Weekend Sale - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: mxmas70

Home > CompTIA > Project+ > PK0-005

PK0-005 CompTIA Project+ Certification (2025) Question and Answers

Question # 4

Which of the following is the best example of a breach of physical security?

A.

System user IDs being used by multiple individuals

B.

Printers that do not request user authentication

C.

Developers having full access to both development and production environments

D.

Project documentation that is only kept on a removable device

Full Access
Question # 5

A data center is under construction, and the project manager wants to address the risks related to physical injuries. Which of the following is the best risk response method for this scenario?

A.

Avoid injuries by using robots to perform tasks.

B.

Transfer risk to an insurance company.

C.

Mitigate risk by training the construction workers.

D.

Accept the risks inherent to construction.

Full Access
Question # 6

The client asks the project manager to establish a communication channel. The client wants to understand what is needed from them and to know the project’s level of compliance with the budget. Which of the following best describes what the project manager should do to assist the client?

A.

Grant the client access to the project repository.

B.

Create a chat to communicate in real time.

C.

Schedule a weekly status meeting.

D.

Send a weekly status report by email.

Full Access
Question # 7

A development team, which is working on a software project demonstrates software functionality 10 project stakeholder a week before the implementation date. Several stakeholders comment that the software does not meet the communicated expectations. Which of the following tools should the project manager use to validate the functionality?

A.

Project status report

B.

Requirements Traceability Matrix

C.

Detect log

D.

Signed project charter

E.

Work breakdown structure

Full Access
Question # 8

A new project manager was assigned to a project during the execution phase. The project manager discovers a lot of potential areas that may prevent the project from completing deliverables Which of the following should the project manager do first?

A.

Review the project risk register.

B.

Update the defect tracker.

C.

Meet with stakeholders to discuss concerns.

D.

Add the potential blockers to the issues list.

Full Access
Question # 9

As a result of an internal assessment, the steering committee states that the company does not currently have the required skill set or technical tools to develop a particular feature in the project. Which of the following procurement methods would help the company?

A.

Subscription

B.

Subcontract

C.

Lease

D.

Build

Full Access
Question # 10

A project manager submits a change request. The change request is rejected because of code freeze. Which of the following actions should the project manager take next?

A.

Update the risk register.

B.

Escalate the issue for exceptional approval.

C.

Communicate to the stakeholders.

D.

Submit a duplicate change request.

Full Access
Question # 11

Which of the following items must be protected as Pll? (Select TWO).

A.

Job title

B.

Home address

C.

Work phone number

D.

Time zone

E.

Date of birth

F.

Blood type

Full Access
Question # 12

A lessons-learned meeting took more than two hours and ended without defining a standardized process. The project manager decides to move forward without allowing changes to the existing process. Which of the following techniques is the project manager using?

A.

Forcing

B.

Avoiding

C.

Compromising

D.

Smoothing

Full Access
Question # 13

Which of the following tools is best to use for storing lessons learned?

A.

Whiteboard

B.

Wiki knowledge base

C.

Content management system

D.

Workflow platform

Full Access
Question # 14

A project manager, who finished a project some time ago, keeps receiving questions from another project manager who is currently leading a similar project. Which of the following is the most likely cause of this situation?

A.

The retrospective session feedback was not communicated properly.

B.

The project resources were released ahead of time.

C.

The documentation was not archived as per the PMO standards.

D.

The validation of deliverables is running behind schedule.

Full Access
Question # 15

Because the project team lacks hands-on experience, the project manager has decided to involve a third-party vendor to complete the development of a product. Which of the following documents should the project manager expedite first?

A.

RFI

B.

RFP

C.

RFQ

D.

RFB

Full Access
Question # 16

Which of the following would be best to utilize when managing communications for project teams across multiple time zones?

A.

Business collaboration tool

B.

Email

C.

Virtual meetings

D.

Enterprise CMS

Full Access
Question # 17

A program manager is reviewing the project portfolio and prioritizing each project based on the company's strategic plan. Which of the following should be considered in this evaluation? (Select TWO).

A.

Company vision

B.

Global environment

C.

Brand value

D.

Mission statement

E.

Portfolio budget

F.

Local legislation

Full Access
Question # 18

Which of the following best describes the reason a chat messaging service would be used as the primary form of communication for a project team?

A.

The team is working in different rooms within the same building.

B.

The team is working remotely two days per week.

C.

The team has members distributed around the world in different time zones.

D.

The team is based in the same office but has a large number of members.

Full Access
Question # 19

A project team wants to compare two potential vendors' costs and risks for completing project tasks. Which of the following visualizations will best facilitate this analysis?

A.

Scatter diagram

B.

Decision tree

C.

Pareto chart

D.

Histogram

Full Access
Question # 20

Which of the following communication tools would a project manager use to broadcast information without being assured the information will be received?

A.

Telephone

B.

Videoconference

C.

Face-to-face

D.

Email

Full Access
Question # 21

A PM is working with stakeholders in the discovery phase and comparing the cost of the project to the cost savings the project will produce when it is complete. The output of this exercise will produce the:

A.

ROI.

B.

SOW.

C.

RFI.

D.

RPR

Full Access
Question # 22

Which of the following is an activity related to operational security?

A.

Processing background screening

B.

Setting up a firewall

C.

Establishing a zone of trust

D.

Implementing multifactor authentication

Full Access
Question # 23

A project manager wants to schedule a troubleshooting session for team members who are located in Germany and California. Which of the following is most important for the project manager to consider when setting up the session?

A.

Cultural differences

B.

Technological factors

C.

Time zones

D.

Language barriers

Full Access
Question # 24

A PM is working on the schedule for a project that has technical tasks and requires a SME's knowledge. The PM decides the best way to track this project is to have the project lead provide high-level updates. Which of the following is the best tool to track this data?

A.

Gantt chart

B.

Project organization chart

C.

Program Evaluation Review Technique chart

D.

Milestone chart

Full Access
Question # 25

A client made a change request. Implementing the change will cause a delay in the project and a budget overrun. Which of the following should the project manager do first?

A.

Update the WBS.

B.

Escalate to the CCB.

C.

Accept the change.

D.

Implement the change.

Full Access
Question # 26

A project team is defining operational training, discussing a go-live date, and describing the operational handoff. Which of the following best describes what the team is developing?

A.

The project closeout report

B.

A handover to operations

C.

Phase-gate review documentation

D.

A transition plan

Full Access
Question # 27

Which of the following is a test that is done on an existing system to ensure the previous functionality still works after a change has been made?

A.

Smoke testing

B.

Regression testing

C.

Unit testing

D.

User acceptance testing

Full Access
Question # 28

A sponsor prefers to communicate with the team using email, phone calls, conversations in the hallway, and impromptu meetings. Which of the following types of communication is the sponsor using?

A.

Informal communication

B.

Formal communication

C.

Synchronous communication

D.

Asynchronous communication

Full Access
Question # 29

A project manager queries stakeholders to identify the right communication channel to be used during the project life cycle. After reviewing the responses, the project manager reports that 70% of the stakeholders prefer email communication, and the rest prefer face-to-face communication. The project manager should update the stakeholder register with:

A.

the preferred sponsor's communication channel.

B.

the preferred project manager's communication channel.

C.

the preferred reported communication channel.

D.

email communication as the preferred communication channel.

Full Access
Question # 30

Functional managers are reluctant to provide a project manager with resources for a project because they think the project should include a certain scope. The project manager reviews the project documentation and confirms the items the functional managers wanted to include were out of scope. Which of the following would be the best course of action for the project manager to take?

A.

Satisfy the functional managers by agreeing with their point of view in order to get the necessary resources.

B.

Advise the functional managers to submit a change request, record the issue in the issue log. and escalate the issue to the project sponsor

C.

Schedule a team meeting to discuss creative ways to incorporate the scope without having to formally submit a scope change request.

D.

Inform the functional managers that the project will produce only what has been approved and project modifications cannot be made at this point.

Full Access
Question # 31

During a project closure meeting, stakeholders did not agree that the project achieved the expected results. Which of the following documents should the project manager consult?

A.

Work breakdown structure

B.

Project charter

C.

Quality plan

D.

Solution design

Full Access
Question # 32

Which of the following best explains the importance of artifacts during the discovery/concept preparation phase of a project?

A.

To develop a detailed project plan and timeline

B.

To enable a lessons learned session

C.

To identify and assess potential vendors for the project

D.

To ensure that all stakeholders have a shared understanding of the project's objectives

Full Access
Question # 33

Which of the following statements best describes zero-based budgeting?

A.

Start with the budget from the last project and add any new expenses.

B.

Start with allocating expenses based on the importance of the project.

C.

Start the project with a fixed amount decided by the management team.

D.

Start with no financial plan and justify each new expense.

Full Access
Question # 34

A company is implementing a new radar system from July to September. The project manager knows these months are the peak hurricane season for this region. Which of the following should the project manager develop to mitigate the risk to the project?

A.

Data plan

B.

Contingency plan

C.

Rollback plan

D.

Recovery plan

Full Access
Question # 35

A project manager makes a company-wide announcement about the successful completion of a project and thanks team members. Which of the following is the project manager doing?

A.

Bringing attention to the project sponsor

B.

Sharing lessons learned

C.

Collecting feedback

D.

Celebrating the team's hard work

Full Access
Question # 36

A PM received feedback from the project sponsor that the resources involved in the project are unsure of their daily activities. Which of the following is the MOST effective step for the PM to take to ensure clarity within the team?

A.

Create a list of tasks and share it with the team.

B.

Resend the scope of work to the team.

C.

Review the Gantt chart weekly with the team.

D.

Have the project sponsor meet with the team.

Full Access
Question # 37

Two stakeholders, who have a history of animosity toward one another, are in disagreement during a project. The project's timeline depends on the stakeholders accomplishing their tasks. Which of the following conflict resolution methods would be best to utilize?

A.

Smoothing

B.

Confronting

C.

Forcing

D.

Compromising

Full Access
Question # 38

During the testing process, testers have found multiple bugs that could jeopardize the project commitment date Which of the following tools should the project manager use first to update the findings?

A.

Defect log

B.

Change log

C.

Issue log

D.

Risk log

Full Access
Question # 39

Which of the following cloud models can be used to speed up the development of a service that integrates with the operating system and accelerates the delivery of a software project?

A.

SaaS

B.

IaaS

C.

DaaS

D.

PaaS

Full Access
Question # 40

A project manager is reviewing a signed legal document pertaining to the hiring of a vendor who will develop an experimental solution. The vendor could not provide accurate estimates at this time because the requirements will probably be changing. The document also contains information about the resources involved and the rates the vendor will charge for the work. Which of the following best describes the legal document the project manager is reviewing?

A.

Time and materials contract

B.

Master service agreement

C.

Fixed-price contract

D.

Non-disclosure agreement

Full Access
Question # 41

During the planning phase, a PM reviews the SOW from the contractor, grades the full-time equivalents' resumes, evaluates the titles and salaries, and estimates the number of hours for each milestone by full-time equivalents. The PM is most likely:

A.

negotiating resources.

B.

assigning resources.

C.

assessing the resource pool.

D.

adding resources to the schedule.

Full Access
Question # 42

The project team determines that software installation can only begin after the desktops have been installed and can be powered on. Which of the following dependencies does this represent?

A.

External

B.

Internal

C.

Mandatory

D.

Discretionary

Full Access
Question # 43

A project manager is responsible for implementing a large, centralized repository that stores raw information from various sources in a structured and organized way. Which of the following should the project manager implement?

A.

Shared folder

B.

Infrastructure

C.

Multitiered architecture

D.

Data warehouse

Full Access
Question # 44

For an upcoming project kickoff. a PM is looking for a way to illustrate roles for major project activities. Which of the following would be the MOST useful option?

A.

Resource plan

B.

Organizational chart

C.

Project charter

D.

RACI chart

Full Access
Question # 45

A project manager sent equipment to a global project team for testing purposes. Only 70% of the project team received the equipment for testing. Which of the following considerations is impacting the rest of the team?

A.

Quality assurance

B.

Organizational branding restrictions

C.

State privacy acts

D.

Country legal regulations

Full Access
Question # 46

Which of the following BEST identifies the intent and purpose of a project closeout report?

A.

To provide documentation of lessons learned

B.

To document variances from the initial project baseline

C.

To validate that a project has been successfully completed

D.

To release resources and terminate all access rights

Full Access
Question # 47

Project team members are leaving the company due to a stressful work environment. The project manager needs to capture this concern about potentially losing team members again. Which of the following logs should the project manager use?

A.

Risk

B.

Change

C.

Defect

D.

Issue

Full Access
Question # 48

In a functional organization, a project has been completed successfully. Which of the following actions would the project manager MOST likely perform?

A.

Assemble a new project with existing resources.

B.

Obtain the final report from release management.

C.

Notify the functional manager that resources are released.

D.

Allocate resources in a different project

Full Access
Question # 49

A project is about to start; however, the client is uncertain about the desired details for the final product. Which of the following methodologies should the project manager use?

A.

Agile

B.

SDLC

C.

Waterfall

D.

PRINCE2

Full Access
Question # 50

During a code implementation, a senior developer and junior tester are discussing the testing scenarios that were performed. A major malfunction resulted in an inoperative product condition. As a result, the team was forced to work until midnight to restore operations. Which of the following should the PM have generated FIRST to alleviate the impact of this issue prior to deployment?

A.

A risk budget

B.

A risk impact

C.

A change request

D.

A contingency plan

Full Access
Question # 51

A project manager is overseeing the implementation of a major upgrade to a critical ERP system. The project sponsor is requiring that the upgrade should not exceed more than three hours of downtime for the implementation and validation in production. During cutover, the team runs into a validation issue after 2.5 hours, and the process is only 70% through the validation steps Which of the following actions should the project manager take?

A.

Notify customers the downtime will take longer than expected.

B.

Add new team members to help speed up validation.

C.

Begin executing the rollback plan.

D.

Record the issue and proceed with the implementation.

Full Access
Question # 52

Which of the following statements best describes Kanban?

A.

A workflow management method to maximize efficiency and enable continuous improvement.

B.

A board representing the different stages of a software solution.

C.

A dashboard used to facilitate scope alignment with the project team.

D.

A spreadsheet representing development tasks and how they relate to the business process being improved.

Full Access
Question # 53

A stakeholder called a project manager on the telephone to ask for a status report. Which of the following describe this type of communication? (Select two).

A.

Formal

B.

Internal

C.

Informal

D.

Verbal

E.

Indirect

F.

External

Full Access
Question # 54

Which of the following is the main reason for documenting artifacts?

A.

To provide a record of the project's progress and achievements for future reference

B.

To show stakeholders that the project is on track and progressing as planned

C.

To help team members be aware of roles and responsibilities

D.

To ensure that the project team understands the importance of the project to the organization

Full Access
Question # 55

During a stand-up meeting, a team member asks to include a change that an important stakeholder requested in the project board. This request is denied, and the team member has to go back to what was originally planned for the sprint. Which of the following individuals should the stakeholder have asked to request the change instead of the team member?

A.

Architect

B.

Project sponsor

C.

Scrum master

D.

Product owner

Full Access
Question # 56

A PM is working on a strategy to store records. Which of the following dements must be included in this plan? (Select TWO)

A.

Data management

B.

Issue management

C.

Work breakdown structure

D.

Document management

E.

Communication management

F.

Risk management

Full Access
Question # 57

Although a project was successfully released into production a month ago, a project manager continues to receive project-related work. Which of the following is the reason for this issue?

A.

The project manager did not release the resources.

B.

The project is in the verification testing phase.

C.

The project manager did not complete the project closure phase.

D.

The project manager did not remove access.

Full Access
Question # 58

During a complex, multiyear project, a PM must discern which project tasks overlap so resources can be allocated appropriately. Which of the following is best for determining this information?

A.

PERT chart

B.

Milestone chart

C.

Gantt chart

D.

Budget burndown chart

Full Access
Question # 59

A project manager is in the process of evaluating the probability and impact of a risk by assigning numbers such as a monetary value. Which of the following is the project manager using?

A.

Monte Carlo simulation

B.

Root cause analysis

C.

Quantitative risk analysis

D.

Risk response analysis

Full Access
Question # 60

A project was closed according to the planned project schedule. Security teams later identified that one of the contractors stole data after the project's closure. Which of the following would have most likely prevented the data from being stolen?

A.

Removing access

B.

Closing contracts

C.

Project sign-off

D.

Project evaluation

Full Access
Question # 61

A project manager working in a strong matrix organization was selected to manage a new project with trending technologies. During the kickoff meeting, one of the stakeholders mentions that the company has never worked with such technologies. Which of the following should the project manager do next?

A.

Train the project team members and develop a detailed scope statement.

B.

Assign project resources and procure additional team members.

C.

Perform a preliminary procurement needs assessment and determine budget considerations.

D.

Define units of work and develop a project schedule.

Full Access
Question # 62

A PM needs to calculate the progress of the whole project scope for a presentation to the sponsor. Which of the following is the first document the PM should update?

A.

Project network diagram

B.

Gantt chart

C.

Issue log

D.

Risk report

Full Access
Question # 63

During a quality analysis review, the causes of several issues have been highlighted. Which of the following should the project manager use to identify the MOST important causes?

A.

Ishikawa diagram

B.

Scatter diagram

C.

Pareto chart

D.

Decision tree

Full Access
Question # 64

A manufacturing company is experiencing a high number of defects in its products and wants to identify the root cause to improve its processes Which of the following should the company use?

A.

Run charts

B.

Fishbone/lshikawa diagrams

C.

Scatter plot

D.

Decision tree

Full Access
Question # 65

A project team needs to understand what needs to be done, who needs to complete the tasks, and when the tasks need to be completed. Which of the following artifacts would be the best to capture this information?

A.

SWOT

B.

Risk register

C.

Project schedule

D.

RAC

Full Access
Question # 66

During a kickoff call, a project was rejected by the legal department due to the risk of violating new legislation. Which of the following was applied?

A.

Awareness of the local environment

B.

Awareness of the brand value

C.

Awareness of the resource constraints

D.

Awareness of the company's mission

Full Access
Question # 67

A developer recommends modifying an existing portion of code that is not part of the scope and is causing low performance on the current solution. Which of the following actions should the project manager most likely take?

A.

Ask a developer to create a change request.

B.

Do nothing because recommendation is scope creep.

C.

Ask a developer to implement the recommendation.

D.

Communicate the change status.

Full Access
Question # 68

Several months after a project has ended, a project team member is still charging time to the project and is unable to charge time to new projects. Which of the following did the project manager neglect to do?

A.

Remove the team member's access.

B.

Release the project resources.

C.

Collect the stakeholders' feedback.

D.

Have the closeout report approved.

Full Access
Question # 69

A project manager is using an agile methodology to lead the implementation of several features that should be developed concurrently. Which of the following items should the project manager view as a concern?

A.

Each feature will have a different owner.

B.

The majority of the team can only meet on a weekly basis.

C.

The stakeholders have provided a specific deadline to meet.

D.

Each feature has a specific budget allocation.

Full Access
Question # 70

A project sponsor would like to develop a minimum viable product, but the requirements are not well defined. Which of the following should the project sponsor use?

A.

Rational Unified Process

B.

Waterfall

C.

Agile

D.

DevOps

Full Access
Question # 71

A project manager is beginning a new project that will include a high number of complex deliverables. Which of the following is the best to use to track deliverables that are yet to be completed?

A.

Resource management system

B.

Issue log

C.

Ticketing system

D.

Backlog

Full Access
Question # 72

When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?

A.

Critical paths

B.

Resources

C.

Milestones

D.

Work breakdown structures

Full Access
Question # 73

Which of the following best describes a manufacturer's obligation to repair or change, without extra costs, any part of a product that is not functioning?

A.

Service-level agreement

B.

Functional testing

C.

Warranty period

D.

Audit

Full Access
Question # 74

During the project initiation phase, a project team has been identified. Which of the following is the NEXT step for the project manager?

A.

Determine budget constraints.

B.

Validate the business case.

C.

Update the project charter.

D.

Create a project schedule

Full Access
Question # 75

A project is moving into the user acceptance testing phase. Several resources will be needed to execute different steps in the testing plan. Which of the following would be the best tool to allow the resources to remain at their desks and only react when needed?

A.

Ticketing system

B.

Videoconference

C.

Simple messaging system

D.

Corporate social media

Full Access
Question # 76

A project sponsor requires a system that is capable of providing integrated management of all the business's core functions. Which of the following systems is the project sponsor describing?

A.

CMS

B.

CRM

C.

EDRMS

D.

ERP

Full Access
Question # 77

A product manager is producing a project status report for key stakeholders Which of the following should most likely be included? (Select two).

A.

Feedback

B.

Financial summary

C.

Project schedule

D.

Organizational chart

E.

Approval

F.

Risks

Full Access
Question # 78

A project manager distributes minutes after each project meeting. However, the project manager is having difficulties hosting the meetings and documenting the discussions simultaneously. Which of the following should the project manager do in order to be most efficient?

A.

Assign a scribe to take notes.

B.

Record the meeting and transcribe the notes later.

C.

Instruct each team member to take notes.

D.

Get a facilitator for the meetings.

Full Access
Question # 79

Which of the following should be considered first when determining the privacy management for project data?

A.

Evaluating the current privacy protection program

B.

Understanding applicable privacy regulations

C.

Maintaining awareness of industry best practices

D.

Implementing security role-based controls

Full Access
Question # 80

Which of the following BEST illustrates how team members with different roles should interact on the team?

A.

SOW

B.

WBS

C.

RACI

D.

PERT

Full Access
Question # 81

Which of the following is a reason to use a SOW on a project?

A.

To find out the contact information for the vendors

B.

To review the list of stakeholders

C.

To ensure the team stays within the scope of the contract

D.

To give explicit instruction on how to execute the work

Full Access
Question # 82

Project members are based in three countries and each work remotely Which of the following would a project manager use to improve internal project communication?

A.

Progress reporting

B.

Meeting minutes

C.

Team touch points

D.

Change management

Full Access
Question # 83

A few weeks before a project is scheduled to be completed, the client asks to add a new feature to the product that is being developed. The project manager analyzes the project schedule and determines the feature can be implemented quite easily without affecting the completion date. Which of the following should the project manager do first?

A.

Escalate the change to the CCB.

B.

Review the requested change.

C.

Document the change recommendations.

D.

Validate the implementation of the requested change.

Full Access
Question # 84

A developer focused on a single story during an entire sprint. The story was underestimated and, therefore, was not completed. Which of the following steps should the Scrum team take next?

A.

Assign more resources to complete similar stories in the future.

B.

Break the stories into workable items that can be completed within one sprint.

C.

Extend the sprint duration when required with the approval of the product owner.

D.

Release the current progress into production and carry over the rest of the code for the next sprint.

Full Access
Question # 85

Following a successful release, a project manager sent a survey to all stakeholders to gain an understanding of opportunity areas for the team. Which of the following can use the survey results as an input?

A.

Daily stand-up

B.

Project momentum

C.

Performance feedback

D.

Meeting minutes

Full Access
Question # 86

A member keeps bringing up unrelated topics during a team meeting. Which of the following should the protect manager do to keep the discussion on track?

A.

Remind the team member about the meeting agenda and invite the member to add the topic to the next meeting's agenda.

B.

Ask the team member to leave the meeting and create a new meeting to discuss these topics.

C.

Adjust the current meeting's agenda to accommodate the team member's topics.

D.

Allow the team member to bring up the topics, which could lead to important discussions and insights.

Full Access
Question # 87

Which of the following activities would force a team to remove a new package and leave the previous one during a smoke test?

A.

Rollback plan

B.

Downtime stage

C.

Maintenance window

D.

Validation checks

Full Access
Question # 88

A project coordinator has started a new project and is reviewing the following characteristics provided by the customer:

• Two developers

• High uncertainty about existing systems

• Risk of frequent requirement changes

• Tight deadlines

Which of the following project methodologies would be best to use in this situation?

A.

PRINCE2

B.

Scrum

C.

SAFe

D.

XP

Full Access
Question # 89

Which of the following tools should a project manager use to assess the activities performed, work effort applied, and the productivity of a project?

A.

Project status report

B.

Project evaluation review

C.

Project management software

D.

Requirements traceability matrix

Full Access
Question # 90

During a status meeting, the development team reviews work and finds an unforeseen dependency on one of the critical project activities. As a result, the project will most likely be delayed. Which of the following actions should the project manager MOST likely perform?

A.

Work with the project scheduler to update the project timeline.

B.

Communicate to the stakeholders about the updated timeline.

C.

Ask the development team to fast-track upcoming activities.

D.

Add two resources so the critical activities will finish on time.

Full Access
Question # 91

Which of the following is a typical characteristic of Scrum?

A.

Large teams

B.

Low-risk scope

C.

Self-organized team

D.

Well-defined scope

Full Access
Question # 92

Which of the following considers factors such as reliability, scalability, security, and cost-effectiveness within project goals and objectives?

A.

DevOps architecture

B.

Computing services

C.

Data warehouse

D.

Networking and connectivity

Full Access
Question # 93

Which of the following is an activity that should be used in the closing phase of a project to support the project triple constraint?

A.

Evaluating the project

B.

Releasing the resources

C.

Closing the contracts

D.

Reconciling the budget

Full Access
Question # 94

As a part of a project, structured cabling activities have been outsourced to another company. The agreement is that work will take six weeks to complete and will be performed at different locations. Which of the following should the project manager do? (Select two).

A.

Purchase the materials.

B.

Assign the resources.

C.

Accept delays in the work.

D.

Approve the deliverables.

E.

Monitor the performance.

F.

Negotiate with the vendors.

Full Access
Question # 95

An IT infrastructure change request needs to be implemented in the production environment. Which of the following elements are the most important prerequisites? (Select two).

A.

Rollback plans

B.

Project management plan

C.

Deployment plan

D.

Asset management plan

E.

Communication plan

F.

Resource management plan

Full Access
Question # 96

A project manager notices a resource is overloaded and not completing tasks on time. After reviewing the Gantt chart, the project manager notices the resource has multiple simultaneous tasks that could be executed independently. Which of the following should the project manager do next?

A.

Change the precedence of the tasks to "finish-to-start".

B.

Evaluate and modify the schedule with a burndown chart

C.

Assign additional resources to prevent overwork.

D.

Perform critical path analysis

Full Access
Question # 97

A project sponsor has asked for a log listing all the bugs identified within a specific project. Which of the following tools should the project manager provide to the sponsor?

A.

Change log

B.

Issue log

C.

Risk register

D.

Defect log

Full Access
Question # 98

Which of the following factors would be impacted the most by requirements for a project to implement an air quality control system at a coal plant?

A.

Social

B.

Regulatory

C.

Environmental

D.

Governmental

Full Access
Question # 99

A project manager is meeting with business stakeholders to define the time frame for a go-live to occur without impacting business operations. Which of the following is the project manager working on?

A.

Validation check

B.

Downtime window schedule

C.

Customer notifications

D.

Risk analysis

Full Access
Question # 100

Which of the following best describes the role of a PM for a CRM system?

A.

To track sales

B.

To store customer information

C.

To implement new features

D.

To pay vendors

Full Access
Question # 101

Which of the following provides the best justification for undertaking a project?

A.

Scope statement

B.

Business case

C.

Sponsor request

D.

Project charter

Full Access
Question # 102

An IT intern was assigned to set up workstations as part of a project. The IT intern was very careful to do the task well and initially referred to notes while performing the task. By the end of the two-week rotation, the IT intern no longer needed the notes and completed more set-ups in less time. Which of the following MOST likely represents the observed relationship in this scenario?

A)

B)

C)

D)

A.

Option A

B.

Option B

C.

Option C

D.

Option D

Full Access
Question # 103

The high-level technical requirements for a new application state that the application should be suitable to support enterprise-level client-server solutions. Which of the following meets these requirements?

A.

Data warehouse

B.

SQL database

C.

Multitier architecture

D.

Content management system

Full Access