Spring Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: mxmas70

Home > CompTIA > Project+ > PK0-005

PK0-005 CompTIA Project+ Certification (2026) Question and Answers

Question # 4

During the progress of a project, the stakeholders require the delivery of multiple milestones with proper presentation of functionalities. Which of the following is the best methodology to use?

A.

Waterfall

B.

SDLC

C.

XP

D.

Scrum

Full Access
Question # 5

Which of the following tasks should the project manager complete first when validating deliverables?

A.

Assess the documentation.

B.

Obtain stakeholder feedback.

C.

Review the project objectives.

D.

Mitigate risks.

Full Access
Question # 6

A car manufacturer is presenting to three vendors the abilities and qualifications required to develop the last module of a data warehouse application. The manufacturer is emphasizing the technical skills necessary to complete the project on time and highlighting its current internal IT project. Which of the following best describes this activity?

A.

Key stakeholder identification

B.

Preliminary procurement

C.

Solution design determination

D.

Critical factor enlistment

Full Access
Question # 7

A company wants to move its data from on premises to off premises. Which of the following cloud models should be pursued?

A.

XaaS

B.

SaaS

C.

PaaS

D.

laaS

Full Access
Question # 8

A project sponsor asked the PM to provide a summary of the current financial status. The PM uses the following burn up chart for the analysis:

Based on the chart, which of the following is the current status of the project?

A.

Behind schedule and over budget

B.

Behind schedule and under budget

C.

Ahead of schedule and over budget

D.

Ahead of schedule and under budget

Full Access
Question # 9

Project stakeholders have asked the team to use Scrum to run a software implementation project. Which of the following is most likely to take place during a Scrum ceremony?

A.

Reviewing project blockers

B.

Defining roles and responsibilities

C.

Establishing a project schedule

D.

Determining a project budget

Full Access
Question # 10

Which of the following best describes the role of a PM for a CRM system?

A.

To track sales

B.

To store customer information

C.

To implement new features

D.

To pay vendors

Full Access
Question # 11

During the planning phase, a project manager is mapping out the full scope, calculating task durations, and identifying dependencies. Which of the following is the best tool for the project manager to use?

A.

Gantt chart

B.

Milestone chart

C.

Velocity chart

D.

PERT chart

Full Access
Question # 12

A project is running over budget, and due to new legislation in the country, the company needs to release all its contractors on the project or hire them as full-time employees. Which of the following should the PM do next to comply with the new legislation?

A.

Use only full-time employees even if the project is delayed.

B.

Hire all team members to avoid any delay in the project.

C.

Close the contract and pay the contractors cash for the remainder of the project.

D.

Look for an overseas vendor to finalize the project work.

Full Access
Question # 13

During an agile project, a team member checked the project artifacts in order to anticipate when all the work should have been completed. Which of the following charts was the team member most likely consulting?

A.

Pareto chart

B.

Milestone chart

C.

Burndown chart

D.

Gantt chart

Full Access
Question # 14

A developer focused on a single story during an entire sprint. The story was underestimated and, therefore, was not completed. Which of the following steps should the Scrum team take next?

A.

Assign more resources to complete similar stories in the future.

B.

Break the stories into workable items that can be completed within one sprint.

C.

Extend the sprint duration when required with the approval of the product owner.

D.

Release the current progress into production and carry over the rest of the code for the next sprint.

Full Access
Question # 15

Which of the following would be best to utilize when managing communications for project teams across multiple time zones?

A.

Business collaboration tool

B.

Email

C.

Virtual meetings

D.

Enterprise CMS

Full Access
Question # 16

A project team member recalls a specific chat with another member that contained key information related to a previous project, which no one else on the project team is aware of. Which of the following best describes what was needed to address this concern?

A.

Integrity

B.

Security

C.

Archival

D.

Lessons learned

Full Access
Question # 17

During project initiation, a project manager needs to identify goals and deliverables that should be completed by the end of the project and also meet certain cost and time factors. Which of the following would best align with these needs?

A.

Work breakdown structure

B.

Change log

C.

Project success criteria

D.

Milestone chart

Full Access
Question # 18

A stakeholder raises a concern that a certain important functionality might be missing and asks the PM to submit a change request so it can be included. The PM is confident the functionality is included. Which of the following has the PM most likely checked?

A.

Risk register

B.

Detailed scope statement

C.

Requirements Traceability Matrix

D.

Task board

Full Access
Question # 19

During a functional validation exercise, two end users request changes to the product that cannot be implemented without altering the already constrained project budget. The project manager convinces the end users to simplify the change request so it can be accomplished. Which of the following conflict resolution techniques did the project manager use?

A.

Collaborating

B.

Smoothing

C.

Avoiding

D.

Compromising

Full Access
Question # 20

A stakeholder called a project manager on the telephone to ask for a status report. Which of the following describe this type of communication? (Select two).

A.

Formal

B.

Internal

C.

Informal

D.

Verbal

E.

Indirect

F.

External

Full Access
Question # 21

Although a project was successfully released into production a month ago, a project manager continues to receive project-related work. Which of the following is the reason for this issue?

A.

The project manager did not release the resources.

B.

The project is in the verification testing phase.

C.

The project manager did not complete the project closure phase.

D.

The project manager did not remove access.

Full Access
Question # 22

A development team, which is working on a software project demonstrates software functionality 10 project stakeholder a week before the implementation date. Several stakeholders comment that the software does not meet the communicated expectations. Which of the following tools should the project manager use to validate the functionality?

A.

Project status report

B.

Requirements Traceability Matrix

C.

Detect log

D.

Signed project charter

E.

Work breakdown structure

Full Access
Question # 23

The high-level technical requirements for a new application state that the application should be suitable to support enterprise-level client-server solutions. Which of the following meets these requirements?

A.

Data warehouse

B.

SQL database

C.

Multitier architecture

D.

Content management system

Full Access
Question # 24

Which of the following contract types would be most beneficial to both parties in cases in which the scope of the project has a large number of unknowns?

A.

Variable costs

B.

Fixed costs

C.

Front-loaded

D.

Time and materials

Full Access
Question # 25

A project manager buys an extended warranty for a set of servers. Which of the following risk management strategies is the manager using?

A.

Transfer

B.

Avoid

C.

Accept

D.

Mitigate

Full Access
Question # 26

A project team participates in a brainstorming session to define the guidance, direction, and approach for monitoring established procedures for developed products. Which of the following plans is the team creating?

A.

Project transition

B.

Project management

C.

Project communications

D.

Project quality assurance

Full Access
Question # 27

A stakeholder works in a remote location and has not been replying to emails. The Internet service in that location is intermittent, and the stakeholder prefers to be contacted by telephone. Which of the following artifacts should the project manager have prepared to avoid this situation?

A.

Responsibility assignment matrix

B.

Acceptable communication channels

C.

Risk registry

D.

Staff directory

Full Access
Question # 28

A project manager decided to host the development environment on a cloud service. Which of the following would the project manager most likely use for this purpose?

A.

IaaS

B.

XaaS

C.

DaaS

D.

SaaS

Full Access
Question # 29

A project manager is comparing the documentation attached to invoices from main vendors with the requirements described in the SOW in order to decide if all are correct. Which of the following best describes what is being performed?

A.

Approving deliverables

B.

Enforcing vendor rules of engagement

C.

Reporting overall process

D.

Scheduling team touch points

Full Access
Question # 30

The executive leadership of an agile company has launched a new strategy. This new strategy impacts new features that are in development with the project team. Which of the following describes what the team should do next?

A.

Resource loading

B.

Analyzing the critical path

C.

Prioritizing backlog

D.

Determining contingency reserves

Full Access
Question # 31

Which of the following is a Kanban concept?

A.

Ensuring business alignment by development iteration

B.

Representing cost-effective tasks through different colors

C.

Allocating resources to high-priority tasks

D.

Managing flow by limiting work in progress

Full Access
Question # 32

A vendor manager communicates to the project manager that a shipment of new devices required for the completion of a project is delayed. The supplier is planning to deliver the devices two months after the agreed-upon date. Which of the following should the project manager do first?

A.

Hold the project until the devices are delivered.

B.

Evaluate the impact to baselines.

C.

Request another supplier to ship devices.

D.

Update the project timeline with a new project end date.

Full Access
Question # 33

A company is working on a software development project that involves an external customer. Which of the following describes a project manager's responsibility within this type of project?

A.

Manage the project schedule.

B.

Define the functional requirements.

C.

Develop components for the software.

D.

Assess and authorize security policies.

Full Access
Question # 34

By developing a project schedule, a PM has already validated the constraints, outlined the duration of the tasks and the phases, and confirmed the proper sequence and flow of the project. Which of the following activities still needs to be performed to complete the schedule?

A.

Allocate resources.

B.

Determine the project budget

C.

Develop a communication plan.

D.

Establish baselines.

Full Access
Question # 35

A project manager is assigned an initiative in a highly regulated industry that requires employees to safeguard certain pieces of PII. Which of the following is the best approach for the project manager to keep the information confidential?

A.

Encryption

B.

Multifactor authentication

C.

Quality assurance

D.

Password protection

Full Access
Question # 36

A PM is working on the preliminary scope statement and identifies that this project has the same approach as another project that was completed last year. Which of the following actions would the PM most likely perform?

A.

Call the previous PM for advice on risks and issues.

B.

Ask the project sponsor to provide previous final project report results.

C.

Complete the project charter using the other PM's subject matter expertise.

D.

Use existing artifacts and accommodate based on the current project success criteria.

Full Access
Question # 37

A project team is deciding how to break up a large project into smaller components so the project can be delivered without increasing the duration of the iteration cycles. Which of the following describes the grouping of the smaller components?

A.

An issue

B.

A goal

C.

A backlog item

D.

An epic

Full Access
Question # 38

A project sponsor is struggling to provide the latest project status information on a weekly executive call. Which of the following should be reviewed?

A.

Meeting cadence

B.

Gap analysis

C.

Dashboard

D.

Adoption training

Full Access
Question # 39

A global shipping slowdown is causing critical raw materials needed for manufacturing to be delivered late. As a result, a project's production run will be delayed from the beginning.

Which of the following dependencies is most likely happening?

A.

Finish-to-start

B.

Start-to-start

C.

Finish-to-finish

D.

Start-to-finish

Full Access
Question # 40

A project manager will conduct a release on the third Friday of the month. The project manager has notified users that the application will be unavailable for eight hours. Hence, users need to save any information in advance. Which of the following is the project manager most likely conducting?

A.

Application deployment

B.

Rollback plans

C.

Validation checks

D.

Maintenance window schedules

Full Access
Question # 41

Which of the following best describes a rollback plan?

A.

Apply an alternative plan if the original plan does not work.

B.

Return to the operational state of a system before applying a requested change.

C.

Restart the project with new resources to avoid failures from previous ones.

D.

Repeat the tasks suggested in the requested change until they work.

Full Access
Question # 42

A financial manager reports that several employees' allocations from the past month appear to be 200% even though they are only assigned to a particular project. Which of the following could MOST likely be the cause of this issue?

A.

A project manager assigned the wrong resources.

B.

A project manager did not release the resources

C.

A project manager did not remove the system access.

D.

A project manager did not provide the project sign-off.

Full Access
Question # 43

A project manager reports that the implementation of a new system is on track to be completed under budget and ahead of the schedule. A stakeholder then asks the manager to add mobile device functionality. Which of the following should the project manager do in response to the request?

A.

Decline because it is not included in the project scope.

B.

Assess the impact of the request and create a change request

C.

Create new functional and non-functional requirements for mobile devices.

D.

Revise the baseline of the project plan by adding the new requirements.

Full Access
Question # 44

A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?

A.

RFI

B.

RACI

C.

WBS

D.

SOW

Full Access
Question # 45

A project manager makes a company-wide announcement about the successful completion of a project and thanks team members. Which of the following is the project manager doing?

A.

Bringing attention to the project sponsor

B.

Sharing lessons learned

C.

Collecting feedback

D.

Celebrating the team's hard work

Full Access
Question # 46

Which of the following is part of software change control?

A.

Rollback plans

B.

Maintenance windows

C.

Validation checks

D.

Requirements definition

Full Access
Question # 47

A web designer is currently verifying that the website data is compliant. Which of the following data types will be protected after confirming that the controls are in place?

A.

Credit cards

B.

Mission statements

C.

Site certificates

D.

Trademarks

Full Access
Question # 48

During timeline creation, the project manager is unsure if the development team can complete coding before new servers are installed in the IT department. Which of the following should the project manager do to increase project certainty?

A.

Hold a new backlog prioritization meeting.

B.

Add milestones to check the project's progress.

C.

Adjust the task relationship to complete coding in advance.

D.

Apply contingency buffers to the critical path.

Full Access
Question # 49

A project manager is reviewing a signed legal document pertaining to the hiring of a vendor who will develop an experimental solution. The vendor could not provide accurate estimates at this time because the requirements will probably be changing. The document also contains information about the resources involved and the rates the vendor will charge for the work. Which of the following best describes the legal document the project manager is reviewing?

A.

Time and materials contract

B.

Master service agreement

C.

Fixed-price contract

D.

Non-disclosure agreement

Full Access
Question # 50

The project team identifies a risk of delayed materials on a project in a remote location. Which of the following actions can the team take to transfer the risk?

A.

Determine alternative supplies to use.

B.

Source materials locally from other vendors.

C.

Move procurement under the general contractor.

D.

Schedule deliveries earlier to ensure availability.

Full Access
Question # 51

A manufacturing company is experiencing a high number of defects in its products and wants to identify the root cause to improve its processes Which of the following should the company use?

A.

Run charts

B.

Fishbone/lshikawa diagrams

C.

Scatter plot

D.

Decision tree

Full Access
Question # 52

During quality analysis, different team members are identifying multiple constraints. Which of the following tools should the project manager adopt first to help track and prioritize a resolution?

A.

Issue log

B.

Defect log

C.

Risk register

D.

Change log

Full Access
Question # 53

A company purchases new software. The project manager needs to present the new software’s features to the stakeholders. Which of the following meeting types should the project manager and stakeholders have?

A.

Status

B.

Focus

C.

Brainstorming

D.

Informative

Full Access
Question # 54

During a phase review, two stakeholders discuss the approval of a deliverable. The project manager convinces the stakeholders to agree on a common solution. Which of the following best describes what the project manager did to gain approval from both stakeholders?

A.

Force

B.

Smooth

C.

Compromise

D.

Avoid

Full Access
Question # 55

Which of the following communication methods would be the most appropriate to finalize the handoff of deliverables?

A.

A virtual meeting with all the stakeholders

B.

A face-to-face kickoff meeting with the stakeholders

C.

A closure meeting with the project team and stakeholders

D.

A final report submitted via email to the stakeholders

Full Access
Question # 56

Halfway through a project, the sponsor states that the project is taking too long to complete. Which of the following should the project manager consult?

A.

Gantt chart

B.

Maintenance window schedule

C.

Functional requirements

D.

Test results

Full Access
Question # 57

Which of the following is a characteristic that defines a project?

A.

Will produce a profit

B.

Uses outside resources

C.

Requires a well-defined scope

D.

Has a defined start and finish

Full Access
Question # 58

Which of the following statements best represents a network issue?

A.

The development team on the fourth floor is unable to access servers and email services.

B.

Cell phones served by a specific telecom company are getting a "no service" message.

C.

A user cannot connect to Wi-Fi because of a wrong ID or password.

D.

A user is receiving an automatic reply message saying that an email address does not exist.

Full Access
Question # 59

A critical piece of equipment that is needed for the installation of a point-of-sale solution is delayed from the manufacturer. The delay will cause the project to be significantly behind schedule. The project manager decides to buy the item at a higher cost from another vendor who can supply it immediately. Which of the following risk management approaches has the project manager taken?

A.

Mitigate

B.

Transfer

C.

Accept

D.

Share

Full Access
Question # 60

Project team members enter their time sheets into a system that also displays incurred project cost. Which of the following systems can perform this task?

A.

EDRMS

B.

CRM

C.

CMS

D.

ERP

Full Access
Question # 61

To gather requirements from stakeholders, the project manager sits down with them and allows them to discuss freely. Which a following technique is the project manager utilizing?

A.

Process moving

B.

Brainstorming

C.

Interview

D.

Focus group

Full Access
Question # 62

A project sponsor is trying to use the ROI to determine if the project should be approved. Which of the following best describes what the project sponsor needs?

A.

An analysis of the current situation and the desired outcome

B.

A document with the description of project deliverables and vendor's responsibilities

C.

A description of the value that the project will bring to the company after the investment

D.

An analysis of the costs related to normal operations of the company

Full Access
Question # 63

Given the following network diagram:

Which of the following is the critical path?

A.

A-C-G-K-M

B.

A-B-D-l-L-M

C.

A-B-E-J-L-M

D.

A-B-F-L-M

Full Access
Question # 64

A project team was instructed to refurbish old desktops. The following provides the details of the issues observed:

Which of the following issues should be addressed FIRST?

A.

Replace missing peripherals because this process can be easy and less costly.

B.

An old operating system issue has the most amount of occurrences.

C.

Damage to the monitor has the highest percentage.

D.

Address each issue as discovered to avoid rework.

Full Access
Question # 65

A project manager is unclear about the budget and timeline prior to the start of a project. Which of the following best describes what type of meeting needs to take place?

A.

Kickoff

B.

Demo

C.

Stand-up

D.

Status call

Full Access
Question # 66

A PM is meeting with the project team to identify the baseline go-live date, the operational training, and the handoff procedures. Which of the following phases is the project team performing?

A.

Initiation

B.

Closing

C.

Execution

D.

Planning

Full Access
Question # 67

During a complex, multiyear project, a PM must discern which project tasks overlap so resources can be allocated appropriately. Which of the following is best for determining this information?

A.

PERT chart

B.

Milestone chart

C.

Gantt chart

D.

Budget burndown chart

Full Access
Question # 68

Which of the following software programs would be BEST to use lo store information related to business transactions?

A.

Record management system

B.

Customer relationship management

C.

Enterprise resource planning

D.

Content management system

Full Access
Question # 69

Which of the following best describes the reason a chat messaging service would be used as the primary form of communication for a project team?

A.

The team is working in different rooms within the same building.

B.

The team is working remotely two days per week.

C.

The team has members distributed around the world in different time zones.

D.

The team is based in the same office but has a large number of members.

Full Access
Question # 70

Which of the following BEST describes how an organization should coordinate management of multiple related projects?

A.

Apply the SDLC process.

B.

Establish a program.

C.

Consult the CCB.

D.

Use different frameworks

Full Access
Question # 71

Which of the following best describes the difference between the current state and the desired future state in project management?

A.

The current state is a high-level view of the project scope, and the desired state is what is happening right now.

B.

The current state is where the business is now, and the desired state is where the project is going to take the business.

C.

The current state is a high-level view of the project scope, and the desired future state is the specific outcome the business wants.

D.

The current state defines the specific outcome the business wants, and the desired state documents what is happening now that prevents it.

Full Access
Question # 72

A project is moving into the user acceptance testing phase. Several resources will be needed to execute different steps in the testing plan. Which of the following would be the best tool to allow the resources to remain at their desks and only react when needed?

A.

Ticketing system

B.

Videoconference

C.

Simple messaging system

D.

Corporate social media

Full Access
Question # 73

Which of the following activities should a project manager perform during the closing phase? (Select three).

A.

Lessons learned

B.

Risk analysis

C.

Removing resources

D.

Acquiring resources

E.

Statement of work sign-off

F.

Stakeholder analysis

G.

Removing access

Full Access
Question # 74

A PM is working on the schedule for a project that has technical tasks and requires a SME's knowledge. The PM decides the best way to track this project is to have the project lead provide high-level updates. Which of the following is the best tool to track this data?

A.

Gantt chart

B.

Project organization chart

C.

Program Evaluation Review Technique chart

D.

Milestone chart

Full Access
Question # 75

During the testing process, testers have found multiple bugs that could jeopardize the project commitment date Which of the following tools should the project manager use first to update the findings?

A.

Defect log

B.

Change log

C.

Issue log

D.

Risk log

Full Access
Question # 76

A company is starting a new implementation project The stakeholders are reviewing RFP responses to help make a decision about which project management consulting firm to hire. Given the following information:

Which of the following is the best consulting firm for the company to hire?

A.

Consulting firm 1

B.

Consulting firm 2

C.

Consulting firm 3

D.

Consulting firm 4

Full Access
Question # 77

As a result of an approved change, the project manager updates the project plan with the newest project end date. Which of the following change control processes should the project manager complete NEXT?

A.

Document the request in the change control log.

B.

Communicate the change deployment.

C.

Conduct an impact assessment.

D.

Implement the change.

Full Access
Question # 78

The project manager must create a project charter. Which of the following should be included in the charter?

A.

Project schedule

B.

Resource allocation

C.

Risk plan

D.

Stakeholder identification

Full Access
Question # 79

During the testing phase of a project, the legal department rejected a deliverable due to compliance issues. The project manager reviewed the risk register and triggered the mitigation plan for this item. Which of the following documents should the project manager update next?

A.

Schedule

B.

Status report

C.

Issue log

D.

Task board

Full Access
Question # 80

During a project closure meeting, stakeholders did not agree that the project achieved the expected results. Which of the following documents should the project manager consult?

A.

Work breakdown structure

B.

Project charter

C.

Quality plan

D.

Solution design

Full Access
Question # 81

A PM is working on a strategy to store records. Which of the following dements must be included in this plan? (Select TWO)

A.

Data management

B.

Issue management

C.

Work breakdown structure

D.

Document management

E.

Communication management

F.

Risk management

Full Access
Question # 82

During a code implementation, a senior developer and junior tester are discussing the testing scenarios that were performed. A major malfunction resulted in an inoperative product condition. As a result, the team was forced to work until midnight to restore operations. Which of the following should the PM have generated FIRST to alleviate the impact of this issue prior to deployment?

A.

A risk budget

B.

A risk impact

C.

A change request

D.

A contingency plan

Full Access
Question # 83

Which of the following statements best describes zero-based budgeting?

A.

Start with the budget from the last project and add any new expenses.

B.

Start with allocating expenses based on the importance of the project.

C.

Start the project with a fixed amount decided by the management team.

D.

Start with no financial plan and justify each new expense.

Full Access
Question # 84

A project manager has decided to wait until all requirements are developed to initiate testing. Which of the following relationship dependencies is the project manager using?

A.

Start-to-finish

B.

Finish-to-finish

C.

Finish-to-start

D.

Start-to-start

Full Access
Question # 85

A meeting agenda included the following items:

. Review the goals of the project.

. Review the progress of the project.

. Discuss if the project is ready to move forward.

Which of the following best describes this type of meeting?

A.

Stand-up

B.

Monthly status

C.

Gap analysis

D.

Gate review

Full Access
Question # 86

Which of the following best describes the meaning of timeboxing in the context of a project kickoff meeting?

A.

Allowing a discussion to proceed until a decision is made

B.

Allowing the meeting attendees more time for deeper conversation

C.

Allowing for a flexible timeline so all aspects of the project are covered

D.

Allowing a conversation to continue for a predefined period of time

Full Access
Question # 87

The quarterly financial report displays losses from a project even though the project was completed successfully several weeks ago. Which of the following actions should the project manager perform next?

A.

Remove access.

B.

Complete the project sign-off.

C.

Release the resources.

D.

Outline the lessons learned.

Full Access
Question # 88

A project manager has been scheduling and facilitating project meetings, scribing the minutes, distributing the minutes, and sending agendas prior to upcoming meetings. However, the project manager is frustrated because action items are not being completed. Which of the following should the project manager do to alleviate these concerns?

A.

Use a software tool during the meeting that can create a transcript of what is discussed.

B.

Have a standing agenda that is vague enough so that it can be used again.

C.

Delegate the roles and responsibilities to improve meeting management.

D.

Reprimand project team members for not completing assigned action items.

Full Access
Question # 89

One of the key steps in controlling changes lo software is obtaining approval. Which of the following statements best describes the reason for this key objective?

A.

To send the appropriate customer notifications

B.

To avoid a negative impact on other software functionalities

C.

To ensure adequate resources are in place to implement the change

D.

To confirm that the software is a business priority

Full Access
Question # 90

A project manager queries stakeholders to identify the right communication channel to be used during the project life cycle. After reviewing the responses, the project manager reports that 70% of the stakeholders prefer email communication, and the rest prefer face-to-face communication. The project manager should update the stakeholder register with:

A.

the preferred sponsor's communication channel.

B.

the preferred project manager's communication channel.

C.

the preferred reported communication channel.

D.

email communication as the preferred communication channel.

Full Access
Question # 91

Which of the following should a product manager choose in order to enable collaboration between team members located in different regions? (Select two).

A.

Real-time surveys/polling

B.

Wiki knowledge base

C.

Spreadsheets

D.

Meetings/face-to-face

E.

Real-time, multi-authoring editing software

F.

Charting/diagramming

Full Access
Question # 92

Which of the following activities are performed during the closing phase? (Select three).

A.

Requesting project charter sign-off

B.

Recognizing project team efforts and rewarding team members

C.

Working with the financial team to obtain return of investment

D.

Revoking resource credentials from the system

E.

Updating the risk register with new findings

F.

Informing the functional manager about the release of resources

G.

Monitoring project team performance

Full Access
Question # 93

A PM wants to provide a visual representation of how a project is organized into tasks and how the tasks relate to each other. Which of the following can the PM use?

A.

Milestone chart

B.

Gantt chart

C.

PERT chart

D.

WBS

Full Access
Question # 94

Project A is running behind schedule. The team realizes that Project B is working on an API that was planned to be developed by Project A. The project manager from Project A decides to use the API from Project B. Which of the following risk management strategies describes this example?

A.

Exploit

B.

Share

C.

Transfer

D.

Accept

Full Access
Question # 95

A project team has been assigned to improve the customer service of a retail company. The team has conducted a thorough analysis of the existing process, determined areas of improvement, and identified the desired outcomes of the project. Which of the following best describes this analysis?

A.

Process improvement

B.

Business objectives

C.

Current state vs. future state

D.

Project success criteria

Full Access
Question # 96

Which of the following project types is best managed as a waterfall project?

A.

Data analytics

B.

Research

C.

Software development

D.

Real property

Full Access
Question # 97

During a PMO audit, an auditor notices a discrepancy between the existing financial report and the financial information provided by the project manager at the end of the project in the previous quarter. Which of the following activities would have most likely avoided this discrepancy?

A.

Validation of deliverables

B.

Closing contracts

C.

Project sign-off

D.

Removing access

Full Access
Question # 98

A PM is reviewing objectives for a project in a new industry. Which of the following items should the PM review first?

A.

Applicable regulations and standards

B.

Relevance to the global environment

C.

Company vision, mission, and values

D.

Impact to the corporate brand

Full Access
Question # 99

An software engineer is applying new updates to a program in a sandbox environment. Which of the following risk strategies best describes this practice?

A.

Transfer

B.

Mitigate

C.

Avoid

D.

Accept

Full Access
Question # 100

After new capabilities were deployed in a system, issues with preexisting capabilities were reported. Which of the following testing cycles should be used to prevent this issue?

A.

Performance testing

B.

User acceptance testing

C.

Stress testing

D.

Unit testing

Full Access
Question # 101

After months of recruiting, a team finally found the right candidate for a very specific coding language assignment. Due to this delay, the team has a tight timeline without any float. A day before the candidate is scheduled to join the team, the project manager realizes the candidate has a non-compete agreement from the previous employer. Which of the following should the project manager do?

A.

Withdraw the offer to the candidate and raise this as a risk.

B.

Ignore a potential lawsuit since this is a critical project.

C.

Use a third-party company for the contract to legally avoid responsibility.

D.

Have a meeting with the project sponsor to discuss the situation.

Full Access
Question # 102

Which of the following aspects are true of waterfall as compared to agile? (Select two).

A.

Waterfall is composed of smaller teams working together

B.

Waterfall reinforces customer collaboration

C.

In waterfall, solution validation occurs later in the development cycle.

D.

In waterfall, working software is more of a focus than comprehensive documentation.

E.

Waterfall is less tolerant to changes in scope.

F.

Waterfall is made up of sprints

Full Access
Question # 103

Project members are based in three countries and each work remotely Which of the following would a project manager use to improve internal project communication?

A.

Progress reporting

B.

Meeting minutes

C.

Team touch points

D.

Change management

Full Access
Question # 104

Which of the following is a consideration when determining a project's ESG factors?

A.

Project management methodology

B.

IT infrastructure security

C.

Proper accounting practices

D.

Corporate values compliance

Full Access
Question # 105

Which of the following best describes a program in the context of project management?

A.

It is a group of unrelated projects within an organization

B.

It is used to represent the daily activities of multiple projects

C.

It is a consolidation of related projects with a common goal

D.

It provides the definition of a project workload

Full Access
Question # 106

A new project manager takes over a project midway through the schedule. Which of the following should the project manager do first before continuing the project?

A.

Access project artifacts.

B.

Arrange a brainstorming session.

C.

Conduct a kickoff meeting.

D.

Establish communication channels.

Full Access
Question # 107

During a staff meeting, a project manager voices a concern about the client billing rate for a particular engineer. Which of the following documents would the project manager need in order to find this information?

A.

SLA

B.

TOR

C.

SOW

D.

NDA

Full Access
Question # 108

Which of the following should occur first when planning maintenance windows?

A.

Diagnose potential areas for concern.

B.

Notify the customer base.

C.

Determine a rollback plan.

D.

Understand the organization's production cycle.

Full Access
Question # 109

During the project initiation phase, a project manager needs to construct a project schedule and show the project dependencies. Which of the following should the project manager use for this task?

A.

Waterfall method

B.

Simulation method

C.

Precedence diagramming method

D.

Cost ratio analysis

Full Access
Question # 110

A project manager is using an agile methodology to lead the implementation of several features that should be developed concurrently. Which of the following items should the project manager view as a concern?

A.

Each feature will have a different owner.

B.

The majority of the team can only meet on a weekly basis.

C.

The stakeholders have provided a specific deadline to meet.

D.

Each feature has a specific budget allocation.

Full Access
Question # 111

Which of the following software programs would be best to use to store information related to business transactions?

A.

Record management system

B.

Customer relationship management

C.

Enterprise resource planning

D.

Content management system

Full Access
Question # 112

A project manager is taking notes along with gathering feedback about a prior project in order to consider known issues with a project enhancement. Which of the following best describes the plan that the project team is working on?

A.

A plan for capturing issues and conflicts in a project's knowledge base

B.

A plan for avoiding potential issues that may arise during project execution

C.

A plan for documenting the outcomes of the project

D.

A plan for addressing and resolving identified issues once the project has been completed

Full Access
Question # 113

The PMO wants to streamline the routing and approval of project activities to provide up-to-date visibility of the status. Which of the following collaboration tools would be most appropriate to use?

A.

Real-time, multi-authoring tool

B.

Wiki knowledge base and search engine

C.

Workflow and e-signature platform

D.

File-sharing platform and storage system

Full Access
Question # 114

A number of unexpected issues have occurred during the execution of a project that will negatively impact the timeline and costs. Which of the following would be best for the project manager to do to mitigate this situation?

A.

Update the issue log.

B.

Communicate with stakeholders.

C.

Use the contingency reserves.

D.

Review the risk register.

Full Access
Question # 115

Which of the following statements best describes Kanban?

A.

A workflow management method to maximize efficiency and enable continuous improvement.

B.

A board representing the different stages of a software solution.

C.

A dashboard used to facilitate scope alignment with the project team.

D.

A spreadsheet representing development tasks and how they relate to the business process being improved.

Full Access
Question # 116

A project team is reviewing the project plan and related documents and identifies tasks that could be spread into smaller deliverables. Which of the following documents should the team edit first?

A.

Risk assessment

B.

Preliminary scope statement

C.

Work breakdown structure

D.

Milestone chart

Full Access
Question # 117

A contractor attended a project meeting that was exclusively for company employees. Which of the following actions should the PM take?

A.

Escalate to vendor management.

B.

Consult the request for proposal.

C.

Review the meeting cadence.

D.

Reinforce the rules of engagement.

Full Access
Question # 118

A sponsor prefers to communicate with the team using email, phone calls, conversations in the hallway, and impromptu meetings. Which of the following types of communication is the sponsor using?

A.

Informal communication

B.

Formal communication

C.

Synchronous communication

D.

Asynchronous communication

Full Access
Question # 119

A new project team started work three months ago. The team members are increasing their work productivity and are comfortable asking for help with tasks. Which of the following describes the current stage of the project team?

A.

Performing

B.

Adjourning

C.

Forming

D.

Norming

Full Access
Question # 120

A project manager wants to schedule a troubleshooting session for team members who are located in Germany and California. Which of the following is most important for the project manager to consider when setting up the session?

A.

Cultural differences

B.

Technological factors

C.

Time zones

D.

Language barriers

Full Access
Question # 121

A project manager is responsible for implementing a large, centralized repository that stores raw information from various sources in a structured and organized way. Which of the following should the project manager implement?

A.

Shared folder

B.

Infrastructure

C.

Multitiered architecture

D.

Data warehouse

Full Access
Question # 122

Which of the following are primary features provided by a standard laaS solution? (Select two).

A.

Encryption

B.

Storage

C.

Networking

D.

User interface

E.

Access

F.

Database

Full Access
Question # 123

During the stabilization phase for recently deployed software, an end user reports a bug that is compromising data integrity. Which of the following tools will the project manager MOST likely use?

A.

Issue log

B.

Defect log

C.

Change log

D.

Task board

Full Access
Question # 124

A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?

A.

RFB

B.

RFQ

C.

RFI

D.

RFP

Full Access
Question # 125

Which of the following cloud models can be used to speed up the development of a service that integrates with the operating system and accelerates the delivery of a software project?

A.

SaaS

B.

IaaS

C.

DaaS

D.

PaaS

Full Access
Question # 126

Which of the following pieces of data are examples of Pll?

A.

Medical record and test result values

B.

IP address and email address

C.

Name and year of birth

D.

X-ray and blood type

Full Access
Question # 127

A project team has just experienced an unexpected event and implemented a work-around. Which of the following documents should be used to record the event? (Select TWO).

A.

Risk report

B.

Defect log

C.

Issue log

D.

Backlog

E.

Change log

F.

Progress report

Full Access
Question # 128

Following the approval of a change by the CCB, which of the following should a project manager consider next when deploying a new networking device into an existing production environment?

A.

Maintenance window

B.

Risk assessment

C.

Operational security

D.

Validation check

Full Access
Question # 129

A procurement team analyzes solutions submitted from multiple vendors for the upcoming release of a required development service. The procurement team identifies a potential partnership. Which of the following would the procurement team most likely request?

A.

Quote

B.

Information

C.

Proposal

D.

Bid

Full Access
Question # 130

Which of the following concepts represents multiple resources interfaced to run reports?

A.

Code repository

B.

Data warehouse

C.

Storage server

D.

File-sharing system

Full Access
Question # 131

Which of the following best describes why a project manager would decide to sign a fixed-price contract with a vendor?

A.

The scope of the project deliverable is clearly defined.

B.

There is a non-disclosure agreement in place.

C.

There are multiple requirements for the product.

D.

The PM wants to simplify the logistics of the required product.

Full Access
Question # 132

Which of the following would help a project manager identify that project goals have been reached?

A.

Audit report

B.

Key performance indicators

C.

Backlog

D.

Lessons learned

Full Access
Question # 133

Which of the following items must be protected as Pll? (Select TWO).

A.

Job title

B.

Home address

C.

Work phone number

D.

Time zone

E.

Date of birth

F.

Blood type

Full Access
Question # 134

Several months after a project has ended, a project team member is still charging time to the project and is unable to charge time to new projects. Which of the following did the project manager neglect to do?

A.

Remove the team member's access.

B.

Release the project resources.

C.

Collect the stakeholders' feedback.

D.

Have the closeout report approved.

Full Access