Question # 4

In accordance with The Joint Commission's Emergency Management Chapter, which of the following is one of the most effective tools to plan an emergency response exercise?

A.

ILSM

B.

PCRA

C.

HVA

D.

ICRMR

Full Access
Question # 5

A hospital will purchase builder risk insurance to address which of the following?

A.

medical costs in the event a worker gets hurt on a construction site

B.

payment to subcontractors in the event the prime contractor fails to pay subcontractors

C.

replacement or repair value of a damaged structure

D.

liability caused by general contractor default

Full Access
Question # 6

What is the maximum capacity of soiled linen or trash receptacles allowed in patient rooms or nurse stations?

A.

8 gal.

B.

16 gal.

C.

32 gal.

D.

64 gal.

Full Access
Question # 7

The annual utility bill at a hospital is $1.2M for a 500,000 sq. ft. facility. The current construction project will add 100,000 sq. ft. to the facility. What is the anticipated annual utility budget after the construction project is completed?

A.

$240,000

B.

$1,440,000

C.

$1,728,000

D.

$1,828,000

Full Access
Question # 8

When balancing cost and function of access control needs for a single person office where access is restricted to the occupant, the best solution is a

A.

keypad lock.

B.

key lock.

C.

biometric lock.

D.

badge access lock.

Full Access
Question # 9

In an outpatient clinic classified as a business occupancy, The Joint Commission requires fire drills to be held how often?

A.

every 12 months

B.

every 6 months

C.

every 3 months

D.

once a month

Full Access
Question # 10

Which of the following should be considered when determining the simple payback of an energy-saving alternative?

A.

annual operating cost

B.

annual rate of inflation

C.

replacement cost

D.

life of the equipment

Full Access
Question # 11

When preparing to open up a newly constructed wing, who is required to survey the new area?

A.

police department

B.

fire department

C.

utility department

D.

engineering department

Full Access
Question # 12

According to NFPA 80, the maximum undercut allowed for rated fire doors is how many inches?

A.

1/2

B.

3/4

C.

5/8

D.

1

Full Access
Question # 13

Which of the following is the NFPA reference code for fire alarm system testing?

A.

70E

B.

72

C.

99

D.

101

Full Access
Question # 14

A justification for having an institutional standard for a ball valve instead of a gate valve is that ball valves

A.

handle higher temperatures.

B.

last longer.

C.

are easier to inventory.

D.

have packing that is easily replaced.

Full Access
Question # 15

When more than one employee works on equipment that must be locked-out in accordance with OSHA regulations, which of the following is an acceptable procedure to follow?

A.

Utilize a single lock and apply a tag to the energy-isolating device with the name of each employee listed.

B.

Utilize a single lock on the energy-isolating device and provide each employee with a copy of the key to the lock.

C.

Utilize a multiple lockout device on the cabinet and place one commonly keyed lock on the multiple lockout device for each employee.

D.

Utilize a multiple lockout device that allows each individual working on the equipment to apply a personal lock on the energy-isolating device.

Full Access
Question # 16

Regulated medical waste should be handled in which of the following ways?

A.

labeled with specific content

B.

refrigerated at 40° F

C.

incinerated within 10 days of collection

D.

separated from other types of waste

Full Access
Question # 17

The Safe Medical Device Act of 1990 requires reporting of incidents involving a medical device when which of the following occurs?

A.

inappropriate application of the device

B.

recall

C.

death or injury

D.

major breakdown

Full Access
Question # 18

Construction and/or renovation project submittals and shop drawings are reviewed to ensure

A.

code compliance.

B.

compliance with plans and specifications.

C.

the project has minimal change orders.

D.

the contractor understands the intent of the specifications.

Full Access
Question # 19

According to NFPA 13, when replacing standard response sprinkler heads with quick response heads, all heads must be replaced in the entire

A.

compartment.

B.

zone.

C.

building.

D.

corridor.

Full Access
Question # 20

An NFPA document using the word "shall" indicates that the item is a

A.

recommendation.

B.

guideline.

C.

performance standard.

D.

mandate.

Full Access
Question # 21

When storing oil or petroleum products over 1,320 gallons above ground or 42,000 gallons underground, a Spill Prevention, Control, and Countermeasure (SPCC) program is required in accordance with

A.

Federal Regulations 40 CFR Part 112 Oil Pollution Act.

B.

The Joint Commission Utility Management standards.

C.

OSHA Regulations 1926.153 Liquefied Petroleum Gas Act.

D.

NFPA 430 Storage of Liquid and Solid Oxidizers.

Full Access
Question # 22

When a motor malfunctions on an air handler, what is the first step to be taken in the replacement of the motor?

A.

Megger the motor windings.

B.

Remove the motor/machine guard.

C.

Disconnect the power wiring.

D.

Initiate lockout/tagout procedures.

Full Access
Question # 23

A diesel emergency generator is rated at 500 KVA. When the generator is tested, the load on it is 220 KVA. According to the NFPA, the MINIMUM testing requirements are to run the unit

A.

monthly under load for 30 minutes.

B.

annually with supplemental loads for 2 hours.

C.

monthly until the water temperature and oil pressure have stabilized.

D.

annually with supplemental loads for 30 minutes.

Full Access
Question # 24

According to NFPA 70, what is the minimum working clearance required for enclosed electrical equipment with 600 volts or less?

A.

18 in.

B.

24 in.

C.

36 in.

D.

48 in.

Full Access
Question # 25

A visual indication that an electrical receptacle is hospital grade is that the receptacle

A.

has a label.

B.

is tamper-resistant.

C.

has a green dot.

D.

is red.

Full Access
Question # 26

In order to ensure a safe environment for patients, what department must be involved during the planning of all construction projects?

A.

Information Technology

B.

Biomedical Engineering

C.

Patient Services

D.

Infection Control

Full Access
Question # 27

Fire drills in healthcare occupancies shall include the

A.

evacuation of bedridden and infirmed patients to the adjacent smoke compartment.

B.

transmission of a fire alarm signal and audible alarms on each shift.

C.

transmission of the fire alarm signal and simulation of emergency fire conditions.

D.

evacuation of patients to areas of refuge and evacuation of staff from the building.

Full Access
Question # 28

In which type of boiler do the gases of combustion pass through tubes surrounded by water?

A.

water tube

B.

fire tube

C.

vertical tube

D.

cast iron sectional

Full Access
Question # 29

What is the required fire rating of a door in a 2-hour rated wall assembly?

A.

1/2 hour

B.

1 hour

C.

1 1/2 hours

D.

2 hours

Full Access
Question # 30

How many emergency management disaster drills are required per year in a healthcare occupancy?

A.

1

B.

2

C.

3

D.

4

Full Access
Question # 31

The time that materials or assemblies have withstood a fire exposure, as established in accordance with test procedures of NFPA 251, is referred to as the

A.

flame spread rating.

B.

fire resistance rating.

C.

fire assembly rating.

D.

fire protection rating.

Full Access
Question # 32

A high kW demand on a facility electrical consumption report is noted for a one-hour interval. Consumption is less than normal for the same interval. Which of the following could be the cause?

A.

high electric heat loads

B.

utilizing a generator to load shed

C.

equipment restart after a power interruption

D.

shutdown of a 1,000-ton chiller