Weekend Sale - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: mxmas70

Home > Exin > EPI Data Centre > CDCS

CDCS EXIN EPI Certified Data Centre Specialist Question and Answers

Question # 4

A data center is in an area where utility power is highly available—only a few outages per year, typically <1 hour per event and <50 hours/year not available. What type of generators should be installed?

A.

Continuous generators in at least N+1

B.

A combination of standby, prime, and continuous sized to 500% of the load

C.

Standby generators; no N+1 needed as the risk of a failure to start is negligible

D.

Standby generators, ideally in an N+1 configuration

Full Access
Question # 5

You need to determine the strategy for the cooling audit. All the servers are based on a front-to-rear (F-R) airflow design.

Which location for the temperature/humidity measurement should you recommend for the audit?

A.

At the back/rear of the server at 50 mm/2 inch

B.

At 1.5 meters/5 feet above the floor in the middle of the cold aisle

C.

At the front/intake of the server at 50 mm/2 inch

D.

At 1.5 meters/5 feet above the floor in the middle of the hot aisle

Full Access
Question # 6

Do you need to consider bullet (ballistic) protection when designing a data center?

A.

No; bullet protection is not a requirement of ANSI/TIA-942

B.

No, there is no reason for implementing bullet protection as you cannot predict the type of weapons that might be used

C.

Yes, but only when the data center is built in an area with a high criminality rate or with a risk of terrorist attacks

D.

Yes, bullet protection is a requirement of ANSI/TIA-942 for Rated-3/4 data centers

Full Access
Question # 7

The humidity in the computer room has changed from about 50% down to 35% Relative Humidity (RH).

What influence does this have on Electrostatic Discharge (ESD)?

A.

No influence as long as the temperature is at approximately 20°C/77°F

B.

Relative humidity has no influence on ESD

C.

ESD levels will go up

D.

ESD levels will go down

Full Access
Question # 8

EMF shielding material needs to be installed as EMF levels from the transformer room into the computer room are measured at 100 mG. The transformer room is ~10 meters away, separated by a corridor. Where should shielding be installed?

A.

It does not matter; either close to the transformer room or computer room is okay

B.

As close as possible to the transformer room

C.

As close as possible to the computer room

D.

Shielding is not required as 100 mG is within acceptable levels

Full Access
Question # 9

What mainly affects the cooling capacity of a raised floor tile?

A.

Type of ICT equipment, location of the air conditioner, pressure under the raised floor, allowable temperature in the hot aisle

B.

Relative humidity in the computer room, temperature of the cold air, pressure under the raised floor, construction material of the tile

C.

Percentage of the surface opening, obstruction of the supporting construction, pressure under the raised floor, damper construction

D.

Percentage of the surface opening, airflow direction of the ICT equipment, temperature difference between the air intake and air exhaust of the ICT equipment, construction material of the tile

Full Access
Question # 10

A sprinkler system employs automatic sprinklers attached to a piping system containing water and connected to a water supply so that water discharges immediately when a head opens. What is this called?

A.

Dry pipe system

B.

Deluge system

C.

Pre-action system

D.

Wet pipe system

Full Access
Question # 11

A data center requires an audit to find out whether it conforms with ANSI/TIA-942 Rated-3 (concurrently maintainable).

Will the network architecture be part of this audit?

A.

No, as concurrently maintainable only applies to electrical and mechanical (power and cooling).

B.

Yes, but only if the network administration does not comply with ANSI/TIA-606.

C.

Yes, amongst other aspects, the network architecture should be Rated-3 compliant with the requirements of ANSI/TIA-942.

D.

No, only the type of cabling used will be audited.

Full Access
Question # 12

Which standard defines the requirements for network administration?

A.

ISO/IEC 30129

B.

ANSI/TIA-568

C.

ASHRAE

D.

ANSI/TIA-606

Full Access
Question # 13

A 5kW (power consumption) server keeps crashing with the message 'temperature too high'.

The intake temperature is measured at 25 °C/77 °F and a relative humidity (RH) level of 50%.

The exhaust temperature is 29 °C/84 °F and 45% RH.

The raised floor is providing an adequate amount of CFM/CMH at a reasonable velocity.

The pressure under the raised floor is approximately 25 Pa/0.1 inch Hâ‚‚O.

Analyze the situation and indicate what the most likely cause is for this server to crash.

A.

Dust inside the server causing issues with convection-based heat transfer

B.

The exhaust temperature is exceeding the ASHRAE recommended values

C.

The raised floor pressure is too low and/or the raised floor tile % opening is not adequate

D.

No cause could be determined as the CFM/CMH of the air conditioning equipment is not stated

Full Access
Question # 14

A computer room needs to be fitted out with a gas-based fire suppression system. The computer room will be a high-density data center with about 30% of the racks being closed circuit cooling blade-center racks.

Should the supplier of the fire suppression system be informed on the design of the racks?

A.

No, cooling and design of racks have no influence on the fire suppression system design.

B.

Only when the rack height obstructs a potential fire suppression release point.

C.

Yes, the design of the racks has an influence on the fire suppression system design.

D.

Only when the racks might block access to the fire panel.

Full Access
Question # 15

Management requests a 15-minute battery bank at full UPS load. UPS specs:

    30 kVA, PF 0.8

    Battery 384 V (192 cells), end discharge 308 V

    Inverter PF 0.8, 400 V output

What information is missing to perform the calculation?

A.

UPS efficiency

B.

Inverter efficiency / output PF

C.

Load imbalance

D.

Available battery charging current

Full Access
Question # 16

You want to make cooling more effective by setting cold aisle temperature to 4 °C (39 °F). Is this acceptable?

A.

Yes, but only if cooling systems can maintain this continuously

B.

Yes, as long as dewpoint doesn’t go below -9 °C (16 °F)

C.

No, 4 °C (39 °F) is below the allowable ASHRAE range

D.

No, intake air must be exactly 20 °C (68 °F)

Full Access
Question # 17

Given: A = attenuation in dB, R = real measured value, M = maximum acceptable value. Which formula should be used to calculate the required attenuation factor of EMF shielding material?

A.

A = 10 log (R/M)

B.

A = 20 log (M/R)

C.

A = 10 log (M/R)

D.

A = 20 log (R/M)

Full Access
Question # 18

The pipes of a VESDA smoke detection system are installed at the air intake of the air conditioner inside the computer room.

Is this a good practice from an early smoke detection point of view?

A.

It depends on the type of gas-based fire suppression which will be installed.

B.

Yes, as this reduces the amount of piping to be installed in the data center, as all air will go through the air conditioner.

C.

No, the piping should be installed at the air exhaust of the air conditioner, as there can also be a fire inside the air conditioner itself.

D.

No, it will give a longer reaction time for the smoke detection system and there might also be bypass airflow.

Full Access
Question # 19

The data center has been in operation for about 1 year and 2 months. The dust levels in the computer room are relatively high.

What is the most likely root cause?

A.

The cleaning crew is not doing their work properly

B.

Every computer room has high dust levels due to constant high-speed air movement

C.

Low pressure in the computer room

D.

Floorboards are most likely not fitted correctly

Full Access
Question # 20

When installing a raised floor, can we use a spirit level bar to level the floor?

A.

Yes, spirit level bars can be used as long as their length is longer than 60 cm/2 ft (the size of a typical raised floor tile).

B.

No, because using a spirit level bar, a measurement error will be transferred from pedestal to pedestal.

C.

Yes, but spirit level bars can only be used in the vertical plane.

D.

Yes, using a spirit level bar for raised floors higher than 40 cm is preferred.

Full Access
Question # 21

What is a potential disadvantage of using water mist as a fire extinguishing system?

A.

It only uses 10% of the water normally used in a water-based fire suppression, which might not be enough to suppress the fire

B.

It will rapidly increase the humidity level in the data center, which can cause a potential risk for the operation of the equipment

C.

It extracts oxygen from the air creating a potential risk for humans inside the computer room

D.

It has droplets that are too small (100-120 microns) so it can only be used for small fires

Full Access
Question # 22

A computer room is fitted with a hypoxic-based fire suppression system. On what principle does it work?

A.

It removes the heat from the fire

B.

It lowers the oxygen levels in the room

C.

It removes the fuel from the fire

D.

It uses water as an extinguisher

Full Access
Question # 23

Which class of UPS is ideal for data centers?

A.

VFD (Voltage and Frequency Dependent)

B.

VI (Voltage Independent)

C.

VFI (Voltage and Frequency Independent)

D.

First class

Full Access
Question # 24

The UPS of a data center, with an ANSI/TIA-942 Rating-4, is installed with the rectifier connected to power feed A and the bypass/reserve line input connected to power feed B.

To which feed will the output of the UPS be synchronized?

A.

The UPS will not synchronize to any of the feeds but use an internal clock to set the output voltage and frequency

B.

Depends on the setting of the UPS, as the UPS can normally be set to either feed

C.

Feed A

D.

Feed B

Full Access
Question # 25

Do you need to consider bullet (ballistics) protection when designing a data center?

A.

Bullet (ballistics) protection is required by ANSI/TIA-942 for all data centers.

B.

Bullet (ballistics) protection is only required when the data center is located in an area with a high crime rate.

C.

Bullet (ballistics) protection is required by ANSI/TIA-942 for data centers Rated 3/4.

D.

Bullet (ballistics) protection is only required if the facility is a potential target or the building is in the vicinity of a potential target.

Full Access
Question # 26

What should you consider when using raised floor tiles with air deflectors or louvers?

A.

Tiles with air deflectors or louvers can be very heavy.

B.

Tiles with air deflectors or louvers will reduce the cooling capacity of the tile.

C.

Tiles with air deflectors or louvers do not allow for a flexible cooling solution.

D.

Tiles with air deflectors or louvers can only be used to cool storage equipment.

Full Access
Question # 27

It is assumed that EMF shielding material must be installed as the EMF levels coming from the transformer room into the computer room are measured at 100mG. The transformer room is approximately 10 meters away from the computer room and is separated by a corridor. You can assume that no physical issues are present for installing shielding material at any area/location.

Where should you recommend the shielding material to be installed?

A.

As close as possible to the computer room

B.

As close as possible to the transformer room

C.

It does not matter, either close to the transformer room or the computer room is okay as there is no impact to cost or shielding material performance

D.

Shielding is not required to be installed as 100mG is within the acceptable levels for computer rooms

Full Access
Question # 28

Management has requested a 15-minute battery bank assuming full load on the UPS. The UPS vendor has provided the following specifications of the UPS:

•Rated power: 30 kVA

•Rectifier input voltage: 400 V/3 phase

•Rectifier input power factor: 0.8

•Battery rated voltage: 384 V

•Number of cells: 192

•End of discharge voltage: 308 V

•Inverter output voltage: 400 V/3 phase

•Inverter output power factor: 0.8

What information is missing to perform the battery calculation?

A.

UPS efficiency

B.

Inverter efficiency

C.

Load imbalance on the phases

D.

Available battery charging current

Full Access
Question # 29

Which of the following statements is correct?

A.

With current increasing, single-phase cables emit more EMF than three-phase cables

B.

With current decreasing, three-phase cables emit more EMF than single-phase cables

C.

With voltage increasing, single-phase cables emit more EMF than three-phase cables

D.

With voltage decreasing, three-phase cables emit more EMF than single-phase cables

Full Access
Question # 30

An air-conditioner unit needs to be selected. Two types are available:

Unit-A has a Sensible Heat Ratio (SHR) of 0.7.

Unit-B has a Sensible Heat Ratio (SHR) of 0.9.

From an efficiency point of view, which one should be selected?

A.

It does not matter, as the Sensible Heat Ratio has nothing to do with efficiency.

B.

Not relevant, as Sensible Heat Ratio is only specified for air-conditioner equipment to indicate the ratio between intake temperature and exhaust temperature.

C.

Unit A

D.

Unit B

Full Access
Question # 31

Should aerosol cleaning solutions be used in the computer room?

A.

No, unless leak detection installed

B.

No, it will contaminate the room

C.

Yes, only if room smells bad

D.

Yes, if not connected to power

Full Access
Question # 32

You want to manage temperature and humidity only at the facility level in your data center. All servers use front-to-rear airflow. Which location for measurement should you recommend?

A.

At the back/rear of the server at 50 mm (2 in)

B.

At 1.5 m (5 ft) above the floor, 0.4 m (15 in) in front of the rack

C.

At the front/intake of the server at 50 mm (2 in)

D.

At 1.5 m (5 ft) above the floor, 0.4 m (15 in) at the back of the rack

Full Access
Question # 33

A data center is located in an area where the demand for power is higher than the utility power company is able to deliver. This results in frequent power outages and, therefore, power shedding (scheduled/controlled power shutdown for areas) is frequently applied. The mains power is more than 650 hours/year not available.

What type of generators should be installed?

A.

Standby generators should be installed in at least an N+1 configuration

B.

Continuous generators should be installed, at least in an N+1 configuration

C.

A combination of standby-, prime-, and continuous-generators, as the duration of the power outage is unpredictable. The total available capacity of the generators should be at least 500% of the data center load

D.

Continuous generators should be installed; no N+1 configuration is needed as the generators will run all the time

Full Access
Question # 34

In which stage of the data center life cycle does commissioning take place?

A.

Retire

B.

Operate/optimize

C.

Implement

D.

Design

Full Access
Question # 35

From the options indicated, what is the correct starting point for the raised floor installation?

A.

Point A

B.

Point B

C.

Point C

D.

Point D

Full Access
Question # 36

The logical overview of the data center looks as pictured. To what TIA-942 Rating is this design made based on electrical only?

A.

Rating - 4

B.

Rating - 3

C.

Rating - 2

D.

Rating - 1

Full Access