Spring Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: mxmas70

Home > IAM > IAM Certificate > IAM-Certificate

IAM-Certificate The Institute of Asset Management Certificate Question and Answers

Question # 4

Which of the following requirements would you expect to find included within an Asset Management Strategy?

A.

Asset data configuration

B.

Asset register

C.

Project handback to operations

D.

Maintenance special tools

E.

Future demand

Full Access
Question # 5

FMECA stands for:

A.

Failure Mode Effect and Consequences Analysis

B.

Fault Mitigation Effect and Criticality Analysis

C.

Failure Mitigation Effect and Consequence Analysis

D.

Failure Mode Effects and Criticality Analysis

E.

Fault Mode Effect and Cost Analysis

Full Access
Question # 6

What is the purpose of whole-life cost analysis?

A.

To determine the option for a particular decision which has the lowest costs over the life of the asset

B.

To determine the most important costs associated with an asset

C.

To determine the renewal costs at the end of an asset’s life

Full Access
Question # 7

The costs included in an outline business case for the purchase of new assets should include:

A.

Only costs that are known and therefore accurate

B.

All costs for the design and creation phase of the asset

C.

All costs quoted by potential suppliers excluding operation and maintenance costs

D.

All costs, including estimated asset disposal costs but excluding design costs

E.

All known and estimated costs for the asset lifecycle

Full Access
Question # 8

In the context of Asset Management, and the ‘line of sight’ through the organisation, it is important that a project business case and evaluation process connect with:

A.

The Risk Management Strategy

B.

The Capital Budget

C.

The Operational Budget

D.

The Resourcing Strategy

E.

The Asset Management Objectives

Full Access
Question # 9

Which of the following statements is true:

A.

Corporate objectives are derived from the Asset Management strategy

B.

Corporate objectives drive the activities within the Asset Management system

C.

Corporate objectives should be set by comparing the organisation’s performance to its most closest associated peer

Full Access
Question # 10

Who should demonstrate leadership in ensuring adequate, periodic review of the suitability, adequacy and effectiveness of the Asset Management System?

A.

The Senior Engineer

B.

The Head of Asset Management

C.

The Board Audit Committee

D.

The Top Management Team

E.

An Independent Auditor

Full Access
Question # 11

Which of these statements is UNTRUE?

A.

Asset information is always worth collecting regardless of cost

B.

Asset information has maintenance costs as well as collection costs

C.

Asset information can be treated as an asset in its own right

Full Access
Question # 12

Which of the following best describes the 'useful life' of an asset?

A.

The period of time until maintenance costs of an asset are exceeding boundaries specified by stakeholders

B.

The period of time until an asset is physically non-functioning

C.

The number of years until an asset is fully depreciated and has reached an economic value of 'zero' in the asset register

D.

The amount of time specified by the original equipment manufacturer

E.

The period of time for which the asset can economically perform a required function

Full Access
Question # 13

You have recently been hired by a large infrastructure organization that has a diverse range of assets and asset types. Which of the following statements is true when developing Asset Management Plans for an organization like this?

A.

It is best to only have a single overarching Asset Management Plan that covers all asset types because having individual asset plans for each asset type will create misalignment and unnecessary confusion.

B.

It is best to only have individual asset plans for each asset type. There is no need for an overarching Asset Management Plan as it will add unnecessary complexity.

C.

It is best to have only a single Asset Management Plan, because all asset management activities for each asset type need to be treated equally.

D.

The number and type of Asset Plans is not relevant as long as maintenance is carried out to the most critical asset groups.

E.

It is best to have individual asset plans for each asset type with an overarching Asset Management Plan that outlines the overall asset management objectives of the organisation.

Full Access
Question # 14

Characteristics of organisational context that affect what is achievable and worthwhile in asset management fall into three categories:

A.

Asset systems criticality

B.

Scale and complexity of the asset portfolio

C.

Volatility of the business environment

D.

All above true

Full Access
Question # 15

The contents of an asset management policy can include...

A.

the requirements of the key stakeholders of the organisation, high level asset management roles and responsibilities, the asset management principles for the organisation, a framework for the setting of the asset management strategy and objectives and a review frequency

B.

the mandated requirements of the organisation, high level asset management roles and responsibilities, the key departments involved in asset management, a framework for the setting of the asset management strategy and objectives and review frequency

C.

the mandated requirements of the organisation, high level asset management roles and responsibilities, the asset management principles for the organisation, a framework for the setting of the asset management strategy and objectives and details of the asset management plan

D.

the mandated requirements of the organisation, the asset management principles for the organisation, high level asset management roles and responsibilities, a framework for the setting of the asset management strategy and objectives and a commitment to continuous improvement

E.

the mandated requirements of the organisation, the asset management principles for the organisation, high level asset management roles and responsibilities, key risks for the organisation and a review frequency

Full Access
Question # 16

(Exposure to) the possibility of loss, injury, or other adverse or unwelcome circumstance; a chance or situation involving such a possibility, is the definition of .......

A.

Value

B.

Asset

C.

Risk

D.

Cost

Full Access
Question # 17

Asset Management is explicitly focused on helping organisations to achieve their defined objectives and to determine the optimal blend of activities based on these objectives.

A.

True

B.

False

Full Access
Question # 18

A significant risk of asset failure that will impact service to customers is identified by an asset operator and reported to his line manager. When is the right time to add the risk to the risk register?

A.

When the risk is identified to the line manager

B.

Before the next scheduled risk review meeting

C.

When the owner of the risk register asks for emerging risks

D.

After the asset has failed and the cause has been investigated

E.

When budget has been allocated to mitigate the risk

Full Access
Question # 19

What is NOT usually considered in the decision to decommission and dispose of assets?

A.

The residual value of assets

B.

Alternative uses for the assets

C.

The depreciated value of the assets

D.

The environmental impact of disposing of the assets

E.

Legislation regarding disposal of the assets

Full Access
Question # 20

To successfully establish, operate and improve asset management within an organisation, it is essential that leadership, and commitment, is demonstrated by all levels of management – from senior executives to supervisors.

A.

False

B.

True

Full Access
Question # 21

Which of the following would you normally expect to include as key components of the Asset Management Strategy?

A.

Risk registers, statutory/environmental/financial constraints, O and M manuals, detailed work plans

B.

Maintenance schedules, stakeholder lists, annual financial reports, asset forecasts

C.

Improvement objectives, maintenance schedules, asset forecasts, As-Built drawings

D.

Improvement objectives, strategic risks and opportunities, statutory/environmental/financial constraints, asset forecasts

E.

Strategic risks, constraints, O and M manuals, As-Built drawings

Full Access
Question # 22

You have been asked to optimise asset investment planning. What is the best source of information for this?

A.

Tendered costs

B.

Whole-life cost models

C.

Engineering estimates

D.

Suppliers' quotations

E.

Published data

Full Access
Question # 23

The following things are taken into consideration in developing an asset management strategy, except :

A.

Consistency

B.

Life cycle approach

C.

Asset requirements

D.

Management needs

Full Access
Question # 24

What is the most effective measure when determining the current health of your assets?

A.

Condition assessment

B.

Demand forecast

C.

Maintenance reports

D.

Asset age

E.

Historical maintenance cost

Full Access
Question # 25

Value based on AM is ......

A.

Value creation

B.

Waste elimination

C.

Value objective

D.

The Assets

Full Access
Question # 26

Which of the following statements best describes the difference between an Asset Management Policy and an Asset Management Strategy?

A.

Policy defines objectives and time; strategy defines principles

B.

Policy defines principles; strategy certifies condition

C.

Policy defines objectives and time; strategy summarizes work plans

D.

Policy defines principles; strategy defines objectives and time

E.

Policy defines financial trade-offs; strategy summarizes planning

Full Access
Question # 27

An ISO 55000 asset management system provides the structure, methodology and mechanism to helping asset-intensive organizations deliver on their objectives.

A.

True

B.

False

Full Access
Question # 28

How is risk best quantified within an ISO 55001 compliant Asset Management System?

A.

Risk is quantified as a product of asset criticality (scored 1 to 10) and frequency of unavailability

B.

Risk is quantified by defining the boundaries of acceptable risk, i.e. the organization’s “risk appetite”

C.

Risk is quantified by multiplying the event probability (or frequency) by the event consequences

D.

Risk identification processes quantify risk within an organization

E.

It is not possible to quantify risk

Full Access
Question # 29

What are the main cost elements of a whole-life cost approach?

A.

Installation, failure and refurbishment costs

B.

Asset deterioration and reliability costs

C.

Maintenance, associated financing costs, refurbishment, and disposal costs

D.

Installation, maintenance and operations, and disposal costs

Full Access
Question # 30

In what year did the term "asset management" start to be used?

A.

1980

B.

1981

C.

1982

D.

1983

Full Access
Question # 31

How many roles are there in the IAM Competences Framework?

A.

Five

B.

Six

C.

Seven

D.

Three

Full Access
Question # 32

A policy is best defined as...

A.

Overarching objectives setting context and direction

B.

Intentions and direction as formally expressed by top management

C.

Activities to create value for customers

D.

Temporary endeavor to create unique output

E.

Action plans to attain objectives

Full Access
Question # 33

How do Risk Based Maintenance (RBM) and maintenance work planning relate?

A.

RBM is used to identify the failure modes, which, after evaluation, are the basis for the maintenance work planning of repair tasks

B.

Historical achievement of previous maintenance plans is used as the starting point for RBM

C.

The Computerised Maintenance Management Systems (CMMS) optimises the planned maintenance work tasks and the output is the basis for the RBM methodology

D.

RBM identifies optimised maintenance tasks with frequencies, which, after evaluation and combination of tasks, are the basis for the maintenance work planning

E.

There is no relationship between RBM and planned maintenance. RBM is used to generate the risk register and is independent work planning

Full Access
Question # 34

Which of the following statements is not a management asset?

A.

A recognition that assets have a life cycle

B.

An approach that looks to get the best out of the assets for the benefit of the organisation and/or its stakeholders

C.

Understanding and managing the risk associated with owning assets

D.

A substitute for quality management

Full Access
Question # 35

Why should an organization conduct internal audits of the asset management system?

A.

To ensure compliance with financial requirements determined by national and international legislation

B.

To make sure it meets the requirements set by regulators and government to assure assets are recorded and reported in the Tax Register

C.

To assess if it is providing the required level of savings set by top management

D.

To ensure it is being applied to drive down the cost of maintenance whilst improving the ratio of planned versus reactive work orders

E.

To assess conformity with the organization's own requirements and check it is effectively implemented and maintained

Full Access
Question # 36

Based on ISO 55000 regarding asset management system, which of the following statements is false?

A.

Is not a software

B.

Is application agnostic

C.

Provides a documented foundation for the asset management operation

D.

Is a regulation to help the organization

Full Access