Pre-Summer Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: mxmas70

Home > PMI > PMI Agile > PMI-ACP

PMI-ACP PMI Agile Certified Practitioner (PMI-ACP) Question and Answers

Question # 4

An employee just received an Agile certification and has been promoted to team leader. They are working on a project that is experiencing issues with late deliverables. After monitoring project progress, they notice that one impediment is continuously repeated at start of each phase, affecting team ' s productivity.

How should the team leader exhibit servant leadership?

A.

By being a change agent

B.

By being the authority on processes

C.

By being a coach

D.

By removing impediments

Full Access
Question # 5

A manufacturing shop is using Kanban to plan, visualize workflow, and limit work in process (WIP). Which productivity key performance indicator (KPI) should the team lead be monitoring on a regular basis?

A.

Lead time

B.

Team velocity

C.

Burndown rate

D.

Earned value (EV)

Full Access
Question # 6

An agile project manager is planning the initial scope, schedule, and cost range estimates on a new project. The team will be using Kanban to control work.

What metrics should the team use to measure performance?

A.

Lead time, throughput, and due date performance

B.

Work in progress limits, Kanban board, and time boxes

C.

Work item types, sprint cadences, and defect classes

D.

Burndown charts, scatter diagrams, and throughput

Full Access
Question # 7

A project team tasked with delivering a solution with extremely aggressive timelines is facing an issue with meeting their sprint velocity targets.

To address this issue and bring the project back on track, what action should the team take?

A.

Perform value stream analysis to eliminate the processes with wastage.

B.

Reevaluate the minimum viable product (MVP) deliverables to remove high-risk stories and meet timelines.

C.

Adjust the story points included in each sprint to represent the actual velocity.

D.

Include high-risk stories in earlier sprints to deliver incremental velocity.

Full Access
Question # 8

During a project review, the team discovers customer feedback that would add scope. The project leader is concerned that the team will be unable to incorporate this feedback and still meet the product launch date.

What should the project leader do?

A.

Finalize the feedback in the form of a change request

B.

Limit the scope of the feedback to only those changes that the team can feasibly accommodate

C.

Encourage all feedback then work with the customer to prioritize work for future sprints

D.

Allow the team to decide what feedback to incorporate

Full Access
Question # 9

During an agile team retrospective, some junior team members discussed an approach that could improve the overall team performance.

How should the agile practitioner handle the recommendation?

A.

Record the suggestion to be considered for future projects.

B.

Invite the team to evaluate the suggestion and measure the effectiveness of the implementation.

C.

Let the product owner consider the proposal and decide whether to adopt the suggested practice.

D.

Let the team ' s senior members decide whether to adopt the suggested practice.

Full Access
Question # 10

During a six-week iteration, an issue is identified by a team member. After analysis, the team member determines that it will take at least two weeks to resolve. What should the team member do?

A.

Notify the product owner and begin resolution.

B.

Communicate the issue to the team in the next stand-up meeting.

C.

Immediately begin resolution, and communicate it to the team during the retrospective.

D.

Work on the next activity, and communicate it to the team during the retrospective.

Full Access
Question # 11

A large, corporate organization is forced to hire new team members in a geographically remote location from the current team. The manager of the department is concerned about the team not being colocated.

What behavior would indicate the team is not working well together?

A.

Team members are sending more emails to the team.

B.

The duration of feedback cycles has increased.

C.

The velocity has increased by having the new team work on items.

D.

New team members requested to move meetings due to time differences.

Full Access
Question # 12

An agile coach is guiding a team across multiple locations. They need a united communication approach that involves task-oriented communications and discussion boards with effectiveness.

Which method of communication would be most effective?

A.

Interactive communication

B.

Pull communication

C.

Interpersonal communication

D.

Push communication

Full Access
Question # 13

A new agile project leader habitually becomes involved in the work from a support perspective and uses information radiators to ensure that all actions to remove impediments are visible to the team.

What is the agile project leader doing?

A.

Practicing the servant leadership style of working with an agile team

B.

Building a collaborative teamwork culture

C.

Following a participatory decision-making model

D.

Adopting the practice of receiving feedback that will facilitate team improvement

Full Access
Question # 14

A new agile project manager accepts an assignment to manage a well-established team. Many team members have worked together on this product for several years. During a meeting, the project manager notices that team members offer little vocal interaction, yet all required tasks are completed on time.

What type of behavior does this describe?

A.

Synchronous

B.

Collaborative

C.

Passive-aggressive

D.

Random

Full Access
Question # 15

Which agile practice would most significantly increase a team ' s velocity?

A.

Daily standups

B.

Iteration and release planning

C.

Training in areas of weakness

D.

Iteration

Full Access
Question # 16

An agile lead is working on a project to build a new product that will bring substantial business value to a company. Company executives want to present the first release at an important industry fair the following month. The agile lead started the project the previous month, and the team planned the release to take 8 iterations. For the past 4 iterations, work has been performed as planned and on time. In the current iteration, however, one team member will be out for the remainder of the project. Without this team member, velocity would drop 30%.

What should the agile lead do to ensure the release will be on time for the fair?

A.

Reduce the scope of the release to meet the deadline.

B.

Deliver as many features as possible based on the new velocity.

C.

Extend the project timeline to accommodate the missing team member.

D.

Hire a new team member to replace the missing one.

Full Access
Question # 17

Midway through a project, the product owner learns from the sponsor that a major component, which is already 20 percent complete, is unimportant to users. The component was part of the approved scope and a key selling point for the project.

What should the product owner do next?

A.

Obtain approval from the change control board to discontinue the component

B.

Ask the team to continue developing the component

C.

Ask the team to discontinue developing the component

D.

Request the sponsor ' s formal approval to discontinue the component

Full Access
Question # 18

A newly formed Scrum team wants to foster an environment of transparency and experimentation. The team decides to use a Kanban board to record and track encountered impediments. Emphasis is placed on how issues are resolved and the strategies for preventing them in the future. Over time, what will be the result of this approach?

A.

Kaizen

B.

Specific, measurable, assignable, realistic, and time-based (SMART) goals

C.

Key performance indicators (KPIs)

D.

Muda

Full Access
Question # 19

A team developing application software is working in pairs. A project manager notices that important information is sometimes not shared among team members, leading to delays in the development process.

What should the project manager do to improve team performance and eliminate any communication impediments?

A.

For new pairs of developers based on the years of expertise and project management Knowledge

B.

Use task boards so the team can keep track of the work done and future implementation planning.

C.

Schedule in-person meetings at the end of each iteration, allowing team members to share knowledge and experience.

D.

Seek expert judgment and a new collaboration model that will strengthen team cohesiveness.

Full Access
Question # 20

What should the Scrum Master do next?

A.

Monitor the threats and risks while allowing the team member to multitask on both projects

B.

Assign more resources to the sprints to compensate for the absences of the team member

C.

Ensure that the threats and risks are communicated and addressed

D.

Assign fewer stories to the sprints so that the team member can still meet sprint goals

Full Access
Question # 21

Due to its complexity, a new team member struggles with developing a concise user story.

What advice should the agile practitioner give to assist with developing the story?

A.

Hand the story over to a more experienced team member

B.

Break the story up and focus on the most valuable parts

C.

Discuss the story at the next retrospective

D.

Pick another story from the product backlog

Full Access
Question # 22

How should the agile team address this?

A.

Conduct an internal review to validate functionality before shipping

B.

Audit the quality control process to ensure that the product adheres to requirements

C.

Lengthen iterations to ensure there is sufficient time to build functionality

D.

Hold product review sessions with the client to obtain product acceptance

Full Access
Question # 23

A mobile application project is halfway through development. The team reaches a stabilized velocity after 8 iterations. The sprint duration is two weeks and requirements assigned by the product owner are not changing frequently.

What is the estimated time remaining for the project?

A.

Eight months

B.

Two months

C.

Four months

D.

Six months

Full Access
Question # 24

A new Scrum team is struggling with the various ceremonies of Scrum. Among other things, the product owner and stakeholders find the technical architecture and design presentations during sprint reviews less than informative.

What should the team do?

A.

Refocus the sprint review meetings to demonstrate working software and seek feedback on the product.

B.

Reach out to other, more experienced teams to seek input as to how to present the technical details in a more informative manner.

C.

Explain the importance of the technical architecture and design presentations and improve the presentation format.

D.

Invite technical managers and architects who will be a more appropriate audience to their sprint reviews.

Full Access
Question # 25

During an interview for an agile team lead for a global company, a candidate is asked: " How do you ensure your project is aligned with the stakeholders ' priorities? "

How should the candidate respond?

A.

Engage the change management team to determine prioritization of the backlog.

B.

Allow the stakeholders to decide on the priority and build the backlog.

C.

The entire team should discuss and prioritize the backlog factoring in stakeholder input.

D.

Only the agile team lead and team need to decide how to prioritize the project deliverables.

Full Access
Question # 26
A.

Add new security features to the backlog and prioritize.

B.

Execute a spike to research security features for the project.

C.

Ask questions to determine where and how the product owner wants to use the product.

D.

Ask questions to determine if the product owner can define the desired level of security.

Full Access
Question # 27

How should the project manager introduce the team, communicate the importance of the team charter, and help develop a high-performing team?

A project charter has been completed and is ready for approval. The project ' s goal and approach have been clearly determined and a list of generalized specialists has been set.

How should the project manager introduce the team, communicate the importance of the team charter, and help develop a high-performing team?

A.

Analyze the list of all project participants and stakeholders, clarifying stakeholder roles and responsibilities.

B.

Promote consensus-driven decision-making and a shared vision for team commitments and decisions.

C.

Determine roles and responsibilities among team members and promote hierarchy, responsibility, and ownership among team members.

D.

Have team members introduce one another and create a hierarchy that reflects responsibilities, roles, and decision-making.

Full Access
Question # 28

Over the last two sprints, a number of potential problems have threatened the team ' s ability to hit the targeted release date.

What should the agile practitioner do?

A.

Deal with the issues in a retrospective if they ever come up again.

B.

Create a task board to track issues when they appear.

C.

Identify and monitor issues through a risk burndown chart.

D.

Create an issue log as an information radiator and monitor.

Full Access
Question # 29

An agile project manager is working on a project to develop a customer service website. The project manager is organizing a workshop to plan the next release: To add the feature of receiving and resolving customer complaints. Which two actions should the project manager ask the team members to take before the workshop? (Choose two.)

A.

Prepare an effort estimation for each story based on their technical expertise.

B.

Compile a list of ideas to improve the velocity of the team so they can plan more story points in the next sprint.

C.

Prepare a list of tasks required to accomplish the goal and the order in which they should be executed.

D.

Read and identify user stories from the backlog that will contribute to accomplishing the goal.

E.

Consider the possible risks of each selected user story and the value they add for the final user.

Full Access
Question # 30

What should the team do to improve the accuracy of their estimates?

A.

Decrease the sprint time box until the team is able to deliver the entire agreed-upon sprint backlog in a single sprint

B.

Discuss estimating techniques in the daily scrum meeting

C.

Increase the size of the development team until the team is able to deliver the entire agreed-upon sprint backlog in a single sprint

D.

Begin tracking estimated effort metrics as an input to performance evaluation

Full Access
Question # 31

What should the agile coach tell the team?

A.

Continuing to track velocity allows functional managers to assess whether or not the team is performing at the desired rate.

B.

The trends will show how the team performs against other Scrum teams in the organization.

C.

Tracking velocity will provide a baseline for the team to see how their continuous improvement efforts are working.

D.

Tracking velocity will document and communicate team health to the stakeholders.

Full Access
Question # 32

An organization wants to execute a corporate website redesign project using Scrum. There is an experienced pool of agile team members from a previous project, as well as a pool of available internal team members with some Scrum background.

What should be considered when selecting the team?

A.

Review any reports of conflict between each of the team members over the last two years, and select only those with a track record of working well together.

B.

Ensure there is a balanced mix of people who are experts and members with broad experience based on the work to be performed and determine training needs.

C.

Ensure that none of the team members are geographically dispersed so that all team members can be colocated.

D.

Review each team member ' s contributions to the velocity of their previous projects and select the highest performers.

Full Access
Question # 33

During sprints, the development team members are frequently invited to various meetings to provide technical opinions, consuming the team ' s working time and causing compliance issues. Which action should the scrum master take to address this situation?

A.

Request additional resources to prevent compliance issues while still fostering a collaborative workplace.

B.

Escalate the concern to the product owner and request that they prioritize the development work.

C.

Designate a single team member to attend the meetings and establish a capacity buffer for each sprint.

D.

Reject all external meetings for the development team so they can fully focus on their sprint tasks.

Full Access
Question # 34

Several team members have complained to senior management about their Scrum Master ' s processes. What should the Scrum Master do to address the team ' s process concerns?

A.

Include senior management in the process decisions.

B.

Communicate the processes and expectations to the team.

C.

Conduct retrospectives at the end of every sprint.

D.

Include process feedback in the next sprint planning session.

Full Access
Question # 35

An agile team consisting of eight members is in their 11th iteration of a project. In the last iteration, the team was not able to complete every scope item it had committed to before the demonstration.

Which approach should the agile lead take?

An agile team consisting of eight members is in their 11th iteration of a project. In the last iteration, the team was not able to complete every scope item it had committed to before the demonstration.

Which approach should the agile lead take?

A.

Coach the team to decompose the backlog activities to granular, simple tasks that are easier to estimate and complete.

B.

Evaluate the team ' s capacity and help them select user stories for the iteration based on 60% of their capacity utilization.

C.

Discuss options to add more people to the team so they can complete the tasks on time and within budget.

D.

Evaluate the team ' s capacity and help them select user stories for the iteration based on 80% of their capacity utilization.

Full Access
Question # 36

The team is aware that they will need to integrate a new component to their solution in the next few weeks. The team does not have any experience with this component.

What should the team do next?

A.

Ask for a team extension so that an engineer with the needed experience can be added to the team.

B.

Suggest that the Product Owner perform the initial investigation and present the outcome to the team.

C.

Request that the Product Owner include a spike in the next iteration ' s backlog so they can perform an initial investigation.

D.

Propose alternative components with which the team has experience.

Full Access
Question # 37

The product owner is very concerned about work not being completed and tested before a hard release date.

What can the agile team do to mitigate this risk?

A.

High-risk features can be prioritized to fit into releases with less work in progress.

B.

Low-risk, low-value features can be prioritized and completed first.

C.

High-risk, low-value features can be evaluated by the team early in the release.

D.

The work in progress can be adjusted to get more reviews with high-risk features.

Full Access
Question # 38

An agile team is continuously interrupted by stakeholders wanting to ask product backlog questions. Distractions can have a negative impact on value delivery and quality.

Who is responsible for protecting against distractions?

A.

Product owner

B.

Project manager

C.

Agile leader

D.

Developers

Full Access
Question # 39

During the high-level estimation for a project, the team contacted the product owner about the client’s requirements. The team is seeking guidance as their estimate is too big and there is a risk of not finishing the project in time.

What should the product owner do to help the team?

A.

Work with the client to ensure that the requirements are clear enough to allow a correct estimation and refine the backlog if needed.

B.

Assist the team with schedule planning to mitigate risks, including the possibility of crashing if needed.

C.

Implement clear measurements to control any deviation and therefore ensure the project ' s success per client requirements

D.

Recommend that the team skip requirements that are too complex and estimate them later through progressive elaboration.

Full Access
Question # 40

For what is the MoSCoW method used?

A.

Estimating story size

B.

Prioritizing stories

C.

Validating a product

D.

Tracking progress

Full Access
Question # 41

When considering impact on a project, to whom should an agile project manager give top priority on the stakeholder list?

A.

The stakeholder who can prevent the project from delivering within budget

B.

The stakeholder who can prevent the project from achieving its goals

C.

The stakeholder who can delay the project

D.

The stakeholder who can work as a friend and help prepare the stakeholder list

Full Access
Question # 42

What should the team have done to improve retrospective outcomes?

A.

Invited subject matter experts (SMEs)

B.

Conducted problem detection to determine root causes

C.

Measured and reported the outcome of improvement actions to the team

D.

Kept track of all current issues in a log and then reviewed their progress at the end of every iteration

Full Access
Question # 43

A project team realizes that an important task on the iteration backlog will take more time than originally estimated.

What should the project team do?

A.

Continue working on the task until it is completed

B.

Remove the task owner from the project team

C.

Add resources to reduce time to task completion

D.

Stop working on the task and include it in the next iteration

Full Access
Question # 44

An agile practitioner is working on a project to migrate data from computer systems to another location. To accomplish this task, they need to run four activities sequentially that different teams are performing. The teams are migrating two systems per day, but the agile practitioner thinks that three systems should be done per day.

What can be done to improve process efficiency?

A.

Use burndown charts to find gaps. delays, and constraints in the current process and develop a plan to reduce or remove them.

B.

Use value stream mapping to find gaps, delays, and constraints in the current process and develop a plan to reduce or remove them.

C.

Use Pareto analysis to find gaps, delays, and constraints in the current process and develop a plan to reduce or remove them.

D.

Use root cause analysis to find gaps, delays, and constraints in the current process and develop a plan to reduce or remove them.

Full Access
Question # 45
A.

Keep sprints short.

B.

Invite the stakeholder to the daily stand-ups.

C.

Ask the stakeholder for estimates for each user story.

D.

Schedule more demos during each sprint.

Full Access
Question # 46

A member of the development team displays disrespectful behavior and continuously argues with colleagues. This is negatively impacting team morale.

Which action should the scrum master take to resolve this situation?

A.

Mitigate the new conflicts that appear and rely on the self-organization of the team.

B.

Escalate the issue to senior management to make a decision.

C.

Follow the organization ' s policies to remove the team member to boost team engagement.

D.

Attend daily coordination meetings and retrospectives with the agile coach.

Full Access
Question # 47

A large project team of 20 people from different functional areas has just been formed and the project starts next week. The team will be working on a regulated and strictly controlled pharmaceutical product but does not have subject matter expertise.

Which two actions should the scrum master take as priorities? (Choose two.)

A large project team of 20 people from different functional areas has just been formed and the project starts next week. The team will be working on a regulated and strictly controlled pharmaceutical product but does not have subject matter expertise.

Which two actions should the scrum master take as priorities? (Choose two.)

A.

Schedule a meeting to engage stakeholders to prepare for kickoff

B.

Schedule a meeting to agree to the goals for all future iterations.

C.

Guide the team to work collaboratively and share learnings.

D.

Organize a sprint planning meeting to define actions.

E.

Organize a meeting to outline roles and responsibilities.

Full Access
Question # 48

A development team has started working on a new service but is unsure if the service fits the customer ' s requirements. What should the product owner do to ensure that the service will benefit the customer?

A.

Release the minimum viable product (MVP) to a group of customers and end users for their feedback.

B.

Build a prototype and review it with the targeted customer segment for their feedback.

C.

Invite a group of customers and end users to the biweekly demos to obtain feedback.

D.

Release the prototype of the software for 6 months to a pilot group of customers for feedback.

Full Access
Question # 49

What should the team do next?

A.

Use agile estimation techniques to create a shared understanding of when the user stories will be completed.

B.

Agree upon development and testing activities for the user stories.

C.

Complete the user stories, and provide a demo for the product owner and customer.

D.

Complete the user stories, and hold a retrospective to discuss them.

Full Access
Question # 50

Which of the following allows DevOps to enable and sustain a fast workflow from development into operations?

A.

A mindset shift to establish controls over all development and operations processes.

B.

Planned incremental iterations and a focus on people over processes.

C.

A culture of collaboration, tools, and processes to support continuous delivery.

D.

New tools that enable teams to continuously build, test, and integrate.

Full Access
Question # 51

An agile team is struggling with an issue. A team member mentions that another team had a similar issue that was resolved, but lessons learned documents are unavailable.

What should the agile practitioner do?

A.

Suggest that all agile teams share weekly reports on their projects.

B.

Encourage the team to independently find a solution.

C.

Work with the team to create a solution for disseminating team knowledge throughout the company.

D.

Recommend hiring an external expert to advise on the best methods for sharing knowledge among teams.

Full Access
Question # 52

Unable to meet a sprint ' s committed velocity, an agile team approaches the agile coach to define the next sprint ' s velocity. What should the agile coach advise?

A.

Split each story into multiple stories to meet the desired velocity.

B.

Set the velocity to the delivered story points of the last sprint.

C.

Use different estimation methods for stories and defects to meet the desired velocity.

D.

Re-estimate by assigning more story points to smaller stories to increase the velocity.

Full Access
Question # 53

There is a throughput of 200 tickets in a customer service line. The tickets are raised by employees, with each 8-hour shift averaging 50 tickets in progress.

What is the cycle time to resolve a ticket?

A.

0.25 hour

B.

1 hour

C.

2 hours

D.

4 hours

Full Access
Question # 54

How can an agile team working on a new product ensure alignment with external stakeholders?

A.

Ask the product owner to provide a detailed product specification document

B.

Conduct story-mapping exercises to clarify deliverables and release priorities

C.

Hold a kick-off meeting to assign roles and responsibilities

D.

Work with the scrum master and stakeholders to ensure agile principles are followed

Full Access
Question # 55

What is the disadvantage of using velocity as a measure of team efficiency in agile approaches?

A.

Capacity planning will not be accurate.

B.

Inaccurate pressure on customers.

C.

Quality increases while output decreases.

D.

Delivery speed increases while morale decreases.

Full Access
Question # 56

During a current sprint, a team member asks permission from the Scrum Master to investigate an alternative design approach.

What should the Scrum Master do?

A.

Discourage the team member from deviating from the plan and document the request during the retrospective

B.

Encourage the team member to research the issue and present the findings during the retrospective

C.

Discourage the team member from using experimentation/spikes unless it is fully developed and accounts for a variety of use cases

D.

Encourage the team member to use experimentation/spikes for continuous improvement and help the team understand why it is important

Full Access
Question # 57

When working on a new product, what should an agile team do to ensure alignment with external stakeholders?

A.

Hold a kick-off meeting to assign roles.

B.

Review the project vision statement.

C.

Ask the product owner for a detailed product-specification document.

D.

Work with the Scrum Master to ensure that agile principles are followed.

Full Access
Question # 58

A project manager is working on a user story about migrating to a new version of a database but is unsure of the dependencies. What can the product owner request from the team to understand the risks?

A.

Refinement meeting

B.

Daily standup meetings

C.

Retrospective

D.

Spike

Full Access
Question # 59

A project team has been working on a new application. The application is technically challenging, because the team is using new technology unknown to the development team and business requirements are unclear. The product owner has been working closely with the stakeholders to ensure alignment with requirements and other issues. The agile lead is working with the team and product owner on the product backlog.

What is the role of the team?

A.

Estimate and define the work items.

B.

Assess user story quality and independent, negotiable, valuable, estimable, small, and testable (INVEST) criteria.

C.

Add features to the product backlog.

D.

Determine if the demand is or is not feasible.

Full Access
Question # 60

A new CIO advocates an agile framework for new IT projects, but the team has reservations. How should the CIO ensure that the team will be aligned with this?

A.

Obtain executive team buy-in by conducting a meeting to present the advantages of agile principles and processes.

B.

Issue a memo of understanding that agile principles should be implemented for all new projects.

C.

Introduce agile principles and processes, then make the change an experiment to obtain buy-in.

D.

Require all staff and management to attend agile training and adhere to its principles.

Full Access
Question # 61

What should the agile team do?

A.

Adhere to the new deadline and immediately advise the client that the schedule has been expedited.

B.

Advise the client that it is best to continue as planned rather than introduce unforeseen risks by expediting the schedule.

C.

Submit a change request to the client with a 50% increase in charges due to the new potential profit.

D.

Request additional resources to meet the expedited deadline and obtain training for the new resources.

Full Access
Question # 62

A team working with a new technology faces a significant amount of uncertainty about its ability to deliver stories due to technical issues. What should the team do?

A.

Capture risks and make them visible, and use a burndown chart to focus on reducing risks early in the project.

B.

Ask the Scrum Master to extend the sprint ' s duration to allow more time to work through technical issues.

C.

Place the impacted stories on the story board, and use daily stand-ups to make the product owner aware of the technical issues.

D.

Seek guidance from the development manager.

Full Access
Question # 63
A.

Small user stories

B.

Simple acceptance criteria

C.

Lean features

D.

Lean backlogs

Full Access
Question # 64

A client is pressed for time and wants to launch a product with three components as soon as possible to gain market share. An agile lead proposes the following agile strategy to gain time: Three teams will work on the design and development of each component. Once all three components are finished, they will be tested and integrated.

Is this agile strategy appropriate?

A.

Yes, this is a case of sequential development where working in parallel is an accepted strategy in agile to gain time.

B.

Yes, this is a case of hybrid development where a product is divided into components and agile is used for component development and integration.

C.

No, dividing the development team into three separate teams will diminish communication and result in delays.

D.

No the feedback loops are being altered, which can result in big failures and delays

Full Access
Question # 65

Members of an agile team are complaining that user stories are too large, taking multiple sprints to complete them. They say this way of working is becoming difficult to handle and it has been challenging to map relationships between stories. This situation is affecting the value delivery for the product owner.

What should the scrum master do to handle this situation?

A.

Separate large user stories.

B.

Apply work-in-progress limits.

C.

Organize user stories into epics.

D.

Replace user stories into features.

Full Access
Question # 66

An agile team has defined their definition of done (DoD) for a sprint. However, during the demo, the product owner is not sure if a user story can be marked as done.

Select the most appropriate sequence of activities that would need to be completed to meet a well-defined, mature definition of done (DoD).

A.

Code is unit tested, code is peer reviewed, functional testing is passed, business testing is passed, and all acceptance criteria are met.

B.

Code is unit tested, all acceptance criteria are met, business testing passed, code is merged, code is peer reviewed, and documentation is updated.

C.

All acceptance criteria are met, documentation is updated, functional testing is passed, business testing is passed, and code is peer reviewed.

D.

Code is unit tested, all acceptance criteria are met, business testing is passed, functional testing is passed, code is merged, and documentation is updated.

Full Access
Question # 67

A newly formed team is struggling to work together and agree on how to complete tasks in the upcoming sprint. What should the scrum master do to support the team?

A.

Resolve the disagreement for the team as a servant leader.

B.

Encourage the team to continue trying to resolve their disagreements.

C.

Advise the team on the correct course of action to avoid disagreements.

D.

Remove the team members that are in disagreement to ensure unity in the team.

Full Access
Question # 68

What should the agile practitioner do?

A.

Ask the product owner to inform all stakeholders about the project ' s progress.

B.

Send meeting notes to all stakeholders after each review meeting.

C.

Include the results of the review meetings in the information radiators.

D.

Convince the stakeholders of the benefits of attending the review meetings.

Full Access
Question # 69

While struggling to take ownership of delivery, an agile team fails to keep up with its sprint commitments.

What should the agile coach do?

A.

Work with the sponsor to develop team expectations

B.

Provide the customer with a list of deliverables and obtain agreement

C.

Encourage the team to more frequently interact with all stakeholders

D.

Work on finishing upfront product design rather than comprehensive documentation

Full Access
Question # 70

During the iteration planning of a newly onboarded agile team, the product owner adds a set of high priority user stories into the iteration backlog. What should the team do first to define the tasks needed to implement the user stories?

A.

Self-organize

B.

Assign tasks to each team member

C.

Meet with the customer

D.

Identify the Scrum Master

Full Access
Question # 71

If an individual is working on a project team in a phase delivering an increment, according to the definition of done (DoD), who was that defined by?

A.

Project sponsor and project team

B.

Scrum master

C.

Product owner

D.

Stakeholders and project team

Full Access
Question # 72

What should the agile coach ensure that developers do?

A.

Establish pair programming partners, and regularly perform peer reviews.

B.

Perform demos at the end of each iteration.

C.

Send coding to the quality assurance (QA) team upon completion.

D.

Demonstrate each feature to the client as soon as coding is complete.

Full Access
Question # 73

A team member on a self-directed team is concerned that a feature the customer wants is outside of what the team will be able to deliver. What should the team member do next?

A.

Escalate the concern to the project sponsor for necessary action

B.

Adjust the feature to make it work as needed

C.

Work directly with the customer to arrive at a suitable compromise

D.

Log this into the risk register and inform the team at the next standup meeting

Full Access
Question # 74

During the review session, the product owner discovers that the user interface has a response time of 10 seconds. The non-functional requirements state that it should respond in less than two seconds. The team complains that this requirement was not communicated to them.

What should have been done to avoid this?

A.

A comprehensive user story with all non-functional requirements should have been created

B.

Non-functional requirements should have been added to the acceptance criteria

C.

Non-functional requirements should have been added to the definition of done

D.

A team review of the scope of work should have been conducted

Full Access
Question # 75

Midway through a sprint, a team member discovers that the product design fails to adhere to the organization ' s enterprise architecture standards. Since this required escalation to the architecture team for further analysis and resolution, the team was unable to deliver its sprint goal and the sprint was cancelled.

What should the team have done to avoid this?

A.

Escalated the issue to management

B.

Ensured the early engagement of key stakeholders

C.

Provided feedback to the architecture team to change the enterprise architecture standards

D.

Raised an exception for non-adherence to the enterprise architecture standards for this product

Full Access
Question # 76

What should a Scrum Master do when one team member falls behind in their tasks?

A.

Move the task to another team member who has spare capacity in the sprint

B.

Ask the team for suggestions

C.

Privately offer the team member encouragement to meet task commitments

D.

Notify the product owner

Full Access
Question # 77

An agile team is in their 2nd iteration planning session. During the session, they are debating on whether regression and integration testing should be part of every iteration or part of the hardening iteration.

What should the agile lead recommend?

A.

Integration testing with other upstream or downstream applications and all bug fixes should be done as part of the hardening iteration.

B.

Integration testing with other upstream or downstream applications should be done by the team as part of every iteration.

C.

Continuous integration and regression testing should be done by the team as part of every iteration.

D.

Regression testing should not be done by the team as part of every iteration but only as part of the hardening iteration.

Full Access
Question # 78

What should the agile coach do?

A.

Start the hiring process for a new, equally skilled database administrator as a replacement.

B.

Move this database administrator to another team so that team members learn database-related tasks.

C.

Add another database administrator to balance the workload and aid with knowledge retention.

D.

Obtain agreement from the team that, on upcoming sprints, the database administrator will act only in an advisory capacity.

Full Access
Question # 79

During initial planning, a project team investigates several approaches to building new application software, emphasizing the most valuable deliverables. The team needs to convince stakeholders and win their approval.

How can the project team achieve this?

A.

Use a successful platform on which several object-oriented products have been developed in the past.

B.

Create a quick mock-up of the product to serve as a visual tool and adjust it until consensus is reached.

C.

Include brief exploratory iterations, proof-of-concept (POC). to reduce project risk at the beginning of every project cycle.

D.

Deliver an iteration planning diagram, allowing a 2-week refactoring period at the end of the project.

Full Access
Question # 80

Business partners are attending a daily standup meeting for a project. The business partners are asking questions about the sprint backlog and delivery timing.

How should the project manager explain why this is not the forum to ask these questions?

A.

The daily standup meeting provides a status update for the scrum.

B.

The daily standup meeting helps to resolve issues that arise within the backlog.

C.

The daily standup meeting helps the team prioritize the work.

D.

The daily standup meeting helps the team keep and synchronize commitments.

Full Access
Question # 81

A project manager is working on an agile team. A team member mentions that risks threatening the release date of the current sprint are not being addressed.

What should the project manager do to make sure team members are following up on risks?

A.

Hold one daily coordination meeting to determine the reason team members are not following up on risks.

B.

Ask the team to review the executed tasks and follow up on the upcoming threats.

C.

Display the major risks, assumptions, issues, and dependencies (RAID) log visually to highlight the risk status.

D.

Create one sprint to update and follow up on major release risks.

Full Access
Question # 82

Roadmaps are defined as covering a rolling 12 months. When creating a product roadmap in an agile environment, what factor should the agile lead take into consideration?

A.

Just-in-time (JIT) refinement

B.

Stories to be released in each sprint

C.

Infrastructure updates

D.

Funding decisions

Full Access
Question # 83

How can the scrum master respond to a stakeholder who suggests using velocity as a metric to measure team efficiency in an agile project?

A.

Velocity of a Scrum team will stop once it becomes stable and only then the team will become efficient with its deliverables.

B.

Velocity can only measure if a Scrum team has a stable and predictable run rate but not whether or not they are delivering better deliverables efficiently.

C.

Velocity will become more predictable only in stable teams and velocity should not be measured in Scrum teams until that occurs.

D.

Velocity is a great way of measuring the Scrum team ' s efficiency, and a stable velocity means the team is predictable and efficient.

Full Access
Question # 84

As user stories are developed, what should be done to record and update acceptance criteria?

A.

Add more user stories.

B.

Use sprint retrospectives.

C.

Update current user stories.

D.

Update new tasks in the project plan.

Full Access
Question # 85

An organization is using a predictive approach to managing projects. The executives like to see more deliverables in a short time and require that the milestones be achieved on time.

What value can the organization gain by moving to an iterative approach?

A.

New tools that deliver iterative and incremental work

B.

A more predictable delivery schedule and better quality

C.

Higher levels of activity-based planning and user histories

D.

Increased focus on the value and benefits delivered

Full Access
Question # 86

As a team completes their 21st sprint, new information reveals that a number of significant system integrations must be made to ensure the project scope is met.

How should the project management plan be adjusted?

A.

Holistically at the project level

B.

At the end of each sprint

C.

At a sprint level after each demo

D.

Periodically, at both the release and project level

Full Access
Question # 87

During product development, changes in technology and regulations require the team to reassess product architecture.

How should this technical debt be captured?

A.

Include it in the product backlog and use a new indicator to annotate that it is technical debt

B.

Include it in the product backlog as a low-priority issue

C.

Since it is not a part of Agile methodologies, it should not be tracked

D.

Have team members maintain personal lists of issues and consolidate the lists during review

Full Access
Question # 88

An agile team is having a meeting with a customer to formulate the product requirements for the next iteration. The outcome of the meeting is a set of clear and detailed requirements.

What should the team do next?

A.

Run automated tests on the legacy functionality.

B.

Ask the customer to write tests that will be used to know when a story has been correctly developed.

C.

Start coding on the selected user stories to meet the requirements.

D.

Write tests that will be used to know when a story has been correctly developed.

Full Access
Question # 89

An agile team is building a training safety video based on current government regulations. The agile coach knows the regulations are likely to change before the release date.

How should the agile coach address this change?

A.

Plan for the second release to include regulatory changes and new features.

B.

Hold off making changes during the current release because the regulatory changes cannot be planned for.

C.

Verify the team is building the product in increments which can be adapted at the last minute if necessary.

D.

Monitor regulatory discussions to get a head start on the upcoming regulatory changes.

Full Access
Question # 90

During a backlog refinement meeting, a senior team member raises a concern about an epic sizing that requires the use of a new interface for a vendor product. The product owner acknowledges this as a risk. What should the product owner do now?

A.

Log the risk in the risk register, and share the information with impacted stakeholders at the next monthly review meeting.

B.

Create a spike story to determine what needs to be done to use the new interface.

C.

Lower the epic ' s priority so that it can be deferred, and analyze it during backlog refinement meetings.

D.

Move the work to the vendor, since they have better knowledge of interface implementation.

Full Access
Question # 91

A client needs to release their product to market earlier than planned. They need to start receiving the expected revenue, according to their financial forecast, which will require completing the work left on all user stories in the backlog.

What should the project lead do to accommodate this request?

A.

Review the burn up chart to make predictions of how many iterations left are required to complete user stories left and make required adjustments to finish earlier.

B.

Review the burn down chart to make predictions of how many iterations left are required to complete user stories left and make required adjustments to finish earlier.

C.

Ensure the team focus on completing the current items in the backlog and do not accept any request for changes.

D.

Work with the product owner to launch a minimum viable product (MVP) and focus on completing only this portion of work by the new deadline.

Full Access
Question # 92

What should the agile coach do?

A.

Meet with the agile team lead to discuss ways to improve team velocity and get back on track

B.

Use this as a learning opportunity and allow the team to handle the situation when the marketing campaign begins

C.

In the upcoming retrospective, discuss ways to improve sharing project status information

D.

Meet with the marketing stakeholders to explain that the team will miss the planned release date

Full Access
Question # 93

HOTSPOT

Organizations that implement agile project management focus on upgrading existing products and services through cost reductions, time savings, or quality enhancements for existing customers (i.e., operational agility). Organizations need to realize that the major financial gains from agile project management will result from the practice of what? (Select answer from dropdown)

Full Access
Question # 94

What should the project leader do?

A.

Assign the spike to another resource to continue research for the long-term solution

B.

Re-establish the spike; encourage experimentation and collaborate with the team

C.

Stop experimentation and negotiate the short-term solution with the customer

D.

Schedule a root-cause analysis with the development team on the main issues with the spike

Full Access
Question # 95

The Scrum Master for a large project must provide an estimate of what can be delivered in six months.

What should the Scrum Master do?

A.

Commit to a specific feature set for delivery

B.

Explain that a commitment will be provided after planning

C.

Have the team estimate in story points to commit to a specific set of features

D.

Use the team ' s historical velocity to calculate a range of features that can be delivered

Full Access
Question # 96

Halfway through the execution of an agile project, a retrospective meeting is held. One of the team members believes that the actual time and cost to complete the work has consistently been greater than what was originally estimated.

Which of the following activities should be performed next?

A.

The product owner should reduce the scope of the project so that the items delivering the highest business value can be completed.

B.

The team should perform a spike to conduct research on their technical solutions and prove their viability.

C.

The team should consolidate small stories into larger ones so that there are less work items to be estimated.

D.

The team should reevaluate time and cost estimates to reflect the latest understanding of the work effort.

Full Access
Question # 97

A team worked with a customer to estimate all user stories for the must have features. During release planning sessions, the customer indicated they prefer 3-week iterations that begin on Thursdays and end on Wednesdays. The team spent several days determining which stories should be developed for iteration 0 and understanding the customer’s priorities for the remaining stories. The project sponsor attends the Friday meeting and requests a high-level estimate of when they can invite the chief executive officer (CEO) to a demonstration of the minimum viable product (MVP).

What should the team tell the sponsor at this point in the planning process?

A.

They do not have enough information to estimate a date range yet but can provide the number of 3-week iterations required.

B.

They can provide an anticipated date with the assumption that conditions will be ideal.

C.

They can provide a broad range but cannot realistically set a target release date until the team ' s velocity stabilizes.

D.

They will send an update when all of the stories are estimated and prioritized in the backlog.

Full Access
Question # 98

What should the team do?

A.

Re-estimate the sprint ' s completed stories to increase and adjust the sprint ' s velocity.

B.

Increase the duration of the next sprint to accommodate the incomplete user stories and maintain velocity.

C.

Work with the product owner to create a spike with another agile team.

D.

Re-estimate the incomplete stories for the next sprint because its relative size has changed.

Full Access
Question # 99

The coach on a new agile team notices that one team member is influencing most of the team ' s decisions. What should the coach do?

A.

Replace the team member with a more collaborative individual.

B.

Permit the team member to continue influencing because agile teams are self-organizing.

C.

Ask probing questions to other team members to encourage dissenting viewpoints.

D.

Intervene if the team ' s velocity drops.

Full Access
Question # 100

Toward the end of a project, the product owner discovers that the project has a high probability of failure due to a critical feature not functioning as expected.

What should the product owner do?

A.

Terminate the project to cut losses

B.

Review possible options and make an informed decision to cut losses based on delivered business value

C.

Bring in experts to increase the probability of success

D.

Continue the project, release the product without the failing feature, and fix the feature in a subsequent release

Full Access
Question # 101

What should the project team do next?

A.

Estimate the project team ' s capacity.

B.

Determine how much work can be delivered.

C.

Calculate how much work will fit into the next iteration.

D.

Estimate items in the product backlog.

Full Access
Question # 102

During a sprint review, the Product Owner identifies a required improvement for a feature’s user interface (UI) delivered during the sprint.

What should the Product Owner do next?

A.

Create a user story for this new improvement and put it in the product backlog for prioritization and validation by the customer

B.

Create a user story for this new improvement and prioritize it for the next sprint

C.

Document it as a requirement creep

D.

Ask the team to take on additional story points to improve the UI

Full Access
Question # 103

An Agile Project Manager observes that the Scrum team is falling behind on the completion of a particular sprint.

What should the Agile Project Manager do?

A.

Facilitate by providing directions to the team about how they can get back on track.

B.

Request key stakeholders to extend the sprint to enable the team to complete their tasks on time.

C.

Ask the customers to help the team complete the testing on time to be able to finish their tasks on time.

D.

Understand the impediments and facilitate issue resolution to enable the team to succeed.

Full Access
Question # 104

Who should the Scrum Master invite to the meeting?

A.

The core team and the customer

B.

The product owner and key stakeholders

C.

The customer and the sponsor

D.

The core team and the product owner

Full Access
Question # 105

A project is to be started with a team of nine existing and nine new members. The Scrum Master feels that the team is too large and wants to break it into three teams. The Scrum Master sets a constraint that each team have an equal number of existing team members for knowledge sharing and experience.

What should the Scrum Master do to accomplish this?

A.

Ask the team members ' functional managers for guidance on how to group the team members.

B.

Observe which team members are comfortable working together, then assign accordingly.

C.

Ensure that members begin to self-organize as small teams with efficiently distributed skills.

D.

Assign team members to their respective teams based on the skills known to the Scrum Master.

Full Access
Question # 106

What should the project leader do?

A.

Encourage the team to self-organize and determine how to best complete their existing work and this spike.

B.

Encourage the team to complete their just existing work since the team velocity indicates they are already struggling to meet the release goal.

C.

Direct the team to defer the spike until the next release and add the action on the backlog for prioritization.

D.

Direct the team to work on the spike immediately given the importance of reporting functionality to complete the iteration.

Full Access
Question # 107

A business analyst has been assigned to optimize a process to deliver healthcare services to patients in a clinic. In creating a value stream map, what will the business analyst’s key observations include?

A.

Process breakdowns and workflow

B.

Wait times and cycle times

C.

Process maps and story points

D.

Activity sequences and earned value (EV)

Full Access
Question # 108

A company is planning to launch a new service to improve the customer checkout experience.

What should the project manager do to meet the objective of reducing time to market to gain a competitive advantage in the industry?

A.

Engage the project stakeholders to assess the best practices to apply and plan the deliverables before implementation.

B.

Recommend an Agile delivery approach and provide information to the stakeholders on Agile values and principles.

C.

Educate the team about Scrum and ensure that all members are aligned to the roles required.

D.

Consult executive leadership for the most appropriate method for delivery using existing organizational practices.

Full Access
Question # 109

An agile coach is working on a digital transformation project. The project team is in the middle of a 5-week sprint. The agile coach notices constant arguing among team members on what should be the preferred technical approach to solve a current business problem. What can the agile coach do to promote collaboration and consensus-building among team members?

A.

Work with team members to resolve the issue.

B.

Escalate the issue to the product owner.

C.

Allow team members to resolve the issue.

D.

Escalate the issue to senior management.

Full Access
Question # 110

What should the Scrum Master advise the team to do?

A.

Implement the story since the team is running behind schedule.

B.

Create a spike to finalize the story ' s technical approach.

C.

Transfer the story to a Scrum team experienced in solving similar problems.

D.

Ask the product owner to reduce the story ' s priority and wait until more technical details are available.

Full Access
Question # 111

Several team members are new to agile and there is a lot of confusion. It seems everyone is coming in with different experiences and following their own agendas. The scrum master decided to hold a presentation on core agile principles and values.

What should the scrum master emphasize to the team during the presentation?

A.

The value of agile ceremonies and methods

B.

Performance and chain of command

C.

Product deliverables, procedures and features

D.

Collaboration, value delivery and shared mindset

Full Access
Question # 112

An organization is undergoing an agile transformation to improve its market position. Management wants minimal overhead in connection with the agile initiative and wants the agile teams to control the work in process (WIP) and ensure that iterations do not result in waste.

Which approach should be used in this scenario?

A.

Feature-driven development

B.

Extreme Programming (XP)

C.

Scrum

D.

Kanban

Full Access
Question # 113

What should the agile project manager do?

A.

Discuss and address this in the iteration retrospective

B.

Let the product owner know it is the project manager ' s responsibility to drive a team ' s tasks

C.

Discuss the roles and responsibilities of the project team with the product owner

D.

Ask the product owner to work extra hours to answer the team ' s questions

Full Access
Question # 114

Answer Options:

A.

The iteration is in jeopardy.

B.

The team has removed scope.

C.

The iteration is ahead of schedule.

D.

The team ' s velocity is constant.

Full Access
Question # 115

A team retrospective was going well until the team lead introduced the " define the next experiment " topic; then the discussion became an argument. A new team member feels strongly that the approach used on their previous team would improve this team ' s efficiency and effectiveness. The team lead is adamant that they remain with the current approach and the discussion dissolves into a circular argument.

A.

Remind the group that all input is welcome but dissension is not productive and suggest the group move on to another task more agreeable to everyone.

B.

Restate both stances, ask for details of both approaches, and create a chart of similarities and differences.

C.

Construct an Ishikawa diagram for each approach, and use the 5 Whys technique to determine the effectiveness of each approach.

D.

Interject and request this experiment be postponed for 2 months, so the new team member has time to observe the current approach.

Full Access
Question # 116

An agile team is preparing a release plan for a project. What information will the team need to complete this plan?

A.

Amount of work needed to complete a single user story

B.

Amount of work that can be accomplished by each team member

C.

Amount of work that can be accomplished in an iteration

D.

Amount of work that can be accomplished by the entire team

Full Access
Question # 117

What should the agile practitioner do?

A.

Regularly circulate an updated, detailed version of the project plan

B.

Frequently update the online project management office (PMO) repository site

C.

Invite the stakeholders to daily stand-ups

D.

Post a project board in an area where all can view it

Full Access
Question # 118

An agile project was underway for two months and delivered the expected value to the stakeholders. However, during a sprint review, a team member complained that the product owner constantly changes requirements and the member feels that this is blocking the team’s performance.

How can the scrum master handle this situation?

A.

Work with the product owner to include fewer features in the next sprint planning.

B.

Hire more team members to elevate the team ' s velocity to increase performance.

C.

Tell the team members that changes are natural and welcome if the project is delivering value.

D.

Schedule more meetings with the team and the product owner to refine the backlog constantly.

Full Access
Question # 119

An agile team lead noticed their team’s velocity was slowing down. They did not deliver a working software during the last iteration and there have been miscommunications between team members.

What should the agile team lead do at the end of this iteration?

A.

Focus on performance in the retrospective, then present performance indices and validate with the team.

B.

Start using feedback loops in every sprint to reevaluate project and team performance.C Emphasize business requirements and investigate the pair-programming approach

C.

Run a spike at the end of the sprint to investigate the issue and reduce project risk.

Full Access
Question # 120

An executive notices a Kanban board in a highly visible location and expresses concerns to the project manager that too many people will see it. What should the project manager do?

A.

Cover up the Kanban board every time the project team is not actively updating it.

B.

Demonstrate how the Kanban board is necessary for assigning proper ownership for the work that has been done.

C.

Explain that the Kanban board enables the team to complete the work and increases transparency on work that is not done.

D.

Remove the Kanban board immediately and place it in a location where it is not visible.

Full Access
Question # 121

A user interface (UI) developer has features for channels ready for review. During the team review, the architect is disappointed that Splunk software has not been implemented for better server and client logs. The architect insists on the implementation of Splunk software, which will impact the release date.

Which one of the following is the ideal option for the team to resolve this conflict?

A.

Have the team brainstorm and propose error logging at the client level, which will have a higher impact with less effort within the release timeline.

B.

The product owner should explain to the architect that monitoring, alerting, and logging are not essential for the customer and can be prioritized post-release.

C.

Inform the sponsor that features are being added and will extend the release date after getting approval and communicating this to the architect.

D.

Ask the developer to build and let the testing be postponed until after the release, and inform the architect that the feature will be implemented.

Full Access
Question # 122

A project team developer has been involved in a large corporate initiative that has negatively impacted team productivity on another project to which they have been assigned.

How should the developer have handled this situation?

A.

Worked as planned to meet the team ' s commitments and participated in other events as time permitted.

B.

Worked extensively on the corporate initiative in order to inform the team of that effort.

C.

Asked to be relieved of project tasks to maintain team velocity.

D.

Have not participated in any initiative that could take focus away from the team ' s project and goals.

Full Access
Question # 123

A scrum master is working with a team on a complex software project that is scheduled to run for 2 years with a series of product releases. The scrum master is responsible for planning the project for the next 6 months and has advised planning the project up front.

What should the scrum master do?

A.

Add the releases into a roadmap with milestones and activities.

B.

Identity dedicated tasks and activities with regular feedback loops.

C.

Deliver in small and continuous iterative releases.

D.

Identify the requirements ' schedule within set time scales.

Full Access
Question # 124

What should be done with this story?

A.

Mark it as incomplete and prioritize it for the next sprint

B.

Mark it as complete, since the product owner has the final say

C.

Discard it and create a new story for the remaining scope of work

D.

Mark it as complete, since the team completed the scope of work

Full Access
Question # 125

During sprint planning, the product owner wants the team to prioritize and deliver a number of features that have the highest business value. Due to technical dependencies, the team does not agree with the prioritization.

What should the project leader do?

A.

Encourage the product owner and team to reprioritize the features and select ones which can be delivered without any dependencies

B.

Encourage the team to continue with the current plan, do what they can, and carry forward the work not done to the next iteration

C.

Ensure the team captures the technical dependencies as issues within the backlog and prioritize based on value optimization

D.

Ensure that the required subject matter experts (SMEs) are engaged by the product owner to help with backlog prioritization

Full Access
Question # 126

A product owner with experience in a predictive approach wants the team to develop very detailed schedules and cost estimates for the next 10 sprints. What should the Scrum Master do?

A.

Suggest the product owner start by focusing on the next 2 sprints instead of 10.

B.

Spend the first few sprints to develop detailed schedules and budgets.

C.

Invite the product owner to the retrospective to explain the team ' s approach to schedule and budget.

D.

Explain that detailed project schedules and budgets are not artifacts in agile projects.

Full Access
Question # 127

What should the team do?

A.

Collaborate with the product owner to reprioritize the product backlog, thus ensuring that more features will be completed before the release.

B.

Ask the team lead to calculate the team ' s target velocity according to the project plan, and assign additional resources to increase capacity.

C.

Focus on velocity and schedule concerns during the retrospective to inspect, adapt, and improve the process and plans.

D.

Reestimate the backlog items from the release, ensuring that contingency is included to set stakeholder expectations.

Full Access
Question # 128

What should the agile team lead do?

A.

Create a central repository for information, and provide access to Team B

B.

Use an information board that will be visible to all passing through the workspace

C.

Email all stakeholders with status updates

D.

Provide Team B with the information on an " as needed " basis

Full Access
Question # 129

Following a successful product release, senior management asks an agile team how to improve the value of the product for the next release.

What should the team do?

A.

Conduct frequent demos and obtain feedback from users throughout the development of the next release

B.

Inform senior management that since the product was successfully released, the project is considered delivered and should be closed

C.

Request additional budget to implement a Scrum of Scrums approach to scale the teams and add capacity

D.

Implement a better definition of done to ensure that continuous integration processes are managed effectively

Full Access
Question # 130

A new project has been approved and is critical for an organization. The project sponsor has a limited budget, and the deadline to have all requirements meet the definition of done (DoD) is short.

Which approach should the agile practitioner take to facilitate the project ' s success?

A.

Set up weekly calls with the key stakeholders to participate in iteration reviews and release decisions.

B.

Analyze the impacts of these constraints on the project followed by a report sent to the sponsor to anticipate any risk of delays.

C.

Set up a meeting with the client to review the scope and timelines to manage expectations.

D.

Encourage the team to build increments and ensure the customer provides early feedback for a minimum viable product.

Full Access
Question # 131

What should the agile practitioner have done to ensure stakeholder satisfaction?

A.

Communicated early and often, as outlined in the communications matrix

B.

Ensured engagement among stakeholders and the product owner

C.

Conducted additional stakeholder reviews and demos

D.

Worked with the product owner to prioritize user stories

Full Access
Question # 132

There is a debate within the organization on whether projects need to be agile or waterfall. Some agile terms and principles are understood differently by the key stakeholders and this delays the decision-making process.

How should the scrum master proceed?

A.

Allow stakeholders to discuss without the scrum master ' s intervention.

B.

Recommend an external facilitator as no one in the organization is able to eliminate this roadblock.

C.

Facilitate a face-to-face discussion and have stakeholders agree to shift to agile for future projects.

D.

Organize training sessions to create awareness around the agile values for stakeholders.

Full Access
Question # 133

An agile team is struggling to achieve their goal during the first release due to an unstable environment beyond the authority of the product owner. Close to the end of the current sprint, the release manager resigns and a new person takes over.

What should the Scrum Master do?

A.

Report the issue to the product owner and request help.

B.

Let the new release manager participate in the daily standup.

C.

Invite the new release manager to the sprint demo and ask for help.

D.

Send a status report to the release manager highlighting the issue.

Full Access
Question # 134

An agile development team is working on a digital transformation project and is facing challenges in obtaining consistent feedback from stakeholders who are dispersed around the world. The product owner is under pressure as this lack of engagement has led to prolonged decision-making cycles and has adversely affected the outcomes of sprints.

How should the team improve stakeholder engagement to help ensure timely feedback and better decision-making? (Refer to Stakeholder Power/Interest Grid)

A.

Implement a dynamic feedback platform leveraging collaboration tools, accommodating diverse schedules and enabling stakeholders to provide feedback asynchronously.

B.

Establish a rotating stakeholder committee composed of representatives from different regions and departments, ensuring diverse perspectives are considered in decision-making processes.

C.

Enforce a strict policy requiring stakeholders to attend weekly synchronous feedback sessions, leveraging technology to accommodate various time zones and scheduling conflicts.

D.

Appoint regional liaison officers responsible for coordinating stakeholder interactions within their respective time zones, facilitating regular communication and feedback exchange.

Full Access
Question # 135

A product owner is working on a special agile project for the automobile industry. The project team is responsible for all of the issues related to vehicle electronic control units. The team has observed a significant backlog of items in the “In progress ' column (Refer to the kanban board). This accumulation is causing delays in task completion and impacting overall project timelines. The team operates in a dynamic environment where requirements frequently change, and stakeholders demand quick turnarounds.

What should the project team adopt to address this issue and improve task flow, considering all the demands?

A.

Increase the number of items allowed in the ' In progress " column to accommodate the high volume of tasks and provide flexibility.

B.

Limit the work in progress (WIP) and implement strict policies to encourage team members to focus on completing existing tasks before starting new ones, ensuring a balanced workload.

C.

Move tasks to the ' Done " column regardless of their completion status to give the appearance of progress and alleviate the pressure of the backlog.

D.

Add more team members with varying levels of expertise to handle the increased workload, aiming to accelerate task completion and reduce the backlog in the ' In progress " column.

Full Access
Question # 136

A team member is stressed due to a heavy workload, while other team members have some slack in their schedules.

How should the team lead address this?

A.

Inform management and suggest that additional resources may be required

B.

Discuss the issue with the team in the daily stand-up meetings

C.

Meet personally with the stressed team member to brainstorm ways to better manage their time

D.

Begin tracking the stressed team member ' s tasks in a separate backlog for additional analysis and reporting

Full Access
Question # 137

During a coaching session, an agile project manager discussed embracing communication to keep all stakeholders aligned. The agile project manager recently had a discussion with their team and decided to display a product roadmap.

What is the agile project manager trying to show?

A.

The project ' s total number of story points.

B.

Product releases and what will be included.

C.

The number of completed user stories.

D.

Where the team is in the project life cycle.

Full Access
Question # 138

How can an agile project manager ensure that all stakeholders have a clear understanding of the release plan by the end of a release planning meeting? (Choose two.)

A.

Stated understanding of the release goal

B.

Complete vision of the end product

C.

Timeline of the project

D.

List of the user stories that will be part of the next releases

E.

Complete roadmap of the next iterations

Full Access
Question # 139

On an agile project, some of the development team is struggling to understand how the tasks and user stories fit into the overall product.

How should this be addressed?

A.

Review the iteration goals and have the team each describe the work to create shared understanding

B.

Create a story map for the minimal viable product (MVP) functionality

C.

Capture this as a task in the retrospective and ensure there is more detail provided at the next planning session

D.

Have the Product Owner explain the product vision and review the release plan with the team

Full Access
Question # 140

During backlog refinement, a team routinely creates tests to demonstrate to the customer that each acceptance criterion has been met. Most acceptance tests results are observable or demonstrable, but testing for one requirement is providing a challenge to the team. The requirement states that the home button should be recognizable and the team is unsure how to test this.

What should the team lead do?

A.

Determine if the home button is present and if it is shaped like a house, it is recognizable.

B.

Record the product owner ' s opinion on how they will know if the button is recognizable.

C.

Skip creating a specific test for Ibis particular requirement because it is too abstract

D.

Consult the design team as subject matter experts (SMEs) for criteria on what makes a button recognizable.

Full Access
Question # 141

A team is building a product in three-week iterations. During the last retrospective, it was identified that there was a 20% increase from previous iterations in the number of reported defects and change requests.

Since this is causing the product ' s value to decrease, what should the team do?

A.

Reevaluate the duration of the cycles, as faster cycles may allow for earlier detection of defects.

B.

Run a sprint to clear all reported defects before taking new stories.

C.

Change the control mechanism so that items are better tested before delivery.

D.

Increase the opportunities to confirm common understanding with the client.

Full Access
Question # 142

One of the overseas stakeholders on an agile project has not been actively involved in the project ' s development. What would be the first step to reengage the stakeholder?

A.

Increase the frequency of emails and/or try to call the stakeholder.

B.

Remind the stakeholder of their obligation to engage in the project.

C.

Talk to the stakeholder ' s superior so they can offer coaching and guidance on project involvement.

D.

Set up a meeting with the stakeholder to modify the working agreement and ensure future engagement.

Full Access
Question # 143

What agile tools can help the team address these issues?

A.

Information radiators and wireframes

B.

Information radiators and story maps

C.

Process flows and personas

D.

Personas and extreme characters

Full Access
Question # 144

A scrum master is 6 days into a 10-day iteration. A customer representative approaches the scrum master and asks whether they can access the latest update on the project.

Which action should the scrum master take?

A.

Share the information radiator.

B.

Email the latest release plan.

C.

Invite them to the next retrospective.

D.

Send the latest project report.

Full Access