has been discussing risk prioritization with the project team. The project manager determines that additional parameters are needed to iteratively assess and prioritize the project risks.

Match the project manager's goals on the left with the relevant risk parameter on the right.

Full Access
Question # 268

A senior vice president requested the creation of more agile teams to run projects of varying lengths and complexities in parallel with each other.

This will impact the amount of time the project managers will be able to dedicate to each project. The project managers typically dedicate 50% of

their time to projects regardless of their complexity.

What should the project manager do as a servant leader to help achieve this transformation?

A.

Review the organizational process assets (OPAs) to evaluate mitigation plans for similar risks.

B.

Create a risk entry regarding the project manager's capacity and develop a mitigation plan.

C.

Empower the team to develop the necessary skills to move the project forward independently.

D.

Issue a change request to hire additional project managers based on the increased workload.

Full Access
Question # 269

In a financial company, a strategic project has been planned to use a predictive approach. During project planning, the product leader requests

that milestones be submitted for review. There is a defined scope and an established deadline to conclude the project.

What should the project manager do first to meet the product leader's expectations?

A.

Change the project charter to indicate that the approach will be different.

B.

Inform the product leader that they must wait until the end of the project.

C.

Meet with the software team to review the possibility of monthly milestone reviews.

D.

Modify the project management plan to use an agile framework to incorporate milestones.

Full Access
Question # 270

A project manager has been assigned to deliver a challenging project on time and within budget. The project manager needs to empower the team members by removing organizational impediments and facilitating collaboration.

What should the project manager do to lead the project?

A.

Use a servant leader approach.

B.

Assume the functional manager role.

C.

Perform the project sponsor activities.

D.

Act as the project owner.

Full Access
Question # 271

A project manager is leading a diverse project team that includes new and experienced team members. A conflict has occurred between two team members. One team member prefers using digital tools for project communication. The other team member prefers in-person meetings and phone calls for communication.

What should the project manager do to manage this conflict?

A.

Arrange a team-building activity to foster understanding and open communication among the team members.

B.

Allow the team members to continue using their preferred communication tools and methods.

C.

Initiate a conversation with the team members individually to understand their situations regarding communication.

D.

Instruct the team members to adapt to the project's communication tools and methods.

Full Access
Question # 272

A credit collection company is implementing new software to assist customer service agents when calling clients for payments. The software will benefit the company by freeing up staff to work on other projects. Several business areas want to take advantage of this benefit.

What should the project manager do?

A.

Request all of the business areas to plan for a portion of the benefit equally and include it in their staffing plans.

B.

Set up a stakeholder session with all teams to agree and document the benefits and establish ownership.

C.

Ask the project sponsor for approval to distribute the project benefits equally to the business areas.

D.

Ask the project sponsor to make a decision on who will own the benefit and document the decision.

Full Access
Question # 273

A customer's technical lead discussed a new feature with the project manager. The project manager believes the new feature will boost performance significantly and adds it as a high-priority item in the sprint backlog. At the end of the sprint, all of the planned stories were not completed because the new feature took more time.

What should the project manager do next?

A.

Agree with the project team to modify and delete some of the stories in the current sprint backlog

B.

Obtain approval from the project team and add the new story to the product backlog

C.

Receive an agreement from the product owner and add the new story to the product backlog

D.

Negotiate with the scrum master before adding the new story to the sprint backlog

Full Access
Question # 274

A project manager is working with team members and customers who are operating in multiple countries. The team is working on implementing a new technology that includes ambiguities, uncertainties, and unknowns, both in terms of technology and of the end-user expectations for this solution.

What should the project manager do to keep the stakeholders engaged?

A.

Use email as a communication channel.

B.

Use feedback and decision-making tools.

C.

Use meetings as a communication channel.

D.

Use a shared collaboration platform.

Full Access
Question # 275

In an agile project, the team is disagreeing about which user story to complete first. One is technically complex and long to complete. The second is a lower priority but easy to complete.

What should the project manager do?

A.

Have the team complete the technically complex story first.

B.

Work with the product owner to clarify and prioritize the backlog stories.

C.

Have the team complete the less complex story first.

D.

Work with the agile coach on the user stories to avoid conflict.

Full Access
Question # 276

A project manager is assigned to a new project that will launch the digital version of a current product. Even though the product is well known, the vision for its digital version

is not clear to the stakeholders.

What should the project manager do to increase value delivery?

A.

Use spikes to dig deeper into the technical challenges of the new product, thus reducing the technical risk.

B.

Create a visual task board with all of the relevant stakeholders to support backlog prioritization.

C.

Work with the team on the definition of a minimum viable product (MVP) and present it to the stakeholders.

D.

Gather the team to create a comprehensive product roadmap but only commit to requirements for the next quarter.

Full Access
Question # 277

A company must implement a new regulation. The government has specified the date when the regulation will be enforced but has only provided high-level information on

the regulation's requirements. Therefore, changes in definitions are to be expected due to uncertainty.

Which life cycle should the project manager use for this project?

A.

A predictive execution strategy

B.

A hybrid execution strategy

C.

An iterative execution strategy

D.

An agile execution strategy

Full Access
Question # 278

A drone manufacturing company is designing its first drone. The new project architect has called the project manager to review the project scope. The architect wants to reshuffle the scope and schedule to test the drone functionality first. The project team disagrees because the scope has already been approved and any change might affect the timelines set by the CEO.

What should the project manager recommend?

A.

Review the timelines with the architect and invite the CEO to the meeting to make sure all the stakeholders are involved.

B.

Reject the review as the completed project timeline is set by the company's CEO and has already been approved.

C.

Agree to review the architect's new proposal to assess the impact on the timelines set by the CEO.

D.

Register an issue in the log regarding the timeline delay to the CEO's approved plans before agreeing to change the project scope.

Full Access
Question # 279

A project to construct an electricity generation plant is on site near a nature reserve. An environmental activist group is questioning the need for

the project. The customer has informed the project manager to disregard the group as they are not in support of the project.

What should the project manager do next?

A.

Ask the customer to contact the activist group and let them know the project status and completion date.

B.

Add the activist group to the list of stakeholders and analyze the impact they may have on project delivery.

C.

Obey the directive from the customer since they are funding the project and are the most important stakeholder.

D.

Request the project team disregard all communication from the activist group and continue with their project work.

Full Access
Question # 280

During the initial stage of a project, the team estimated activities for the next iteration in story points. It was agreed that each story point would be assumed to be equal to one day of effort during project execution. There are some activities estimated as two story points and others estimated as 100 story points.

What should the project manager ask the team to do next?

A.

Execute the smaller estimated activities.

B.

Resize the story points.

C.

Negotiate the estimation so it gets smaller.

D.

Break down the larger activities into smaller ones.

Full Access
Question # 281

A company is starting a critical project with a strict deadline. During the first planning meeting, the team realizes that the list of requirements has

too many items to allow on-time delivery.

What should the project manager do first?

A.

Update the risk register and present a contingency plan to meet the deadline.

B.

Suggest to the customer to reduce the backlog to meet the date.

C.

Increase the capacity of the team to finish the project on time.

D.

Ask the team to propose a minimum viable product (MVP) to meet the date.

Full Access
Question # 282

A project manager leads an agile development project. During the sprint planning meeting, the development team expresses concerns that the proposed scope of the next sprint is much larger than expected given the current resource allocation. The project manager believes the scope is essential to meet the project milestones.

How should the project manager approach negotiating an agreement with the team to ensure the project remains on track?

A.

Allocate additional resources to the development team to ensure the original scope can be completed on time.

B.

Suggest prioritizing the most critical features for the next sprint as well as reevaluating the remaining scope.

C.

Agree on reducing the scope to match the team's resources and plan to add the removed items to future sprints.

D.

Insist on keeping the original scope and explain the importance of meeting all the project milestones on time.

Full Access
Question # 283

A project manager is assigned to a project where a vendor has been engaged to build a new system One week before user acceptance testing (UAT) is scheduled the vendor informs the project manager that they can only deliver half of the promised functions by the UAT start date.

What should the project manager do next?

A.

Wait until the vendor cannot deliver and then invoke liquidated damages based on the contract

B.

Escalate to management and prepare tor project closure by canceling the contract with this vendor

C.

Adjust the protect schedule to accommodate the current development progress of the vendor

D.

Communicate with the vendor and project team and explore possibilities lor resolving the issue

Full Access
Question # 284

A company is working on a project to develop an integration of their existing systems. There are known issues in production.

What should the project manager do?

A.

Identify and remove impediments and mitigate the risks.

B.

Ensure the product owner reviews requirements with the team.

C.

Include acceptance criteria in the definition of done (DoD).

D.

Review the quality control processes and procedures.

Full Access
Question # 285

A project manager is managing a project with a cost performance index (CPI) of 1.05 that is trending downward. To maintain on-time completion, the scrum master needs to add 30 additional team members in the next month to enable more sprints. The project manager is concerned because the schedule performance index (SPI) is 1.0.

What is the first step the project manager should take?

A.

Meet with the project team to forecast the SPI trend to determine if there are funds available to pay the 30 team members.

B.

Quantify the cost for the 30 team members and determine if there is budget available to fund the expanded team.

C.

Inform the project team that since the CPI is trending downward, there are funds available to expand the team.

D.

Engage with the human resources (HR) representative to begin selecting candidates for the 30 open positions.

Full Access
Question # 286

In an agile project, the team decided to have a rotating group of facilitators for the daily scrum. Overall, most of the facilitators have grown and done well in this role; however, a few of them tend to run inefficient daily scrums.

What should the project manager do next?

A.

Retrain all team members on daily scrum facilitation to ensure there is consistency in the approach.

B.

Ask the facilitators who are doing well to continue and recommend that the others stop facilitating.

C.

Praise the team for self-organizing and growing, then work one-on-one with the facilitators, as needed.

D.

Return to using the scrum master as the facilitator for the daily scrums now that the trial period is over.

Full Access
Question # 287

During the lessons learned workshop, one stakeholder mentioned that the project was unsuccessful as it did not deliver the expected business value. What should the

project manager do to address this concern?

A.

Review the project management plan tasks with the stakeholders.

B.

Review the project management plan budget with the stakeholders.

C.

Review the business benefits realization plan with the stakeholders.

D.

Review the communications management plan with the stakeholders,

Full Access
Question # 288

A project scope statement has been approved, and the project manager and core team have been assigned to the project. Suddenly, the project

manager takes a temporary leave of absence due to a medical emergency. While the project manager is on leave, the team develops the project

schedule. When the project manager returns, a detailed schedule is almost complete.

What should the project manager do?

A.

Ensure that the schedule is aligned with the vision and objectives.

B.

Escalate the compliance issue to the project management office (PMO).

C.

Congratulate the team and move on to the execution phase.

D.

Develop a new detailed schedule with the team and project sponsor.

Full Access
Question # 289

All project team members refer to the project manager for various decisions. This causes delays for some tasks, as the project manager is usually preoccupied in meetings throughout the day.

What should the project manager do to prevent these delays?

A.

Review the Pareto diagram to identify the source of delays.

B.

Meet with the team in 2 weeks to respond to all of the open tasks.

C.

Consolidate the decision-making authority to remain with the project manager.

D.

Delegate the decision-making authority of some tasks to the team.

Full Access
Question # 290

A project manager just took over a construction project which was already in its execution phase. Labor union representatives of the construction workers ask to revise the overtime per hour rate, as wage per hour have increased across the industry.

What should the project manager do first?

A.

Obtain approval from sponsors to increase the rates because it can affect project due to lack of resources.

B.

Carefully read the agreements and see if there was any clause if the per hour rate could be increased.

C.

Assign a team member to negotiate the increased wage per hour with the labor union representatives.

D.

Negotiate with the labor union representatives if the clause about increased wage per hour meets their requirements.

Full Access
Question # 291

A project team member identified a procurement risk and sent an email to the project sponsor highlighting the risk.

The sponsor forwarded the email to the project manager asking for further details. After speaking with the sponsor, the project manager decided to take preventive action.

Which document should the project manager review with their team?

A.

Risk management plan

B.

Quality management plan

C.

Communications management plan

D.

Procurement management plan

Full Access
Question # 292

A project manager works in a hierarchical organization. The project team members are used to being told what to do, and the performance reviews include the percentage of

completion of the allocated tasks. After a conversation with the sponsor, the project manager realizes that they need to reassign a couple of tasks to meet the next

milestone. This change can be perceived as poor performance by the current assignees.

What should the project manager do?

A.

Organize a team meeting and inform the team members that, as the person accountable for delivery, they decided to change the task allocation.

B.

Ask the less experienced team member privately to stop working on the task and inform another team member that the work has been reassigned.

C.

Ask the more experienced team member privately to take the task and inform the other team members that work has been reassigned.

D.

Organize a team meeting to inform team members about a change in direction and work with them to change the task allocation.

Full Access
Question # 293

A company is going through structural changes. A couple of people will leave the company as their positions were made redundant. The team members are unhappy as they do not understand why the changes are being made when the project is on track.

What should the project manager do?

A.

Advise the team to continue their work as planned because the schedule cannot be changed.

B.

Organize a team meeting to discuss the changes and their importance for the company.

C.

Advise the team that the changes were decided by the CEO and must be implemented.

D.

Inform the project sponsor about the team's unhappiness and ask for overtime pay.

Full Access
Question # 294

An agile team is working on a 2-week sprint to deliver business value. About 1 week after the sprint starts, the team members do not feel

confident about the product increment they are building. They do not want to wait until the end of the sprint and want to validate the product

increment with the product owner now.

What should the project manager do to mitigate this risk?

A.

Extend the sprint end date in anticipation of feedback from the product owner that will require extra work.

B.

Schedule an additional interim demo with the product owner.

C.

Address the issue as part of the retrospective.

D.

Ask the team to work overtime toward the end of the sprint to meet the original sprint end date.

Full Access
Question # 295

A project manager received a request to add features and functions to the project after the scope had already been established. What should the project manager do?

A.

Follow the requirements management process.

B.

Follow the stakeholder engagement process.

C.

Follow the risk management process.

D.

Follow the change management process.

Full Access
Question # 296

A project manager is leading a project that needs to be deployed quickly to the market. An influential stakeholder does not believe that the project management processes bring business value.

What can the project manager do to gain the support of the stakeholder?

A.

Ask the stakeholder for a meeting to review the project's charter and project management plan.

B.

Disregard the stakeholder's concerns and continue following the project management plan to execute the project.

C.

Hold a training workshop to educate the stakeholder about project management best practices.

D.

Clarify the project roles and responsibilities, and share the purpose to gain the stakeholder's buy-in.

Full Access
Question # 297

During the release of an important product, a vice president for a different product line brought a valid concern to the project team, which had to be completed before the release. The vice president has not participated in other product discussions until now. This additional work resulted in a delay of the product release.

How should the project manager have handled this situation earlier in the project?

A.

Identified the vice president as a stakeholder

B.

Recorded the vice president's concerns in the risk register

C.

Escalated any dissent to top management right away

D.

Shared project boundaries so that everyone was aware of the scope

Full Access
Question # 298

A project is currently in the execution phase. Because of the complexity of the project and the large number of regulatory requirements involved, the project manager decides to hold a management review with senior executives to ensure the successful implementation of project deliverables.

What should the project manager review during the management review to ensure the meeting is effective?

A.

The deliverables that are performing well and those that need more work.

B.

Metrics and key performance indicators (KPIs) that objectively reflect the status of deliverables.

C.

Potential changes to the project's strategy and the feedback from senior executives.

D.

Specialized reports created specifically for the meeting as per directions from the project sponsor.

Full Access
Question # 299

A member of a testing team in an agile project works well with the project team. However, in the previous two iterations, this team member's performance was poor, and the team had difficulty meeting the iteration goals.

How should the project manager handle this situation?

A.

Inform the human resource (HR) department about the issue.

B.

Allow the project team to discuss the problem with this team member.

C.

Discuss the issue with the team member's functional manager.

D.

Speak to the team member regarding the need to improve performance.

Full Access
Question # 300

A project manager is leading a project that includes several organizations with unique corporate cultures. These diverse corporate cultures are affecting project expectations. The varying expectations often lead to conflicts, which often require the project manager's involvement.

What should the project manager do first to evaluate the cultural differences within the organizations?

A.

Establish a probability and impact matrix and plan response criteria.

B.

Disregard the situation since it is not hindering the project deliverables.

C.

Develop a joint policy among the various organizations.

D.

Escalate the issue to the project sponsor and seek their guidance.

Full Access
Question # 301

A project manager leads a project that implements a new process throughout the organization. The rollout is done in stages and the project manager planned a demonstration for the pilot business units. A manager from a business unit that is scheduled for a later date asks to be invited to the sprint review.

What should the project manager do?

A.

Refer the sprint review request to the project sponsor.

B.

Ask the manager to get an approval from the product owner.

C.

Invite the manager to the scheduled sprint review.

D.

Organize a special demonstration for the manager only.

Full Access
Question # 302

A project manager is leading a project in an organization that has a functional structure. The project manager has been informed by the team that the tasks related to the purchase of services are taking too long, as the purchasing department has other priorities.

What should the project manager do?

A.

Modify the project schedule to accommodate the delays in the purchase of services.

B.

Request that the purchasing tasks be outsourced through an existing purchasing vendor.

C.

Meet with the purchasing manager to find the source of the delays and agree on a purchasing schedule.

D.

Ask the project team to keep developing other tasks that do not depend on the purchase of services.

Full Access
Question # 303

During a regular project progress meeting, the CEO informed the project manager that a major stakeholder has been unaware of recent developments on the project. The

project manager is sure that the stakeholder was duly identified and classified in the stakeholder register.

Which project document should the project manager review in order to determine the reason for this issue?

A.

Requirements traceability matrix

B.

Stakeholder register

C.

Stakeholder engagement assessment matrix

D.

Issue log

Full Access
Question # 304

Drag the items on left side to the matching term within the correct project approach on the right side.

Full Access
Question # 305

A company is experiencing a high rate of rejected project deliverables. The project manager is requested to suggest a solution to improve quality. What should the project manager suggest?

A.

Request that all team members receive the newest quality standards training and review one another's work.

B.

Request that a quality specialist be assigned to the project to check the final product at the end of the project.

C.

Break down the project into several iterations and incorporate a quality check by a quality auditor in each iteration.

D.

Break down the project into several iterations and incorporate automatic testing and quality improvement sessions.

Full Access
Question # 306

A project manager is working on an agile project in a changing business environment. The project sponsor is worried about benefits realization

and asks the project manager to pay attention to changes that can affect the project.

Which action should the project manager take to identify changes that may affect the product?

A.

Implement face-to-face communication between the team and product owner to change the iteration objectives as needed.

B.

Stop the iteration as soon as possible in case an external change that makes the product invaluable is identified.

C.

Take action to reprioritize the backlog after every iteration to evaluate if user stories are still valuable to the business.

D.

Apply a pair programming technique to react to changes immediately, even in the middle of the interaction.

Full Access
Question # 307

A self-organizing team for a critical project is consistently delivering value according to their commitments. During a retrospective, the project manager observed that most of

the team members were stressed due to over commitments.

What should the project manager do?

A.

Help the team members by organizing regular stress-relieving and team- building sessions.

B.

Request additional resources to continue delivering value while reducing team stress.

C.

Support the team during the planning phase to only commit to what they are able to deliver.

D.

Ask individual team members to plan staggered leave to avoid becoming stressed.

Full Access
Question # 308

A team member who is working on a critical project deliverable reported that their computer is not working. The IT department says that due to a high workload, they will not

be able to provide assistance for 1 week.

How should the project manager address this situation?

A.

Ask the team member to find an innovative solution or workaround to overcome the issue and avoid project delays.

B.

Schedule a meeting with the project sponsor to request a budget to buy or rent a new computer.

C.

Explore options with the IT department to expedite the necessary repairs based on criticality of the project.

D.

Use project reserves to buy new equipment to avoid an impact to the critical path of the project.

Full Access
Question # 309

After the demo on a software project, one of the key stakeholders contacted the scrum master and complained that they were unaware of changes made to the project. After checking, the scrum master learned that the stakeholder's details were incorrectly entered into the register.

What should the scrum master do?

A.

Ask the product owner to update the stakeholders' contact information at every meeting to address any changes.

B.

Update the stakeholder's information and inform them that they must make the team aware of any changes.

C.

Consider it a loss since the stakeholder should have ensured the contact information was up to date.

D.

Check the stakeholder register and ensure that every stakeholder's information is correct and current.

Full Access
Question # 310

An internal virtual team is meeting daily to review iteration progress, as well as to conduct other technical and followup calls with key stakeholders. The team seems to be disengaged.

How should the project manager approach this situation?

A.

Give the team members a few days off to reduce stress.

B.

Reduce the number of internal and external meetings.

C.

Review team assignments and reduce the workload.

D.

Schedule one-to-one meetings and team-building meetings.

Full Access
Question # 311

A project manager is managing a project to deploy new software to 200 end users. During the implementation, there is a missed process that

caused some of the users to lose their computer data.

What should the project manager do first?

A.

Meet with the team to discuss the root cause and encourage the team to take note of it and continue to focus on the deployment.

B.

Record this case until the final lessons learned session is complete to prevent impacting the team's morale during implementation.

C.

Meet with the team members and request they conduct a review of the case by providing feedback as lessons learned.

D.

Invite a consultant to review the process in order not to repeat the same issue and share the results with the team.

Full Access
Question # 312

A new project manager took over a project that has been ongoing for a while. Some project team members are not clear on when the project will end and feel the project has already transitioned into business as usual.

What should the new project manager do first?

A.

Meet with the team and gather their input on the completion rate.

B.

Revisit the timelines of the deliverables and the project.

C.

Consult the sponsor and secure approval to complete the project.

D.

Transition to an agile delivery so project closure will be faster.

Full Access
Question # 313

A project manager is leading a project that has a dependency on the client's vendor management system for critical requirements. The vendor

management team will not derive any benefits from the project. However, the project requires support from the vendor management head.

What should the project manager do next?

A.

Get support from the sponsor to hire a subject matter expert (SME) from the vendor management team to work on the project.

B.

Review the terms of reference of the steering committee to include the vendor management head.

C.

Work with the sponsor on a communications management plan to obtain support from the vendor management head.

D.

Obtain help from the sponsor to highlight any nonfinancial benefits for the vendor management team.

Full Access
Question # 314

Midway through the execution of an agile project, there is a shift in the strategic objectives at the organization level to promote digital transformation. What should the project manager do next?

A.

Prepare a user story to handle the change and assign it to the next iteration.

B.

Escalate to the product owner and cancel the upcoming iterations.

C.

Update the risk-prioritized backlog with the strategic change.

D.

Schedule a meeting with the team to assess the impact of the change.

Full Access
Question # 315

A project manager is working on a complex project with a high degree of change. What strategy should the project manager use to ensure a

successful project completion?

A.

Update the project management plan to reduce the possibility of scope creep.

B.

Schedule a regular risk review with the project management team.

C.

Increase the active engagement and participation of key stakeholders.

D.

Create a project change roadmap to keep track of all unforeseen changes.

Full Access
Question # 316

A client from the travel and hospitality industry is building software for an ongoing project. The project sponsor and key project stakeholders ask to add four new functionalities to the upcoming sprint.

What should the product owner do next?

A.

Ask the team to start implementing the new tasks.

B.

Add the new tasks to the current sprint backlog.

C.

Request a change control to expand the scope with the new tasks.

D.

Prioritize the new tasks in the planning of the upcoming sprint.

Full Access
Question # 317

A project manager is leading a software development project that will assist in maintenance management for a power plant. The project manager is analyzing project performance data and trying to forecast if the project will have any slippage in the future.

What should the protect manager do?

A.

Perform quality control analysis.

B.

Perform root cause analysis (RCA).

C.

Perform trend analysis.

D.

Perform schedule analysis.

Full Access
Question # 318

During a sprint, the team is experiencing conflict because the customer asks for additional features that increase the complexity. The scrum master is trying to resolve the conflict.

Which approach should the scrum master use?

A.

Discuss the definition of done (DoD) with the customer.

B.

Approach the product owner to determine the next course of action and update the backlog.

C.

Discuss the acceptance criteria with customer.

D.

Perform backlog prioritization to ensure that everyone is working on the highest value features.

Full Access
Question # 319

An organization is using a hybrid delivery approach for a business project. The product owner, the person who was also managing the project, was promoted to a more senior role. A new project lead has joined the project.

Which artifact should the project lead use to ensure that the project benefits have been identified?

A.

Solution architecture

B.

Product backlog

C.

Statement of work (SOW)

D.

Business case

Full Access
Question # 320

A project manager is leading a cross-departmental project that involves many stakeholders. During the project, the project manager observes that the stakeholders are diverse and have different expectations about how the project should be handled. This leads to frequent confusion and misunderstandings among the stakeholders.

What should the project manager do to integrate the diverse stakeholder groups?

A.

Advise the team members to focus on project work and avoid getting distracted by the stakeholders’ disagreements.

B.

Hold separate meetings with the individual stakeholders and escalate their concerns to the project sponsor.

C.

Develop a joint quality policy for the project and seek a commitment by all of the departments.

D.

Analyze the probability and impact of the risks linked with the situation and implement the proper response plan.

Full Access
Question # 321

A vendor project manager and team are implementing a software solution across the organization. A customer stakeholder who was not present during the sales process is demanding that the team implement requirements that are out of scope without adding additional cost to the project.

What should the project manager do next?

A.

Escalate the issue of the additional requirements to the executive leadership team.

B.

Refer the stakeholder to the delivery specifications in the statement of work (SOW).

C.

Implement all the requirements the customer has requested.

D.

Adjust the scope baseline and schedule baseline accordingly.

Full Access
Question # 322

During sprint planning, the product owner wants to prioritize items with high business value. However, the project team is concerned about technical debt and infrastructure dependencies to deliver the expected value.

How should the project manager handle this issue?

A.

Support the project sponsor so the decision is made top-down and the team follows the provided direction.

B.

Support a voting exercise so all team members can express their opinion and the reason behind their vote.

C.

Support the product owner so only items with high business value are included in the next sprint.

D.

Support the project team so technical debt and infrastructure dependencies are included in the next sprint.

Full Access
Question # 323

A major public-transportation construction project is aimed at significantly reducing emissions. The project has been severely delayed due to noncompliance with environmental codes and bylaws.

What should the project manager have done to prevent this?

A.

Incorporated sufficient schedule reserves based on similar delays in past projects.

B.

Appointed a senior environmental compliance officer to report directly to the project manager.

C.

Mapped environmental compliance requirements, identified risks to achieving them, and prepared mitigations.

D.

Approached the regulator for a partial waiver in light of the environmental importance of the project.

Full Access
Question # 324

A customer complains that a software update project is failing to deliver value according to the original scope. What should the project manager do to resolve the problem?

A.

Ensure that the project issue log is up-to-date with the customer's issues related to the missed stories.

B.

Ensure that the project change log is up-to-date with the stories based on the missed requirements.

C.

Ensure that the project backlog has the features and stories prioritized correctly.

D.

Ensure that the project risk register is current and reflects the impacts posed by stories not delivered.

Full Access
Question # 325

A project manager is assigned to a regulatory project for their country. The deadline for delivering results in compliance with the new laws is very tight, and the project team members have not yet been assigned. One of the project manager's peers informs the project manager that a project with the same scope for a different country was completed 1 year ago.

What should the project manager do first?

A.

Register a new risk in the risk management plan.

B.

Ask for additional resources and review the project estimate.

C.

Review organizational process assets (OPAs) and perform analogous estimating.

D.

Complete a bottom-up estimation for the project activities.

Full Access
Question # 326

Key decision makers are meeting to define the objectives of a new database migration project. There are many disagreements about scope and time lines among the leaders of various company departments.

How should the project manager impartially prioritize the requirements to be integrated?

A.

Retain only requirements that result in profitable revenue growth.

B.

Ensure the CEO selects the requirements from all department leaders.

C.

Give each department a fixed budget that will cover ten requirements.

D.

Rank the requirements with the highest benefit-cost ratio as more important.

Full Access
Question # 327

A flagship project is sponsored by the CEO and has a critical go-live date. The project's product requires a regulatory review and approval before it can go live. The CEO instructed to allow only 2 weeks for regulatory approval in the schedule; however, the director for the regulatory liaison indicated 6 weeks was a more realistic timeline.

What should the project manager do?

A.

Proceed with the direction given by the director for the regulatory liaison, as they are the subject matter expert (SME).

B.

Follow the CEO's directive, as they are the highest authority in the company and are the ultimate decision maker.

C.

Meet with the CEO and the director to discuss and register it as a major risk if agreement cannot be made.

D.

Schedule final testing activities in parallel with the regulatory approval activities to compensate for lost time.

Full Access
Question # 328

A project manager is working as a servant leader for a pilot project to adopt agile practices. After three sprints, the team demos the product to the

main stakeholders, but receives negative feedback about the product's features. The team feels that all the features met the acceptance criteria

defined by the product owner and does not understand what went wrong.

How should the project manager mitigate the product rejection?

A.

Share the product backlog for the main stakeholders to review in advance.

B.

Engage the main stakeholders in the upcoming sprint review sessions.

C.

Create dedicated sprints to implement feature fixes for the rejected ones.

D.

Ask the project sponsor to evaluate the assignment of a new product owner.

Full Access
Question # 329

An organization embarking on a significant transformation initiated a project to improve and document business processes. One of the objectives of the project is to implement agile project delivery.

What is the main reason for adopting agile?

A.

Projects will be completed faster, saving time and money.

B.

Projects will deliver early and use value based on priority.

C.

Projects will be delivered with very low risk to the organization.

D.

Projects will be delivered with significant cost savings.

Full Access
Question # 330

A project manager is working on a multinational project that has more than 100 stakeholders. The project manager is concerned about the

appropriate stakeholder participation and involvement level required for successful project delivery.

What should the project manager do?

A.

Communicate with the stakeholders to find a solution.

B.

Review the issue log with the project stakeholders.

C.

Evaluate the stakeholder engagement assessment matrix.

D.

Perform a stakeholder assumption and constraint analysis.

Full Access
Question # 331

A vice president has asked a project manager to support a new urgent project and has informed team members that the project will start soon. The CEO of the company has not yet approved the project to start. The vice president is concerned that the project will not be approved by the CEO on time.

What should the project manager do next?

A.

Ask the vice president to approve the project charter to kick off the project

B.

Ask the vice president to define who will be the product owner for the project

C.

Investigate if the value and benefits of the project are identified

D.

Start working on the project immediately and determine the scope later

Full Access
Question # 332

A project manager is reviewing a draft of the project charter with key stakeholders. During the meeting, a conflict occurs between the sponsor and the product owner.

How should the project manager deal with the situation?

A.

Postpone the meeting and invite a subject matter expert (SME) to join the next meeting.

B.

Continue the meeting and ask the project sponsor and product owner to take their discussion offline.

C.

Postpone the meeting and ask the project sponsor and product owner to take their discussion offline.

D.

Continue the meeting and use facilitation techniques to improve communication within the team.

Full Access
Question # 333

A project manager is working on an agile project that is within the scope of a recently announced corporate audit. The project manager was

appointed to attend the first meeting with the auditors scheduled for the following week.

What should the project manager do to prepare for the audit?

A.

Reserve story points for the next iteration if needed.

B.

Review the project information.

C.

Ask the development team to provide compliance information.

D.

Ask for a waiver during the audit.

Full Access
Question # 334

During the execution phase of a project, a new department has been created in the company. The manager of this department has requested to

be involved in the regular project communications and reporting cycles.

What should the project manager do?

A.

Ask the project team members to include the manager in all of their communications regarding this project.

B.

Inform the manager that only stakeholders identified in the communications management plan should be involved.

C.

Perform a stakeholder analysis and update the communications management plan to reflect the new situation.

D.

Suggest the manager contact the steering committee and project management office (PMO) to be included.

Full Access
Question # 335

A project manager is in the process of closing out a project and has been asked by the project management office (PMO) to confirm that the transfer of knowledge to the operations team for support operations has been successfully completed. Which technique should the project manager apply to verify the knowledge transfer?

A.

Brainstorming

B.

Meetings

C.

Regression analysis

D.

Expert judgment

Full Access
Question # 336

A project manager is preparing a budget estimation for an international construction project. They decide to consult the project team members who are experienced in this type of project and are familiar with the local laws of the country.

Which budgeting approach would be the least risky for the project team to apply?

A.

Review historical data and provide parametric estimations for the activities, including local law restrictions.

B.

Use a top-down estimation and add contingencies to cover any future impacts regarding the legal context.

C.

Make a general estimation using a standard legal approach and then look to include early definitions.

D.

Discuss and compile the local information about laws to develop bottom-up estimations.

Full Access
Question # 337

A project manager is performing the scrum master role for a project team of developers. At the daily standup, a couple of developers complain about the noise from a neighboring team, the performance of their laptops, and the difficulty in booking meeting rooms.

What should the project manager do?

A.

Acknowledge the impediments and facilitate their resolutions.

B.

Note the impediments and escalate them to the product owner.

C.

Note the impediments and work on addressing them later.

D.

Assign actions to all stakeholders and oversee their implementation.

Full Access
Question # 338

During a project, the project manager finds an opportunity to reduce the project cost by completing a deliverable ahead of schedule with a minimal

impact on project resources. However, the client has only been focused on the next milestone.

How should the project manager approach this situation?

A.

Apply additional resources to realize the early deliverable and ensure the next milestone is achieved.

B.

Focus on the deliverable of the next project milestone as per the client's strict instructions.

C.

Review the change management plan to discuss early benefits realization with the client.

D.

Evaluate whether the client's request will add extra features to the project deliverable.

Full Access
Question # 339

A project team is defining the ground rules during their first meeting as a team. During this session, only a few of the team members suggested and approved the ground rules while most remained silent. As a result, the team's ground rules favor those few team members.

What should the project manager do?

A.

Conduct a round table and ask the team to share their opinions one by one.

B.

Propose new team ground rules and communicate them to all.

C.

Ask the silent team members to share their opinions via email.

D.

Perform focus group interviews based on the new team ground rules.

Full Access
Question # 340

In an agile environment, a project is running iteration four out of six. A team member leaves the company with no replacement.

What should the project manager do?

    Update the issue log and refer to the resource management plan to address the situation.

    Ask the team for extra work to fulfill the project commitment.

    Reduce the scope of the project and inform stakeholders.

A.

Ask the sponsor for an experienced team member in the company to help the project team.

Full Access
Question # 341

A project manager who recently joined the company has been assigned to manage a software project for a major recurring customer. What should the project manager do to

enhance the budget estimations for the project?

A.

Discuss the budget with the team during the daily standups to ensure the budget is under control.

B.

Review budget-related lessons learned from similar projects.

C.

Invite the client to the kick-off meeting and create the project budget during the meeting,

D.

Implement an agile approach to avoid using a fixed budget,

Full Access
Question # 342

During the service procurement process for a strategic project, only one bidder submitted a bid. The price of the offer is significantly large and the project sponsor is not convinced that the return on investment (ROI) can be achieved.

How should the project manager address this issue?

A.

Re-visit the project charter and seek other alternatives.

B.

Proceed and issue the purchase order as this project is important.

C.

Speak with the CEO and ask for their support to approve the offer.

D.

Analyze the bounds of negotiations for project agreements.

Full Access
Question # 343

A project to develop an enterprise resource system for a university is in the planning phase. The project has internal stakeholders such as operational departments, students, and academic staff, as well as global stakeholders who receive the information from the university on a regular basis. All the stakeholders have very different expectations and needs from the system.

What should the project manager do to ensure effective communication?

A.

Plan to implement a united communication platform, where all information about the project will be shared and updated regularly.

B.

Ensure all the information about the project implementation is provided to all of the different stakeholders in a unified communication format.

C.

Define communication target groups and provide information, messages, channels, and the frequency of communication for each group.

D.

Arrange an information session for all of the stakeholders about the plans for handling their various communication needs.

Full Access
Question # 344

A project manager is assigned to a time-bound internal project on quality improvement. During project execution, the project manager observes that a specific team member is being isolated

by other team members.

Which three actions should the project manager take? (Choose three)

A.

Arrange and conduct team-building sessions to improve team effectiveness.

B.

Allow team members to resolve personal issues without involving the project manager.

C.

Get feedback from other team members to understand what led to this situation.

D.

Identify the isolated team member as a risk and document the situation in the risk register.

E.

Obtain feedback from the isolated team member to understand the situation.

Full Access
Question # 345

A project manager is assigned to a major system integration project that is currently in the execution phase. The project relies heavily on the presence and availability of certain products and services, which are provided at various periods throughout the project phases by selected third-party vendors.

What should the project manager do to ensure the successful execution of the project?

A.

Perform procurement control checks throughout the project

B.

Activate the mitigation plan for the procurement risks

C.

Oversee the selection process for the vendor to procure the needed products and services

D.

Ask the procurement department to select the vendor using established processes

Full Access
Question # 346

A highly critical project is in jeopardy due to missing professional resources. What should the newly assigned project manager do first?

A.

Find available professionals within the organization to fill the gaps.

B.

Allocate funding for seeking external professionals to fill the gaps.

C.

Determine the possibility for team members to split up the required tasks.

D.

Request additional budget for team training for the missing expertise.

Full Access
Question # 347

A project is near completion but it is behind schedule. The contingency budget has already being used, although the remaining budget should be

enough to complete the project. The only subject matter expert (SME) assigned to the project has been asked by their manager to solve a

problem in the operations department.

What should the project manager do?

A.

Escalate the situation to the project sponsor.

B.

Free the resource to handle the operations priority.

C.

Ask the manager to submit a change request.

D.

Design a negotiation strategy for this situation.

Full Access
Question # 348

A stakeholder is requesting that the project manager share project status updates

on a regular basis. This stakeholder is not included in the regular distribution list.

What should the project manager do?

A.

Start sending status updates to this stakeholder based on the request.

B.

Ask the stakeholder's manager if the stakeholder can be added to the list.

C.

Review the stakeholder engagement and communications management plans.

D.

Escalate the stakeholder’s request to the project sponsor.

Full Access
Question # 349

A company is leading a project to develop a new product using an agile approach. A supplier was contracted to provide a solution for one of the product features based on mandatory scope, stable requirements, and fixed-price contract. During a meeting with the supplier, the project manager was informed that the company's business analyst also asked the supplier to add a solution for another feature as part of their deliverable.

What should the project manager do?

A.

Add the feature to the supplier's requirement list so they can deliver it.

B.

Ask the supplier to accommodate the additional scope under the current agreement.

C.

Ensure the project team understands the agreement and contract in place with the supplier.

D.

Monitor the work the business analyst is performing to avoid scope creep.

Full Access
Question # 350

Early in a project, a team member failed to effectively communicate the reason for their absence from three team meetings. How should the project manager handle this situation?

A.

Reaffirm the required project obligations directly with the team member. oy

B.

Ask the team member to explain the reason for the absences.

C.

Assess the impact of the team member's absence on the task involved.

D.

Send a formal letter to the team member stating that their absences are noted.

Full Access
Question # 351

At the end of planning a new project, the project manager needs to schedule the

kick-off meeting but is having difficulty finding a common time slot when all necessary

stakeholders can be available onsite. How should the project manager proceed to

schedule the kick-off meeting?

A.

Email all stakeholders with the objectives of the project and ask for feedback.

B.

Wait for a date when all required attendees can be available onsite.

C.

Run separate meetings to accommodate everyone's schedule.

D.

Schedule a virtual meeting so onsite and remote stakeholders can attend at the same time.

Full Access
Question # 352

An organization uses a hybrid approach to project management. A project manager has been assigned to an external project, project A, where two of the three modules in the project require machine learning skills. The only machine learning expert in the project manager's organization is engaged in an internal project, project B, that is about to end.

What should the project manager do?

A.

Prioritize project A over project B since A is an external project and B is an internal project.

B.

Plan projectA in sprints, starting with the module that does not require machine learning skills.

C.

Engage the human resource manager to employ a machine learning expert for project A.

D.

Plan project A to start at the end of project B when the machine learning expert is available.

Full Access
Question # 353

A project manager receives feedback from the customer's leadership team regarding their annoyance about the frequency of email updates. What should the project manager have done first to prevent this?

A.

Understood the customer's company culture

B.

Updated the communications management plan

C.

Analyzed customer interest and engagement

D.

Scheduled weekly update meetings

Full Access
Question # 354

The project manager of a hybrid project learns that a stakeholder has approached a team member directly to request a change This change will impact the project m a significant way The project manager should ten the stakeholder that the correct procedure tor new requirements is to provide a request directly to whom?

A.

Product owner

B.

Change control board (CCB)

C.

Project sponsor

D.

Project manager

Full Access
Question # 355

A project needs to purchase a specific piece of equipment, as stated in the

project documents and approved by the project sponsor. The procurement division is

questioning the need to buy the specific brand of equipment and has suggested buying a cheaper alternative instead.

What should the project manager have done earlier in the project to ensure the purchase of the specific equipment?

A.

Communicated the project charter to the procurement division

B.

Included a procurement division member on the project team

C.

Reminded the project sponsor about the procurement division's reputation

D.

Communicated the project management plan to the procurement division

Full Access
Question # 356

During a meeting for product review, a key stakeholder announces that because they are receiving adequate information about the project they will not attend any further meetings. What should the project manager do?

A.

Log this as an issue in the issue log and address it with the project sponsor.

B.

Ignore the stakeholder as the product is almost complete.

C.

Explain that the needs will be updated in the stakeholder engagement plan.

D.

Inform the stakeholder that changes can happen in this project.

Full Access
Question # 357

A project manager is managing an internal project that was poorly defined. Recently, the project manager received several change requests raised by the organization's upper management.

What should the project manager do first?

A.

Review the benefits of the proposed changes in relation to the business case.

B.

Assess the time overrun, and start implementation to avoid additional delays.

C.

Request a provisional budget increase to avoid any budget overruns.

D.

Motivate the team to avoid the frustration of working on a prolonged project.

Full Access
Question # 358

A junior project manager with experience in predictive projects has joined a company that uses hybrid approaches for project delivery. A senior project manager with experience in hybrid approaches is assigned to be a coach. Match the activity descriptions on the left to the correct tools on the right.

Full Access
Question # 359

A team is assembled for a new project that will be using a predictive approach through requirements gathering and an agile approach for development and testing Not everyone on the team has experience working in agile. The schedule has started slipping due to the unclear structure of the agile development approach.

What should the project manager have done to avoid this situation?

A.

Established daily standup meetings to track and report on team progress and escalated delays to stakeholders as they occurred

B.

Set up weekly status meetings to review team progress, prepared weekly status reports to track progress and regularly escalated delays

C.

Met with the team, allowed team members to make decisions about what to do and established performance goals

D.

Conducted routine meetings and identified team members who are under performing

Full Access
Question # 360

A senior management team member contacts an agile project lead and mentions

that certain features the senior manager thought would be in the current release were not

included. What should the agile project lead do?

A.

Assure the senior manager that these features will be queued up in the next sprint.

B.

Meet with the team to understand why the senior manager’s features were not included.

C.

Invite the senior manager to the next planning meeting.

D.

Send the product roadmap to the senior manager.

Full Access
Question # 361

A few developers have submitted their resignation after completing their annual review and receiving their annual bonus. The project manager cannot find replacements for all of the developers in time to meet the project's deadline.

What should the project manager do?

A.

Request additional budget to recruit more developers.

B.

Lower the recruitment criteria.

C.

Log the issue in the issue log.

D.

Analyze the impact and inform the stakeholders.

Full Access
Question # 362

In a functional organization, a product analyst is assigned to a short-duration application development effort The analyst expresses concerns about the task and asks the project manager to provide the support of a peer with expertise in this domain

What should the project manager do?

A.

Make sure the analyst has regular pairing meetings with the other team member throughout task execution

B.

Ask the analyst to use skills to develop the tool, then move development to another team member

C.

Enroll the analyst in a capacity-building program and keep this analyst assigned to the task

D.

Recognize the analyst's concerns and reassign the task to another team member

Full Access
Question # 363

An agile team is making infrastructure changes to the human resources (HR) application system. Conflicting requirements are being submitted by various stakeholders.

What should the project manager do to help move the project forward?

A.

Review documents provided by other teams, such as lessons learned and the risk matrix.

B.

Attend the Scrum of Scrums to identify roadblocks and manage dependencies.

C.

Study the technology to assist the team in decision-making if progress slows.

D.

Encourage the stakeholders to collaborate by facilitating meetings and sharing knowledge.

Full Access
Question # 364

A project manager prepared the base budget model to deliver a highly

customizable software solution. The solution will be delivered in multiple countries with

significantly different cultures and will be staged over phases.

What should the project manager do next?

A.

Review the base model with the team leaders in each country to establish an

independent budget for each phase.

B.

Overestimate costs and underestimate revenues to include the impacts of different

cultural elements.

C.

Apply the company's operational budgeting model.

D.

Ask the project management office (PMO) to review the draft budget.

Full Access
Question # 365

An agile project team is building a new product. The stakeholders require ongoing

illustration of project business value.

How should the project manager proceed?

A.

Prepare performance value reports for the business on an ongoing basis.

B.

Include demonstrations of the built portion of the product at the end of every sprint.

C.

Prepare a project report for the stakeholders and distribute it weekly.

D.

Confirm the minimum viable product (MVP) and demonstrate it to the business when it is ready.

Full Access
Question # 366

A project team member complained to the project manager that they are not sure f on the latest requirements document because it was emailed to them about one week ago. They mentioned that, in the past they worked on a document tor more than 20 hours only to find out later that another team member had already updated that same document but did not send them the latest revisions.

What should the project manager do to avoid this situation in the future?

A.

Encourage better team communication by positioning team members closer together.

B.

Implement a project management information system (PMIS)

C.

Update the communications management plan to ensure correct delivery of the latest version

D.

Restrict team members from sending the requirements documents via email

Full Access
Question # 367

A business analyst on the project meets the customer in the elevator and says that due to constant changes in requirements the development of the product will take more time than expected What should the project manager do?

A.

Submit a change request to the change control board (CCB) in order to reflect the new requirements and longer timeline of the project

B.

Refer to the resource management plan to find out if more business analysts may be assigned to process the requirements changes

C.

Point out to the project team and the customer that all information concerning the timeline of the project should be communicated by the project manager.

D.

Explain that distribution of important news can only be done using traceable communication methods

Full Access
Question # 368

At the closing phase of the project the project manager sends the completion reports to the client as a formal written document, indicating that the contract has been completed The client refuses to approve the document since the defect rate is 0.1%. The project manager insists that it is an acceptable rate as the standard defect rate of the industry is 0.15%.

What should have been done to avoid this situation?

A.

The acceptance criteria should have been properly defined in the contract

B.

The client requirements should have been clearly defined in the contract

C.

The Manage Quality process should have been appropriately conducted

D.

The project manager should have reviewed the standard industry defect rate

Full Access
Question # 369

During the execution phase of a project a new project manager is assigned to replace the previous project manager As the project manager starts managing the project, they discover that team performance is significantly decreasing, which is impacting the project's key performance indicators (KPIs). This team has delivered good performance on similar projects in the past

What should the project manager do next to improve this situation?

A.

Call for a team meeting to identify the root cause for the declining performance

B.

Estimate the baseline impacts and submit a change request.

C.

Implement compression techniques to bring the project back on track.

D.

Review the resource management plan and organizational assets

Full Access
Question # 370

A key agile project team member takes a leave of absence in the middle of an iteration and will not return to work for a while What should the project manager do next regarding the feature on which the team member was working?

A.

Assign the feature to another team member, and have them try to complete the feature by the end of this iteration

B.

Review team capacity and reassign the functionality to additional iterations as required

C.

Determine if the team member can work from home to complete the functionality.

D.

Review the work in progress with the product owner to determine the next step

Full Access
Question # 371

A new team member inquires about how much they need to learn about the organizational process assets (OPAs) residing on the company intranet. Another team member states they only need to know the basics. However, the project manager believes the team member should know everything regarding the OPAs.

What should the project manager do?

A.

Create a training schedule for the new team member to follow over the next few weeks.

B.

Escalate the inquiry to the team member's functional manager.

C.

Clarify the relevance of reviewing the documentation on the intranet.

D.

Ask a senior team member to help the new team member navigate through all the documentation.

Full Access
Question # 372

A business stakeholder for a project is reluctant to accept an agile approach due to a previous bad experience, and is pushing for a predictive approach. What strategy should the project manager use to persuade the stakeholder to use an agile approach?

A.

Propose a phased project approach with multiple small interactions and build trust with the stakeholder through frequent value delivery.

B.

Document the request and escalate to upper management to consider a modification of the project charter.

C.

Agree on a predictive approach, but apply agile concepts under the project management umbrella.

D.

Ensure the stakeholder that an agile approach will deliver all of the expected results in a shorter period of time.

Full Access
Question # 373

A junior team member escalates an issue to the project manager about another

member's interpersonal skills causing the team to be less effective.

What should the project manager do first?

A.

Have the team members resolve the issue on their own.

B.

Highlight the impact of their behavior and motivate the team member to make improvements.

C.

Gather information and find the root cause of the problem.

D.

Document the escalated issue and address it at the end of the project.

Full Access
Question # 374

During the initiating phase of a project, a key stakeholder requests frequent changes to the project scope What should the project manager do to improve the stakeholder's engagement?

A.

Discuss the work breakdown structure (WBS) with the key stakeholder and refine the requirements

B.

Update the project backlog and discuss it with the key stakeholder

C.

Update the project charter and discuss it with the key stakeholder.

D.

Discuss the project scope statement with the key stakeholder and build prototypes

Full Access
Question # 375

A project manager has noticed that the performance of a new team member has increased dramatically over the past few months The project manager has been measuring this team member's performance through the cost performance index (CPl) and schedule performance index (SPl) of work packages. The project manager has also assigned new. unrelated work packages to this team member The project manager wants to formally record the team member's success in the project documentation

What should the project manager do?

A.

Attach a note to the project management plan about the team member

B.

Hold a project team meeting about the team member's contribution and take minutes

C.

Record the team member's contribution in the responsibility assignment matrix (RAM)

D.

Send a communication to management recognizing the team member's contributions

Full Access
Question # 376

A project manager is attending a progress meeting with a client The client requests a design change which might potentially add value to the project What action should the project manager take?

A.

Accommodate the change request to serve the client's needs

B.

Consult with team members and allow them to make a decision

C.

Convince the client not to make changes to the project

D.

Make transactional decisions focusing on the project goals

Full Access
Question # 377

A project manager is managing a project that is halfway through its execution phase and the quality standards of the deliverables were formally accepted However, a government agency has recently Introduced new standards that may significantly impact the project The deliverables must be changed to align with the new quality standards

What should the project manager do?

A.

Set up a structured, independent processes to determine if project activities followed the standards.

B.

Schedule training for the project team on the new regulations introduced by the government agency

C.

Evaluate the impact the new regulations will have on the project and submit a change request

D.

Update the lessons learned register and inform senior management of the new standards

Full Access
Question # 378

During a project planning meeting, the customer is not sure how to build a brand new product and is worried about extra costs and work.

The customer is asking the project manager for guidance.

What should the project manager do?

A.

Wait to start the project execution phase until all requirements and acceptance criteria are clear.

B.

Ask the customer to include all of the requirements in the project charter to officially start the project planning phase.

C.

Schedule a brainstorming session and select the top ten most important requirements.

D.

In the planning meeting, focus on releasing a minimum viable product (MVP) quickly and getting feedback from the end users.

Full Access
Question # 379

A project is behind schedule and over budget, resulting in a problem for the next deliverable. The project manager informs the stakeholders, who are very concerned about the project. What should the project manager do to alleviate the stakeholders' concerns?

A.

Send communications for clarification so there is a full understanding about the situation.

B.

Demonstrate the performance indexes and recommend corrective actions to the stakeholders

C.

Schedule a kick-off session to explain the problems of the project and gain approval and support

D.

Speak with the sponsor and explain the situation so that the sponsor can explain it to the stakeholders

Full Access
Question # 380

A project manager is assigned to a new project. The project management office

(PMO) and the project manager agree that this is the right opportunity to include daily

standup meetings. The project team has never used such tools, and a few members are

challenging the decision.

What should the project manager do in this situation?

A.

Engage an external vendor to perform the design phase under an iterative approach.

B.

Request that new team members familiar with iterative approaches be assigned to this project.

C.

Update the project schedule to consider a daily standup as part of the project design phase.

D.

Define the ground rules, responsibilities, and conflict management strategies.

Full Access
Question # 381

During a meeting to define project scope a stakeholder tells the project manager that the main requested feature in the contract is not applicable, and this is documented m the lessons learned. What should the project manager do?

A.

Check with the team to learn what can be done, and consult an expert

B.

Ask the sponsor to close the project and pay the contracted penalty.

C.

Check that this information was documented correctly

D.

Meet with the sponsor to ask for their support

Full Access
Question # 382

A project manager has been assigned to complete a worksite project that was started by a different project manager. The project is now in the execution stage. Upon careful review, the project manager realizes that the local community was not included in the stakeholder register, which has resulted in extreme opposition from the community.

How should the project manager handle this issue?

A.

Disregard these stakeholders since the relevant documents have been secured to execute this project.

B.

Update the stakeholder register and risk management plan.

C.

Update the stakeholder register and revise the stakeholder engagement plan.

D.

Explain to the community members why they were not included as stakeholders for the project.

Full Access
Question # 383

A team has been consistently delivering outcomes. However, based on their current performance, it was discovered that their velocity has decreased by 30%.

What should the project manager do to ensure the velocity is under control?

A.

Ask the product owner to look at a minimum of four to eight iterations and replan the velocity for the next iteration based on the team's current performance.

B.

Ask the scrum master to plug gaps in the team's performance by adding a team member to compensate for the velocity decrease.

C.

Request that the team improve their cycle time to compensate for the velocity decrease.

D.

Request the team to improve the lead time, cycle time, and response time individually and track closure.

Full Access
Question # 384

A project manager is leading an agile project in an organization that has not executed this type of project before. In order to ensure the project is following the compliance requirements, what should the project manager do?

A.

Follow the organization's process and deliverables for predictive projects, even if

they compromise the agility and performance of the project.

B.

Use the risk register to document all of the compliance vulnerabilities generated by

the project so that all decisions are well documented and approved by stakeholders.

C.

Meet with the project management office (PMO)/compliance entity to work on

process tailoring to ensure that the agile deliverables support the compliance requirements of the organization.

D.

Coach upper management on agile practices, explaining that an agile project is concerned with value delivery, and negotiate a way out of the compliance requirements.

Full Access
Question # 385

A project team's performance has declined for the last three iterations Some of the team members are disappointed, and raise their concerns during the retrospective meeting What should the project manager do?

A.

Focus on remediation not merely on correcting symptoms

B.

Compare the team's performance against other project teams

C.

Identify potential failure points based on the iteration workload

D.

Motivate the team to perform better

Full Access
Question # 386

A Scrum team working in an aircraft manufacturing company has completed Its first iteration for a critical project. It is very Important for the project sponsor to complete the project on time and under budget A burndown chart indicates that the project is behind schedule

Which two actions should the project manager take to manage Impediments and improve the team's velocity? (Choose two)

A.

Look for processes that cause bottlenecks and slow down the team's agility

B.

Assign the items with high complexity lo senior developers

C.

Empower the learn to make decisions to remove impediments

D.

Work with the team to remove impediments as quickly as possible

E.

Move the items with high complexity to the last iterations

Full Access
Question # 387

A project manager is managing the scope of the project and creating a work breakdown structure (WBS) with the team members. How should the project manager organize the WBS?

A.

Cost oriented

B.

Deliverable oriented

C.

Customer oriented

D.

Team oriented

Full Access
Question # 388

An operations manager continuously raises concerns about a project's benefits to the company While some concerns are valid most of the time these concerns have caused delays in project meetings

How should the project manager handle this'?

A.

Discuss the meeting delays with the director of operations and ask for support with the concerns.

B.

Review the operations manager's concerns and ensure these concerns are addressed

C.

Escalate the concerns to the project sponsor and discuss options to address them

D.

Include the operations manager's concerns in the risk register and assign actions to mitigate the risks.

Full Access
Question # 389

Experienced team members assigned to a critical project are also supporting several other projects and this is delaying the critical project. If this critical project is not

delivered, the company could receive a fine from the government. What should the project manager do?

A.

Discuss the issue with the project sponsor.

B.

Review the resources required for the tasks on the critical path.

C.

Review and update the risk management plan.

D.

Allocate resources to develop the competencies of the other team members

Full Access
Question # 390

A key stakeholder is upset because the final product delivery has been postponed for the third time. The project manager meets with the stakeholder and discovers that there is a risk of revenue impact if a new feature is not released in 1 month.

What should the project manager do?

A.

Inform the stakeholder that the new requirement will be considered in the next release planning session.

B.

Inform the sponsor of the latest changes and ask the sponsor to prioritize the features.

C.

Ask the product owner to determine if this requirement needs to be treated as a top priority.

D.

Direct the development team to work on this requirement right away.

Full Access
Question # 391

A self-organizing team was delivering as committed. The team accepted a development task with new technology and the iterations started to have reduced velocity. What management decision is suited for this situation?

A.

Provide opportunity for team members to learn and adjust to the technology.

B.

Move team members who are not performing from the team.

C.

Add new members to the team and increase the velocity

D.

Re-assign the project to a team that has worked with this technology

Full Access
Question # 392

During a project status update by the project management office (PMO), the CEO is concerned that the status of all projects suddenly changed from green to red, without warning. Upper management is used to reading traditional reports related to progress and cost, and they want to continue viewing this information.

How should the PMO implement a better way to report the project's health?

A.

Perform a root cause analysis (RCA) to find out why the status of projects is deteriorating so fast.

B.

Explore reporting the earned value (EV) key performance indicators (KPls) using agile progress as an input.

C.

Ask the project managers to report on their projects using a Kanban board format.

D.

Request the program managers to be more accurate when presenting status reports.

Full Access
Question # 393

During the initiation stage of a multimedia exhibition-design project the project manager is developing the project management plan What should the project manager do to complete this task?

A.

Benchmark other similar exhibitions' deliverable lists and final outcomes

B.

Initiate a survey to solicit end-customer opinions and prioritize exhibition contents

C.

Clarify the high-level business requirements with the event organizer as a basis for forming the deliverables list.

D.

Initiate an additional services agreement in case the key deliverables list was not clearly stated in the contract

Full Access
Question # 394

An agile project team discovers that they are unable to implement a feature completely in the first iteration The team believes it may not be able to complete the tasks in the second iteration. The feature is a critical component that the customer has prioritized.

What should the team do?

A.

Go back to the customer and explain that they cannot implement the feature completely in one iteration.

B.

Reduce the scope of the feature to fit into one iteration and deliver it to the customer

C.

Ask the customer to simplify the feature so that it can be implemented in one iteration

D.

Split the feature into smaller subfeatures. implement them, and then deliver them incrementally in multiple iterations

Full Access
Question # 395

An organization is transitioning to an agile environment. The project manager finds that most of the team members are not familiar with an agile environment.

What should the project manager do to address this concern?

A.

Change the approach with the team.

B.

Meet with an agile coach to handle this issue.

C.

Analyze the level of the team's agile maturity.

D.

Support the team members' growth and development.

Full Access
Question # 396

The project sponsor requested technical specifications for a project-related component. The project sponsor does not have the authorization to see the specifications, but insists on seeing them.

What should the project manager do first in this situation?

A.

Meet with the project sponsor as soon as possible to discuss the matter further

B.

Update the issue log to make the project team aware and to develop a strategy

C.

Create a stakeholder engagement plan to help the team formulate a response

D.

Provide the specifications to the project sponsor with some information removed

Full Access
Question # 397

In a weak matrix environment, two key team members are falling behind with their tasks, which will affect the success of the project.

Further investigation by the project manager reveals that they have unresolved issues with each other. The project manager asks them to find a way to resolve the issues, but this is unsuccessful. The project manager then holds a meeting with them to work outa permanent solution to the issues, but this is also unsuccessful.

What should the project manager do next?

A.

Escalate the issue to a higher authority.

B.

Suspend the two key team members immediately.

C.

Put the issue on the agenda for the next team meeting.

D.

Reassign one of the key team members to a different task.

Full Access
Question # 398

A project manager has just taken over a project that is halfway through its schedule. In a brief meeting with the client’s key project team, the project manager receives several requests from a specific client team member who was not at the project team meeting. The requests for information seem to be for trivial information that was previously submitted in project documents.

What should the project manager do first?

A.

Send an email to the client team member explaining that they have the information already.

B.

Review the stakeholder register to gain insight into the expectations of that team member.

C.

Inform the client project manager that they are sending too many trivial requests.

D.

Update the project risk register to include potential delays in answering these requests.

Full Access
Question # 399

In a global project, the project manager has to plan and manage communication between the team members and stakeholders in order to ensure the project will remain on track and achieve its goals.

What should the project manager do?

A.

Consider cultural differences among stakeholders.

B.

Conduct an integration meeting among all stakeholders.

C.

Schedule communication training for management-level stakeholders.

D.

Understand how political aspects can affect the project.

Full Access
Question # 400

A project manager decided to incorporate the latest technological advancement with the client's devices at no additional cost to the project.

Upon completion and submission of the project deliverables, the client rejected the devices, despite having the latest features.

What should the project manager have done?

A.

Incorporated the change within the scope of the project

B.

Reviewed the quality inspections

C.

Complied with the customer specifications

D.

Documented the technical reviews with the new change

Full Access
Question # 401

A project manager is working on the budget for a long-term project. The project manager creates a work breakdown structure (WBS) and estimates the cost for each work package based on past projects.

What else does the project manager need to do before determining the budget baseline?

A.

Look at a previous project to ensure the budget totals match.

B.

Require all stakeholders to review and approve the estimates.

C.

Revise the project timeline and scope based on the WBS.

D.

Add contingency into the budget for inflation and other changes.

Full Access
Question # 402

A project sponsor receives project information and updates in a timely manner, but

the sponsor is concerned because key information is missing in the reports. What should the

project manager do?

A.

Review the communication needs of key stakeholders.

B.

Confirm that the project information is understood and feedback is received.

C.

Determine communication methods, frequency, and level of detail.

D.

Provide all project information to the stakeholder.

Full Access
Question # 403

Since the beginning of a project, the product owner keeps asking during ceremonies about the budget spent for each product iteration The product owner seems much more interested in the cost rather than the product itself.

What should the project manager have done earlier to change the product owner's behavior''

A.

Worked on a fixed-price contract to switch the product owner's attention to value instead of money

B.

Worked on a communications management plan with reports of budget spent in each iteration versus planned to avoid these discussions during ceremonies

C.

Worked on different approaches of estimating to give confidence of the cost spent in each product increment.

D.

Worked with the product owner to clarify their role in an agile project and the scope of the agile ceremonies

Full Access
Question # 404

A project manager scheduled a session to identify risks on the current project. Most of the stakeholders did not attend the meeting, although they previously confirmed their attendance.

How should the project manager proceed in order to complete the risk register?

A.

Cancel the meeting and create the risk register using the project documents.

B.

Continue the meeting and send the updated risk register to all stakeholders.

C.

Run the meeting and follow up with each one of the absent stakeholders to get their input.

D.

Escalate the issue of stakeholders not attending the meeting to the project sponsor.

Full Access
Question # 405

A large company has agreed on a business case for an environmental project. The

project will cause some major changes in their operations, such as reduction in paper use,

which will obviously affect all of the users.

What is the first thing the appointed project manager should do?

A.

Evaluate the impact to the users and create a plan to address it.

B.

Inform users about the new changes and ask for their collaboration.

C.

Ask all managers to collaborate implementing this change to users.

D.

Start implementing the change so that users will eventually get used to it.

Full Access
Question # 406

A project manager for a large project's agile team is developing new workflows to meet changing business needs. As the second sprint is running, the product owner and agile team begin to receive more details that impact the scope change of running items. The agile team

requests a change in the sprint goals and sprint backlog items.

What should the project manager do?

A.

Create a parallel sprint to deliver the additional items.

B.

Guide the agile team to add the new scope to the product backlog.

C.

Pause the sprint to allow time to include the new items.

D.

Moderate the expectations for sprint quality.

Full Access
Question # 407

A team member is hosting an event and invites several colleagues through their work calendars Another team member, who was not invited to the event, is noticeably distracted during several standup meetings

What should the project manager do?

A.

Ask the individual who is hosting the event to use private communication methods.

B.

Set up a meeting with the distracted team member to discuss any issues

C.

Add a social events section to the charter to handle these situations

D.

Ask the individual who is hosting the event to mark it as private

Full Access
Question # 408

A project scope was developed with numerous assumptions. During the execution phase, the assumptions changed, which has jeopardized the planned business value of the project.

% What should the project manager do next?

A.

Update the assumptions log and change log, and implement the change control process.

B.

Report on the changed assumptions to the project sponsor and seek support to prioritize the change requests.

C.

Inform the client that the project cannot meet the project timeline and additional costs will be incurred.

D.

Deliver what was planned in the project management document according to the specifications.

Full Access
Question # 409

In an agile project, the project manager notices that one team member rarely reports blockers during daily check-ins. Additionally, the team member is too shy to participate in team activities and prefers to provide status updates individually to the project manager.

How should the project manager rectify this situation?

A.

Review team culture and the personality traits of the individual to address status update gaps.

B.

Create a safe space for status updates and encourage the team to approach the project manager.

C.

Review the team status updates more thoroughly to address the gaps.

D.

Support team inclusion and change the format of status updates to email.

Full Access
Question # 410

A project manager is transferred to another country to perform a project within their organization. What should the project manager do first to ensure collaboration within the team for a successful delivery?

A.

Determine a leadership style that is suitable for that location.

B.

Check if resources from headquarters can also be assigned to the project.

C.

Mentor the team members to perform project management.

D.

Assign a local resource to manage communication with the team.

Full Access
Question # 411

The business manager and the product owner are requesting a more flexible way to incorporate changes into the product baseline They are concerned about losing time to market with respect to other vendors

What should the project manager do?

A.

Review the assumption log and project management plan for changes.

B.

Identify adequate change management tools to conduct the project

C.

Establish a change control board (CCB) with key stakeholders.

D.

Allow key stakeholders to make some changes to deliver the product faster

Full Access
Question # 412

During a project review meeting, several project team members expressed that they did not have an understanding of the benefits of certain features for the project What should the project manager do next?

A.

Review the project scope statement

B.

Confirm ownership for ongoing value realization

C.

Escalate the issue to the project sponsor

D.

Appraise the stakeholders of value gain progress

Full Access
Question # 413

A project manager is assigned to a strategic communication project that involves

subject matter experts (SMEs), interns, and new recruits. The project manager discovers

that the project is not gaining much traction due to knowledge gaps from the interns. The

budget for training is exhausted and the project needs to be delivered without delay.

Which two actions should the project manager take? (Choose two)

A.

Identify the sources and specifics of the knowledge gap from the interns and new

recruits.

B.

Hire more SMEs and inform the human resources manager to lay off the

nonperforming interns and new recruits.

C.

Initiate a project change request for additional budget to train the interns and new

recruits.

D.

Ignore the issues with the project and try to deliver the project successfully without

asking for training funds.

E.

Put the interns and new recruits into groups and assign a SME as a mentor.

Full Access
Question # 414

One of the service providers on a complex project has been facing resource

availability problems over the last six months. However, the service provider has assured the

project manager that the deliverables will be on time.

How should the project manager address this situation?

A.

Update the issue log.

B.

Perform a qualitative risk analysis.

C.

Perform a root cause analysis.

D.

Implement a risk response plan.

Full Access
Question # 415

At a meeting to receive approval for the project management plan, a project manager realizes that there is so much detail in the presentation that many of the stakeholders are not actively engaged in the process. The stakeholders are agreeing to the scope, goals, and timelines without giving them substantial thought.

How should the project manager proceed?

A.

Stop the meeting and reschedule for another time with a more concise presentation.

B.

Set up information review sessions before reconvening another approval session.

C.

Get approval and promise to email more information to the stakeholders to clarify the technical details.

D.

Obtain approval as fast as possible and close the meeting.

Full Access
Question # 416

An intern is replacing a critical resource midway through a sprint To help the intern get up to speed, the project manager assigns a senior engineer in the team as the intern's mentor Two months later, the project goes into critical status, delaying the release milestone by a month.

What should the project manager have done to avoid this scenario?

A.

Convinced the critical resource to remain on the project.

B.

Requested an experienced resource as a replacement

C.

Allocated additional time for mentoring

D.

Negotiated additional time to complete the project

Full Access
Question # 417

A project manager joins a startup and discovers that the chief technology officer (CTO) encourages the team to overlook some procedures in the interest of speed. What should the project manager do to ensure that all the procedures are followed in the future?

A.

Develop new procedures that are easy for the team to follow.

B.

Escalate the issue to the CEO and the board members.

C.

Instruct the team that the procedures should always be followed.

D.

Initiate a review of the procedures with the CTO and the team.

Full Access
Question # 418

A project management team received news that a competitor has released the

latest version of a program. What should the team do next?

A.

Review the project plan to evaluate if any updates should be made.

B.

Crash the existing schedule with additional resources to deliver more features.

C.

Stop the project immediately as the market opportunity has already been missed.

D.

Continue with the project plan and target delivery date as expected.

Full Access
Question # 419

local company is developing a new product and. for the first time, using a remote

team for the programming tasks of features. The design for the product comes from the local team. During the third sprint review, the product owner has concerns about the project's

outcomes. The remote development team is complaining that they do not clearly understand the requirements conveyed in the daily standup meetings.

How should the project manager address this situation?

A.

Evaluate and reassign the developing tasks to a local vendor who has worked on previous projects.

B.

Document the risk in the risk management plan and use contingency reserves to hire a local vendor.

C.

Review lessons learned from previous projects and organizational process assets (OPAs).

D.

Determine the communication needs, environment, and tools to get the message across.

Full Access
Question # 420

A company is moving its headquarters to another city. The project manager responsible for the assignment has been using a predictive approach during the transition. However, the information systems will be migrated using an agile approach. The project manager needs to decide which kind of control to sign with the vendor responsible for migrating the systems.

How should the project manager address this situation?

A.

Negotiate payment after all project migration is completed

B.

Sign a single agreement for the whole project

C.

Use fixed-price increments as user stories are completed.

D.

Confirm payment after each project retrospective

Full Access
Question # 421

A project manager is using a hybrid approach for project delivery. The

development team was sized, but is not yet fully resourced. The project manager is working

on defining the project schedule.

What should the project manager do to address the issue of developer availability?

A.

Organize a planning session with the development team and use their estimations to complete the schedule.

B.

Ask the resource manager when the new contractor is available to start and change the delivery date for the project schedule.

C.

Ask the sponsor to provide the desired completion date for project activities and complete the schedule.

D.

Use expert judgment to estimate all of the tasks and complete the schedule in the allocated time.

Full Access
Question # 422

A project manager is managing a project which is approaching the end of the execution phase. A high-level stakeholder informs the project manager that a very important requirement was not included in the scope of the project, and that without that requirement the project will deliver no value.

What is the first thing the project manager should do"?

A.

Include the requirement into the project and schedule it as soon as possible

B.

Inform the project sponsor about the situation and request assistance

C.

Evaluate the impact that the inclusion of this new requirement will have on project performance

D.

Inform the stakeholder that it is impossible to add new requirements to an approved project scope

Full Access
Question # 423

At the end of the last iteration, the customer rejects the deliverables since they did

not meet the customer's expectations. What should the project manager have been done

to prevent this situation?

A.

Involved the customer more in the planning process for the project, and ensured

agreement on the proceedings.

B.

Included all relevant criteria in the agreed upon definition of done (DoD), and crafted a shared product vision.

C.

Provided the customer with the backlog and the specified user stories at the beginning of the iteration.

D.

Developed the DoD in close cooperation with all stakeholders to ensure their expectations were included.

Full Access
Question # 424

The project manager has recently received funding approval for a training program

for the entire project team but has not yet defined the most effective training course. One

team member submitted a request for specialized training that is required for the project.

How should the project manager handle this request?

A.

Send this change request to the change control board (CCB) for approval.

B.

Approve the request for the specialized training.

C.

Reject the request as it does not impact the project deliverables.

D.

Validate if the training is within scope and budget.

Full Access
Question # 425

A project manager is working on a large project with a very difficult client. During

the course of the project, the project manager realizes that if the project team had a little more time and funding to make some minor changes, the client could realize the benefits of 25% of the project outcomes early.

How should the project manager approach this?

A.

Concentrate on the current project milestones.

B.

Update the project management plan for this new work.

C.

Develop a business case and submit it to the client.

D.

Make all the changes and then show the client the results.

Full Access
Question # 426

While developing a new product, a key stakeholder expresses concern about

insufficient information on product feature requirements. The product team disagrees and

mentions that detailed requirements have been provided.

What should the project manager do to handle this situation?

A.

Organize a discussion with the product team to clarify the missing information.

B.

Redirect the stakeholder to discuss this request with the functional manager.

C.

Record the new requirements and ask the product team to develop them.

D.

Conduct new risk and scope analyses, identifying the missing information.

Full Access
Question # 427

A new project manager is assigned to a project in the execution stage. A few key stakeholders inform the new project manager that the project has some serious issues.

What should the newly assigned project manager do first to understand the issues?

A.

Escalate the issues to the project sponsor.

B.

Review the issues log to ensure the issues are captured.

C.

Check the risk management plan to ensure there is a strategy to address the issues.

D.

Ask the key stakeholders to discuss the issues with the project team.

Full Access
Question # 428

During a project review meeting, the project sponsor is worried that the protect may not be delivering results as planned Based on that the project manager is evaluating the project status. What information should the project manager use as an indicator that the project is actually delivering value?

A.

Stakeholders are satisfied with the current status.

B.

The project is under budget and on schedule

C.

The project is aligned with the project charter

D.

The protect is aligned with the benefits management plan

Full Access
Question # 429

An agile project is starting and the assigned team is new to agile During the first daily meetings, the project manager observes that the team is having problems meeting goals What should the project manager do?

A.

Plan an outdoor activity tor the team to get to know each other

B.

Ask the team to review agile protect management approaches.

C.

Ask the human resources department for an experienced agile team

D.

Conduct a meeting to help the team define the team charter

Full Access
Question # 430

A project manager is preparing a project closure report. The project sponsor is confident about the success of the project, but the client is not sure that the project outputs will achieve their business needs.

Which aspect should the project manager highlight in the closure report to address the stakeholder's concern?

A.

How the quality was managed

B.

How the acceptance criteria were met

C.

How the scope was managed

D.

How the stakeholders were managed

Full Access
Question # 431

In the middle of a project, a business unit manager who regularly interacts with the project manager's team is promoted to a higher management position. The replacement manager is from the same unit and is somewhat familiar with the project.

After getting more information about the new manager, what is the project manager's next step?

A.

Contact the previous business unit manager to learn more about the new manager.

B.

Update the stakeholder register and the stakeholder engagement plan to include the new manager.

C.

Send the new manager a copy of the project charter to ensure the project objectives are understood.

D.

Schedule a meeting with the new manager to discuss the business analysis team's plans.

Full Access
Question # 432

The team architect resigned from the company. The new architect points out a

design flaw during a planning meeting that may potentially impact the final quality.

What should the project manager do first?

A.

Review the scope management plan.

B.

Update the design with changes.

C.

Request an architecture review.

D.

Update the quality management plan

Full Access
Question # 433

A year after implementing a policy change to improve diversity and inclusion within two teams, there is increasing conflict within the company What should have been done to prevent this conflict?

A.

The organization should have introduced the concept of diversity broadly

B.

The leadership team should have worked closely with the marketing team to get insight on diversity

C.

Organization-wide diversity training should have been provided to the workforce

D.

The critical departments in the organization should have been involved in this exercise

Full Access
Question # 434

A company is developing a new product. During project planning, a stakeholder from the legal department does not attend any of the project meetings and is not interested

in the product design.

How should the project manager deal with this situation?

A.

Escalate the issue to the project sponsor and seek assistance.

B.

Engage the project stakeholder and ensure all requirements are captured.

C.

Review the stakeholder engagement plan and communication strategy.

D.

Review the product requirements and update the stakeholder register.

Full Access
Question # 435

During the execution phase, the project manager discovered that the deliverables

are not meeting the quality specifications requested by the main stakeholder. This has

caused the schedule performance index (SPI) to deteriorate from 0.98 to 0.72 and the cost

performance index (CPI) from 1.5 to 1.1.

What action should the project manager take to mitigate the issue of the deliverables being

rejected during the next iteration?

A.

Submit a change request to prioritize resolutions for the quality issue to minimize the impact on the rest of the deliverables.

B.

Reinforce the definition of done (DoD) during sprint planning so that the team has a common understanding of expectations.

C.

Assure that the product backlog is properly prioritized to avoid dependencies that cause rejection.

D.

Create a dedicated sprint to complete all of the pending specifications from previous sprints.

Full Access
Question # 436

A project manager is in the middle of an agile project comprised of 100 user stories broken down into five iterations Each user story is worth USS50 The actual expenditure is US$2,000 and 50 user stories have been delivered.

Which statement is true''

A.

The project is on budget and on schedule.

B.

The project is over budget and behind schedule

C.

The project is under budget and behind schedule.

D.

The project is under budget and on schedule.

Full Access
Question # 437

The project manager has finished all the tasks of the project and immediately starts on a new project. A few months after beginning the new project, the accounting manager asks for confirmation of previous projects because the budget is still open with no further cash flows.

What should the project manager have done?

A.

Conveyed task completion information to accounting

B.

Closed the procurement process properly

C.

Completed the transition process

D.

Performed administrative closure of the project

Full Access
Question # 438

A project started 12 months ago and is currently on iteration 12 of 14. The team

has performed well and completed all deliverables on time. However, some team members

are starting to complain about the length of the project, creating a risk for lack of

performance at this critical stage.

What should the project manager do as a servant leader to mitigate this risk?

A.

Meet with the team to reinforce their responsibilities and the consequences if the

project deliverables are not completed on time.

B.

Apply additional controls to the project deliverables to ensure that all milestones

are achieved on time.

C.

Contact the functional manager to ensure that team motivation remains high until

the end of the project.

D.

Schedule a team event with the project sponsor to highlight the importance of the

project and recognize the work of the team.

Full Access
Question # 439

In a fixed time and budget project the customer wants the development of a core component to be based on agile practices, as the final scope of (he requirement has not yet been fully developed. The project manager is participating in contract development with the sales team and wants to ensure that development costs do not impact the profitability of the project.

Which two controls should the project manager incorporate into the contract to specifically address the development of the core component? (Choose two)

A.

Limit the number of iterations for development in the contract.

B.

Establish a governance committee to review the contract delivery

C.

Tier the contract for fixed and agile components

D.

Provide alternatives to scope change at specific project phases within the contract.

E.

Require that only internal resources be utilized for this project

Full Access
Question # 440

In a construction project for a new building, the project manager decides to apply agile principles for the building foundation phase While evaluating the project schedule with the team, the project manager believes that the estimates are inaccurate. How should the project manager address this issue?

A.

Create a product backlog

B.

Perform sprint reviews with the team

C.

Assess the previous project velocity

D.

Reduce the story size by splitting stories

Full Access
Question # 441

A multinational company is launching a company-wide digital transformation project that covers all of its regions and business lines. The project is expected to go through five phases and finish in 2 years. The project manager schedules a kick-off meeting.

What should the project manager do next?

A.

Ensure there is enough budget to mandate all team members to fly to corporate headquarters for the kick-off meeting.

B.

Consider using digital or virtual tools to conduct the kick-off meeting to minimize geographic boundaries.

C.

Document the kick-off meeting and close out the planning phase after the meeting is held.

D.

Limit to one kick-off meeting in the project's first phase in order to control the budget.

Full Access
Question # 442

A team member has indicated their user story will not be finished until the end of the iteration as their functional manager has requested they assist in resolving a high-priority production issue. What should the project manager do?

A.

Discuss with the product owner that the user story will not be completed this iteration.

B.

Meet with the team member's functional manager to try to remove the impediment.

C.

Tell the project team member not to work on the production issue and to inform their manager.

D.

Escalate the issue to the project sponsor to resolve and adjust the project burndown chart.

Full Access
Question # 443

A project team is working on a product that is planned for multiple iterations. They are delivering incremental value.

When should the value be demonstrated?

A.

After full development is completed

B.

When a major feature is completed

C.

At the end of each and every iteration

D.

When the sponsor approves the increment

Full Access
Question # 444

During a project status meeting with senior managers, the project manager gives an update about the status of a deliverable. Some of the senior managers claim not to Know about the deliverable.

What should the project manager do next?

A.

Validate if the project charter changed from the original one.

B.

Meet with these stakeholders to review the project charter.

C.

Check if these stakeholders attend regular project meetings.

D.

Review the project charter to validate this claim.

Full Access
Question # 445

A project manager is managing a national rollout for an innovative product in a regulated environment that is expected to change. The project management office (PMO)

needs visibility of the regulatory constraints while maintaining a degree of flexibility.

Which tool can the project manager use?

A.

Use a burndown chart to provide transparency.

B.

Use a kanban board to increase accountability.

C.

Use a product backlog to manage changes.

D.

Use a burnup chart to provide transparency.

Full Access
Question # 446

A project manage is in the middle of an angle project comprised of 100 user stories broken down into five iterations. Each user story is worth U$$50. The actual expenditure is U$$2,00 and 50 user stories have been delivered.

Which statement is true?

A.

The project is over budget and behind schedule.

B.

The project is under budget and on schedule.

C.

The project is under budget and behind schedule.

D.

The project is on budget and on schedule.

Full Access
Question # 447

A project manager has been assigned to a new project that is similar to a project that was closed last year. There is no schedule baseline, but the project manager received the activity list and wants to prepare a reasonable schedule.

What should the project manager do?

A.

Adopt the same timeframe as the closed project for the current project.

B.

inform the sponsor that the activity list is not adequate for creating a schedule baseline.

C.

Create a draft schedule based on the activity list and the historical data from the closed project.

D.

Evaluate each activity duration and build a new project schedule.

Full Access
Question # 448

A project manager identifies a risk that has a high probability of occurring. How should the project manager manage this risk?

A.

Submit a change request to transfer the risk to a third party in case it becomes an issue.

B.

Remove the user stories associated to that risk and avoid the impact to the project deliverables.

C.

Assign a qualified team member to be the risk manager for the project.

D.

Ask the team to monitor the risk and provide an alert if it becomes an issue.

Full Access
Question # 449

During the third iteration of a project, the product owner requests another mandatory feature. This also happened in the previous two sprints, which resulted in failure and caused frustration within the team.

What should the project manager do next?

A.

Incorporate the changes in the last sprint before the first release.

B.

Call for an internal meeting to discuss the changes and their value.

C.

Ask the product owner to prioritize the backlog with the project team.

D.

Request the scrum team to prioritize the product backlog.

Full Access
Question # 450

A complex project is in the execution phase. A key stakeholder who is new to the project has not been approving project deliverables, which could impact the overall

progress.

What should the project manager do next?

A.

Capture this in the issue log and escalate it to the project sponsor.

B.

Meet with the stakeholder to understand what is causing the delays.

C.

Facilitate a brainstorming session to find potential workarounds.

D.

Discuss the need to influence this stakeholder with the sponsor.

Full Access
Question # 451

A project manager is assigned to a dental equipment development project that is in the middle of its design phase. After reviewing the project prototype, it is identified that a couple of requirements specifications are missing.

Which action should the project manager take next?

A.

Discuss with the team and build a workaround plan to immediately deliver the pending requirements specifications.

B.

Ask the team to wait until they are able to update the requirements specifications.

C.

Prepare a change request for the change control board (CCB) to remove the missing requirements specifications.

D.

Meet with the development team to review and assess the requirements specifications.

Full Access
Question # 452

During the implementation phase of a project, functional managers are adding new requirements, which may impact cost and schedule baselines. The project manager

notices that some of the team members are communicating with their managers directly to fulfill their requests. This will lead the project to go beyond the agreed baselines.

How should the project manager handle this situation?

A.

Set up a proper governance structure to ensure functional managers’ requests are processed correctly.

B.

Modify the communications management plan to enable functional managers to add changes to the project.

C.

Follow the project constraints and move forward with the agreed schedule baseline and the cost baseline.

D.

Ask the functional managers to communicate with their peers and emphasize the impact of their requirements.

Full Access
Question # 453

A scrum team's daily meetings are conducted by teleconference between three teams, each located in different countries. The meetings typically

last 45 minutes with many misunderstandings due to language barriers.

How should the project manager resolve this issue for the next iteration?

A.

Transfer half of the backlog items to the next iteration to allow more time to complete the meetings.

B.

Extend the meeting to 1 hour and request that all of the participants bring up all of the issues.

C.

Instruct the meeting participants to speak only about blockers during the meeting.

D.

Train the three team leads to conduct a local meeting, then run an overall status meeting.

Full Access
Question # 454

During the execution of a project to develop a prototype, the customer asks the project manager to stop the prototype line and purge a specific

component based on recent reliability tests that have deemed the component to be deficient. The project manager checked the quality

management plan and there is no reference to this component.

What should the project manager do next?

A.

Inform the project sponsor of the situation and wait for the sponsor to provide further directions.

B.

Call a technical meeting with the customer to agree on a specification for the component and document it in the quality management plan.

C.

Submit a change request to proceed with the replacement of the component and wait for further customer instructions.

D.

Keep running the manufacturing line because there are no quality specifications for this component.

Full Access
Question # 455

A CEO of a general contracting company urgently asks the project manager to sign up two project team members to participate in a specific training course. Halfway

through the training, both team members complain that the training is too difficult, above their experience level, and that the material does not align with their tasks.

What should the project manager have done to prevent this situation?

A.

Communicated with the two team members that the purpose of the training is to provide material that might be useful to them in the future

B.

Sent an immediate request to the human resources (HR) department to replace the current team members with higher skilled candidates

C.

Observed and assessed the competencies and skills of the team members and analyzed the training material beforehand

D.

Planned a training to follow the specific course to bring the two team members to the required experience level

Full Access
Question # 456

A project manager works in an organization that embraces using different project approaches. The project manager's current project uses a

predictive approach with clear requirements. A few months following the kickoff, the project manager notices that the virtual development teams

are not communicating enough, and coordination is becoming an issue. The teams are not aligned on the tasks being done or the current

impediments.

What should the project manager do?

A.

Ask the members to be more proactive and share ideas with each other.

B.

Set up a daily virtual meeting with the development team.

C.

Plan a monthly virtual meeting to align and to review the plans.

D.

Review the issue with the project sponsor and ask for support.

Full Access
Question # 457

A software delivery project began having technical impediments. The issue may cause a delay of the deliverables. The technical service team has been working on the issue, but the issue is unresolved even after 1 week of maintenance.

What should the senior project manager do now?

A.

Use interpersonal skills to expedite the issue.

B.

Send a gentle reminder to the technical service team.

C.

Update the issue log with the status and priority.

D.

Issue a formal warning to the technical service team.

Full Access
Question # 458

During the last iteration of a hybrid project, one of the key members of the team wants to leave the project. What should the project manager do to address this concern?

A.

Keep activities as planned regardless of the resource change.

B.

Update the burndown chart to reflect this resource's absence.

C.

Have a meeting with the resource to understand the issue.

D.

Request an additional resource to finish the project.

Full Access
Question # 459

A project manager has been assigned as the servant leader for an ongoing project that historically has presented unexpected problems. The main stakeholder is hesitant to continue with the rest of the sprints even though there are no open issues or indications of risks at this stage.

What should the project manager do to address this problem?

A.

Increase the contingency reserves to cover unknown-unknowns.

B.

Implement short cycles for inspection and provide feedback.

C.

Increase the management reserves to convert the known-unknowns.

D.

Create a new risk entry to identify the stakeholder as a detractor.

Full Access
Question # 460

A project manager is working on a project with three virtual teams. Team A is in a different time zone than teams B and C. The project was going

well, but recently team A has started feeling left out. Information reaches team A late or is sometimes missed, and teams B and C give preference

to each other's problems over team A. The project manager has already set project guidelines, but realizes they need to be improved.

Which two things should the project manager do to help the teams collaborate better? (Choose two)

A.

Schedule weekly progress meetings with all three teams and have them take turns as key players.

B.

Plan for team members to temporarily work at each other's locations to better provide a sense of community.

C.

Update the communications management plan and encourage the teams to review it promptly and proactively.

D.

Create a status reporting template and share it with all team members before the day ends.

E.

Schedule daily meetings with each team to understand their progress and concerns in detail.

Full Access
Question # 461

The testing backlog for a hybrid project has increased significantly and is becoming a bottleneck. The team has researched a tool that could

resolve the bottleneck, and the project manager has been informed.

What should the project manager do next?

A.

Add developers to remove the backlog.

B.

Escalate the issue with the product owner.

C.

Reduce the testing scope of the backlog.

D.

Enroll team members in training on the tool.

Full Access
Question # 462

The investment committee is the authority for the approval of funding required for a business improvement project. The investment committee approved funding to complete

the preliminary feasibility study. The project is on an expedited schedule, and the project manager requires interim funding to continue with the preliminary feasibility

activities that must commence immediately.

How should the project manager get these funds approved?

A.

Wait until the next investment committee meeting to submit the request and include the delay in the schedule due to work that could not start.

B.

Continue with the preliminary activities and inform the investment committee at the next monthly meeting.

C.

Exclude the preliminary scope from the full project scope and continue it as a new project that does not require investment committee approval.

D.

Submit the request to the project director for interim approval and include this approval for discussion at the next investment committee meeting.

Full Access
Question # 463

A major issue about conflicting priorities has been highlighted by the project team with regard to a few stakeholder requirements. What should the project manager do?

A.

Prioritize other items for the team and deal with the conflicting requirements later.

B.

Allow the project team to decide what is the most appropriate requirement to follow.

C.

Escalate to the project management office (PMO) and request a solution for the requirements.

D.

Negotiate a common agreement with the involved stakeholders regarding the requirements.

Full Access
Question # 464

A project manager is working with a customer's team on a new project. Some product definitions and requirements are still not clear, but the customer wants to start

activities as soon as possible. The organization is also expecting product delivery for a specific date due to a regulatory requirement. Due to the nature of the project, the

project manager has decided to use a hybrid approach.

Why did the project manager choose a hybrid approach?

A.

A hybrid approach will ensure the delivery date is accomplished and will eliminate product uncertainties.

B.

A hybrid approach will enable project activities to start immediately and allow for a plan for the requirements definitions.

C.

A hybrid approach will allow the project manager to revise the product specifications.

D.

A hybrid approach will allow for management of the requirement uncertainties as well as the date restriction.

Full Access
Question # 465

During a team meeting, the new agile project manager becomes aware that there are many complaints from the customer regarding project stability and other critical issues.

A team member states that the deliverables were developed by experienced employees who confirmed that the project was stable.

How should the new project manager address these concerns?

A.

Allow the agile team to decide what they are able to deliver in each iteration

B.

Ask the team for additional feedback and add tasks to the task board,

C.

Hold a brainstorming session to identify the root cause of the complaints.

D.

Document the customer's complaints and critical issues in the issue log.

Full Access
Question # 466

A project manager is leading a hybrid project. The work breakdown structure (WBS) and the schedule were developed, but the project manager is having difficulty assigning specific resources to all of the project tasks.

What should the project manager do?

A.

Escalate the issue to the project sponsor and seek their immediate intervention.

B.

Assign the unallocated tasks to the functional role and then reallocate when the resources are available.

C.

Assign the unallocated tasks to the project management office (PMO) manager and reallocate when the resources are available.

D.

Ignore the unallocated tasks for now and reallocate when the resources are available.

Full Access
Question # 467

During the execution phase of a healthcare IT project, the project manager finds one stakeholder is very difficult to communicate with and obtain

feedback from on project deliverables. What should the project manager do?

A.

Share a template with the stakeholder to receive feedback on deliverables.

B.

Ask the project sponsor to arrange a meeting with the stakeholder.

C.

Use networking skills to approach the stakeholder.

D.

Update the stakeholder engagement plan for the stakeholder.

Full Access
Question # 468

A product owner has returned from a meeting with a few key stakeholders, who expressed interest in learning more about the project progress. The product owner is

seeking the project manager's recommendation on how to approach this request.

What should the project manager do to help the product owner?

A.

Provide an overview of the completed functionalities and release plan, and capture expectations for future stakeholder involvement.

B.

Invite the product owner to future demonstrations where they can provide feedback.

C.

Provide access to the latest user acceptance test (UAT) environment so they can see the solution.

D.

Remind the product owner of stakeholder accountability, and ask the product owner to determine the appropriate next steps.

Full Access
Question # 469

A telecommunications project consists of departments spread across several countries with different cultures. The project team rarely meets in person, and each team member works independently using online reporting tools.

What should the project manager do to ensure team members are committed to project success?

A.

Control and follow the project's mam goals, budget, and schedule

B.

Plan regular virtual meetings to motivate and support the team.

C.

Meet in small groups and share information by email with the rest of the team

D.

Create a monthly report so everyone will be informed of the current status.

Full Access
Question # 470

A senior employee with experience relevant to a highly complex project is seeking a promotion to be able to join the project. The employee has made a recommendation regarding the project. The project charter was recently approved.

How should the project manager address the employee's request?

A.

Evaluate the employee's recommendation by reviewing the lessons learned from a similar project.

B.

Create a salience model to determine if the employee will have influence on the project.

C.

Ask the project sponsor to revisit the project charter to consider the employee's recommendation.

D.

Assess the influence and power of the employee to see if the employee will add value.

Full Access
Question # 471

A risk was identified at the beginning of a project, and a response plan was established. Unforeseen consequences resulted in a higher level of

risk. The project manager has an idea that could address the new risk in an efficient way, but the response is different from the original risk

mitigation plan.

What should the project manager do?

A.

Submit the new response plan to the stakeholders for their review.

B.

Obtain management approval prior to implementing the new risk response.

C.

Use the management reserve to mitigate the risk.

D.

Implement the new response to address the risk.

Full Access
Question # 472

A project team is performing extremely well when it comes to delivering the value-added features to the customer in each sprint. However, they are missing the

documentation portion and the project manager must find a way to make sure the documentation is kept current.

Which action should the project manager take?

A.

Create a specific sprint to deliver the project documentation.

B.

Assign a dedicated resource to work on the documentation during the project.

C.

Make documentation a standard part of the definition of done (DoD).

D.

Focus on the documentation after the features are delivered.

Full Access
Question # 473

A new team member joins an agile team. In a previous role, this team member was a subject matter expert (SME). This team member often directs the team on how to solve problems based on previous experience.

What should the project manager do first?

A.

Update the definition of done (DoD) to include a review by the new team member to ensure the best outcome of each deliverable.

B.

Ask the new team member to create a wiki that the rest of the team can reference in the future for all questions.

C.

Ask the new team member to size all the stories in the backlog so that the rest of the team can focus on delivery.

D.

Let the new team member know that even if they know the answer, it is better to give the team a chance to solve their own problems

Full Access
Question # 474

During execution of an agile project, a project manager realizes the budget is almost completely used, but the project is not close to being completed. What should the project manager do to address this concern?

A.

Review the project time line and find opportunities to reduce the project schedule.

B.

Review the budget with the project sponsor and ask for an increase to the budget

C.

Review the backlog and find opportunities to reprioritize the work and reduce the project scope

D.

Review the resource management plan and find opportunities to reduce project costs.

Full Access
Question # 475

A project manager is managing a project that has a new sponsor who is cutting the budget As a servant leader how should the project manager handle the budget cuts with the team?

A.

Notify the project sponsor that the budget reduction will require a schedule slip and scope reduction.

B.

Inform each team member that they must release a portion of their budget but must remain on schedule with no change to the scope

C.

Meet with the schedule coordinator and financial analyst to tell them which budget lines to reduce and where to release slack

D.

Collaborate with the team to assess the impact of the change on the project and recommend an updated project plan

Full Access
Question # 476

An agile project to provide a material information system has started. During the kick-off meeting, the team realizes that the stakeholders require a solution in 2 months, but it will take at least 4 months to deliver the entire project.

Who should the project manager contact to help the team accelerate the delivery?

A.

The human resources (HR) department—to ask for more resources to add to the project team.

B.

The product owner and the stakeholders—to prioritize the requirements in the product backlog.

C.

The team—to have them increase their velocity to accomplish the stakeholders requirements.

D.

The stakeholders—to have them prioritize the requirements in the product backlog.

Full Access
Question # 477

A project manager is managing a few innovation projects with a high level of uncertainty. The project manager is experiencing challenges with the large number of change

requests issued due to the nature of the project.

What should the project manager do?

A.

Add a fixed number of change requests allowed by the client on the project baseline.

B.

Request sponsor approval for all change requests to reduce the number of changes.

C.

Initiate the number of iterations to reduce the number of change requests.

D.

Reduce the number of approvers required to implement a change request.

Full Access
Question # 478

A technology project is delivering new functionality on a new platform. Several team resources are starting to train their teams, but they are asking questions about the training that the project will provide.

What should the project manager's first action be?

A.

Indicate that on the new technology is the functional manager's responsibility.

B.

Review the project charter to determine if the training is in scope and, if not, put in a change request.

C.

Consult with the organizational change management specialist as to what the training plan includes.

D.

Document the skill requirements for the product to determine what training is needed.

Full Access
Question # 479

An innovation project with a budget of over US$30 million is expected to have a large impact on the technology industry. The business area is concerned if the project will meet stakeholder expectations and raised this concern with the project manager.

What should the project manager do to manage business concerns and expectations before starting the project?

A.

Meet with the project finance team to measure market variations and product impact.

B.

Direct the project team to estimate user stories in greater detail.

C.

Ask the product owner to prioritize the backlog items based on the return on investment (ROI).

D.

Request that the project team develop a release plan and roadmap for the project.

Full Access
Question # 480

A few new team members working on a public housing project are unfamiliar with the system. They do not understand how to evaluate residents applying for a subsidy to build a house, including the rules and criteria for applicant approval.

What should the project manager do?

A.

Plan a training session for the new team members not familiar with the system.

B.

Communicate the rules and criteria to the team members through email.

C.

Work only with the team members familiar with the system

D.

Document which rules and criteria the new team members are not familiar wit

Full Access
Question # 481

A project manager is working on a software development project. The project manager and the project team identified the project risks. As the

project progressed, one of the risks materialized, and the project manager referred to the risk management plan to determine how to manage the risk. Once the risk management strategy was chosen and implemented, the risk was closed.

At what point did the project manager move the risk from the risk register to the issue log?

A.

Risk monitored

B.

Risk occurred

C.

Risk managed

D.

Risk identified

Full Access
Question # 482

In an organization with good work-life balance, one team was continuously overloaded, thereby delivering the product ft quality. What should the project

manager do?

A.

Request the team to work more for on-time delivery.

B.

Request the team to focus on doing better planning.

C.

Request the replacement of certain team members.

D.

Request management for a high-performing team.

Full Access
Question # 483

A project is about to start. The project manager has found that the client does not have an appropriate knowledge management system and does

not have a requirement for it.

What should the project manager do?

A.

Ask the team to collect the knowledge locally and share it at the end of the project.

B.

Utilize the cloud wiki to collect the necessary knowledge.

C.

Coordinate with the team and the project stakeholders to collect the knowledge.

D.

Provide just-in-time knowledge to the client, upon request.

Full Access
Question # 484

During an agile project a project manager lost one of the resources, and at the same lime, uncovered new requirements, which were added to the backlog What should the project manager do next?

A.

Reevaluate the project schedule as the velocity will be impacted by the loss of resources

B.

Reevaluate the backlog priority with the product owner since the velocity has been impacted

C.

Reevaluate the scope of the current iteration to keep the same velocity and timeline

D.

Reevaluate the velocity as the iteration duration will be impacted by new requirements

Full Access
Question # 485

A project manager is leading three projects in a program focused on starting product commercialization. Once the three projects fareket, the project manager stops attending the recurring team meetings. The program manager asks the project manager to continue attending these meetings to maintain those team touchpoints.

This request does not match the project manager's expectation, since a program manager is overseeing the remaining work

How should the project manager approach the situation?

A.

Attend only the program meetings where the market launch is being monitored

B.

Provide an answer via email recommending a division of tasks between both roles.

C.

Politely inform the program manager that attending these meetings is no longer required.

D.

Schedule a meeting to discuss the different perspectives and agree on a decision.

Full Access
Question # 486

A company is using an agile approach to launch a new product. In the second sprint, the team encounters a technical problem they have never faced before.

What should the project manager do?

A.

Inform the project sponsor about the problem faced by the team.

B.

Ask the product owner to write the specifications for the related user story.

C.

Organize an early retrospective with the team to analyze the problem.

D.

Facilitate a problem-solving session with the team to analyze the problem.

Full Access
Question # 487

A project manager is assigned to a project to develop a mobile app. The sponsor explains that the application should do better than their closest competitor's app. The sponsor's expectation is that the team can be put together and start work immediately.

What should the project manager do?

A.

Start working on the resource management plan in order to identify the best team for the project.

B.

Utilize expert judgment and organizational process assets (OPAs) to estimate the effort and budget.

C.

Review the competitor's app to understand the functionalities that the project scope should consider.

D.

Define the project scope with the stakeholders and determine how formal acceptance will be obtained.

Full Access
Question # 488

A project manager has been assigned to a project where the budget is very tight. Incurring extra costs is not an option.

What should the project manager do to manage this situation?

A.

File a change request to make the customer billable for all extra costs incurred for the project.

B.

Ask the accounting department to forward all project expenses to the project manager's email.

C.

Monitor the budget for the project continually and anticipate any issues if possible.

D.

Ask the project resources to finish their assignments in less time than originally planned.

Full Access
Question # 489

A multimillion-dollar project has started and is in the execution phase. A local regulatory authority has just announced changes to the requirements that will need to be implemented in 6 months, prior to completing the project execution phase.

What should the project manager do next?

A.

Add the new requirements to the project scope immediately since they are mandatory changes.

B.

Review the new requirements with the compliance department to determine if a change request is needed.

C.

Ignore the new requirements as the current budget and schedule do not allow for any changes.

D.

Proceed with the defined project requirements and delay implementing the new requirements.

Full Access
Question # 490

A project is designed to provide local community members with health facilities that will support improved sanitation practices. What should the project manager do to

ensure the community members are up to date on project progress?

A.

Share project updates when requested by the stakeholders.

B.

Share project updates through regular community meetings.

C.

Share the annual reports virtually and in the local newspapers.

D.

Share the project reports with the sponsor to inform community members.

Full Access
Question # 491

A project manager is assigned to a new project team that has several stakeholders who can have significant influence over the project outcomes.

The project manager categorized the stakeholders into four different groups and wants to define the communication strategy.

How should the project manager handle communication?

A.

Utilize a uniform communication structure across all groups.

B.

Define and direct communication to influential stakeholders.

C.

Describe the four groups in the project stakeholder matrix.

D.

Develop and define a communication strategy for stakeholders.

Full Access
Question # 492

A project manager has been managing an agile project for 6 months. Over the last two iterations, the team velocity has decreased due to a new technology that was needed

for the product.

What should the project manager do to continue with the delivery plan and return to the expected velocity?

A.

Use retrospectives to better understand the new technology's impact on the schedule, map the skill gaps, and adjust the team accordingly.

B.

Reevaluate the backlog by looking for high-value/low-effort items, and negotiate a new minimum viable product (MVP) strategy with key stakeholders.

C.

Seek sponsor approval for additional funding to hire new team members, increasing the capacity of the team and compensating for the productivity lost with the new technology.

D.

Replace poorly performing team members with more experienced members, setting an example of accountability for the team.

Full Access
Question # 493

A project manager has been assigned to a hybrid project. The project manager needs to ensure all team members are collaborating and are aware of the project's ongoing changes.

What should the project manager do?

A.

Send out daily emails with the project status and task lists to all team members.

B.

Meet daily with the project team and include a monthly report on the risks and issues.

C.

Distribute a project newsletter that includes any project changes and required project information.

D.

Encourage collaboration on a daily basis, facilitating different communication channels.

Full Access
Question # 494

A project manager is working for an organization in country A and has been tasked with opening the first brick-and-mortar store in country B. The sponsor has identified the city for the store and wants to minimize any potential issues with the local government.

Which action should the project manager take to address the sponsor's request?

A.

Work with the organization's real estate department and reach out to the local government to identify the best location for the store.

B.

Work with the local government to build the profiles of employees that will be working in the store.

C.

Work with the organization's legal department to identify local regulations to ensure project compliance.

D.

Work with the organization's project management office (PMO) to build a project team of residents located in the city.

Full Access
Question # 495

An agile team wants to maximize the work delivered for the upcoming project that involves considerable product complexity. What should the

project manager do to help improve the team's collaboration approach?

A.

Meet with the human resources (HR) department to ask for team support.

B.

Follow the process of the most successful team in the organization.

C.

Compare the team's velocity with other teams in the organization.

D.

Focus on the team's engagement during the next retrospective meeting.

Full Access
Question # 496

In an agile project that is about 45% complete, most team members are siloed and lack an understanding of each other's work. What would have

most likely caused this communication breakdown?

A.

The sprint review meetings were not held regularly.

B.

The daily standup meetings were not consistently attended.

C.

The project manager failed to develop a communications management plan.

D.

The weekly project status reports were not published regularly.

Full Access
Question # 497

A learn member has a sudden emergency that may last for several days. There are no other team members who can cover their tasks and job duties. What should the project manager do to address this concern?

A.

Hold an emergency project team meeting to discuss the situation.

B.

Ask the human resources (HR) manager for an external replacement.

C.

Log the situation in the issue log.

D.

Update the key stakeholders on the issue.

Full Access
Question # 498

A project manager has been assigned to a new digital product line, which the company hopes will boost their revenue. The product is complex and requires customer feedback to continually refine the product. The project is being handled by a cross-functional agile team.

What should the project manager do to ensure value is delivered quickly?

A.

Plan the project to deliver value incrementally with regular releases.

B.

Request a budget increase to pay the subject matter experts (SMEs) more overtime

C.

Identify tasks that can run in parallel to deliver the project faster.

D.

Ask the project sponsor to provide additional resources to fast track the project.

Full Access
Question # 499

A team is working on a project with three iterations. The project manager is reviewing the burndown chart What is the point where the chart shows that the team is performing below the plan?

Full Access
Question # 500

During a project's initiation phase a lessons learned sharing session was held with the team from another project Low construction productivity was discussed as a potential delay to project completion

What should the project manager do next?

A.

Discuss this issue with the project sponsor to request additional funding to implement mitigation

B.

Hire a construction management consultant to develop a comprehensive site execution plan

C.

Prequalify contractors with proven track records to eliminate productivity concerns

D.

Add construction productivity to the risk register and develop a mitigation strategy for site execution

Full Access
Question # 501

A project manager has been assigned to a software development project that will undergo several iterations until the customer is satisfied. Match the tool or technique on the left that the project manager should utilize to ensure tasks are efficiently managed to the correct task on the right.

Full Access
Question # 502

A project manager has taken over a project that has been without a project manager for the last couple of weeks. The team is feeling lost and there are a few team

members who are confused about the next steps and the final outcome of the project.

What should the new project manager do?

A.

Avoid conflict and let the team self-organize on how they want to work on the project tasks.

B.

Ask the project sponsor to provide team members with a project direction regarding outcomes.

C.

Set short-term goals in order to create a winning culture internally and praise team members for achieving them.

D.

Escalate the situation to the steering committee and request that more time be allotted to the project.

Full Access
Question # 503

A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The burndown chart is shown below. What should the team do next?

A.

Ask the product owner if some low-priority stories could be cut from the sprint.

B.

Continue with the sprint as the progress shows buffers for potential interruptions.

C.

Ask the project team to select any additional stories as they have additional capacity than planned.

D.

Continue with the sprint work as planned and keep monitoring.

Full Access
Question # 504

One of the key stakeholders on the project team reaches out with an additional requirement that may impact the overall schedule. A discussion with another stakeholder suggests thai this might just be a small task.

What should the project manager do?

A.

Coordinate design document preparation

B.

Perform a qualitative risk analysis

C.

Request further clarification of the requirement

D.

Manage the engagement of this stakeholder.

Full Access
Question # 505

In the middle of the execution phase for a big project a new stakeholder who was unfamiliar with the project joined the board of directors and is influencing the decisions made in the project. This change is impacting the project's progress

What should the project manager do first?

A.

Revise the project schedule

B.

Present the project to the stakeholder

C.

Inform the client about the change

D.

Update the risk register with a new risk

Full Access
Question # 506

A project manager collects various pieces of information and consolidates metrics in an agile project. The project manager finds that there is slack in the team in terms of productivity. The number of items sent to development per person has decreased by 10%, and the project manager used a root cause analysis (RCA) and discovered the reason is a lack of knowledge in one of the frameworks used for modeling.

What should the project manager do next?

A.

Foster knowledge sharing and coaching among team members.

B.

Arrange for external training amid the tight project schedules.

C.

Add new members for the underperforming team.

D.

Seek an external expert to review the framework.

Full Access
Question # 507

A project manager wants to ensure that the project acceptance criteria are met for all project deliverables. What should the project manager do to accomplish this?

A.

Schedule regular meetings with project stakeholders to make sure they are satisfied.

B.

Include project stakeholder expectations and needs while creating project acceptance criteria.

C.

Create a statement of work (SOW) and ensure it remains unchanged during the project life cycle.

D.

Discuss project acceptance criteria with the project sponsor before the execution phase.

Full Access
Question # 508

A project manager is managing a large project. A stakeholder has just discovered a new risk that has not been identified in earlier stages.

What should the project manager do?

A.

Communicate the risk to the steering committee and request a mitigation plan from senior management.

B.

Perform a risk analysis directly with the stakeholder who raised the risk and update the risk register.

C.

Confirm to the stakeholder that the risk register has been completed and validated by all stakeholders.

D.

Add the risk to the risk register and reevaluate the register with help from the project team and stakeholders.

Full Access
Question # 509

A project manager is working on a project to build a manufacturing complex. The project will run in three different phases: engineering, procurement, and construction. The

procurement phase is in the initiation stage. The project sponsor wants to pursue the project phases as they have been planned, but also wants to accommodate and adjust to new data, input from the customer, and changes during the various phases as the project progresses.

How should the project manager approach this project?

A.

Apply a predictive project management approach.

B.

Evaluate and decide on a phased project management approach.

C.

Implement an adaptive project management approach.

D.

Use a hybrid model to combine predictive and adaptive life cycles.

Full Access
Question # 510

The current incremental revenue expected by a project deliverable is not fulfilling the business case requirement The deliverable was already closed and handed over to the operations team

Which two actions should the project manager take? (Choose two)

A.

Review the issue with project sponsor and submit a change request

B.

Report the issue to the product manager and business segments

C.

Analyze the business benefits criteria and assumptions

D.

Discuss the issue with the operations team to assess expense overruns

E.

Schedule a project review meeting to analyze the root cause

Full Access
Question # 511

A company changed the product owner on an existing project. The new product owner has less knowledge of the product than everybody else on the team. Due to the product owner's lack of knowledge, the team does not consider the opinions of the product owner seriously and mostly relies on the project manager's opinion.

What should the project manager do?

A.

Assume the role of the product owner while the product owner gets familiar with the product.

B.

Schedule time to share insights with the new product owner about the product and project information.

C.

Work with the project management office (PMO) manager to generate an onboarding plan for the new product owner.

D.

Organize a team-building activity and ask the team to respect the opinions of the new product owner.

Full Access
Question # 512

A project sponsor has approved the project charter and business case. The project manager has reviewed the artifacts to initiate the project and is unclear if the intended benefits of the project align with the strategic objectives of the business.

What should the project manager do first?

A.

Start executing the project since leadership is responsible for the business strategy.

B.

Meet with the project sponsor to better understand the strategic benefits of the project.

C.

Propose an updated business case and project charter that are more aligned with the business strategy.

D.

Conduct qualitative and quantitative risk analysis and record the results in the risk register.

Full Access
Question # 513

A project manager is about to slant the testing phase of a new project. Historical data show there is a high risk of failing the agreed acceptance criteria.

How should the project manager ensure the acceptance criteria are ret?

A.

Perform tests and routinely track results as per the quality management plan.

B.

Make sure the stakeholders are aware of the acceptance criteria.

C.

Negotiate to obtain approval if most of the tests have passed.

D.

Modify the acceptance criteria before the official delivery.

Full Access
Question # 514

An organization initiated a project in a complex program. The project lead notices that the team is demotivated because the current project framework implemented by the project management office (PMO) is not compatible with agile delivery

What should the project lead do?

A.

Escalate the problem to the product owner.

B.

Ask the PMO to review the framework

C.

Request the PMO to define a new framework.

D.

Plan a brainstorming session with the project team

Full Access
Question # 515

A construction project for a nuclear power plant will reduce the region's energy dependence on external electricity supplies. The project manager has received support for

the project from several leaders in the region. However, some people from the government want to stop this project to focus on developing renewable energy sources.

Which stakeholders should the project manager include in the stakeholder engagement plan?

A.

Stakeholders who have been identified and who have needs and a potential impact on the project.

B.

Stakeholders who are selected by the project sponsor who have a potential impact on the project.

C.

Stakeholders who disagree with the project so as to proactively manage their expectations.

D.

Stakeholders who are supporting the project in order to obtain additional resources.

Full Access
Question # 516

During an agile team retrospective, a project team member mentions that the code quality is degrading, which might result in future rework that

could become unmanageable with time. What should the project manager do?

A.

Help the team create the definition of done (DoD) to improve delivery quality.

B.

Add testing items to the backlog to assess quality periodically.

C.

Expand the team in order to improve the quality of the project.

D.

Compare the cost of improving quality against the cost of failure and adjust the budget.

Full Access
Question # 517

During project execution, one of the project tasks is to create an important document for a service vendor. The project manager assigns a senior engineer to clearly detail

the service instructions to avoid any redo loops. Two days after the service information document was sent, the service vendor has doubts and needs more clarity on the task. This redo loop will probably cause a delay of one or more days.

What should the project manager do next?

A.

Escalate the issue to the engineer's functional manager.

B.

Discuss the issue with the engineer and determine how to prevent another problem.

C.

Document the task on the kanban board and make it the highest priority.

D.

Assign another engineer to the task due to the urgency.

Full Access
Question # 518

A project manager is closing a project and preparing to hand it over to the operations team. During handover, a delayed invoice was submitted with a higher-than-planned

cost against the project work. Consequently, project handover was delayed and the project's reported completion costs were increased.

What should the project manager have done to avoid this situation?

A.

Captured and reviewed all of the project work and related costs regularly

B.

Notified all vendors about the invoicing and nonpayment deadlines

C.

Reviewed the total committed cost against the cost invoiced at project closing

D.

Involved the finance team and discussed the issue with the vendor

Full Access
Question # 519

A team member in an agile project informs the project manager they might not be able to finish an assigned task on time, which could generate an obstacle for the rest of

the team. What should the project manager do?

A.

Move the task to the next sprint.

B.

Ask the team member to bring up the concern in the next daily meeting.

C.

Send an email explaining the issue to all team members.

D.

Reassign the task to another team member.

Full Access
Question # 520

Due to unforeseen circumstances, a contractor was unable to mobilize the project team, which was necessary to conduct face-to-face meetings and discussions. Virtual meetings were subsequently put in place, but the local project team and end users now face a communication gap that is causing the team's low performance.

What should the project manager do?

A.

Ask the contractor to solve this problem because this is a contractual obligation.

B.

Terminate the contract and initiate a new one with a local contractor.

C.

Implement key performance indicators (KPIs) and convince the contractor to engage the team.

D.

Reassess continually to remove blockers for the team.

Full Access
Question # 521

The project manager is reviewing a project's progress and notices that one of the risks has become an issue. What should the project manager do to address the situation?

A.

Schedule a high-priority meeting with the project stakeholders to discuss the issue.

B.

Initiate a change request to obtain additional funds from the management reserve.

C.

Meet with the project team and customer to brainstorm about potential solutions.

D.

Collaborate with the relevant stakeholders on implementing the risk response plan.

Full Access
Question # 522

An organization imports many of the materials for a product build. Due to global shipping delays, some of the essential materials have yet to arrive, resulting in the inability to finish building the product for the upcoming release. The project manager is meeting with stakeholders to discuss options.

What should the project manager recommend?

A.

Request marketing to launch an advertising campaign for the product that is currently in stock.

B.

Update the project management plan, factoring in furloughs of the assembly team to reduce expenses.

C.

Explore if the materials could be supplied locally and obtained on time.

D.

Meet with the engineering team to manufacture the materials in-house.

Full Access
Question # 523

A project manager is leading a project that has been in execution for 1 year. An experienced team member is performing well, but often disagrees with the project manager and refuses to implement their decisions. Part of the team supports the team member's defiance, while the other team members do not.

What should the project manager do?

A.

Conduct a performance review and define and document the goals for the team member.

B.

Clarify decisions and request that the project team follows the project manager's decisions.

C.

Understand what the team member wants and find possible opportunities to address it.

D.

Remove existing ground rules and create new ground rules that support the project manager.

Full Access
Question # 524

The first task a project manager needs to complete on a new project is improving stakeholder engagement. How should the project manager complete the power/interest grid based on the following scenario:

• The marketing director is the key stakeholder. as the project will create a new product for the company.

• The finance director is providing funding and does not have much time to follow the tracking of the project.

• The sales representatives assigned to the team provided some negative feedback on the requirements

• The human resources (HR) intern assigned to the team was satisfied with the new product interlace.

Full Access
Question # 525

A company is engaged in a transformation journey, and the project manager for this endeavor is new to this project. During one of the project status update meetings, a key stakeholder, the project manager's functional manager, is dissatisfied with the work in progress, and points to the project manager.

What should the project manager do?

A.

Schedule a one-on-one meeting with the functional manager to prove the project is on time

B.

Listen carefully and show understanding of the growing needs of the functional manager.

C.

Admit that the functional manager is right and promise to rectify the situation immediately.

D.

Show the functional manager that the progress is on time based on the schedule.

Full Access
Question # 526

A company wants to be a pioneer in its industry and has announced the launch date of a new innovative product. After the first sprint planning, the

team realizes that it is not possible to deliver all the features in the required time.

What should the project manager do to ensure success?

A.

Increase the capacity of the team to deliver the completed backlog on time.

B.

Ask the customer to reduce the backlog to meet the launch date.

C.

Assist the team in defining a minimum viable product (MVP) by the launch date.

D.

Schedule a meeting with the stakeholders to review the contingency plan.

Full Access
Question # 527

Within a project, senior management is requesting project information so they can analyze the data to make project decisions. What information

should the project manager provide so that senior management can get a broader view of the project?

A.

Risk register information

B.

Higher-level activities completed

C.

Milestones status report

D.

Resource breakdown structure (RBS)

Full Access
Question # 528

A project manager was recently assigned to a project that is in the execution phase and is experiencing roadblocks. During a review of the

processes and procedures, the project manager notices similarities to a previous project that experienced similar roadblocks. The project manager

reviews the task schedule and finds that certain tasks are well behind expectations. In speaking with the project team, the project manager

confirms that the team is following the processes exactly.

What should the project manager do?

A.

Update the schedule to account for the unexpected delays in the project tasks.

B.

Review the resources allocated to the project and change accordingly.

C.

Review and amend the processes to ensure only value-adding activities are present.

D.

Update the variation register to account for the extended project time.

Full Access
Question # 529

A company has decided to initiate a project to eliminate a sales channel that has been unprofitable for the past 3 years. Some members of the project team are pessimistic about the project.

What should the project manager do in this situation?

A.

Engage the functional managers to describe the project's impact to the team members directly.

B.

Provide team members with specific and clear instructions on the project objectives and tasks.

C.

Communicate the project's impact and plans to engage the project team throughout the project.

D.

Escalate the team's concerns and ask the project sponsor to change the team's composition.

Full Access
Question # 530

A project manager for an iterative project noticed that retrospective items indicate that the team is not fully conversant with the principles of iterative development. The team meets to analyze the gaps in the training that recently concluded with a third-party trainer.

What should the project manager do next?

A.

Initiate hybrid development as an interim approach.

B.

Let the project team self-organize and develop their skills.

C.

Mentor and coach the team to meet the project needs.

D.

Review the training contract to determine the next steps,

Full Access
Question # 531

A project interfaces with other projects that are in the same portfolio but are being developed in international locations. One of the international projects has suggested a tactical change that needs to be implemented in this project.

What should the project manager do next ?

A.

Use the team's connections with international colleagues to get early warnings on future changes.

B.

Keep the focus on the priority items while the change goes through the change control process.

C.

Reject the change request since it may negatively impact the project's performance.

D.

Implement the change request as soon as possible to avoid accumulating new scope.

Full Access
Question # 532

A project manager is working in a company that has several global offices. During resource planning for a new project, the project manager realizes that the company requires projects to include team members from different continents.

What should the project manager do to ensure a successful project execution?

A.

invite all resources to the project manager's location to form a cohesive team until all deliverables are completed,

B.

Send emails with information about the project deliverables on the first day of the project.

C.

Connect with every location and check their preferred methods of communication.

D.

Plan for a meeting with the project sponsor to discuss the possibility of utilizing only local colleagues.

Full Access
Question # 533

A project manager is managing a very important business transformation project. The goal of the project is to extend a desktop application with a mobile application module.

The marketing department believes that a main competitor is working on a similar product.

Which delivery approach should the project manager use for this project?

A.

Traditional delivery, to ensure high quality and that the product meets market demands

B.

Extreme Programming (XP) delivery, to mitigate the high risk related to a new product

C.

Iterative delivery, to ensure that user feedback is incorporated into the second iteration

D.

Incremental delivery, to ensure that mobile capability is released fast to the users

Full Access
Question # 534

A project manager has been authorized to begin a project and realizes that an effective high-performing team is needed to finish the project successfully. What should the project manager do next?

A.

Select members for their skill or potential.

B.

Establish the project scope and set clear team objectives.

C.

Set performance standards and direction.

D.

Hold early kick-off meetings and regular weekly meetings.

Full Access
Question # 535

A new marketing vice president just joined a software startup and is concerned that the agile model does not provide the needed accountability for their role. What should the responsible project manager do to ensure the vice president is comfortable with the project meeting its agreements?

A.

Require proper approval of all requirements from the marketing vice president and formally document the agreements.

B.

Foster an environment of open communication where all parties can discuss issues and agree on objectives.

C.

Establish an executive review board where all stakeholders discuss and approve features and requirements.

D.

Leverage the use of the review/demo sessions with the vice president to acknowledge that the agreements were met.

Full Access
Question # 536

During the project planning phase, a project manager called a meeting to discuss the

product backlog with multiple stakeholders who represent the end users in various capacities.

Only one executive manager attended the meeting.

What should the project manager do?

A.

Meet with each stakeholder individually to gather input to the product backlog and

begin project planning.

B.

Proceed with prioritization of the product backlog based on previous lessons learned

and complete the project planning phase.

C.

Reschedule the meeting to ensure the majority of stakeholders are present for the

product backlog discussions.

D.

Proceed with the meeting in order to keep the project on track and start prioritizing the product backlog.

Full Access
Question # 537

A project manager is working on a cost-reimbursable contract from the client's side. During project execution the project manager notices a major deliverable is missing. The project manager raises this with the seller but the seller advises the project manager that the subject deliverable is not part of the contract. The project manager remembers negotiating and agreeing to this deliverable during the tender process but cannot find it in the contract

What should the project manager do?

A.

Request a change in the contract in order to add the deliverable

B.

Add this deliverable to the requirements traceability matrix

C.

Terminate the contract and commence the closeout process

D.

Look to see if the deliverable is described in the statement of work (SOW)

Full Access
Question # 538

In an agile team, some of the team members are coming forward to ask for more

autonomy on the project. What should the project manager do in this situation?

A.

Encourage the team members to make decisions.

B.

Discourage them as conflicts may be created.

C.

Encourage the team lead to make decisions.

D.

Discourage this request, as it is for the management team.

Full Access
Question # 539

A project team member reads in a financial newspaper that the main project supplier is facing some financial difficulties and communicates this to the project manager. What should the project manager do?

A.

Add the situation to the project risk register to be managed

B.

Identify competitors that are qualified to replace the current supplier

C.

Inform the purchasing department that manages the supplier relationship

D.

Use the issue log to record the situation immediately

Full Access
Question # 540

A project manager has experience working with a specific provider that has been

requested for an upcoming project. This provider often fails to meet deliverable dates; however, it is the only company with the specific experience required for the project.

What should the project manager do during the planning phase?

A.

A. Hire resources to obtain knowledge about the provider's specific capabilities.

B.

B. Add penalty clauses to the contract and update the risk register.

C.

C. Encourage the provider to work overtime with no additional costs to the project.

D.

D. Contract another provider with less experience and give them a chance to provide the deliverables.

Full Access
Question # 541

An agile team has started a new project. When should the project manager organize their first team retrospective?

A.

When the team completes a release of a monumental increment

B.

When the team reaches a major milestone

C.

When more than a few weeks have passed

D.

When the work is progressing well through the team

Full Access
Question # 542

A project manager acquired information from the market that would reduce the business value being delivered by an ongoing protect Based on that information, the project manager believes the project should be stopped

How should the project manager handle the situation?

A.

Remove the items no longer applicable from the backlog and present the backlog to the project team

B.

Continue working on the defined scope and review the risk matrix

C.

Have a discussion with the project sponsor and cancel the project

D.

Have a discussion with the sponsor and recommend the project business value be reassessed

Full Access
Question # 543

A new building project is in the middle of its life cycle. The municipality informs the project manager that due to new regulations, the parking lot around the project has to accommodate twice the number of cars than was initially planned.

What should the project manager do next?

A.

Request the project sponsor to fund this change as it is a new regulation, then order the materials in order to start working.

B.

Assess the impact of the required change and consult with the executive sponsors to determine the best course of action.

C.

Ask the designers to start designing a solution for this new requirement while the project is running and determine the funding for this change.

D.

Have the company's lawyers write to the municipality and reject the change as it was not part of the scope approved by the municipality.

Full Access
Question # 544

A project manager is assigned to an important company project. While reviewing the lessons learned from a similar, previous project, the project manager finds that the biggest challenges were related to learn motivation.

What should the project manager do to avoid these challenges?

A.

Increase the project budget by 10% for team-related activities and awards.

B.

Plan to implement team-building strategies throughout the project.

C.

Ask the functional manager to motivate the team outside of the project.

D.

Colocate the team to encourage more motivational team activities.

Full Access
Question # 545

An agile project manager is evaluating the method that will be used to display the

value of the work performed to date. Which method will they select to display to the project stakeholder?

Full Access
Question # 546

A project manager is managing the development of a dental wire bending machine. The machine is compatible with the three most popular dental wires in the market which covers 90°.© of the market The prototype is now under testing for certification. The manufacturer of one of the three wires announced they will be producing a different wire mat will be incompatible with the machine. This will result in a 25% loss of market coverage from the initially predicted 90% coverage

What should the project manager do?

A.

Investigate the impact of this issue with the team and survey the market for alternative wires with similar characteristics

B.

Stop the project and kick off another project to apply alternative wires for the machine

C.

Meet with the sales and marketing representatives and ask them to convince the manufacturer to reconsider

D.

Meet with the wire manufacturer to secure enough of the existing stock for the machine

Full Access
Question # 547

A globally distributed project team is running behind schedule due to the lack ol team commitment and low morale. In order to bring the schedule back on track, what should the project manager do first?

A.

Seek the sponsor's approval to extend the project schedule.

B.

Set up a meeting to perform a root cause analysis.

C.

Update the issue log and communicate it to the team.

D.

Permanently colocate the team for better performance.

Full Access
Question # 548

A project manager has been assigned to a new project. There is one team member

who never says anything during meetings. After meetings, however, the team member sends

detailed emails with very good suggestions that help with project execution.

How should the project manager guide the team members?

A.

Review the communications management plan with the team members.

B.

Remind the team members to follow the team charter.

C.

Motivate the team members to speak freely in the meeting.

D.

Arrange a team-building activity to involve all team members.

Full Access
Question # 549

Due to a recent company merger, a project manager from company B has been

assigned to a team that is comprised of team members from company A. At the start of the

project, conflicts arise due to a lack of clarity on processes and the project manager's

relationship with company B.

What should the project manager do to resolve this conflict?

A.

Avoid the conflict as the customer feels comfortable with using processes from

company A.

B.

Review the historical information and make the decision based on the return on

investment (ROI).

C.

Ask the team to use company B's processes since they are more familiar with these

processes.

D.

Work with the team to analyze which processes are suitable to use and define them in

the ground rules.

Full Access
Question # 550

During a team meeting the project manager asks the team to complete a personality assessment to help everyone understand themselves and one another better. The project manager analyzes the results and realizes that more than one-half of team members are introverts

What should the project manager do?

A.

Present brainstorming topics a day before the session so the team can reflect and contribute more fully during the session

B.

Adjust the lighting and ambient sounds in the work and common areas to create a relaxing work atmosphere

C.

Ensure the team understands that their input needs to be fully articulated and explained to all team members during daily standups

D.

Require everyone to share personal details at the start of each team meeting to allow learn members to get to know one another

Full Access
Question # 551

A project manager resigned from a recently approved project. A new project manager has been assigned to the project and needs to determine the delegated authority. What should the new project manager do next?

A.

Refer to the project charter

B.

Review the project resource matrix

C.

Assess the stakeholder register

D.

Update the communications management plan

Full Access
Question # 552

A project manager is managing a government project that targets the development of

small businesses in remote towns. The project team is having difficulty conducting

entrepreneurship training in some of the targeted towns because the local municipal

governments will not authorize the training. As a result of the delay, project implementation is at risk.

What is a probable reason for this?

A.

The project should have constructed training centers in the remote towns.

B.

The project did not identify and engage the correct stakeholders.

C.

The project should have representatives in all the remote towns.

D.

The project did not fully engage the project sponsor.

Full Access
Question # 553

A project requires testing of the final product to be done at another department's

testing facility, which is known for having low availability. This situation could potentially

impact the project schedule.

What should the project manager do next?

A.

Update the risk register.

B.

Update the issue log.

C.

Update the lessons learned register.

D.

Update the project schedule.

Full Access
Question # 554

A project team consists of members based in country A and subject matter experts

(SMEs) based in country B with a 12-hour time difference. What can the project manager do

to improve interactions between the team members in both countries?

A.

Ensure full participation of both the product owner and business SMEs in scope

planning sessions.

B.

Identify virtual communication methods and arrange for regular team meetings

accordingly.

C.

Explore the opportunity to have both teams colocated.

D.

Plan for frequent face-to-face meetings.

Full Access
Question # 555

In a hybrid project, 100 new base stations are being added to a 4G mobile network

every month. At the end of the first month, the team is behind the target and the operator is

losing money. The stakeholders are requesting information on when the base stations can go

live and begin to bill.

What should the project manager do to take the schedule back and accelerate the return on

investment (ROI) of the project?

A.

Change the project approach to predictive.

B.

Increase reporting to the business.

C.

Clarify the agile and predictive modules.

D.

Reconsider necessary schedule reserves.

Full Access
Question # 556

A project manager is leading a major water pipeline project and realizes midway into

the project that the project completion date is not achievable. Local farmers who rely on the

water for irrigation may be affected due to the delay. The project manager is afraid of their

displeasure and reaction, which will affect the project.

How should the project manager plan the communication to the stakeholders?

A.

Document and accept this risk and communicate this decision to the project sponsor.

B.

Collect feedback from the farmers and keep the information within the project team.

C.

Deliver the information to the stakeholders with the project management office's (PMO)

assistance.

D.

Propose a solution to the stakeholders and communicate it to the local farmers.

Full Access
Question # 557

A project manager is leading a project in which key performance Indicators (KPls) are measured through earned value management (EVM). Match each measurement on the left with the correct category on the right.

Full Access
Question # 558

An agile project manager has just been given a sizeable software development project to implement. Early in the initiation stage, the project sponsor requests an indication of time lines for delivery of the initial release.

What tools should the agile project manager use to do these estimates?

A.

Product backlog, budget, resource management plan

B.

Budget, minimum viable product (MVP), retrospective notes

C.

Resource management plan, retrospective notes, backlog grooming

D.

Backlog grooming, product backlog, minimum viable product (MVP)

Full Access
Question # 559

A project manager is assigned to a new water treatment plant project that has been

delayed for many years. It is revealed in the project charter that the sponsors of this project

are from three different business units. This is the first time the sponsors have ever

implemented such a project.

What should the project manager do?

A.

Establish mentoring and coaching sessions.

B.

Review the knowledge repository for similar projects.

C.

Schedule the project kick-off meeting immediately.

D.

Meet with the project sponsors to align expectations

Full Access
Question # 560

A project manager is using a hybrid approach to comply with a regulatory requirement. The planning and closing phases will use a predictive approach, and the execution phase will use an iterative approach. During the second sprint review, the project sponsor requested a change in priority tor some of the product backlog items

What should the project manager do as a servant leader?

A.

Ask the sponsor to submit a change request to the change control board (CCB)

B.

Support the product owners decision to change the priority of the product backlog items

C.

Accept the request and include the product backlog items in the next sprint

D.

Review the impact of the change on the schedule management plan baseline

Full Access
Question # 561

An agile project manager has learn members from different continents on the project team. During the dairy scrum meetings the project manager notices that there are gaps in understanding about the project goals and objectives

What should the project manager do?

A.

Schedule team-building activities to encourage collaboration among the team

B.

Coach the team members to resolve the gaps in understanding

C.

Conduct a kick-off meeting and communicate the goals and objectives of the project

D.

Continue the meetings and communicate the goals and objectives to resolve the gaps

Full Access
Question # 562

During a meeting with a customer, it was determined that participants of the meeting

had different draft versions of an important design document. What should the project

manager do first to ensure that this does not happen again?

A.

Revisit the communication process control.

B.

Ensure only the approved version is shared.

C.

Investigate how draft versions were shared.

D.

Ensure only the latest version is shared.

Full Access
Question # 563

When a project manager is trying to determine a leadership style to use on a project what should they consider?

A.

Number of tasks on the protect

B.

Culture of the organization

C.

Project timeline

D.

Experience of the project manager

Full Access