During the project life cycle for a major product, a stakeholder asked to add a new feature. Which document should they consult for guidance?
During project execution, a team member has identified and then analyzed an opportunity that
will yield a net saving of 10% and reduce time in the schedule by 20%
Which strategy should the project manager adopt to accommodate this opportunity?
The following is a network diagram for a project.
The critical path for the project is how many days in duration?
All testing on a project has been performed successfully and all acceptance criteria have been met. What is the next step?
If a project manager effectively manages project knowledge, a key benefits is that:
Projects programs subsidiary portfolios.... objectives refer to?
Projects, programs, subsidiary portfolios, and operations managed as a group to achieve strategic objectives refers to?
What specific quality considerations should be examined while completing Quality Management plan?
The project has a current cost performance index of 0.80. Assuming this performance wi continue, the new estimate at completion is $1000. What was the original budget at completion for the project?
Which of the following is a set of interrelated actions and activities performed to achieve a prespecified product, result, or service?
In agile projects while performing scope management. What is the definition of requirements
A project manager oversees a project in an adaptive environment. After each iteration, which type of meeting should the project manager conduct?
Which index is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal?
Which of the following is an input to Direct and Manage Project Execution?
A company has implemented an adaptive project management framework for a new project. When planning for an iteration, how should risks be addressed? Choose two.
Which project management process is used by the project manager to ensure that stakeholders receive timely and relevant information?
Change requests are an output from which Project Integration Management process?
Which process is engaged when a project team member makes a change to project budget with project manager's approval
Which of the following activities are included as part of a project manager's responsibilities?
What important qualities should project managers possess for strategic and business management?
What risk response strategy involves removing high- risk scope elements from a project?
What process in Project Schedule Management identifies and documents specific actions to be performed to produce a project’s deliverables?
A project manager should consider the impact of project..............manager following
A project manager should consider the impact of project decisions on supporting and maintaining the product along with project results Which process is the project manager following?
Considering a highly dynamic project environment, which approach should the project manager adopt to manage the project team?
Which of the following investigates the likelihood that each specific risk will occur?
Which items are an output of the Perform Integrated Change Control process?
The following is a network diagram for a project.
How many possible paths are identified for this project?
A recently hired project manager is looking for templates to use for projects on which they will work. To what category of enterprise environmental factors should the project manager refer?
A project manager can choose from several techniques to resolve conflicts between team members. Which technique can result in a win-win solution?
A work package has been scheduled to cost $1,000 to complete and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed. What is the cost variance?
A business manager wants to start a project to launch a new product and submits a business case to the Portfolio Steering Committee for review. The committee asks the manager for details about the expected business value of the project.
How can the manager document the business value for the Portfolio Steering Committee?
A project team is working on a new driverless vehicle and is organizing a workshop with experts to analyze the data received from the prototype. Who should the project manager invite to provide expert advice?
What earned value (EV) measure indicates the cost efficiency of the work completed?
Which of the following lists represents the outputs of the Monitor Communications process?
The degree of uncertainty an entity is willing to take on in anticipation of a reward is known as its risk:
A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the deliverable in a timely manner. This issue could have been avoided if they had created and followed a:
Which project manager competency is displayed through the knowledge, skills, and behaviors related to specific domains of project, program, and portfolio management?
A company must implement sales software because it is opening a new branch in a foreign market. Although this software is used in every domestic branch, multiple changes are expected during the implementation because It is a foreign location.
Which type of life cycle would the project manager use in this case?
What is the process of ensuring that project resources are assigned and available?
A project manager has reached an agreement on the requirements and now needs to define the workflow for the end user. A critical step must be completed and validated by the end user before proceeding.
Which modeling tool best describes this process?
A project manager is reviewing the change requests for project documents, deliverables, and the project plan. In which project management process does this review belong?
What quantitative risk analysis technique is used to select the optimum course of action from a number of alternatives?
Which action should the project manager take after the team finishes executing the scope?
Which of the following is an example of an organizational system that is arranged based on the job being performed?
With regard to a project manager's sphere of influence in a project, which of the following does the project manager influence most directly?
Which two of the following can be used as communication tools between the business analyst and the rest of the project team? (Choose two)
Which component of the project management plan should be updated if a change occurs?
Which is a list of organizational systems that may have an impact on a project?
Which of the following documents ate created as part of Project Integration Management?
What can increase the complexity of the Manage Stakeholder Engagement process?
Which statement about identification and engagement of stakeholders during a project is correct?
Which of the following is an example of an internal factor that influences the outcome of the project?
Which of the following tools or techniques is used for Estimate Activity Durations?
The Agile principle "welcome changing requirement, even late in development" relates to which agile manifesto?
Which is an example of leveraging evolving trends and emerging practices in Project Integration Management?
If you are using an Ishikawa diagram to determine the root cause of problems, which process are you engaged in?
In which of the Risk Management processes is the project charter used as an input?
The project management plan requires the acquisition of a special part available from a supplier located abroad. Which source selection method is being used?
The features and functions that characterize a result, product, or service can refer to:
Which Control Stakeholder Engagement tool or technique allows the project manager to consolidate and facilitate distribution of reports?
Due to today's competitive global market, organizations require more than technical project management skills. Which of the following skills can support long-range strategic objectives that contribute to the bottom line?
In an adaptive or agile life cycle, how are the customer and sponsor involved in the project scope management activities?
Which of the following is an input to the Perform Qualitative Risk Analysis process?
A complete set of concepts, terms, and activities that make up an area of specialization is known as:
The cost baseline and project funding requirements are outputs of which process in Project Cost Management?
What is the discipline that focuses on the interdependences between projects to determine the optimal approach for managing them?
What conflict resolution technique involves delaying the issue or letting others resolve it?
Which process involves subdividing project deliverables and project work into smaller, more manageable portions?
A project manager needs to tailor the Project Cost Management process. Which considerations should the project manager apply?
Stakeholder identification and engagement should begin during what phase of the project?
A project manager is reporting the project performance as 25 days worth of work completed against 13 days originally planned. What is the schedule variance (SV)?
When a project is undertaken to reduce defects in a product or service, the objective of the project is to create a/an:
What type of meeting is held to discuss prioritized product backlog items?
Which is the best way for a project manager to ensure efficient and frequent communication with management and stakeholders in an agile/adaptive environment?
Responsible, accountable, consult and inform (RACI) is an example of which of the following?
The project manager is dividing the project scope into smaller pieces, and repeating this process until no more subdivisions are required. At this point the project manager is able to estimate costs and activities for each element.
What are these elements called?
Once the make-or-buy analysis is completed, which document defines the project delivery method?
A project manager Is addressing risks and potential concerns related to stakeholder management, and Is clarifying and resolving previously Identified issues. In which process is the project manager engaged?
Status of deliverables, implementation status for change requests, and forecasted estimates to complete are examples of:
What should a project manager use to determine how much money is needed to complete a project?
Which of the following is used as an input to prepare a cost management plan?
Which type of dependency is legally or contractually required or inherent in the nature of work and often involves physical limitations?
Which document describes the necessary information to determine if a project is worth the required investment?
Which Define Activities output extends the description of the activity by identifying the multiple components associated with each activity?
Which stakeholder classification model groups stakeholders based on their level of authority and their active involvement in the project?
What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?
The project manager notes that stakeholders are aware of the project and potential impacts and are actively engaged in ensuring that the project is a success. The engagement level of the stakeholders should be classified as:
Which type of analysis systemically gathers and analyzes qualitative and quantitative information to determine which interests should be taken into account throughout the project?
At which point of the project is the uncertainty the highest and the risk of failing the greatest?
Which tool and technique identifies inefficient and ineffective policies, processes, and procedures?
The individual or group that provides resources and support for a project and is accountable for success is the:
What type of project structure is a hierarchically organized depiction of the resources by type?
While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery. What is the MOST appropriate approach to managing this situation?
An adaptive team is in the process of merging a legacy system from an acquired company. In order to check the project status and manage the flow of work, they are using a scrum board for this project. What data should be included in this information radiator?
The component of the human resource management plan that includes ways in which team members can obtain certifications that support their ability to benefit the project is known as:
Which basic quality tool is most useful when gathering attributes data in an inspection to identify defects?
An intentional activity to modify a nonconforming product or product component is called:
Which process involves determining, documenting, and managing stakeholders' needs and requirements to meet project objectives?
Which Manage Communications tool or technique focuses on identifying and managing barriers?
Technical capability, past performance, and intellectual property rights are examples of:
The component of the risk management plan that documents how risk activities will be recorded is called:
Funding limit reconciliation is a tool and technique of which Project Cost Management process?
Impacts to other organizational areas, levels of service, and acceptance criteria are typical components of which document?
Which quality tool incorporates the upper and lower specification limits allowed within an agreement?
The following chart contains information about the tasks in a project.
Based on the chart, what is the cost performance index (CPI) for Task 2?
The Project Human Resource Management process that involves confirming human resource availability and obtaining the team necessary to complete project activities is:
Variance and trend analysis is a tool and technique used in which process?
Organizational theory is a tool used in which Project Human Resource Management process?
Which conflict resolution technique searches for solutions that bring some degree of satisfaction to all parties in order to temporarily or partially resolve the conflict?
Change requests are processed for review and disposition according to which process?
A project manager managing a cross-cultural virtual project team across several time zones should be concerned about the impacts of which communication technology factor?
What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the earned value (EV) is $50?
Which process involves the creation of a document that provides the project manager with the authority to apply resources to a project?
Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?
An issue log is an input to which Project Human Resource Management process?
When does the project team determine which dependencies are discretionary?
Skills necessary for project management such as motivating to provide encouragement; listening actively; persuading a team to perform an action; and summarizing, recapping, and identifying next steps are known as:
Which tool or technique of the Define Activities process allows for work to exist at various levels of detail depending on where it is in the project life cycle?
The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule is known as:
During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?
Which quality management and control tool is useful in visualizing parent-to-child relationships in any decomposition hierarchy that uses a systematic set of rules that define a nesting relationship?
The following is a network diagram for a project.
What is the critical path for the project?
The process of confirming human resource availability and obtaining the team necessary to complete project activities is known as:
A projects purpose or justification, measurable project objectives and related success criteria, a summary milestone schedule, and a summary budget are all components of which document?
Documented identification of a flaw in a project component together with a recommendation is termed a:
A tool and technique used during the Perform Qualitative Risk Analysis process is:
The degree, amount, or volume of risk that an organization or individual will withstand is known as its risk:
Retreating from an actual or potential conflict or postponing the issue to be better prepared or to be resolved by others describes which of the five general techniques for managing conflict?
Which type of risk diagram is useful for showing time ordering of events?
Based on the following metrics: EV= $20,000, AC= $22,000, and PV= $28,000, what is the project CV?
Which of the following correctly explains the term "progressive elaboration'?
In which domain of project management would a Pareto chart provide useful information?
The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline is:
Which type of estimating is used to improve the accuracy of an activity's duration?
Which technique is commonly used for the Perform Quantitative Risk Analysis process?
The process of monitoring the status of the project to update project progress and manage changes to the schedule baseline is:
In which process is a project manager identified and given the authority to apply resources to project activities?
In which type of organizational structure are staff members grouped by specialty?
Configuration identification, configuration status accounting, and configuration verification and audit are all activities in which process?
Payback period, return on investment, internal rate of return, discounted cash flow, and net present value are all examples of:
Which of the following are processes associated with Project Cost Management?
Which type of project management office (PMO) supplies templates, best practices, and training to project teams?
Which Plan Schedule Management tool or technique may involve choosing strategic options to estimate and schedule the project?
Organizational process assets, a lessons-learned database, and historical information are all inputs to which process?
The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?
Processes in the Planning Process Group are typically carried out during which part of the project life cycle?
The following is a network diagram for a project.
The free float for Activity E is how many days?
A team is working on a project using an adaptive approach. During project execution, the project gets delayed by one month due to an unforeseen risk. What should the team do next to deliver this project?
A project sponsor has asked the project manager to determine how soon the project can be completed. Which of the following methods can a project manager use to find this information?
Which of the following project documents is an input to the Control Scope process?
What process is used to identify quality requirements and/or standards for a project and its deliverables'?
Conditions that are not under the control of the project team that influence, direct, or constrain a project are called:
The ability to influence cost is greatest during which stages of the project?
Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?
The methodology that combines scope, schedule, and resource measurements to assess project performance and progress is known as:
Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?
Which Process Group and Knowledge Area include the Sequence Activities process?
Which Define Activities tool or technique is used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts?
Which process involves defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive plan?
Which tools or techniques are used in the Plan Schedule Management process?
In the Plan Procurement Management process, which source selection criteria analyzes if the seller's proposed technical methodologies, techniques, solutions, and services meet the procurement documents requirements?
Which of the following are an enterprise environmental factor that can influence the Identify Risks process?
The group technique that enhances brainstorming with a voting process used to rank the most useful ideas for prioritization is called the:
Which tool or technique can a project manager use to select in advance a team member who will be crucial to the task?
Which type of contract is a hybrid of both a cost-reimbursable and a fixed-price contract?
At which stage of team development do members begin to work together, adjust work habits, and trust each other?
When cost variance is negative and schedule variance is positive, the project is:
In which type of contract are the performance targets established at the onset and the final contract price determined after completion of all work based on the sellers performance?
Which type of dependency is contractually required or inherent in the nature of the work?
Market conditions and published commercial information are examples of which input to the Estimate Costs process?
Prototype development may be used as a tool for which of the following risk response strategies?
Who determines which dependencies are mandatory during the Sequence Activities process?
In a construction project schedule, what is the logical relationship between the delivery of the concrete materials and the pouring of concrete?
The milestone list is an input to which process from the Planning Process Group?
Which of the following strategic considerations often results in project authorization?
The risk management team of a software project has decided that due to the lack of adequate talent in the company, development of a specific part of the system is under high risk, so the team has decided to outsource it. This is an example of which risk response?
Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen?
Who provides the inputs for the original estimates of activity durations for tasks on the project plan?
It’s time to perform code review on a software project that has over three million lines of code written. Which management tool should the project manager use?
The table represents the possible durations of a specific project task.
Using the three-point estimating technique what is the expected number of days it should take to complete the task?
In a demonstration meeting with a customer, the project team presented deliverables that were considered ready for customer use. The team based the results on a checklist of all the required criteria for the project.
Which of the following elements is the team using?
Why is working in iterations usually more time consuming than using a predictive life cycle?
In one of the project meetings during a project execution, a new stakeholder attends and highlights a new risk. What should the project manager do next?
In the project charter process, which three of the following are discussed during meetings held with stakeholders? (Choose three) D Cost
Which can be used to convert a verified deliverable to an accepted deliverable?
Which three of the following are key traits of a project leader? (Choose three)
What should a project manager consider to address the full delivery life cycle for large projects?
Which of the following set of elements is part of an effective communications management plan?
According to the PMI Talent Triangle. leadership skills relate to the ability to:
The project manager is distributing project communications, collecting and storing project information, and retrieving documents when required. In which process is the project manager involved?
Under which circumstances should multiple projects be grouped in a program?
In a large organization, with projects of different types and sizes, what kind of approach or method would be best to use?
Which of the following must be included in the risk register when the project manager completes the Identify Risks process?
How should a project manager plan communication for a project which has uncertain requirements?
Which of the following is a conflict resolution technique that emphasizes areas of agreement rather than areas of difference?
Which of the following Project Communication Management processes uses performance reports as an input?
A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?
What risk technique is used to quantify the probability and impact of risks on project objectives?
What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?
The project manager is working in the processes of Project Resource Management. Which process is the project manager developing if they are using parametric estimation?
A team was hired to develop a next generation drone. The team created a prototype and sent it to the customer for testing. The feedback collected was used to refine the requirements. What technique is the team using?
Which components of the project management plan are inputs used when creating the stakeholder engagement plan?
The project manager is using co-location and providing training to the project team. On which of the following Project Resource Management processes is the project manager working?
A project manager is launching an information system to provide a lessons learned database. This action is necessary for recipients to access content at their own discretion. Which communication method is described?
A method of obtaining early feedback on requirements by providing a working model of the expected product before actually building is known as:
Job satisfaction, challenging work, and sufficient financial compensation are values related to which interpersonal skill?
A project manager should communicate to stakeholders about resolved project issues by updating the:
The following chart contains information about the tasks in a project.
Based on the chart, what is the schedule performance index (5PI) for Task 4?
Which key interpersonal skill of a project manager is defined as the strategy of sharing power and relying on interpersonal skills to convince others to cooperate toward common goals?
Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?
Define Activities and Estimate Activity Resources are processes in which project management Knowledge Area?
Which type of analysis is used as a general management technique within the Plan Procurements process?
Which of the following statements is true regarding project and product lifecycles?
During which process would stakeholders provide formal acceptance of the completed project scope?
The key benefit of the Monitoring and Controlling Process Group is the ability to:
A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what type of contract?
Which of the following reduces the probability of potential consequences of project risk events?
Which activity involves ensuring that the composition of a projects configuration items is correct?
Which of the following types of a dependency determination is used to define the sequence of activities?
In which process might a project manager use risk reassessment as a tool and technique?
Which input provides suppliers with a clear set of goals, requirements, and outcomes?
Which document defines how a project is executed, monitored and controlled, and closed?
The planned work contained in the lowest level of work breakdown structure (WBS) components is known as:
Which process numerically analyzes the effect of identified risks on overall project objectives?
Which schedule compression technique has phases or activities done in parallel that would normally have been done sequentially?
What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur is very high (0.80)?
Which of the following consists of the detailed project scope statement and its associatedWBSand WBS dictionary?
Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?
Which of the following is a tool and technique for Estimate Activity Durations?
Sharing good practices introduced or implemented in similar projects in the organization and/or industry is an example of:
As part of a mid-project evaluation, the project sponsor has asked for a forecast of the total project cost. What should be used to calculate the forecast?
The most commonly used type of precedence relationship in the precedence diagramming method (PDM) is:
Which group creativity technique asks a selected group of experts to answer questionnaires and provide feedback regarding the responses from each round of requirements gathering?
An electronics firm authorizes a new project to develop a faster, cheaper, and smaller laptop after improvements in the industry and electronics technology. With which of the following strategic considerations is this project mainly concerned?
A collection of projects managed as a group to achieve strategic objectives is referred to as a:
Which Process Group's purpose is to track, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes?
Which process is included in the Project Integration Management Knowledge Area?
What is the name of a graphic display of project team members and their reporting relationships?
Which action should a project manager take to ensure that the project management plan is effective and current?
In an organization with a projectized organizational structure, who controls the project budget?
Which estimating technique uses the actual costs of previous similar projects as a basis for estimating the costs of the current project?
What is the name of the statistical method that helps identify which factors may influence specific variables of a product or process under development or in production?
Which of the following statements correctly characterizes pull communication?
Which tools or techniques will a project manager use for Develop Project Team?
Which of the seven basic quality tools is especially useful for gathering attributes data while performing inspections to identify defects?
The process of formalizing acceptance of the completed project deliverables is known as:
The formal and informal interaction with others in an organization industry, or professional environment is known as:
A procurement management plan is a subsidiary of which other type of plan?
What is the number of stakeholders, if the project has 28 potential communication channels?
Which Develop Schedule tool and technique produces a theoretical early start date and late start date?
While preparing the project management plan on a weekly basis, the project manager indicates the intention to provide an issues report to the staff via e-mail. In which part of the plan will this type of information be included?
Which of the following is a tool or technique used in the Determine Budget process?
The contract in which the seller is reimbursed for all allowable costs for performing the contract work and then receives a fee based upon achieving certain performance objectives is called a:
Which process is responsible for monitoring the status of the project and product scope and managing changes to the scope baseline?
When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:
Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?
Which of the following includes how requirements activities will be planned, tracked, and reported?
Which type of diagram includes groups of information and shows relationships between factors, causes, and objectives?
Which of the following response strategies are appropriate for negative risks or threats?
The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost performance index?
The technique of subdividing project deliverables into smaller, more manageable components until the work and deliverables are defined to the work package level is called:
Activity cost estimates are quantitative assessments of the probable costs required to:
The process improvement plan details the steps for analyzing processes to identify activities which enhance their:
The processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project has been undertaken to achieve are grouped within which Process Group?
The initial development of a Project Scope Management plan uses which technique?
In the basic communication model, which term refers to the method that is used to convey the message?
Using the three-point estimating technique, if the most likely duration is four months, the optimistic duration is two months, and the pessimistic duration is one year, how many months is the expected activity duration?