Black Friday Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: mxmas70

Home > Construction Specifications Institute > CDT Certification > CDT

CDT Construction Documents Technologist Question and Answers

Question # 4

What activity helps the owner assess the viability of a project, evaluate financial resources, and understand the project's potential impact on the community?

A.

Schematic programming

B.

Site selection

C.

Due diligence investigation

D.

Master planning

Full Access
Question # 5

The names of the project, owner, architect/engineer and consultants, and the general project data such as a location map are normally included in which of the following?

A.

Sheet index

B.

Cover sheet

C.

General notes

D.

Building code summary

Full Access
Question # 6

Procedural requirements for alternates, project meetings, and submittals belong where?

A.

Divisions 02-49

B.

The general conditions

C.

The supplementary conditions

D.

Division 01

Full Access
Question # 7

As a project manager representing a private client, which of the following instances would best benefit from a constructability review meeting?

A.

The client is unfamiliar with this type of project.

B.

The project team consists of multiple new members.

C.

The site presents unusual challenges and constraints.

D.

The contractor is unable to commit to original schedule.

Full Access
Question # 8

In which project phase would outline specifications be created in order to be used as a checklist for further development of the project documents?

A.

Project Conception phase

B.

Schematic Design phase

C.

Design Development phase

D.

Construction Documents phase

Full Access
Question # 9

Who is responsible for planning, maintaining, and supervising construction safety measures and programs?

A.

Architect/engineer

B.

OSHA

C.

Owner's inspector

D.

Contractor

Full Access
Question # 10

What is the procedure for guarding against defects and deficiencies before and during the execution of the work?

A.

Quality assurance

B.

Quality control

C.

Quality management

D.

Quality monitoring

Full Access
Question # 11

What requirement is set by authority, custom, or general consensus that is also an established accepted criterion?

A.

Building code

B.

Quality control standard

C.

Reference standard

D.

Specification master

Full Access
Question # 12

Which team member is actively involved and interested in all phases of the project?

A.

Contractors

B.

Owners

C.

Architects/engineers

D.

Manufacturers/suppliers

Full Access
Question # 13

Cost classification, data organization, and specifications use which written formats?

A.

OmniClass and UniFormat

B.

UniFormat and MasterFormat

C.

OmniClass and MasterFormat

D.

SectionFormat® and MasterFormat

Full Access
Question # 14

The emphasis shifts from overall relationships and functions to more technical issues during which design phase?

A.

Preliminary design

B.

Schematic design

C.

Design development

D.

Construction documents

Full Access
Question # 15

Which of the following ensure that all systems work together effectively to meet the overall project performance goals?

A.

Total project commissioning

B.

Inspection by architect

C.

Safety testing

D.

Field testing

Full Access
Question # 16

How does the architect/engineer control the project cost when not enough information is available to make product decisions during the design phases of a project?

A.

Alternates

B.

Unit prices

C.

Contingencies

D.

Allowances

Full Access
Question # 17

According to standard general conditions, which of the following is true about shop drawings?

A.

They are contract documents.

B.

They illustrate some portion of the work.

C.

They are reviewed only by the architect/engineer.

D.

They include performance charts, instructions, and brochures.

Full Access
Question # 18

A facility manager needs to replace a broken insulated glazing unit in an existing facility. Which source would be most appropriate for determining where and how to order the new unit?

A.

Record drawings

B.

Manufacturer's representative

C.

Project manual

D.

Record submittals

Full Access
Question # 19

An architect/engineer wants to schedule monthly meetings with a contractor and owner to discuss matters pertinent to timely and successful completion of the work. Which type of meeting should they schedule?

A.

Workflow meeting

B.

Preinstallation meeting

C.

Progress meeting

D.

Schedule monitoring meeting

Full Access
Question # 20

The architect/engineer reviews submittals for which of the following reasons?

A.

To correct or change the design

B.

To monitor design conformance

C.

To review installation procedures

D.

To review substitution requests

Full Access
Question # 21

If the contractor discovers that a part of the contract documents is in violation of the building code, what should the contractor do?

A.

Notify the architect/engineer in writing

B.

Proceed with the work in accordance with the contract documents

C.

Request a variance from the building authority

D.

Stop all work until the issue is resolved

Full Access
Question # 22

Which term or word is appropriate to use in specification text?

A.

Any

B.

As per

C.

As required

D.

Work

Full Access
Question # 23

During the project closeout phase, what is an appropriate task for the facility manager?

A.

To ensure they have received the required spare parts, extra stock materials, and any necessary training needed in order to maintain the facility in the first year

B.

To coordinate with the architect a final clean-up and site restoration

C.

To hire a new security company to ensure maintenance and ground management

D.

To draft the final changes on the as-built documents

Full Access
Question # 24

Which entity maintains project record documents?

A.

Architect/engineer (A/E)

B.

Contractor

C.

Owner

D.

Owner or A/E

Full Access
Question # 25

During the schematic design phase, a contingency line item in the estimate would be included to cover which of the following?

A.

Allowances

B.

Unit prices

C.

Unknown factors

D.

Alternates

Full Access
Question # 26

Which of the following is an example of preconstruction submittals?

A.

Product data

B.

Shop drawings

C.

Schedule of values

D.

Warranty documentations

Full Access
Question # 27

Which of the following is a component of the contract documents?

A.

Procurement requirements

B.

Resource drawings

C.

Shop drawings

D.

Addenda

Full Access
Question # 28

Which documents are commonly included as procurement documents?

A.

Project record documents

B.

Contract documents

C.

Consensus documents

D.

Bidding documents

Full Access
Question # 29

There are over 3,500 different grades of steel. The amount of carbon, level of impurities, and additional elements all contribute to what grade steel is classified as in building projects. Therefore, which of the following is the method of specification writing used to limit lengthy descriptions of materials?

A.

American National Standards Institute (ANSI)

B.

Descriptive

C.

Performance

D.

Reference standard

Full Access
Question # 30

Within the context of the construction industry, what does BIM stand for?

A.

Building Information Modeling

B.

Business Information Manual

C.

Building Interior Maintenance

D.

Building Inspection Manual

Full Access
Question # 31

Which of the following participants is involved in the Integrated Project Delivery (IPD) method?

A.

Authority having jurisdiction

B.

Commissioning agent

C.

Contractor

D.

Inspector

Full Access
Question # 32

Which of the following is NOT a method of specifying?

A.

Perspective

B.

Proprietary

C.

Performance

D.

Reference standard

Full Access
Question # 33

Which document obligates the architect/engineer to review submittals during construction administration?

A.

AIA Document A201, General Conditions of the Contract for Construction

B.

AIA Document B101, Standard Form of Agreement Between Owner and Architect

C.

AIA Document D200, Project Checklist

D.

AIA Document G612, Owners Instructions to the Architect

Full Access
Question # 34

Which of the following statements best describes stakeholder and participant interest in a project?

A.

Participants have direct interest in the project while stakeholders have indirect interest

B.

Stakeholders have direct interest in the project while participants have indirect interest

C.

Both stakeholders and participants have direct interest in the project

D.

Both stakeholders and participants have indirect interest in the project

Full Access
Question # 35

You are working on a project that is subject to regulatory reviews both at the city and at the state level. Both agencies have acknowledged receiving the construction documents. This project has already been awarded to a general contractor, and you are representing the owner who wants to start construction immediately. How would you advise the owner?

A.

Construction may begin immediately as long as a safety manager is present, and the contractor avoids all excavation work until after the permits are issued.

B.

Since the state approval is more critical than the city approval, construction may proceed immediately after the state permits are issued.

C.

Since the city approval is more critical than the state approval, construction may proceed immediately after the city permits are issued.

D.

Construction may begin only after both city and state permits have been issued.

Full Access
Question # 36

During procurement activities, what is the process of notifying prospective or qualified bidders requesting proposals for a specific project or issuing an invitation to bid?

A.

Solicitation

B.

Instructions for Procurement

C.

Instructions to Bidders

D.

Request for Scope of Work

Full Access