Weekend Sale - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: mxmas70

Home > SAP > SAP Certified Specialist > E_S4CON_2505

E_S4CON_2505 SAP Certified Specialist - SAP S/4HANA Conversion and SAP System Upgrade Question and Answers

Question # 4

Which of the following SUM activities require a stack XML file calculated by the maintenance planner? Note: There are 3 correctanswersto this question.

A.

DMO without system update

B.

SAP S/4HANA conversion without DMO

C.

Prerequisite check

D.

Benchmark tool

E.

SAP S/4HANA conversion including DMO

Full Access
Question # 5

What do you need to consider when performing the SI checks for an SAP S/4HANA conversion? Note: There are 2 correctanswersto this question.

A.

You need to build up an SI check framework by applying SAP Notes.

B.

The errors from the SI checks must be solved; otherwise, SUM will report an error.

C.

You need an SAP system based on AS ABAP 7.50 or above for the SI check framework.

D.

The SI checks are executed in the development system and the results are transported into the subsequent systems.

Full Access
Question # 6

Which steps should be performed during the adjustment of dictionary objects (SPDD) in the development system before SUM continues? Note: There are 2 correctanswersto this question.

A.

Assign the transport request as a modification adjustment transport.

B.

Manually activate the adjusted dictionary objects.

C.

Release the transport request containing the modification adjustment.

D.

Create new versions of the objects you need to adjust.

Full Access
Question # 7

You are running an SAP ECC system. For which of the following activities does SUM allow you to use the near-Zero Downtime Maintenance (nZDM) capabilities? Note: There are 3 correctanswersto this question.

A.

Use DMO for SUM.

B.

Perform an SAP S/4HANA conversion without DMO.

C.

Perform an SAP S/4HANA conversion including DMO.

D.

Upgrade the SAP system.

E.

Apply SAP support packages.

Full Access
Question # 8

What do you need to know about the SAP S/4HANA Conversion Guide? Note: There are 2 correctanswersto this question.

A.

It contains a section about the simplification item (SI) checks.

B.

It explains the database migration option (DMO) of SUM.

C.

It is a database-specific document.

D.

It explains where to find information about the custom code analysis.

Full Access
Question # 9

You want to use the Custom Code Migration Worklist via remote code analysis using the ABAP Test Cockpit (ATC). How can you get the latest content of the simplification database?

A.

Apply the corresponding SAP Note via the Note Assistant.

B.

Generate it by analyzing the specific custom code via RFC.

C.

Download it from the SAP Support Portal.

D.

Configure it within transaction ATC.

Full Access
Question # 10

You are performing an SAP S/4HANA conversion for your production system. This conversion project requires that certain business functions are switched on. Following SAP recommendations, how will you achieve this? Note: There are 2 correctanswersto this question.

A.

Import a transport request from the development system that contains the recording of the activation.

B.

During conversion, SUM delivers some business functions already activated.

C.

Activate the required business functions in the switch framework from section S/4H_ALWAYS_ON_FUNCTIONS.

D.

Activate the required business functions manually in the production system.

Full Access
Question # 11

You are performing an SAP S/4HANA conversion with DMO. You are using the downtime-optimized data conversion (DoC). Which steps can partially be moved to uptime processing? Note: There are 2 correctanswersto this question.

A.

Software update

B.

Main import

C.

Migration

D.

Conversion

Full Access
Question # 12

You are using DMO of SUM. You defined 40 parallel R3load processes during uptime and 80 parallel R3load processes during downtime. The server provides 8 CPU cores. Phase EU_CLONE_MIG_DT_RUN is running. In the Charts Control Center, you can see 40 process buckets being executed in parallel. Why are 40 Process Buckets executed in parallel?

A.

These are 40 pairs of R3load processes, so there are 80 R3load processes running.

B.

There is a maximum of 40 parallel R3load processes within this specific phase.

C.

SUM is still running in uptime; the 40 defined R3load processes are considered.

D.

The number of CPU cores does NOT allow more than 40 R3load processes to be run in parallel.

Full Access