Which of the following phases in the fundamental test process is considered to deliver a document which can be used as a major input for test process improvement? 1 credit
The business has asked for a weekly progress report. Which of the following would be appropriate as a measure of test coverage? 2 credits
Which of the following is a valid drawback of independent testing? 1 credit
A number of options have been suggested for the level of independence to be employed for the testing on the next project, and are shown below.
i. External test specialists perform non-functional testing.
ii. Testing is outsourced.
iii. Testing is carried out by the developer.
iv. A separate test team carries out the testing.
v. Testing is performed by the business.
vi. Testing is performed by a different developer.
Which of the following orders the above in a correct order of independence? 1 credit
Which from the following list are typically found to enable the review process to be successful? [K2]
a. Each review has clear defined objectives
b. The lower the number of defects, the better the review process
c. The right people for the review objective are involved
d. There is an emphasis on learning and process improvement
e. Management are not involved in the process at all
f. Checklists should not be used, as these slow down the process
g. Defects found are welcomed and expressed objectively
Consider the following pseudo code:
1. Begin
2. Input X, Y
3. If X > Y
4. __Print (X, ‘is greater than’, Y)
5. Else
6. __Print (Y, is greater than or equal to’, X)
7. EndIf
8. End
What is the minimum number of test cases required to guarantee both 100% statement coverage and 100% decision coverage?
Which of the following would you least expect to form part of the analysis of initial tool costs? 1 credit
Select THREE issues from the options provided that should at least be raised. 1 credit
Consider the typical objectives of testing. Which of the following metrics can be used to measure the effectiveness of the testing process in achieving one of those objectives? 1 credit
Regarding the process described above, what is the most important recommendation you would make using IEEE 1044 as a guide? 2 credits
Given is the following defect removal chart reported at the end of system testing - showing total defects detected and closed defects (fixed and successfully retested). A number of open defects are classified as critical. All tests have been executed.
Based on the chart above, what is the most appropriate next test phase? 1 credit
Relying only on the information provided in the scenario, select the TWO items and/or features for which sufficient information is available to proceed with test design. 2 credits
During the development of a software change for a system, the developer makes a mistake in his work, which leads to a fault in the code. Unfortunately the fault is not found by software testing and is released into live.
What is the definite consequence of this mistake?
A system requirement states that up to 100 users should be able to carry out a transaction, with responses returned within 5 seconds.
What type of non-functional testing would you carry out to verify these requirements?
In general which part of the testing activity is most difficult to estimate? 1 credit
Which aspect in the test estimate is the main risk in this project? 1 credit
Identify THREE items that would be part of the work-breakdown structure showing the key testing activities for the acceptance test project. 2 credits (for 2 out of 3 correct 1 credit)
Risks should be constantly reviewed. Given the current situation, which one of the following factors is most likely to lead to a revised view of product risk? 3 credits
Evaluate the status of the project against the defined exit criteria. Which of the following options shows the correct status? 2 credits
Which of the following are valid reasons for adopting a different life cycle (from the V model), for increments after the first year? 2 credits
i. We do not have a clear understanding of the requirements from a customer perspective.
ii. We see the risk of delivering requested functionality late as being higher than the risk of delivering a lower quality product.
iii. We do not have a budget for additional regression testing which is needed to ensure that existing functionality is not compromised by future iterations.
iv. The company test strategy does not fit well within the V life cycle model.
Which of the following would be the most significant input to estimating the time to carry out the specified testing tasks? 3 credits
What would be a test approach regarding the test design techniques to be applied that would fit an item with the highest risk? 2 credits
Which of the following product risks would be most effectively addressed just by static testing? 3 credits
Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:
a. Any deviation from the procedures described in the test
b. strategy document
c. The overall estimated costs, timescales and resource
d. requirements
e. A detailed schedule of testing activities
f. The development deliverables to be tested
g. Which test staff members (names) will be involved and when
h. Level of requirements coverage achieved
Which TWO of the above mentioned characteristics relate to the phase test plan? 1 credit
As part of the test strategy, entry and exit criteria will be defined for each test level. Which is NOT a valid reason for using entry and exit criteria? 1 credit
Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:
a. Any deviation from the procedures described in the test strategy document
b. The overall estimated costs, timescales and resource requirements
c. A detailed schedule of testing activities
d. The development deliverables to be tested
e. Which test staff members (names) will be involved and when
f. Level of requirements coverage achieved
Which THREE of the above mentioned characteristics relate to the master test plan? 1 credit
Which one of the following estimation approaches is appropriate at this stage of the project? 2 credits
Part of the testing strategy indicates that you are going to be using systematic test design techniques. Your manager has asked that you present the main advantages of using these techniques at the next board meeting. Identify THREE main benefits of using systematic test design techniques within this company. 2 credits (for 2 out of 3 correct 1 credit)
You have been asked to write a testing strategy for the company. Which statement best explains how risk can be addressed within the testing strategy? 1 credit
Which of the following team roles would be most appropriate to enhance the team and why? 2 credits
In addition to introducing the new team member, you have decided to raise motivation. Which of the measures listed below would be the best measure to take in order to increase the motivation of the team? 2 credits
You are considering involving users during test execution. In general, what is the main reason for involving users during test execution? 1 credit
The test improvement project will take place in an organization developing a safety-critical avionics application. Which one of the following standards do you believe would be most appropriate to take into account for compliance during your assignment? 1 credit
Comparing TMMi and TPI, which is not a valid reason for choosing either TPI or TMMi? 2 credits
A test assessment has been carried out using the selected model as a reference framework. A number of recommendations have been identified and you are asked to prioritize them. Based on your knowledge of the project, you are expecting severe resistance to change. Which of the following would be the most important selection criterion for defining the priority of the recommendations? 2 credits