Applying FIDIC Silver Book (edition 1999), which one of the following elements shallnotform part of the time Programme/revised programme?
A new important feature of the FIDIC Yellow and Silver Books (edition 2017) is the inclusion of the default position that the Works or relevant part of the Works designed by the Contractor shall be fit for their ordinary purposes. Is this statement true or false?
Under FIDIC Red and Yellow Books (edition 2017), which two of the following elements shall form part of the revised programme?
Choose all of the correct answers (multiple possibilities)
You are the Contract Manager of the Contractor in a building project. The Contract has been awarded to your firm, but the Engineer has not been selected. The Contract Agreement states that the Commencement Date shall be notified by the Engineer, which must be done within 14 days after the signing of the Contract Agreement. The Employer requested your firm to commence works on the 14th day after signing the Contract Agreement. Your director, Y, wants to wait with commencing the works until the Engineer has been selected or until the 42 days since the date your firm receives Letter of Acceptance. Is Y correct?
Which of the following form a Contractor's entitlement, in case the Contractor does not receive an interim payment within the allocated contractual deadline for payment? (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).
Under the FIDIC Red and Yellow Books (edition 1999), which two of the following statements are correct regarding the issuance of Interim Payment by the Engineer?
(Choose all correct answers — multiple possibilities)
When does discharge become effective under the FIDIC Red Book (edition 1999)? (1 correct answer applies)
A Contractor under the FIDIC Silver Book (edition 1999) has not been able to finish the Works within the Time for Completion as mentioned in the Contract and has overrun the Time for Completion by 3 months. This results in a significant claim of $4,500,000 from the Employer. The Employer has submitted this claim to the Contractor according to the procedures as mentioned in the Contract. The Contractor asks you for advice and refers to Clause 8. Which one of the following statements is NOT true?
In a drafted FIDIC Silver Book (edition 1999), the following sentence has been added to Sub-Clause 3.5:
"In case of an Instruction regarding a pending or proposed Variation, Contractor shall carry out any determination regardless of a possible notice of dissatisfaction."
What GP(s) is/are breached?
In a construction project using the FIDIC Silver Book (edition 1999), if the Parties prefer the dispute board to be appointed on an "ad-hoc" basis instead of as a standing Dispute Avoidance and Adjudication Board (DAAB), what is it called? (1 correct answer applies)
The FIDIC Books are evolutions of earlier contract models, and although the different versions of a specific model are not the same, familiarity in definitions and structure makes it easier to work with different FIDIC books as well as with their different editions.
Is this statement true or false?
Which two statements are correct regarding the FIDIC Red Book (edition 2017)?
You are the Contract Manager of the Engineer and person Y is the Contract Manager of the Employer in a construction project under FIDIC 2017 Red Book. The project is late in schedule and Y has issued Employer's claim on Delay Damages. You have asked Y to consider whether the Contractor's delay to completion is a reflection of cash-flow shortfall from interim payments before making deductions to the Contractor's payment. Y replied that even if the Contractor pays Delay Damages to the Employer, the Contractor is still obliged to complete the Works and is not relieved from its duties and obligations. You warned Y of the risks of further reduction of cash-flow by the deduction of Delay Damages from payments. As this could worsen the situation of the Contractor, leading to further delays to the completion of the Works. Who is right?
Which one of the following statements is correct regarding the Employer's Representative under the FIDIC Silver Book (edition 1999)?
Which of the following documents form part of a FIDIC Construction Contract ["Red Book" (1999)], hence, to be drafted and included among the Tender Documents? (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).
Which two of the following statements are correct regarding the dayworks under FIDIC Red, Yellow, and Silver Books (both editions)?
Choose all of the correct answers (multiple possibilities).
You are the Contract Manager of the Engineer in a hotel project. In May 2020, the Employer and the Contractor signed a Contract based on the FIDIC Yellow Book (edition 2017), as per which the Contractor will design and build a hotel project with Contract Price of 5,100,000 USD. The Time for Completion for this project is 12 months (May 2021). The Contract also named a nominated Subcontractor (as referred to in Sub-Clause 4.5) who provides mechanical, electrical, and plumbing services for the project (including the fire fighting system), which was accepted by the Contractor without any discussions.
The Project was delayed due to issues with the fire fighting system, and you issued the Taking-Over Certificate in June 2022.
The Employer sent a Notice of Claim to the Contractor on Delay Damages with a maximum value equal to 10% of Contract Price (510,000 USD). The Employer also gave a Notice to the Contractor stating that the Contractor has failed to submit the evidence of payment to the nominated Subcontractor as well as the reason for withholding payment to the nominated Subcontractor. Therefore, the Employer has paid the nominated Subcontractor directly the entire amount due, coming to 100,000 USD. The Employer intends to include this amount as a deduction in the Final Payment to the Contractor.
As Contract Manager of the Engineer, you are tasked to make a fair determination of the Notices of the Employer. In your "Notice of the Engineer's determination", what is your determination for the deduction of the next Interim Payment to the Contractor in relation to the amount directly paid to the nominated Subcontractor?
You are the Contract Manager for the Engineer in a hotel project using FIDIC Red Book (edition 1999). The Employer demands perfection in the project's design and construction quality. There are many Variations initiated by the Employer during construction. Which one of the following is NOT considered as a Variation?
Which of the following statements are not correct? [2017 Edition]
Choose all of the correct answers (multiple possibilities).
Which two of the following statements are correct regarding Dispute under the FIDIC Red, Yellow, and Silver Books (edition 2017)?
Choose all of the correct answers (multiple possibilities)
Under the FIDIC Red Book (edition 1999): the Contractor submitted Final Statement in accordance with the Contract and the Contractor wants to correct it. Can the Contractor correct the Final Statement?
The procurement process of a project executed based on any FIDIC Contract model is exactly the same in terms of definitions, time and steps, which makes it universal and more easy to use worldwide. Is this statement true or false?
Which of the following cases will allow the Employer to claim under the Performance Security? [2017 Edition] (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).
Under the FIDIC Red and Yellow Books (edition 1999): if the Engineer gives an instruction which requires the Employer's prior approval, the Contractor is required to verify whether the Engineer has obtained the Employer's prior approval or not. Is this statement true or false?
You are the Contract Manager of the Engineer in a condominium project under FIDIC Yellow Book (edition 2017), with Time for Completion of 5 months.
The Contractor received a Letter of Acceptance on 1 May 2022. The Contract Agreement was signed on 1 June 2022. The Contract Agreement states that the Commencement Date shall be notified by the Engineer, but it shall be no later than 14 days after the signing of the Contract Agreement, subject to the issuance of the construction permit.
1 July 2022 is the first day the Engineer was at Site. On the same day, the Engineer issued a Notice to the Contractor that the Commencement Date shall be 15 July 2022. However, the construction permit was issued only on 1 August 2022.
The Project was completed on 1 December 2022. After completion, the Employer submitted a claim for Delay Damages. Following consultations, the Parties could not reach agreement on the Commencement Date.
What is the correct Commencement Date?
You are the Contract Manager of the Employer's Representative in a Thermal Power Plant Project. The Contract for this project is EPC Turnkey Contract using the FIDIC Silver Book (edition 2017) with a Contract Price of 28 million USD. The Employer's Requirements require that: "the Contractor design in accordance with international and national technical regulations, and standards, [etc.]".
For piling works, the Employer's Requirements state that the Contractor will design according to a specific national standard for piling works NTS-PW-01. After all piles for the jetty have been installed, a pile load test on lateral bearing capacity shows that actual lateral bearing capacity is much lower than the calculated lateral bearing capacity. It was later revealed by the Technical Standard Committee that there was a typo mistake during preparation of the NTS-PW-01 (translated from a foreign standard). The lateral bearing capacity of installed piles had been substantially overestimated as a result of this typo. Contractor submits a claim for 200,000 USD regarding extra costs for installing additional piles as a result of errors in the Employer's Requirements.
In the hydrological information of Site Data provided by the Employer, the annual high water level is 4.0m. However, during the design stage, with updated data from local stations along the rivers, the Contractor found out there was a mistake in the calculation. The annual high water level should be 4.5m. As a result, the Contractor has to design and build additional flood walls along the river to protect the Plant from flooding. The Contractor claims an amount of 300,000 USD to construct the flood wall, based on Unforeseeable difficulties.
As the Employer's Representative, after you have consulted with both Parties but failed to reach agreement, you will make a fair determination of the Claims of the Contractor.
In your "Notice of the Employer's Representative's determination", what is your determination for the Contractor?