Which of the following are control measures recommended by the Sheet Metal and Air Conditioning National Contractors Association (SMACNA) for the Indoor Environmental Quality Credit, Construction Indoor Air Quality Management Plan?
For Energy and Atmosphere Credit, Advanced Energy Metering, what is the minimum percentage requirement for metering any individual energy end uses?
A LEED Building Design and Construction project includes an outdoor stage for theatrical performances. In pursuit of Sustainable Sites Credit, Light Pollution Reduction the engineer has specified an LED fixture to illuminate actors on the stage while limiting light pollution. Which of the following suggestions should the LEED AP give to the project owner?
What is the basis of energy consumption in determining the percentage of green power or carbon offsets?
Which of the following goals does selecting low-emitting materials serve in the context of MRc3: Low-Emitting Materials?
An owner has requested that the project team redesign a large office building. As part of the redesign, the owner would like to move the main entrance to the opposite side of the building. Achievement of which credit may be affected by the move?
While working on a 12,000 ft² (1,114.8 m²) medical building, a LEED AP asks the flooring manufacturer to submit the Environmental Product Declaration (EPD) for the flooring specified. The manufacturer doesn ' t have an EPD for their products, but all products meet ISO 14040/44 for Life Cycle Assessment (LCA). They ask if it would be acceptable to send the ISO 14040/44 LCA information in lieu of an EPD. How do you respond?
Under Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification, a current facilities requirements and operations and maintenance plan must contain which information necessary to operate the building efficiently?
When the LEED AP is applying the Integrative Process to a Building Design and Construction project, when should the Owner’s Project Requirements (OPR) be created and updated?
Which of the following standards is used to perform a Whole-Building Life-Cycle Assessment (LCA) to measure the Global Warming Potential (GWP) of materials in LEED projects?
Which of the following contributes to the value of the commissioning process?
Which of the following would be most useful to a school project that is attempting to pursue Water Efficiency Credit, Indoor Water Use Reduction?
An office building design has demonstrated reductions in landscape water use of 30% over baseline and indoor water use of 40%. These reductions qualify the project for:
Smoking is prohibited inside LEED-certified buildings in order to eliminate the health risks associated with environmental tobacco smoke. Which building type is exempt from this requirement?
A new school with a 20 car parking lot has set aside four preferred parking spaces for green vehicles. What else must the project team provide to achieve Location and Transportation Credit, Green Vehicles?
Which one of the following represents quality transit service as defined in Location and Transportation Credit, Access to Quality Transit?
A downtown office building is unable to construct dedicated parking for its occupants. However, the building developer has partnered with a parking garage to offer discounted parking for its occupants. If the discounted parking rate is $450 per month, how much must the rate be for green vehicles for the building to receive one point for Location and Transportation Credit, Green Vehicles?
Which system is eligible for the Energy and Atmosphere Credit, Renewable Energy Production?
What building classification requires the energy model to determine the predicted power usage effectiveness (PUE) for Energy and Atmosphere Prerequisite, Minimum Energy Performance?
What are the Storage and Collection of Recyclables requirements for only Retail projects under the Materials and Resources Prerequisite?
During a design charrette, community neighbors raise a concern about potential glare resulting from a project ' s highly reflective roof. Which option should the LEED AP recommend to best address these concerns?
A developer is building a new shopping mall in a temperate climate. The developer wants to reduce operating costs and improve occupant experience. Which design scheme should the project team present?
According to the Integrative Process Credit, Integrative Process, the goal-setting workshop should identify
The LEED project has a main entrance and two service entrances in an alley behind the building. Which entrances need non-smoking signage and at what maximum distance from the door(s) can the non-smoking signage be posted?
Which of the following buildings meets the Minimum Program Requirements for LEED certification?
Commissioning (Cx) and verification are requirements to qualify for LEED certification. What are the basic systems that need to be commissioned?
What is the minimum percentage of the total vehicle parking capacity that should have Electric Vehicle Supply Equipment (EVSE) installed to earn 1 point for commercial projects?
To ensure long-term energy efficiency and grid resilience, which strategy should the project team prioritise first?
Which of the following Sustainable Sites credits are eligible to be used as a campus approach?
What is the best strategy for a LEED AP to suggest in order to quantify the impact of increasing the window-to-wall ratio on a Building Design and Construction project?
Which of the following LEED credit data should be used for a comprehensive 25-year carbon-emissions projection for a new building project?
In the context of Core and Shell projects, which of the following strategies effectively aligns tenant spaces with LEED goals for sustainability?
During the early stages of a LEED project, the team was able to reduce the number of lighting fixtures in classrooms by 25% because the project team selected a paint color whose light reflectance value was 75% instead of the initially proposed 64% value. This strategy is an example of applying which of the following credits to the project?
According to LEED guidelines, which of the following project types should utilize the LEED BD+C rating system?
Which of the following is required in determining the baseline for Water Efficiency Prerequisite, Indoor Water Use Reduction?
According to the Integrative Process Credit, the discovery phase of energy-related systems should identify
Which of the following products must always be included in Materials and Resources credits?
A decorative overhead light fixture is specified for a project that costs $1,500 USD and uses recycled water bottles as part of the diffuser shade. The shades are 10% of the overall weight of the fixture and are 50% post-consumer recycled content. Assuming no other portions of the fixture meet sustainability criteria, what would the contributing value of the fixture be?
U.S. Green Building Council (USGBC) ' s vision for using LEED internationally includes
What requirement must be met when creating a Demand Response Program that satisfies Energy and Atmosphere Credit, Demand Response?
Which of the following is a strategy to reduce waste produced by a project?
A project is designed to remodel an existing warehouse into multi-family housing. The exterior facade of the warehouse will remain, but 40% of the interior will be demolished and replaced for interior new construction. New materials will be used for the new construction. To achieve points in the Materials and Resources Credit, Building Life-Cycle Impact Reduction, which credit path option would apply?
A Photovoltaic (PV) system was installed on a 35,000 ft2 (3 252 m2) project. What actions need to take place in order to meet compliance for Energy and Atmosphere Prerequisite, Fundamental Commissioning (Cx) and Verification?
Which of the following organizations is responsible for providing alternative compliance paths that reflect regional variations for LEED credits?
Which of the following types of water should a project team focus on utilizing to achieve water savings and acquire points under WEc2: Enhanced Water Efficiency, Option 6. Water Reuse, Path 1. Reuse-Ready System, while reducing reliance on potable water?
Which rating system is appropriate for a new mixed-use building with 300,000 ft2 (27 871 m2) of residential units, 150,000 ft2 (13 935 m2) hotel and 50,000 ft2 (4 645 m2) of retail space?
When designing for operational decarbonization, a recommended practice when specifications call for refrigerants with a Global Warming Potential (GWP) above 700 is to develop a list of equipment options using:
Short-term bicycle storage in Location and Transportation Credit, Bicycle Facilities must be within 100 ft. (30 m) walking distance of any:
When required to measure residential and non-residential densities, Location and Transportation Credit, Surrounding Density and Diverse Uses, Option 1. Surrounding Density requires project teams to measure the residential and non-residential densities in what way?
Discussing the project goals to help identify the credits and options that the team should attempt is an example of
A project ' s massing and site orientation can have a direct impact on which of the following prerequisites?
The maximum number of points for Water Efficiency Credit, Cooling Tower Water Use can be obtained by
To achieve SSc6: Light Pollution Reduction using the Backlight, Uplight, and Glare (BUG) Rating Method, projects must demonstrate that all luminaires:
Which of the following scenarios contributes to earning credit under MRc1: Materials and Resources, Option 2. Materials Reuse?
The Exemplary Performance threshold for Sustainable Sites Credit, Rainwater Management requires:
Under LTc3: Compact and Connected Development, Option 1. Surrounding Density, how far from the project site should project teams measure surrounding density?
The project team has decided to substitute the flooring in the school gym with natural rubber flooring that has met the Sustainable Agriculture Standard. The cost of the substituted flooring is $80,000. The project will achieve
A project design team for an elementary school project is attempting to achieve Innovation Credit, Innovation, Option 1. Innovation. Which of the following strategies would qualify?
Which of the following activities must be prohibited within a building as a prerequisite to LEED certification?
If a commercial building is considered to have 100 peak visitors in a day, what is the minimum number of short-term
bicycle storage spaces that must be provided to earn one point under Location and Transportation Credit, Bicycle
Facilities?
Which of the following strategies enhances energy resilience by ensuring that critical loads are powered during a grid outage?
In the context of biophilic design, providing access to outdoor views contributes to enhancing occupant quality of life because doing so:
To assess the feasibility of earning Location and Transportation Credit, Reduced Parking Footprint, the project team should be familiar with what local government regulation?
Who must be a member of the integrated project team for the Integrative Process Prerequisite, Integrative Project Planning and Design?
Green Infrastructure (GI) and Low-Impact Development (LID) rainwater management strategies improve upon the conventional approach for rainwater management by
How much value would these two doors contribute toward Material and Resources Credit, Building Product Disclosure and Optimization – Sourcing of Raw Materials, Option 2. Leadership Extraction Practices?
The project team achieved a strategy not addressed in the LEED Green Building Rating System, which proved to be a significant, measurable environmental benefit for the project. What can the project team do in order to get a benefit for this strategy?
A commercial new construction project consists of mixed space usage. When deciding which LEED rating system to use, the LEED AP should follow which of the following rules?
Which of the following characteristics are a requirement of a compliant water meter?
Which of the following acoustical units are used in Indoor Environmental Quality Credit, Acoustic Performance to measure reverberation time?
Which of the following projects is eligible to pursue the Energy and Atmosphere Prerequisite, Minimum Energy Performance, Option 2. Prescriptive Compliance: ASHRAE 50% Advanced Energy Design Guide?
Which site preparation and construction method contributes to earning the Materials and Resources Credit, Construction and Demolition Waste Management?
For a task chair purchased for a healthcare facility, which portion of the product contributes toward Materials and Resources Credit, Furniture and Medical Furnishings?
What is the reference standard that defines the requirements for LEED energy modeling?
When the LEED AP is applying the Integrative Process to a Building Design and Construction project, which of the following must be included in the Basis of Design (BOD)?
A hospital certified underLEED V5in 2018 is designing and constructing a 21,000 ft² (1,950.96 m²) vertical addition, plus vegetated terraces and a mechanical penthouse.
The original hospital achieved the Gold certification level and was built with the capacity to add three floors—levels six through eight—to the top of the structure. This addition requires partial demolition of the roof and the floor below.
The project is designed to be architecturally cohesive with the existing building façade and is targeting Platinum certification under LEED v5.
The campus is in a dense urban area adjacent to several bus stops, a light-rail transit station within a 2,500 ft. (762 m) walking distance, and a bicycle docking point at the main entrance to the property. An on-campus shuttle service connects patients, visitors, and staff from the parking areas to each medical building and the light-rail station.
The healthcare campus has existing infrastructure; therefore, no new roads, sidewalks, parking structures, or ground-level landscaping will be installed.
The new floors have separate mechanical systems in the penthouse, but piping for public and patient restrooms, janitor closets, and staff break rooms connects directly to the main hospital plumbing system.
The newly installed medical equipment uses gas, steam, and chilled water supplied by the campus central plant.
Which LEED v5 rating system is appropriate for this project?
A project ' s installed water fixtures do not exceed WaterSense maximum levels. Which compliance path should the LEED AP select under Water Efficiency Prerequisite, Indoor Water Use Reduction, and what type of documentation is required to demonstrate compliance with this path?
For a bicycle network to demonstrate compliance with Location and Transportation Credit, Bicycle Facilities, the bicycle network must connect to
Which of the following criteria does a project need to implement in order to qualify for Sustainable Sites Credit: Site Development - Protect or Restore Habitat, Option 1?
Which of the following is omitted from the assessment while performing preliminary energy modeling?
During the early stages of a LEED for Schools project, the team was able to reduce the number of lighting fixtures in classrooms by 25% because the project team selected paint color whose light reflectance value was 75% instead of the initially proposed 64% value. This strategy is an example of applying which of the following credits to the project?
Which of the following requires standard appliances for indoor water reduction?
The goal of the design charrette during Integrative Process Prerequisite, Integrative Project Planning and Design is to:
Which of the following must be included in the Sustainable Sites Credit, Site Assessment?
Landscape irrigation practices consume large quantities of potable water. By evaluating the project ' s outdoor water budget and irrigation water demand early in the design process in Water Efficiency Prerequisite, Outdoor Water Use Reduction project teams will be able to
The Water Efficiency Prerequisite, Outdoor Water Use Reduction requires a reduction over a baseline that is calculated for the site:
A new theater is being designed to enhance acoustical comfort for its audiences. One of the main challenges the design team faces is minimizing excessive reverberation. The team plans to incorporate various materials and design strategies to control sound reflections.
Which of the following design strategies should effectively enhance acoustical comfort?
Operable windows contribute to resilient planning and design in extreme climate conditions by:
Which of the following Water Efficiency credits differ between LEED Building Design and Construction: New Construction and LEED Building Design and Construction: Healthcare?
What type of project would benefit from showing compliance with Energy and Atmosphere Prerequisite, Minimum Energy Performance, Option 2. Prescriptive Compliance: ASHRAE 50% Advanced Energy Design Guide?
During preliminary energy analysis, what energy reduction strategies can best help in reducing the energy load in the new building construction project?
A project team is considering implementing a strategy that has previously been awarded as an Innovation credit on another project. Which actions should be followed if the project team wishes to gain formal pre-approval of the same strategy on the new project?
For a project located on a greenfield site and attempting the Location and Transportation Credit, Sensitive Land Protection, Option 2, what must the development footprint avoid?
What information must be provided to demonstrate compliance with the Owner’s Project Requirements (OPR)?
Which of the following design strategies should enhance a site ' s resilience against extreme heat events due to climate change?
Minimizing light trespass is a key component of which of the following credits?
A design team is evaluating strategies to ensure that a healthcare facility remains operational for critical services during frequent power outages. The building currently relies on a diesel generator for emergency power, but the owner is interested in sustainable alternatives that can also contribute to the project’s energy efficiency during normal operations.
Which of the following strategies should the design team recommend to provide energy resilience for the healthcare facility while enhancing energy efficiency during regular operations?
When designing a building that includes Electric Vehicle Supply Equipment (EVSE), which capability is needed to ensure maximum energy efficiency and cost savings?
The project landscape architect suggests reducing the area planned for surface parking and replacing it with additional vegetated space. What benefit would this strategy provide to the owner?
How can a building owner promote both energy efficiency and thermal comfort in a building?
What role does the Commissioning Provider have during the creation of the Owner ' s Project Requirements (OPR) document?
The design team is attempting to achieve the Increased Ventilation strategy in the Indoor Environmental Quality Credit, Enhanced Indoor Air Quality in a conference room. The associated ASHRAE standard requires 400 CFM (11.3 CMM) of ventilation air, but the local code requires 500 CFM (14.1 CMM) of ventilation air. What is the required minimum amount of ventilation air to achieve this credit?
A new five-story building with a 30,000 ft2 (2 800 m2) footprint is being designed on a previously disturbed100,000 ft2 (9 290 m2) site. The remaining on-grade surface will be 35,000 ft2 (3 250 m2) of asphalt parking, and 35,000 ft2 (3 250 m2) of native vegetated open space. To achieve a point for exemplary performance under Option 1 of Sustainable Sites Credit, Site Development - Protect or Restore Habitat, the design team will have to incorporate a native and/or adapted vegetated roof with a minimum area of
The contractor has submitted waste hauling reports for review in order to achieve Materials and Resources Credit, Construction and Demolition Waste Management. Which of the following materials on the documentation contribute towards the credit?
In the Indoor Environmental Quality Credit, Low-Emitting Materials, what types of products need to be evaluated for
both Volatile Organic Compound (VOC) content of the material and VOC emissions of the material?
An existing vacant office building will be completely renovated and new mechanical, electrical and plumbing systems will be installed. 20% of the building ' s gross floor area will be complete at the time of certification. There will be a data center and some retail stores on the ground floor of the building at a future date. Which rating system is applicable for the building?
Based on the results of a six-hour waste stream study, the project team for a retail project plans to provide dedicated areas for four easily recyclable waste streams: cardboard, plastic, metal and paper. The project is open to the public 10 hours a day, six days a week. Which of the following actions should be the project team ' s top priority in order to demonstrate the minimum requirements to achieve Materials and Resources Prerequisite,
Storage and Collection of Recyclables?
A project ' s total site area is 240,000 ft2 (22 297 m2) and the building footprint is 40,000 ft2 (3 716 m2). How much
outdoor space and vegetated space must it provide to earn Sustainable Sites Credit, Open Space?
A critical factor in determining a project’s eligibility for LTc3: Compact and Connected Development, Option 2. Access to Transit, Path 1. Public Transit Service is the:
A hospital certified underLEED V5in 2018 is designing and constructing a 21,000 ft² (1,950.96 m²) vertical addition, plus vegetated terraces and a mechanical penthouse.
The original hospital achieved the Gold certification level and was built with the capacity to add three floors—levels six through eight—to the top of the structure. This addition requires partial demolition of the roof and the floor below.
The project is designed to be architecturally cohesive with the existing building façade and is targeting Platinum certification under LEED v5.
The campus is in a dense urban area adjacent to several bus stops, a light-rail transit station within a 2,500 ft. (762 m) walking distance, and a bicycle docking point at the main entrance to the property. An on-campus shuttle service connects patients, visitors, and staff from the parking areas to each medical building and the light-rail station.
The healthcare campus has existing infrastructure; therefore, no new roads, sidewalks, parking structures, or ground-level landscaping will be installed.
The new floors have separate mechanical systems in the penthouse, but piping for public and patient restrooms, janitor closets, and staff break rooms connects directly to the main hospital plumbing system.
The newly installed medical equipment uses gas, steam, and chilled water supplied by the campus central plant.
Based on the project design and the credit options that the project team may attempt, what is the highest LEED certification level that can be achieved?
A luxury hotel project is in the design phase and is located on a scenic waterfront. It is one point away from attaining LEED Platinum certification. The LEED AP is recommending that the team pursue Innovation Credit, Innovation, Option 3. Additional Strategies. Which of the following credits would be desirable considering the location of the project?
The Volatile Organic Compounds (VOC) emissions evaluation criteria for adhesives and sealants should be obtained for wet-applied products installed within:
Which item is included in the reuse calculation for Materials and Resources Credit, Building Life-Cycle Impact Reduction?
A building owner is considering the installation of a solar thermal panel on the roof of the building. The initial cost of the system is higher than a conventional natural gas system. Which of the following is true to make the renewable energy option economically feasible?
When attempting Regional Priority Credit, what must be provided in LEED Online?
A LEED Building Design and Construction: Schools project pursuing Location and Transportation Credit, Green Vehicles elects to follow Option 2. Green Buses or School-Owned Vehicles. What action must the project take to meet the Option 2 requirements?
The Lakeside Resort is a hotel in a rural area located about 60 mi. (96.6 km) from the nearest town, which has a population of 10,500. There are no other towns for over 200 mi. (321.9 km). The surrounding community is largely made up of ranches and federal- and state-owned land.
The project consists of a single building that includes the following:
• 150 guest rooms
• A small restaurant
• An indoor pool
• Conference spaces
• Event spaces
• Six tenant spaces
A lease has been secured for a future spa, gift shop, coffee shop, and tour operator. Two of the six tenant spaces have not yet been leased. The property is 10 acres, adjacent to a lake, and has trail access to public lands for hiking. It is anticipated that occupants will mostly arrive by car, but there is one public bus trip per day from the nearest town.
The project consists of the building, parking lots for overnight guests and daily visitors, a walking path to the lake, and hiking trails leading to the public lands. The project has a goal of being Gold certified under LEED for New Construction.
When determining occupancy for the project, how should the project team account for the occupancy for the future spa, gift shop, coffee shop, tour operator space, and the two unknown tenant spaces?
When designing a new building, which of the following strategies can be implemented to accommodate future integration of alternative water sources?
In the step-by-step guidance for Location and Transportation Credit, Bicycle Facilities, which of the following requirements can define a bicycle network?
The project team wants to modify the design of an office building copy room to minimize the risk of airborne contamination to the surrounding space. The design includes a separate exhaust, but due to design constraints the partition walls of the room cannot run deck-to-deck. What can the team do to achieve Indoor Environmental Quality Credit, Enhanced Indoor Air Quality Strategies?