Question # 4

You create a contract item for a material group. You want to prevent certain materials that belong to this material group frorn being ordered with reference to this contract item.

How can you ensure this?

A.

Create material -specilk: source lists for the supplier and set the Blocked indicator.

B.

Create material.-specific source lists for the contract item and set the Fix indicator.

C.

Create material -specific source lists outside the validity peftod of tie contract.

D.

Create material-specilic source lists for the contract item ana set tne Exclusion indicator.

Full Access
Question # 5

Production planning and product costing are to be implemented in your company. Which organizational level must you choose for stock valuation?

A.

Controlling area

B.

Business area

C.

Plant

D.

Company code

Full Access
Question # 6

In your company, you are posting an invoice with a cash discount amount using the posting gross method. What is the result of this in the system?

A.

The cash discount amount is credited to the stock or cost account.

B.

The cash discount amount is posted from a cash discount clearing account to the stock account or cost account.

C.

The cash discount amount is posted to a cash discount clearing account, which is cleared at ^ the time of payment.

D.

The cash discount amount is NOT considered; it is only posted to a cash discount account when the payment is made.

Full Access
Question # 7

At which of the following organizational levels must you maintain a business partner master record for a supplier? Note: There are 3 correct answers to this question.

A.

Client

B.

Plant

C.

Purchasing organization

D.

Purchasing group

E.

Company code

Full Access
Question # 8

How does SAP Fiori achieve the role-based design principle? Note: There are 2 correct answers to this question.

A.

By separating transactional and analytical apps in different business roles

B.

By defining SAP Fiori apps that users can tailor exactly to their needs

C.

By giving end users exactly what they need for their work

D.

By decomposing big transactions into several discrete apps suited to the user's role

Full Access
Question # 9

What must you do when using supplier consignment? Note: There are 2 correct answers to this question.

A.

Create consignment info records

B.

Settle liabilities resulting from consignment stock receipts

C.

Settle liabilities resulting from consignment stock withdrawals

D.

Create consignment storage locations

Full Access
Question # 10

Which of the following statements apply to a manually created reservation? Note; There are 2 correct answers to this question.

A.

You can assign different account assignment objects per item.

B.

You can maintain different movement types per item.

C.

You can set the Movement Allowed indicator per item.

D.

You must enter a material number in the item.

Full Access
Question # 11

Whal must you do to implement split valuation?

Note: There are 2 correct answers to this Question

A.

Add valuation types to all open purchase order iterns.

B.

Assign valuation types to stock types.

C.

Customize valuation categories and valuation types.

D.

Create additional accounting data for the relevant materials.

Full Access
Question # 12

Where does SAP S/4HANA store low-level code? Note:There are 2 correct answers to this question.

A.

Bill of material

B.

Production version

C.

Planning file

D.

Material Master

Full Access
Question # 13

You want to identity the spend of purchase orders that do NOT have a contract reference, although an existing contract could have been used. What key performance indicator (KPI) provides this information?

A.

Contract leakage

B.

Off-contract spend

C.

Unused contracts

D.

Purchase order value

Full Access
Question # 14

Which of the following activities is a prerequisite to enable partner role detarmraton m purchasing?

A.

Assign a partner schema to relevant arrangement types.

B.

Assign a partner schema to lelevanl account groups.

C.

Define permissible partner roles per account group.

D.

Define permissible partner roles per document type.

Full Access
Question # 15

At what level do you maintain the purchasing value key in the material master?

A.

Purchasing organization

B.

Plant

C.

Company code

D.

Client

Full Access
Question # 16

Which object is determined using an access sequence in message determination?

A.

Message schema for a document category

B.

Output device in an output condition record

C.

Message type in a message schema

D.

Output condition record for a message type

Full Access
Question # 17

Which of the following apply when using centrally agreed contracts? Note; There are 2 correct answers to this question.

A.

You can maintain plant-specific conditions in centrally agreed contracts

B.

You can use centrally agreed contracts in a procurement hub scenario.

C.

You CANNOT specify plants in centrally agreed contracts.

D.

You can use centrally agreed contracts without restrictions for any purchasing organization.

Full Access
Question # 18

You want to manually post an initial entry of stock for a material in SAP S/4HANA. You want to enter both a quantity and an amount. How do you proceed? Note: There are 2 correct answers to this question.

A.

On the SAP Fiori launchpad, use the Post Goods Receipt without Reference app.

B.

On the SAP Fiori launchpad, use the Post Goods Movement app.

C.

On the SAP Fiori launchpad, use the Manage Stock app.

D.

In the SAP GUI, use transaction MIGO.

Full Access
Question # 19

Which of the following actions are supported when you post a goods receipt to stock with reference to a purchase order? Note: There are 3 correct answers to this question.

A.

Post a goods receipt for part of the order quantity

B.

Enter a value for the quantity received

C.

Adjust the purchase order quantity to the goods receipt quantity

D.

Split the quantity received to multiple storage locations

E.

Post the quantity received to quality inspection stock

Full Access
Question # 20

What are some key features of purchase-orde r-based invoice verification? Note: There are 2 correct answers to this question.

A.

The system proposes the total delivered quantity as the quantity to be invoiced.

B.

The system proposes the quantity to be invoiced as the difference between the total delivered quantity and the total quantity already invoiced.

C.

Partial deliveries for a purchase order item show up as individual items in the invoice document.

D.

Partial deliveries for a purchase order item are NOT flagged as individual invoice items.

Full Access
Question # 21

How can you completely block a material for procurement in a plant? Note: There are 2 correct answers to this question.

A.

Create an entry in the source list with a blocking indicator and NO supplier

B.

Create a quota arrangement entry with a quantity of zero

C.

Use a relevant plant-specific material status in the material master

D.

Create a blocking entry in the supplier master record

Full Access
Question # 22

In the standard system, a controllable system message is shown when a user creates a purchase order with a delivery date in the past. What must you configure to allow such purchase orders to only be created by authorized users?

A.

Copy the system message to a new version.

B.

Copy the system message to a new version. Set it as an error message. Assign the version with user parameter MSV to non-authorized users.

C.

Copy the system message to a new version. Set it as an error message. Assign the version with user parameter MSV to the authorized users.

D.

Copy the system message to a new version.

Full Access
Question # 23

Which of the following are features of a scheduling agreement? Note: There are 3 correct answers to this question.

A.

A material master record is optional in a scheduling agreement item.

B.

A scheduling agreement can be used for a consignment process.

C.

Scheduling agreement delivery schedule lines can only be created manually.

D.

Item category M (Material unknown) can be used in a scheduling agreement.

E.

A scheduling agreement item is always plant-specific .

Full Access
Question # 24

Which of the following steps can be part of a subcontracting process? Note: There are 3 correct answers to this question

A.

Post subsequent adjustment of component consumption

B.

Create a sales order for components to be provided

C.

Invoice the subcontractor for consumed components

D.

Create an outbound delivery for components to be provided

E.

Purchase components for direct delivery to the subcontractor

Full Access
Question # 25

You send newly created purchase orders to a supplier via EDI,whereas quantity or price changes are transmitted by e-mail. What prerequisites must be met if you are using the condition technique for message determination? Note: There are 3 correct answers to this question.

A.

You have configured different message types for the New and Change print options

B.

The New Message Determination Process for Change Messages indicator is flagged in Customizing.

C.

The condition record contains the Price and Quantity fields.

D.

The Price and Quantity fields are relevant for printout changes.

E.

The dispatch time related to the change message needs to be set to 1 (send with periodically m scheduled job).

Full Access
Question # 26

For which of the following transactions do you receive an error message if the automatic account determination is set up incorrectly? Note: There are 3 correct answers to this question.

A.

Material price change

B.

Purchasing info record price change

C.

Stock transfer posting between stock types

D.

Goods receipt into blocked stock

E.

Stock transfer between company codes

Full Access
Question # 27

Where can you set the parameter that allows changing the account assignment data for a consumable material during invoice receipt?

A.

In the item category

B.

In the purchase order document type

C.

In the material master of the consumable material

D.

In the account assignment category

Full Access
Question # 28

Which of the following are features of a subcontracting procurement process? Note: There are 3 correct answers to this question.

A.

You can post a non-valuated goods receipt for a subcontracting order item.

B.

You can maintain the components to be provided in a bill of material.

C.

You can have subcontracting purchase requisitions created by MRP.

D.

You can assign a subcontracting order item to an account.

E.

You can customize the control parameters for the subcontracting item category.

Full Access
Question # 29

Which of the following are possible personalization options of the SAP Fiori launchpad? Note: There are 2 correct answers to this question.

A.

Add new tile Groups

B.

Add tiles to existing tile groups

C.

Add new catalogs

D.

Add tile groups to business roles

Full Access