Labour Day Sale - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: mxmas70

Home > SAP > SAP Certified Application Associate > C_TS4CO_2021

C_TS4CO_2021 SAP Certified Application Associate - SAP S/4HANA for Management Accounting Associates (SAP S/4HANA 2021) Question and Answers

Question # 4

At what level do you create the structure of the operating concern?

A.

Sales organization level

B.

Controlling area level

C.

Client level

D.

Company code level

Full Access
Question # 5

In the material master record there are three planned prices: ""Planned price 1"", ""Planned price 2""and""Planned price 3"". What do you use them for?

A.

To valuate goods movement

B.

To valuate the materials in cost estimates

C.

To valuate material stocks

D.

To update the standard price during the release of a standard cost estimate

Full Access
Question # 6

What are the some of the characteristics of Profit Center Accounting in SAP S4/HANA? Note: There are 2 correct answers to this question.

A.

It can be used in the settlement rule for internal order.

B.

It is integrated in the universal journal.

C.

It can be used with period and/or cost of sale accounting.

D.

It is possible to derive the profit center from the segment in configuration.

Full Access
Question # 7

Which default values can you configure for the product cost collector? Note: There are 2 correct answers to this question.

A.

Result Analysis (RA) Version

B.

Result Analysis (RA) key

C.

Costing variant for preliminary costing

D.

Variance variant

Full Access
Question # 8

Which of the following steps are part of the procedure to update the standard price of the material? Note: There are 2 correct answers to this question.

A.

Release the cost estimate.

B.

Archive the cost estimates.

C.

Mark the cost estimate.

D.

Split the costs.

Full Access
Question # 9

How can you define the overhead rate in a costing sheet? Note: There are 2 correct answers to this question.

A.

As equivalence number

B.

As quantity-based surcharge

C.

As lot-based surcharge

D.

As percentage rate

Full Access
Question # 10

What are some of the characteristics of planning for internal orders? Note: There are 2 correct answers to this question.

A.

You can plan multiple versions.

B.

You can enter costs and revenues.

C.

You can define tolerance limits for plan overspend.

D.

Availability control can check against plan values.

Full Access
Question # 11

What values flow from Sales and Distribution billing to costing-based Profitability Analysis? Note: There are 2 correct answers to this question.

A.

Cost of goods sold split by cost components

B.

Value of "Gross Margin 2"

C.

Production variances split by variance categories

D.

Value of conditions of pricing procedure

Full Access
Question # 12

At which level do you define the valuation method for results analysis?

A.

Controlling area

B.

Company code

C.

Plant

D.

Operating concern

Full Access