A change log for communications can be used to communicate to the appropriate stakeholders that there are changes:
Which enterprise environmental factors are considered during Estimate Costs?
Which of the following risk response strategies involves allocating ownership of a positive risk to a third party?
The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule is known as:
Which process involves aggregating the estimated costs of the individual schedule activities or work packages?
Which of the following investigates the likelihood that each specific risk will occur?
The process of formalizing acceptance of the completed project deliverables is known as:
Which tools or techniques will a project manager use for Develop Project Team?
Work performance information and cost forecasts are outputs of which Project Cost Management process?
The basis of identification for current or potential problems to support later claims or new procurements is provided by:
A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:
Which input to the Plan Risk Management process provides information on high-level risks?
What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?
The definition of when and how often the risk management processes will be performed throughout the project life cycle is included in which risk management plan component?
Which stakeholder classification model groups stakeholders based on their level of authority and their active involvement in the project?
Which document defines how a project is executed, monitored and controlled, and closed?
Which of the following change requests can bring expected future performance of the project work in line with the project management plan?
The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?
Configuration identification, configuration status accounting, and configuration verification and audit are all activities in which process?
The process of confirming human resource availability and obtaining the team necessary to complete project activities is known as:
A project manager managing a cross-cultural virtual project team across several time zones should be concerned about the impacts of which communication technology factor?
Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a project?
Which process identifies whether the needs of a project can best be met by acquiring products, services, or results outside of the organization?
Which tool or technique is used to manage change requests and the resulting decisions?
Which input may influence quality assurance work and should be monitored within the context of a system for configuration management?
The only Process Group that comprises processes that typically occur from the beginning to the end of the project life cycle is:
A project manager providing information to the right audience, in the right format, at the right time is an example of which type of communication?
Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?
Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements?
Which Plan Schedule Management tool or technique may involve choosing strategic options to estimate and schedule the project?
Which process determines the risks that may affect the project and documents their characteristics?
Which tool or technique is used in the Perform Integrated Change Control process?
A large portion of a projects budget is typically expended on the processes in which Process Group?
Which item is an output of Plan Quality Management and an input to Perform Quality Assurance?
The process of prioritizing risks for further analysis or action is known as:
Change requests are processed for review and disposition according to which process?
A project manager builds consensus and overcomes obstacles by employing which communication technique?
The review of a sellers progress toward achieving the goals of scope and quality within cost and schedule compared to the contract is known as:
Which Process Group and Knowledge Area include the Sequence Activities process?
External organizations that have a special relationship with the enterprise and provide specialized expertise are called:
The process of identifying and documenting relationships among the project activities is known as:
When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?
A technique used to determine the cause and degree of difference between baseline and actual performance is:
Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?
Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend analysis are examples of which tool or technique?
Directing another person to get from one point to another using a known set of expected behaviors and the ability to lead a team and inspire them to do their jobs well is related to?
A new project has been set. Four main stakeholders besides the project manager and four other team members have been identified. How many communication channels are available?
What is the project manager's responsibility in Project Integration Management?
A project is in progress and about to move to a different phase, according to the plan. This will be a good opportunity for the project manager to:
In the basic communication model, which term refers to the method that is used to convey the message?
Which type of contract is a hybrid of both a cost-reimbursable and a fixed-price contract?
The technique of subdividing project deliverables into smaller, more manageable components until the work and deliverables are defined to the work package level is called:
Lessons learned are created and project resources are released in which Process Group?
The project manager is using co-location and providing training to the project team. On which of the following Project Resource Management processes is the project manager working?
The initial development of a Project Scope Management plan uses which technique?
Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?
A project manager at a publishing company decides to initiate the editing phase of the project as soon as each chapter is written. Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start relationship with a 15-day delay?
Due to today's competitive global market, organizations require more than technical project management skills. Which of the following skills can support long-range strategic objectives that contribute to the bottom line?
Which action should the project manager take after the team finishes executing the scope?
A project manager is launching an information system to provide a lessons learned database. This action is necessary for recipients to access content at their own discretion. Which communication method is described?
A project reports an earned value (EV) of USS45 for work completed with an actual cost (AC) of US$40. What is the cost performance index (CPI)?
A project manager has just completed several brainstorming sessions and has gathered the data to show commonality and differences in one single place. What technique was followed?
Which group of inputs will a project manager use during the Monitor Stakeholder Engagement process?
The project manager is creating the communications management plan Which group of inputs Is required to begin?
Which of the following are processes associated with Project Cost Management?
How can a project manager determine if the project activities comply with organizational and project policies, processes, and procedures?
The project leam is brainstorming on approaches to deliver the upcoming product launch for which the project has been chartered. The project manager is laying out hybrid, adaptive, iterative methods. What is the team trying to address?
Which components of the project management plan are inputs used when creating the stakeholder engagement plan?
The procurement requirements for a project include working with several vendors. What should the project manager take into consideration during the Project Procurement Management processes?
A functional manager is delegating a key project to a project team without a project manager. Which communication method will be most effective?
A project manager uses their networking skills to build agreement with a difficult stakeholder. What level of influence did the project manager apply?
In which Project Cost Management process is work performance data included?
During the planning phase, a project manager must create a work breakdown structure (WBS) to improve management of the project's components. What should be included in the WBS?
Stakeholder identification and engagement should begin during what phase of the project?
Which type of estimating is used to improve the accuracy of an activity's duration?
What charts and (igures should project managers use during the Perform Quantitative Risk Analysis process?
A project manager Is addressing risks and potential concerns related to stakeholder management, and Is clarifying and resolving previously Identified issues. In which process is the project manager engaged?
A project manager is reviewing the change requests for project documents, deliverables, and the project plan. In which project management process does this review belong?
Once the make-or-buy analysis is completed, which document defines the project delivery method?
When developing the project schedule, a project manager uses decomposition and rolling wave planning techniques in this process.
Under which circumstances should multiple projects be grouped in a program?
A project stakeholder is requesting changes to the project plan. Which process group addresses this?
A project team submits a weekly progress report to the project manager. The project manager consolidates the same report and sends a complete progress report to the stakeholders. What is this an example of?
Given the following information.
Activity A takes one week.
Activity B takes three weeks.
Activity C takes two weeks.
Activity D takes five weeks.
Activity A starts at the same time as Activity B.
Activity C follows Activity B and Activity A.
Activity D follows Activity C.
How long will it take to complete the project?
What type of meeting is held to discuss prioritized product backlog items?
Which process is engaged when a proiect learn inember makes a change to project budget with the project manager's approval?
During which process of Project Cost Management does a project manager produce the cost baseline?
A project manager is searching for solutions that bring some degree of satisfaction to all parties in order to temporarily resolve a conflict. What conflict management technique is described in this situation?
Which of the following is used to classify stakeholders based on their assessments of power, urgency, and legitimacy?
Deciding the phases of a project life cycle would be considered a part of which of these knowledge areas?
A project using the agile/adaptive approach has reached the Project Integration Management phase. What is the project manager's key responsibility during this phase?
In which sphere of influence is the project manager demonstrating the value of project management and advancing the efficacy of the project management office (PMO)?
During the execution phase of a project a detect is found. The project manager takes responsibility and with the correct documentation, begins the task necessary to repair the defect. What process was applied?
Which of the following must be included in the risk register when the project manager completes the Identify Risks process?
An important project stakeholder has low risk tolerance. Which type ot communication should a project manager use to provide this stakeholder with a difficult update?
Which degree of authority does a project manager have on a project in a strong matrix organizational structure?
Which project manager competency is displayed through the knowledge, skills, and behaviors related to specific domains of project, program, and portfolio management?
A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what type of contract?
Which of the following statements is true regarding project and product lifecycles?
In which type of organizational structure are staff members grouped by specialty?
Which technique is commonly used for the Perform Quantitative Risk Analysis process?
Project contracts generally fall into which of the following three broad categories?
Which standard has interrelationships to other project management disciplines such as program management and portfolio management?
Which of the following types of a dependency determination is used to define the sequence of activities?
Changes to formally controlled documentation, plans, etc. to reflect modified or additional ideas or content are known as:
The process of monitoring the status of the project to update project progress and manage changes to the schedule baseline is:
What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?
When calculating the cost of quality (COQ) for a product or service, money spent for cost of conformance would include the areas of:
How is the schedule variance calculated using the earned value technique?
In which process might a project manager use risk reassessment as a tool and technique?
As the project progresses, which of the following is routinely collected from the project activities?
Which of the following Process Groups covers all nine Project Management Knowledge Areas?
A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?
Define Activities and Estimate Activity Resources are processes in which project management Knowledge Area?
What process is used to identify quality requirements and/or standards for a project and its deliverables'?
What risk response strategy involves removing high- risk scope elements from a project?
Which type of analysis is used as a general management technique within the Plan Procurements process?
The project manager needs to review the templates in use. The templates are part of the:
In which domain of project management would a Pareto chart provide useful information?
A project has an estimated duration of 10 months with a total budget of US$220,000. At the end of the fifth month, it is estimated that at completion, the project will incur US$250,000. If the actual cost (AC) calculated is US$150,000, what is the earned value (EV) of the project?
Match each dimension of the communications management plan to its corresponding focus.
Which Process Group contains those processes performed to define a new project?
Funding limit reconciliation is a tool and technique of which Project Cost Management process?
A method to manage stakeholder expectations in the scope statement is to clearly:
In a construction project schedule, what is the logical relationship between the delivery of the concrete materials and the pouring of concrete?
Which type of elaboration allows a project management team to manage at a greater level of detail as the project evolves?
Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?
Which of the following is an example of the simplest fixed-price contract?
Which can be used to determine whether a process is stable or has predictable performance?
Which of the following correctly explains the term "progressive elaboration'?
Which process involves identifying and documenting the logical relationships between project activities?
Control charts, flowcharting, histograms, Pareto charts, and scatter diagrams are tools and techniques of which process?
Which type of management focuses on ensuring that projects and programs are reviewed to prioritize resource allocation?
Which cost estimate technique includes contingencies to account for cost uncertainty?
When addressing roles and responsibilities,which item ensures that the staff has the skills required to complete project activities?
Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?
Which of the following tools and techniques is used in the Verify Scope process?
Those who enter into a contractual agreement to provide services necessary for a project are:
A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the deliverable in a timely manner. This issue could have been avoided if they had created and followed a:
A complete set of concepts, terms, and activities that make up an area of specialization is known as:
Which Manage Communications tool or technique focuses on identifying and managing barriers?
Which type of probability distribution is used to represent uncertain events such as the outcome of a test or a possible scenario in a decision tree?
Which items are an output of the Perform Integrated Change Control process?
Processes in the Initiating Process Group may be completed at the organizational level and be outside of the project's:
Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?
For a stakeholder with low interest and high power, the project manager should:
The following is a network diagram for a project.
The total float for the project is how many days?
Which quality tool may prove useful in understanding and estimating the cost of quality in a process?
Which type of organizational structure is displayed in the diagram provided?
Which process involves determining, documenting, and managing stakeholders' needs and requirements to meet project objectives?
A risk that arises as a direct result of implementing a risk response is called a:
The process of defining how the project scope will be validated and controlled is known as:
A special type of bar chart used in sensitivity analysis for comparing the relative importance of the variables is called a:
A projects purpose or justification, measurable project objectives and related success criteria, a summary milestone schedule, and a summary budget are all components of which document?
Which Control Stakeholder Engagement tool or technique allows the project manager to consolidate and facilitate distribution of reports?
Power, urgency, and legitimacy are attributes of which stakeholder classification model?
Which of the following is a strategy to deal with positive risks or opportunities?
The process of monitoring the status of the project and product scope as well as managing the changes to the scope baseline is known as:
Which enterprise environmental factors may influence Plan Schedule Management?
Retreating from an actual or potential conflict or postponing the issue to be better prepared or to be resolved by others describes which of the five general techniques for managing conflict?
The degree, amount, or volume of risk that an organization or individual will withstand is called risk:
A full-time project manager with low to moderate authority and part-time administrative staff is working in an organizational structure with which type of matrix?
The following is a network diagram for a project.
The free float for Activity E is how many days?
Which type of dependency used in the Sequence Activities process is sometimes referred to as preferred logic, preferential logic, or soft logic?
Plan Communications Management develops an approach and plan for project communications based on stakeholders' needs and requirements and:
An issue log is an input to which Project Human Resource Management process?
The following chart contains information about the tasks in a project.
Based on the chart, what is the cost performance index (CPI) for Task 2?
Stakeholder communication requirements should be included as a component of:
Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?
Funding limit reconciliation is a tool and technique used in which process?
Exhibit A is an example of which of the following types of Sequence Activities?
Which of the following are an enterprise environmental factor that can influence the Identify Risks process?
Which Process Group contains the processes performed to complete the work defined in the project management plan to satisfy the project specifications?
Activity cost estimates are quantitative assessments of the probable costs required to:
Which tool or technique can a project manager use to select in advance a team member who will be crucial to the task?
How should a stakeholder who is classified as high power and low interest be grouped in a power/interest grid during stakeholder analysis?
Identify Stakeholders is the process of identifying all of the people or organizations impacted by the project and documenting relevant information regarding their interests in, involvement in, and impact on the project:
Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?
Which process is responsible for monitoring the status of the project and product scope and managing changes to the scope baseline?
The item that provides more detailed descriptions of the components in the work breakdown structure (WB5) is called a WBS:
Which of the following response strategies are appropriate for negative risks or threats?
The component of the human resource management plan that includes ways in which team members can obtain certifications that support their ability to benefit the project is known as:
When the business objectives of an organization change, project goals need to be:
The following chart contains information about the tasks in a project.
Based on the chart, what is the schedule performance index (5PI) for Task 4?
Which process is conducted from project inception through completion and is ultimately the responsibility of the project manager?
A project manager requesting industry groups and consultants to recommend project intervention is relying on:
The methodology that combines scope, schedule, and resource measurements to assess project performance and progress is known as:
The following is a network diagram for a project.
What is the critical path for the project?
A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?
Stakeholders can be identified in later stages of the project because the Identify Stakeholders process should be:
One of the key benefits of the Plan Human Resource Management process is that it:
Which Define Activities tool or technique is used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts?
Which of the following is an input to the Develop Project Charter process?
The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost performance index?
The process to ensure that appropriate quality standards and operational definitions are used is:
Who determines which dependencies are mandatory during the Sequence Activities process?
Which of the following is a tool or technique used in the Acquire Project Team process?
Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen?
The group technique that enhances brainstorming with a voting process used to rank the most useful ideas for prioritization is called the:
The project management processes are usually presented as discrete processes with defined interfaces, while in practice they:
Requirements documentation, requirements management plan, and requirements traceability matrix are all outputs of which process?
Processes in the Planning Process Group are typically carried out during which part of the project life cycle?
Which characteristic defines the Delphi technique of group decision-making?
Which of the following activities are included as part of a project manager's responsibilities?
During the execution of a predicted project, the need for a new product feature has been proposed by the customer. What should the project manager do next?
In a demonstration meeting with a customer, the project team presented deliverables that were considered ready for customer use. The team based the results on a checklist of all the required criteria for the project.
Which of the following elements is the team using?
A project manager is reviewing a past project with similar.... team choosing for tailoring?
A project manager is reviewing a past project with similar requirements to the project that is currently chartered. The project team decided to adopt quality tools, techniques and templates recommended at the organizational level after reviewing the lessons learned of the previous project What specific area of quality, is the project team choosing for tailoring?
The table represents the possible durations of a specific project task.
Using the three-point estimating technique what is the expected number of days it should take to complete the task?
A project manager has reached an agreement on the requirements and now needs to define the workflow for the end user. A critical step must be completed and validated by the end user before proceeding.
Which modeling tool best describes this process?
Which three of the following are key traits of a project leader? (Choose three)
What Knowledge Area must be led by the project manager and cannot be delegated to other specialists?
A project manager can choose from several techniques to resolve conflicts between team members. Which technique can result in a win-win solution?
During project execution, a key resource leaves the team for another job. What should the project manager do in this situation?
During the requirements verification process, stakeholders are finding many errors in the requirements definition. What could the business analyst have done to avoid these errors?
During the execution of a project, a stakeholder asks a project manager whether the project is falling behind or ahead of its baseline schedule. The project manager calculates the earned value analysis (EVA) schedule variance and it comes out to be zero. Which of the following is correct about the EVA schedule variance?
Which project life cycle follows a plan reviewed and approved by the stakeholders?
A new business analyst has joined the team in the middle of a project and the requirements traceability matrix has been updated. What should the business analyst do next?
In an adaptive project environment, which action helps the project manager ensure that the team is comfortable with changes?
A project manager was assigned to a project with high uncertainty. What is the recommended method to calculate the project budget?
A community project with a large number of stakeholders is scheduled for delivery in six months. The project manager asked the business analyst to ensure an effective requirements elicitation.
What should the business analyst do?
Which of the following techniques should a project manager of a large project with virtual teams use to enhance collaboration?
What is the recommended approach for handling risk in a high-variability environment?
Which of the following is least influenced by a project manager, according to the project manager's sphere of influence?
A project's business analyst has to understand the newly acquired technology and the impact it will have on the organization. Which tool should be used to understand the new technology?
In a preliminary meeting for a project, team members decide to execute the project with methodology A finance team member wants to know how project cost will be determined at this early stage. How will the project team determine project cost?
A project manager is working on the communications management plan. Which of these documents are inputs to consider?
A business analyst has encountered a conflict related to competing requirements on an existing project. What tool should the business analyst use to resolve this issue?
A project team is working on a new driverless vehicle and is organizing a workshop with experts to analyze the data received from the prototype. Who should the project manager invite to provide expert advice?
A project manager is assigned to a project during the execution phase and consults the documents created by the previous project manager.
Which document should the project manager study to identify the ownership of the project outcome?
In the Control Quality process, which tools and techniques techniques can be applied to verify deliverable?
An organization's project management office (PMO) has issued guidelines that require a specific template to be used for onboarding resources for a project. Where can the project manager find this template?
What describes the relationship between projects, programs, and portfolios?
Match each tool or technique with its corresponding Project Cost Management process.
Company A’s accountant sends notification about a change in the company’s tax classification.
What would a project have to be initiated?
A project manager is calculating the current budget. The earned value (EV) of the project is lower than the actual cost (AC) of the project.
How should the project manager report the status of the project?
Given the following information, what is the schedule variance (SV) for this project?
Early start date (ES): 16 weeks
Actual time: 12 weeks
Schedule performance index (SPI): 1.3
A project team member is discussing a new project with their manager. The project is very similar to a project that was delivered last year and the scope is very well documented.
Which of the following project delivery approaches should be recommended?
After defining activities in project schedule management, which processes should a project manager follow?
A construction project is underway with three months left to complete the building. A public authority responsible for approving the final stage is stalling the project. What should the project manager do?
Select three processes that are associated with Project Schedule Management.
While executing a building construction project, the supplier may delay the delivery and increase the cost of materials due to new safety regulations. The team has identified an option to absorb the cost by reducing the lag for some of the tasks.
What should the team do to ensure that this situation is managed?
In the last two iterations, a project team failed to deliver all of the stories on time. What should the project manager do first in order to prevent this from recurring?
Due to organizational changes, a new product owner joins a project The product owner wants to review the process used to obtain team members, facilities, equipment, materials, supplies, and other resources necessary to complete project work.
What process should the project manager review with the product owner?
A Project manager is using agile in a project. As development life cycle is adaptive, how does the project manager handle key stakeholder involvement?
A project manager needs information to finish their work on the project charter for a clinical trial.
Which procedure is used to obtain the requirements information?
Which organizational process assets update is performed during the Close Procurements process?
What cost control technique is used to compare actual project performance to planned or expected performance?
The formal and informal interaction with others in an organization industry, or professional environment is known as:
Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?
Organizational planning impacts projects by means of project prioritization based on risk, funding, and an organizations:
Which of the following is a narrative description of products, services, or results to be delivered by a project?
Which type of contract is most commonly used by buying organizations because the price for goods is set at the outset and is not subject to change unless the scope of work changes?
Which component of the human resource management plan describes when and how project team members are acquired and how long they will be needed?
While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery. What is the MOST appropriate approach to managing this situation?
The individual or group that provides resources and support for a project and is accountable for success is the:
Which type of analysis is used to examine project results through time to determine if performance is improving or deteriorating?
Projects can be divided into phases to provide better management control. Collectively, what are these phases known as?
The procurement process that documents agreements and related documentation for future reference is known as:
Which Knowledge Area is concerned with the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?
Who, along with the project manager, is supposed to direct the performance of the planned project activities and manage the various technical and organizational interfaces that exist within the project?
Which of the following is an enterprise environmental factor that can influence the Develop Project Charter process?
The project manager notes that stakeholders are aware of the project and potential impacts and are actively engaged in ensuring that the project is a success. The engagement level of the stakeholders should be classified as:
Activity resource requirements and the resource breakdown structure (RBS) are outputs of which Project Time Management process?
Which of the following is an output of the Monitor and Control Project Work process?
Which action should a project manager take to ensure that the project management plan is effective and current?
The CPI is .92, and the EV is US$172,500.What is the actual cost of the project?
What is the term assigned to products or services having the same functional use but different technical characteristics?
Which schedule network analysis technique modifies the project schedule to account for limited resources?
An electronics firm authorizes a new project to develop a faster, cheaper, and smaller laptop after improvements in the industry and electronics technology. With which of the following strategic considerations is this project mainly concerned?