Question # 4

Applying FIDIC Silver Book (edition 1999), which one of the following elements shallnotform part of the time Programme/revised programme?

A.

The intended order of the works.

B.

The sequence and timing of inspections and tests.

C.

The remedial work (if any) instructed under Sub-Clause 7.6.

D.

Review periods under Sub-Clause 5.2.

Full Access
Question # 5

A new important feature of the FIDIC Yellow and Silver Books (edition 2017) is the inclusion of the default position that the Works or relevant part of the Works designed by the Contractor shall be fit for their ordinary purposes. Is this statement true or false?

A.

True

B.

False

Full Access
Question # 6

Under FIDIC Red and Yellow Books (edition 2017), which two of the following elements shall form part of the revised programme?

Choose all of the correct answers (multiple possibilities)

A.

All internationally recognized holiday periods.

B.

The actual progress to date, any delay to such progress and the effects of such delay on other activities (if any).

C.

The sequence and timing of the remedial work.

D.

Only the delivery dates of Plant and Materials which have not been delivered on Site yet.

Full Access
Question # 7

You are the Contract Manager of the Contractor in a building project. The Contract has been awarded to your firm, but the Engineer has not been selected. The Contract Agreement states that the Commencement Date shall be notified by the Engineer, which must be done within 14 days after the signing of the Contract Agreement. The Employer requested your firm to commence works on the 14th day after signing the Contract Agreement. Your director, Y, wants to wait with commencing the works until the Engineer has been selected or until the 42 days since the date your firm receives Letter of Acceptance. Is Y correct?

A.

Yes

B.

No

Full Access
Question # 8

Which of the following form a Contractor's entitlement, in case the Contractor does not receive an interim payment within the allocated contractual deadline for payment? (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

A.

Right after the expiry of the payment deadline, the Contractor may terminate the contract.

B.

If the payment is not made within the time period required, after the expiry of such period, from the next day onwards, the Contractor is entitled to suspend all his/her activities on Site.

C.

In case the Employer paid the Contractor late, the Contractor becomes entitled to receive financing charges applying the % included in the Contract Data (if this is not stated, then applying the percentage as included under the corresponding Sub-Clause).

D.

The Contractor is entitled to suspend the works or reduce the rate of progress of the work, after giving a due Notice (21 days) about this intention.

E.

Beyond receiving the financing charges, the Contractor has no further entitlements in such a case.

Full Access
Question # 9

Under the FIDIC Red and Yellow Books (edition 1999), which two of the following statements are correct regarding the issuance of Interim Payment by the Engineer?

(Choose all correct answers — multiple possibilities)

A.

The Employer is bound by the Certificate issued by the Engineer, and must make payment in full, except for any compensation arising from any claim which the Employer may have against the Contractor.

B.

The Employer is not bound by the Certificate issued by the Engineer.

C.

The Employer is bound by the Certificate issued by the Engineer and must make payment in full, irrespective of any entitlement to compensation arising from any claim which the Employer may have against the Contractor.

D.

If the Employer considers itself entitled to claim against the Contractor, notice and particulars must first be submitted under Sub-Clause 2.5. The Employer's entitlement is then to be agreed or determined by the Engineer, and then, incorporated as a deduction in a Payment Certificate.

Full Access
Question # 10

When does discharge become effective under the FIDIC Red Book (edition 1999)? (1 correct answer applies)

A.

When the Contractor receives full payment certified through the Final Payment Certificate.

B.

When the Contractor receives its Performance Security from the Employer.

C.

When the Contractor receives full payment certified through the Final Payment Certificate and return of the Performance Security.

D.

When the Employer counter signs a discharge notice as issued by the Contractor, following full payment and return of the Performance Security.

Full Access
Question # 11

A Contractor under the FIDIC Silver Book (edition 1999) has not been able to finish the Works within the Time for Completion as mentioned in the Contract and has overrun the Time for Completion by 3 months. This results in a significant claim of $4,500,000 from the Employer. The Employer has submitted this claim to the Contractor according to the procedures as mentioned in the Contract. The Contractor asks you for advice and refers to Clause 8. Which one of the following statements is NOT true?

A.

If there are Variations agreed between the Contractor and the Employer, the Contractor should check if an adjustment for Time for Completion was part of any of these Variations.

B.

The root cause of the delay has to be determined by the Contractor, thereby especially verifying if the cause of the delay lies in a delay caused by the Authorities.

C.

In addition to the delay damages as mentioned in Sub-Clause 2.5, the Employer has the right to claim any extra costs it has to make due to the delay, as delay damages are not seen as compensation for costs incurred by the Employer, but only as an incentive for the Contractor to perform on time.

D.

If the delay is entirely caused by the Employer having instructed the Contractor to suspend progress during the Works, while the cause of the suspension is not the responsibility of the Contractor, the claim for delay damages was wrongfully issued.

Full Access
Question # 12

In a drafted FIDIC Silver Book (edition 1999), the following sentence has been added to Sub-Clause 3.5:

"In case of an Instruction regarding a pending or proposed Variation, Contractor shall carry out any determination regardless of a possible notice of dissatisfaction."

What GP(s) is/are breached?

A.

GP1 only

B.

GP3 only

C.

GP1 and GP3

D.

GP1, GP2 and GP3

Full Access
Question # 13

In a construction project using the FIDIC Silver Book (edition 1999), if the Parties prefer the dispute board to be appointed on an "ad-hoc" basis instead of as a standing Dispute Avoidance and Adjudication Board (DAAB), what is it called? (1 correct answer applies)

A.

Ad-hoc DAAB

B.

DAB

C.

Ad-hoc DB

D.

Ad-hoc arbitration

Full Access
Question # 14

The FIDIC Books are evolutions of earlier contract models, and although the different versions of a specific model are not the same, familiarity in definitions and structure makes it easier to work with different FIDIC books as well as with their different editions.

Is this statement true or false?

A.

True

B.

False

Full Access
Question # 15

Which two statements are correct regarding the FIDIC Red Book (edition 2017)?

A.

Words and expressions stated in Sub-Clause 1.1 Definitions do not apply in respect of Specifications and Drawings.

B.

Contract Data contains information which is required by certain Sub-Clauses in the General Conditions.

C.

There is never a difference in effect whether in the Particular Conditions when the term "Works" is used, or when the term "works" is used.

D.

In some cases, if a certain information is not provided in the Contract Data, the relevant Sub-Clause shall not be applicable.

Full Access
Question # 16

You are the Contract Manager of the Engineer and person Y is the Contract Manager of the Employer in a construction project under FIDIC 2017 Red Book. The project is late in schedule and Y has issued Employer's claim on Delay Damages. You have asked Y to consider whether the Contractor's delay to completion is a reflection of cash-flow shortfall from interim payments before making deductions to the Contractor's payment. Y replied that even if the Contractor pays Delay Damages to the Employer, the Contractor is still obliged to complete the Works and is not relieved from its duties and obligations. You warned Y of the risks of further reduction of cash-flow by the deduction of Delay Damages from payments. As this could worsen the situation of the Contractor, leading to further delays to the completion of the Works. Who is right?

A.

Both you and Y are both correct.

B.

You are correct, Y is wrong.

C.

You are wrong, Y is correct.

D.

Both you and Y are wrong.

Full Access
Question # 17

Which one of the following statements is correct regarding the Employer's Representative under the FIDIC Silver Book (edition 1999)?

A.

The Representatives of both the Employer and the Engineer have no authority to amend the Contract at all.

B.

The Employer may appoint an Employer's Representative to act on his behalf under the Contract.

C.

The Employer must always appoint an Employer's Representative to act on his behalf under the Contract.

D.

The Employer may appoint an Employer's Representative to act on his behalf under the Contract but has to consult the Contractor to agree to this Representative.

Full Access
Question # 18

Which of the following documents form part of a FIDIC Construction Contract ["Red Book" (1999)], hence, to be drafted and included among the Tender Documents? (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

A.

Schedule of Guarantees

B.

Bill of Quantities

C.

Employer's Requirements

D.

Schedule of Baselines

E.

Specifications

Full Access
Question # 19

Which two of the following statements are correct regarding the dayworks under FIDIC Red, Yellow, and Silver Books (both editions)?

Choose all of the correct answers (multiple possibilities).

A.

If a Daywork Schedule is not included in the Contract, the Sub-Clause related to dayworks shall not apply.

B.

The dayworks related Sub-Clause is also applicable to other types of works.

C.

The dayworks related Sub-Clause is only used for remeasurement in the FIDIC Red Book (both editions) only.

D.

The Engineer (or the Employer in case of FIDIC Silver Book) may instruct that "a Variation shall" be executed on a daywork basis.

Full Access
Question # 20

You are the Contract Manager of the Engineer in a hotel project. In May 2020, the Employer and the Contractor signed a Contract based on the FIDIC Yellow Book (edition 2017), as per which the Contractor will design and build a hotel project with Contract Price of 5,100,000 USD. The Time for Completion for this project is 12 months (May 2021). The Contract also named a nominated Subcontractor (as referred to in Sub-Clause 4.5) who provides mechanical, electrical, and plumbing services for the project (including the fire fighting system), which was accepted by the Contractor without any discussions.

The Project was delayed due to issues with the fire fighting system, and you issued the Taking-Over Certificate in June 2022.

The Employer sent a Notice of Claim to the Contractor on Delay Damages with a maximum value equal to 10% of Contract Price (510,000 USD). The Employer also gave a Notice to the Contractor stating that the Contractor has failed to submit the evidence of payment to the nominated Subcontractor as well as the reason for withholding payment to the nominated Subcontractor. Therefore, the Employer has paid the nominated Subcontractor directly the entire amount due, coming to 100,000 USD. The Employer intends to include this amount as a deduction in the Final Payment to the Contractor.

As Contract Manager of the Engineer, you are tasked to make a fair determination of the Notices of the Employer. In your "Notice of the Engineer's determination", what is your determination for the deduction of the next Interim Payment to the Contractor in relation to the amount directly paid to the nominated Subcontractor?

A.

The Employer is entitled to deduct the amount directly paid.

B.

The Employer is not entitled to deduct the amount directly paid.

Full Access
Question # 21

You are the Contract Manager for the Engineer in a hotel project using FIDIC Red Book (edition 1999). The Employer demands perfection in the project's design and construction quality. There are many Variations initiated by the Employer during construction. Which one of the following is NOT considered as a Variation?

A.

The Contractor submits a Value Engineering proposal, in which it proposed to change the colour of the outdoor paint. The Engineer approved the proposal.

B.

The Engineer instructs a change in slopes of stairs to the parking lot with an Instruction in accordance with Sub-Clause 3.3.

C.

The Engineer requests a proposal regarding a change in type of windows and doors of the business centre.

D.

The Employer verbally instructs a change in the layout of the rooftop restaurant. The Engineer issued an Instruction describing the required change with revised design drawings.

Full Access
Question # 22

Which of the following statements are not correct? [2017 Edition]

Choose all of the correct answers (multiple possibilities).

A.

The Contractor or the Engineer can request a meeting.

B.

Only the Engineer can call for a meeting

C.

Subcontractors cannot attend management or progress meetings unless the Engineer's approval is obtained.

D.

Only the Employer can call for a meeting.

E.

The Engineer shall keep records of the Progress Meetings.

Full Access
Question # 23

Which two of the following statements are correct regarding Dispute under the FIDIC Red, Yellow, and Silver Books (edition 2017)?

Choose all of the correct answers (multiple possibilities)

A.

In case the Engineer refuses to issue a Performance Certificate or to issue one with a correct date under Sub-Clause 11.9, and the Contractor has disagreed with the requested entitlement or relief in connection with this refusal, Dispute shall be deemed to have arisen.

B.

If a Party is dissatisfied with the determination and has given Notice of Dissatisfaction (NOD) to the other party within a strict 28-day time limit, a Dispute arises and either Party may proceed under Sub-Clause 21.4 to obtain a DAAB decision on it.

C.

The Dispute must be submitted to the Dispute Avoidance and Adjudication Board (DAAB) within 42 days, otherwise the NOD is deemed to have lapsed and is no longer valid.

D.

Both 'Disagreement' and 'Dispute' are defined terms under the Conditions of Contract.

Full Access
Question # 24

Under the FIDIC Red Book (edition 1999): the Contractor submitted Final Statement in accordance with the Contract and the Contractor wants to correct it. Can the Contractor correct the Final Statement?

A.

Yes

B.

No

Full Access
Question # 25

The procurement process of a project executed based on any FIDIC Contract model is exactly the same in terms of definitions, time and steps, which makes it universal and more easy to use worldwide. Is this statement true or false?

A.

True

B.

False

Full Access
Question # 26

Which of the following cases will allow the Employer to claim under the Performance Security? [2017 Edition] (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

A.

The Contractor failed to renew the Tender Security.

B.

The Contractor abandons the Works and the Employer did not issue Notice of termination.

C.

The Employer had submitted a claim under Sub-Clause 20.2.

D.

The Engineer had issued instruction to replace part of the Works.

E.

The Contractor failed to extend the validity of the Performance Security.

Full Access
Question # 27

Under the FIDIC Red and Yellow Books (edition 1999): if the Engineer gives an instruction which requires the Employer's prior approval, the Contractor is required to verify whether the Engineer has obtained the Employer's prior approval or not. Is this statement true or false?

A.

True

B.

False

Full Access
Question # 28

You are the Contract Manager of the Engineer in a condominium project under FIDIC Yellow Book (edition 2017), with Time for Completion of 5 months.

The Contractor received a Letter of Acceptance on 1 May 2022. The Contract Agreement was signed on 1 June 2022. The Contract Agreement states that the Commencement Date shall be notified by the Engineer, but it shall be no later than 14 days after the signing of the Contract Agreement, subject to the issuance of the construction permit.

1 July 2022 is the first day the Engineer was at Site. On the same day, the Engineer issued a Notice to the Contractor that the Commencement Date shall be 15 July 2022. However, the construction permit was issued only on 1 August 2022.

The Project was completed on 1 December 2022. After completion, the Employer submitted a claim for Delay Damages. Following consultations, the Parties could not reach agreement on the Commencement Date.

What is the correct Commencement Date?

A.

12 June 2022

B.

15 June 2022

C.

15 July 2022

D.

1 August 2022

Full Access
Question # 29

You are the Contract Manager of the Employer's Representative in a Thermal Power Plant Project. The Contract for this project is EPC Turnkey Contract using the FIDIC Silver Book (edition 2017) with a Contract Price of 28 million USD. The Employer's Requirements require that: "the Contractor design in accordance with international and national technical regulations, and standards, [etc.]".

For piling works, the Employer's Requirements state that the Contractor will design according to a specific national standard for piling works NTS-PW-01. After all piles for the jetty have been installed, a pile load test on lateral bearing capacity shows that actual lateral bearing capacity is much lower than the calculated lateral bearing capacity. It was later revealed by the Technical Standard Committee that there was a typo mistake during preparation of the NTS-PW-01 (translated from a foreign standard). The lateral bearing capacity of installed piles had been substantially overestimated as a result of this typo. Contractor submits a claim for 200,000 USD regarding extra costs for installing additional piles as a result of errors in the Employer's Requirements.

In the hydrological information of Site Data provided by the Employer, the annual high water level is 4.0m. However, during the design stage, with updated data from local stations along the rivers, the Contractor found out there was a mistake in the calculation. The annual high water level should be 4.5m. As a result, the Contractor has to design and build additional flood walls along the river to protect the Plant from flooding. The Contractor claims an amount of 300,000 USD to construct the flood wall, based on Unforeseeable difficulties.

As the Employer's Representative, after you have consulted with both Parties but failed to reach agreement, you will make a fair determination of the Claims of the Contractor.

In your "Notice of the Employer's Representative's determination", what is your determination for the Contractor?

A.

The Contractor is not entitled to either of the Claims.

B.

The Contractor is entitled to the Claim for additional costs in relation to the piling, based on errors in the Employer's Requirement only.

C.

The Contractor is entitled to the Claim for the additional flood wall based on Unforeseeable difficulties only.

D.

The Contractor is entitled to both Claims.