A data center is in an area where utility power is highly available—only a few outages per year, typically <1 hour per event and <50 hours/year not available. What type of generators should be installed?
You need to determine the strategy for the cooling audit. All the servers are based on a front-to-rear (F-R) airflow design.
Which location for the temperature/humidity measurement should you recommend for the audit?
Do you need to consider bullet (ballistic) protection when designing a data center?
The humidity in the computer room has changed from about 50% down to 35% Relative Humidity (RH).
What influence does this have on Electrostatic Discharge (ESD)?
EMF shielding material needs to be installed as EMF levels from the transformer room into the computer room are measured at 100 mG. The transformer room is ~10 meters away, separated by a corridor. Where should shielding be installed?
A sprinkler system employs automatic sprinklers attached to a piping system containing water and connected to a water supply so that water discharges immediately when a head opens. What is this called?
A data center requires an audit to find out whether it conforms with ANSI/TIA-942 Rated-3 (concurrently maintainable).
Will the network architecture be part of this audit?
A 5kW (power consumption) server keeps crashing with the message 'temperature too high'.
The intake temperature is measured at 25 °C/77 °F and a relative humidity (RH) level of 50%.
The exhaust temperature is 29 °C/84 °F and 45% RH.
The raised floor is providing an adequate amount of CFM/CMH at a reasonable velocity.
The pressure under the raised floor is approximately 25 Pa/0.1 inch Hâ‚‚O.
Analyze the situation and indicate what the most likely cause is for this server to crash.
A computer room needs to be fitted out with a gas-based fire suppression system. The computer room will be a high-density data center with about 30% of the racks being closed circuit cooling blade-center racks.
Should the supplier of the fire suppression system be informed on the design of the racks?
Management requests a 15-minute battery bank at full UPS load. UPS specs:
30 kVA, PF 0.8
Battery 384 V (192 cells), end discharge 308 V
Inverter PF 0.8, 400 V output
What information is missing to perform the calculation?
You want to make cooling more effective by setting cold aisle temperature to 4 °C (39 °F). Is this acceptable?
Given: A = attenuation in dB, R = real measured value, M = maximum acceptable value. Which formula should be used to calculate the required attenuation factor of EMF shielding material?
The pipes of a VESDA smoke detection system are installed at the air intake of the air conditioner inside the computer room.
Is this a good practice from an early smoke detection point of view?
The data center has been in operation for about 1 year and 2 months. The dust levels in the computer room are relatively high.
What is the most likely root cause?
When installing a raised floor, can we use a spirit level bar to level the floor?
What is a potential disadvantage of using water mist as a fire extinguishing system?
A computer room is fitted with a hypoxic-based fire suppression system. On what principle does it work?
The UPS of a data center, with an ANSI/TIA-942 Rating-4, is installed with the rectifier connected to power feed A and the bypass/reserve line input connected to power feed B.
To which feed will the output of the UPS be synchronized?
Do you need to consider bullet (ballistics) protection when designing a data center?
What should you consider when using raised floor tiles with air deflectors or louvers?
It is assumed that EMF shielding material must be installed as the EMF levels coming from the transformer room into the computer room are measured at 100mG. The transformer room is approximately 10 meters away from the computer room and is separated by a corridor. You can assume that no physical issues are present for installing shielding material at any area/location.
Where should you recommend the shielding material to be installed?
Management has requested a 15-minute battery bank assuming full load on the UPS. The UPS vendor has provided the following specifications of the UPS:
•Rated power: 30 kVA
•Rectifier input voltage: 400 V/3 phase
•Rectifier input power factor: 0.8
•Battery rated voltage: 384 V
•Number of cells: 192
•End of discharge voltage: 308 V
•Inverter output voltage: 400 V/3 phase
•Inverter output power factor: 0.8
What information is missing to perform the battery calculation?
An air-conditioner unit needs to be selected. Two types are available:
Unit-A has a Sensible Heat Ratio (SHR) of 0.7.
Unit-B has a Sensible Heat Ratio (SHR) of 0.9.
From an efficiency point of view, which one should be selected?
You want to manage temperature and humidity only at the facility level in your data center. All servers use front-to-rear airflow. Which location for measurement should you recommend?
A data center is located in an area where the demand for power is higher than the utility power company is able to deliver. This results in frequent power outages and, therefore, power shedding (scheduled/controlled power shutdown for areas) is frequently applied. The mains power is more than 650 hours/year not available.
What type of generators should be installed?
In which stage of the data center life cycle does commissioning take place?
From the options indicated, what is the correct starting point for the raised floor installation?
The logical overview of the data center looks as pictured. To what TIA-942 Rating is this design made based on electrical only?