Weekend Sale - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: mxmas70

Home > NCARB > Architect Registration Examination > PDD

PDD ARE 5.0 Project Development and Documentation Exam Question and Answers

Question # 4

A family-owned apple farm in the Upper Midwest is taking advantage of a change in the local zoning code that added a new Agri-Tourism class in the existing farm zone. This allows the Owner to build a new facility on their existing site. The building will be open to the public and include a brewery, distillery, tap room, and market. The architect is ready to submit the drawings to the Owner for the 50% construction documents review.

To accommodate a compressed construction schedule, the Owner will be utilizing a design-build process. The Contractor has submitted the Pre-Engineered Metal Building (PEMB) shop drawings to the Architect for review, due to the lead time on this critical path item. Once construction begins, farming operations must be able to continue uninterrupted.

Key project information includes:

    Brewing and distilling will operate year-round.

    Brewery will initially include four fermenting tanks. Owner has requested space for at least two additional tanks. Potential expansion will be based on future sales.

    Distillery will produce 16% alcohol, which is classified as a flammable liquid. Fire separations are required.

    Tap Room is designed with seating for 300 people, not including exterior patio seating. It will have views to the working orchards and the historic buildings on site.

    Tap Room is scheduled to be open from August through November. Owner would like options to extend operating dates based on popularity.

    The Market area will feature local farm products and is not conditioned.

    Entire building will be fully sprinklered.

    Selected building materials are low-maintenance, as requested by the Owner, for durability and to reflect the nature of a working farm.

    Mechanical and electrical systems will be hung from the building structure. These loads are included in PEMB shop drawings.

    Public water and sewer is not available at the Project Site.

    Occupancy sensors are included to reduce utility costs and achieve energy conservation requirements.

The following resources are available for your reference:

    Architectural Drawings, including plans, elevations, sections, and schedules

    Consultant Drawings, including structural, HVAC, power distribution, and plumbing

    PEMB Shop Drawings

    Design and Construction Schedule

    Specification Excerpts, showing relevant spec sections

    IBC and ADA Excerpts, showing relevant code and accessibility sections

    After reviewing the documents, the architect discovers a coordination issue in the corridor.

Which modification is required?

A.

Add exit sign at door number 15.

B.

Relocate supply and return air diffusers.

C.

Add access panel for shut-off valves.

Full Access
Question # 5

For the same moment, a glue-laminated beam would require a section modulus of what proportion relative to a sawn timber beam? (Assume Fᵦ of the glue-laminated beam is 2,400 psi and Fᵦ of the sawn lumber beam equals 1,200 psi.)

A.

The same

B.

1/2

C.

3/4

D.

2

Full Access
Question # 6

Refer to the exhibit.

What will the overall coefficient of Heat Transmission (U-value) of the building assembly illustrated in the attached figure become if unfaced R-19 batt insulation is added in the stud spaces in the wall cavity?

A.

0.024

B.

0.043

C.

0.052

D.

0.240

Full Access
Question # 7

Which of the following have natural resins that resist termite attack? (Check the two that apply)

A.

Douglas fir

B.

Red cedar

C.

Cypress

D.

Hemlock

E.

Southern yellow pine

F.

Oak

Full Access
Question # 8

An architect is rehabilitating a historic federal landmark that requires repairs to a garden wall. The existing brick appears to be in good condition; the mortar shows significant signs of deterioration.

Which strategy should the architect propose to repair the damaged wall?

A.

Carefully remove all mortar and repoint all joints to achieve a uniform appearance.

B.

Completely remove deteriorated mortar with electric saws prior to repointing.

C.

Remove loose mortar by hand raking the joints prior to repointing.

Full Access
Question # 9

Which of the following admixtures is used to greatly increase the slump of concrete?

A.

Air-entraining agent

B.

Water-reducing agent

C.

Calcium chloride

D.

Superplasticizer

Full Access
Question # 10

Where is the proper place to put a vapor barrier in a cold climate?

A.

On the exterior between the metal siding and the sheathing

B.

On the exterior between the framing and the sheathing

C.

On the interior between the gypsum wallboard and the framing

D.

In the cavity of the framing space

Full Access
Question # 11

Option 1 is the originally designed connection detail for a banner hanging system of steel tube beams and threaded rods in a high atrium space. The threaded rod connections to the structure are fabricated as part of the structure. The remaining members are field fabricated. The weights of beam and banner are identical at each level. Option 2 has been proposed to alleviate constructability issues. The structural ramifications must be evaluated before this change can be approved.

Click on the nut in option 2 that will realize a greater load due to the proposed change.

Full Access
Question # 12

Refer to the exhibit.

It is required to cut a hole in the web of the beam shown.

Which of the locations would be best? Check the two that apply.

A.

Location 1

B.

Location 2

C.

Location 3

D.

Location 4

E.

Location 5

Full Access
Question # 13

A family-owned apple farm in the Upper Midwest is taking advantage of a change in the local zoning code that added a new Agri-Tourism class in the existing farm zone. This allows the Owner to build a new facility on their existing site. The building will be open to the public and include a brewery, distillery, tap room, and market. The architect is ready to submit the drawings to the Owner for the 50% construction documents review.

To accommodate a compressed construction schedule, the Owner will be utilizing a design-build process. The Contractor has submitted the Pre-Engineered Metal Building (PEMB) shop drawings to the Architect for review, due to the lead time on this critical path item. Once construction begins, farming operations must be able to continue uninterrupted.

Key project information includes:

    Brewing and distilling will operate year-round.

    Brewery will initially include four fermenting tanks. Owner has requested space for at least two additional tanks. Potential expansion will be based on future sales.

    Distillery will produce 16% alcohol, which is classified as a flammable liquid. Fire separations are required.

    Tap Room is designed with seating for 300 people, not including exterior patio seating. It will have views to the working orchards and the historic buildings on site.

    Tap Room is scheduled to be open from August through November. Owner would like options to extend operating dates based on popularity.

    The Market area will feature local farm products and is not conditioned.

    Entire building will be fully sprinklered.

    Selected building materials are low-maintenance, as requested by the Owner, for durability and to reflect the nature of a working farm.

    Mechanical and electrical systems will be hung from the building structure. These loads are included in PEMB shop drawings.

    Public water and sewer is not available at the Project Site.

    Occupancy sensors are included to reduce utility costs and achieve energy conservation requirements.

The following resources are available for your reference:

    Architectural Drawings, including plans, elevations, sections, and schedules

    Consultant Drawings, including structural, HVAC, power distribution, and plumbing

    PEMB Shop Drawings

    Design and Construction Schedule

    Specification Excerpts, showing relevant spec sections

    IBC and ADA Excerpts, showing relevant code and accessibility sections

    After reviewing the documents, the architect discovers a coordination issue in the corridor.

The owner wants to add a small storage closet with dimensions of 4'-0" L x 4'-0" W in the Laundry Room along column line 1. The closet will have access from the corridor only.

Which of the following documents require revision due to this addition? Check the three that apply.

A.

A101

B.

A102

C.

A103

D.

Building Systems Narrative

E.

Initial Cost Estimate

F.

Specification Excerpts

Full Access
Question # 14

For which of the following reasons is sheet piling used? (Check the three that apply)

A.

A grade beam needs support.

B.

Raked shoring should be created.

C.

A pile cap needs support.

D.

An excessive slope on the sides of the excavation would be required.

E.

The soil surrounding an excavation site will not support itself during or after the digging.

F.

The excavation adjoins a property line and the adjacent property cannot be disturbed.

Full Access
Question # 15

An architect is designing a new poured-in-place concrete residential tower with individual condo units. The drawings specify exposed cantilevered concrete balconies with glass guardrail parapets. The exterior wall specifications have already been developed and established. They are now coordinating the specification requirements for construction of the balconies in the project manual.

Which items are required to be specified as part of the balcony scope? (Check the four that apply)

A.

Drainage

B.

Floor finish coating

C.

Furnishings

D.

Door types

E.

Guardrail anchoring

F.

Glazing system

Full Access
Question # 16

Which of the following is an advantage of using a glycol-cooled air conditioning unit for a computer room?

A.

It allows for a greater distance from the computer room to the outside unit.

B.

Glycol is cheaper than water for cooling.

C.

It reduces the amount of heat exhausted from the computer room.

D.

Glycol units are a sustainable cooling solution.

Full Access
Question # 17

Which code dictates the number of required exits for a 300-person assembly space?

A.

International Mechanical Code

B.

ADA

C.

International Building Code

D.

NFPA 70

Full Access
Question # 18

A family-owned apple farm in the Upper Midwest is taking advantage of a change in the local zoning code that added a new Agri-Tourism class in the existing farm zone. This allows the Owner to build a new facility on their existing site. The building will be open to the public and include a brewery, distillery, tap room, and market. The architect is ready to submit the drawings to the Owner for the 50% construction documents review.

To accommodate a compressed construction schedule, the Owner will be utilizing a design-build process. The Contractor has submitted the Pre-Engineered Metal Building (PEMB) shop drawings to the Architect for review, due to the lead time on this critical path item. Once construction begins, farming operations must be able to continue uninterrupted.

Key project information includes:

    Brewing and distilling will operate year-round.

    Brewery will initially include four fermenting tanks. Owner has requested space for at least two additional tanks. Potential expansion will be based on future sales.

    Distillery will produce 16% alcohol, which is classified as a flammable liquid. Fire separations are required.

    Tap Room is designed with seating for 300 people, not including exterior patio seating. It will have views to the working orchards and the historic buildings on site.

    Tap Room is scheduled to be open from August through November. Owner would like options to extend operating dates based on popularity.

    The Market area will feature local farm products and is not conditioned.

    Entire building will be fully sprinklered.

    Selected building materials are low-maintenance, as requested by the Owner, for durability and to reflect the nature of a working farm.

    Mechanical and electrical systems will be hung from the building structure. These loads are included in PEMB shop drawings.

    Public water and sewer is not available at the Project Site.

    Occupancy sensors are included to reduce utility costs and achieve energy conservation requirements.

The following resources are available for your reference:

    Architectural Drawings, including plans, elevations, sections, and schedules

    Consultant Drawings, including structural, HVAC, power distribution, and plumbing

    PEMB Shop Drawings

    Design and Construction Schedule

    Specification Excerpts, showing relevant spec sections

    IBC and ADA Excerpts, showing relevant code and accessibility sections

    After reviewing the documents, the architect discovers a coordination issue in the corridor.

The owner is concerned about elevated noise levels in the Tap Room when fully occupied. The current design utilizes a 2 x 2 acoustic ceiling tile system installed above the fans. An acoustical engineer recommends noise mitigation through limiting reverberation time (RT) to 2.0 seconds or less in the space. This can be achieved by the provided ceiling material options and their corresponding area.

What should the architect recommend that will minimize additional project costs while providing the recommended acoustical solution?

A.

Retain current ceiling cloud layout and a 2 x 2 acoustic ceiling tile system but remove the fans.

B.

Revise design using only one ceiling cloud and cementitious wood fiber panel system (1" in thickness).

C.

Revise design using only one ceiling cloud and cementitious wood fiber panel system (2" in thickness).

D.

Retain current ceiling cloud layout and a 2 x 2 acoustic ceiling tile system and add acoustical sound board above.

Full Access
Question # 19

A family-owned apple farm in the Upper Midwest is taking advantage of a change in the local zoning code that added a new Agri-Tourism class in the existing farm zone. This allows the Owner to build a new facility on their existing site. The building will be open to the public and include a brewery, distillery, tap room, and market. The architect is ready to submit the drawings to the Owner for the 50% construction documents review.

To accommodate a compressed construction schedule, the Owner will be utilizing a design-build process. The Contractor has submitted the Pre-Engineered Metal Building (PEMB) shop drawings to the Architect for review, due to the lead time on this critical path item. Once construction begins, farming operations must be able to continue uninterrupted.

Key project information includes:

    Brewing and distilling will operate year-round.

    Brewery will initially include four fermenting tanks. Owner has requested space for at least two additional tanks. Potential expansion will be based on future sales.

    Distillery will produce 16% alcohol, which is classified as a flammable liquid. Fire separations are required.

    Tap Room is designed with seating for 300 people, not including exterior patio seating. It will have views to the working orchards and the historic buildings on site.

    Tap Room is scheduled to be open from August through November. Owner would like options to extend operating dates based on popularity.

    The Market area will feature local farm products and is not conditioned.

    Entire building will be fully sprinklered.

    Selected building materials are low-maintenance, as requested by the Owner, for durability and to reflect the nature of a working farm.

    Mechanical and electrical systems will be hung from the building structure. These loads are included in PEMB shop drawings.

    Public water and sewer is not available at the Project Site.

    Occupancy sensors are included to reduce utility costs and achieve energy conservation requirements.

The following resources are available for your reference:

    Architectural Drawings, including plans, elevations, sections, and schedules

    Consultant Drawings, including structural, HVAC, power distribution, and plumbing

    PEMB Shop Drawings

    Design and Construction Schedule

    Specification Excerpts, showing relevant spec sections

    IBC and ADA Excerpts, showing relevant code and accessibility sections

    After reviewing the documents, the architect discovers a coordination issue in the corridor.

The owner has revised the pro forma and directed the architect to add two additional Type B units to the design. A code review for the project indicates that the building occupancy is R-2.

What should the architect do to meet the owner's required revisions?

A.

Change the 2nd Floor Unit 1BR-SW into two studios and change the 10th Floor Unit 2BR-E to two 1-bedroom units.

B.

Change the 10th Floor Unit 2BR-E to two 1-bedroom units and change the 7th Floor Unit 2BR-E to two 1-bedroom units.

C.

Change the 5th Floor Unit 2BR-E to two 1-bedroom units and change the 2nd Floor Laundry to a 1-bedroom unit.

Full Access
Question # 20

Refer to the exhibit.

What is the purpose of the flexible connection in the fan coil shown?

A.

To provide a field point of connection of the ductwork to the fan coil unit

B.

To insulate against heat transfer from the fan coil unit

C.

To minimize sound transfer

D.

To transition from the fan coil unit flange to the desired duct size

Full Access
Question # 21

In which of the following locations in concrete masonry should a control joint be placed?

A.

At the first course of masonry walls

B.

At each corner of the foundation wall

C.

At changes in wall height

D.

In the center of window openings

Full Access
Question # 22

Proposed trees along a residential street next to a new development site should first be selected based on which of the following?

A.

Seasonal foliage, color, and scale

B.

Adaptability to local climate and soil conditions

C.

Dense root systems and wind resistance

D.

Provision of natural habitation for local wildlife

Full Access
Question # 23

Which of the following documents should be coordinated in the design of a barrier-free building entrance?

A.

Door schedule, vertical elevations, and structural plans

B.

Hardware schedule, electrical drawings, and sprinkler drawings

C.

Vertical elevations, hardware schedule, and electrical drawings

D.

Door schedule, hardware schedule, and alarm system design

Full Access
Question # 24

The architect has completed 60% of the construction documents. The owner wants to establish the guaranteed maximum price (GMP) at this point before 100% of the construction documents are complete. Several flooring finish items are still undetermined.

What should be included in the project manual to make sure the contractor has a cost to cover all finishes?

A.

Contingency of 10% added to the overall construction cost

B.

Schedule of flooring unit prices to be completed by the contractor

C.

Allowance of $30/sq. yd. for floor finishes

D.

Alternate to change broadloom carpet to carpet tile

Full Access
Question # 25

The single-line diagram for the electrical distribution system shown is for a multi-family project.

Click in the box on the single-line diagram where the transformer is located.

Full Access
Question # 26

Which of the following documents would the architect need in order to prepare the specifications?

A.

Legal survey, engineering drawings, and door schedule

B.

Legal survey, geotechnical report, and traffic management plan

C.

Geotechnical report, building sections, and room finish schedule

D.

Architectural floor plans, room finish schedule, and traffic management plan

Full Access
Question # 27

Refer to the exhibit.

Which of the following is the minimum dimension of Hallway A required to meet ADA requirements, if dimension (B) is 4 inches?

A.

3 ft 8 in

B.

4 ft 4 in

C.

4 ft 10 in

D.

5 ft 0 in

Full Access
Question # 28

Which system would most impact the structural loads in a vegetated roof design?

A.

Fire suppression system

B.

HVAC duct routing

C.

Green roofing assemblies

D.

Lightning protection system

Full Access
Question # 29

Refer to the exhibit.

For a plywood panel carrying the grade stamp shown, which of the following is the maximum recommended span for use in a floor system?

A.

15 in

B.

16 in

C.

32 in

D.

108 in

Full Access
Question # 30

Refer to the exhibit.

During spring rains, the foundation walls around the basement space, as illustrated, experience an increase in lateral pressures.

Which one of the following is also a major concern?

A.

Moisture absorption of the concrete foundation wall

B.

Increased weight on the footings

C.

Vertical upward pressure on the basement floor

D.

Differential lateral pressure on total building structure

Full Access