The BIM manager is coordinating a multi-building project in which each building must maintain a unique internal coordinate system but share a common origin point for site-wide references.
Which two actions are required to correctly manage the coordinate setup in this scenario? (Select two.)
A BIM manager is preparing to share a federated model package with an external cost estimator. The estimator only needs access to quantities and location-based metadata, but not design intent or proprietary elements from other teams.
What is the first step the BIM manager should take to ensure appropriate use and minimize data-related risk?
A museum project anticipating generative iterations is being designed by a team working across multiple time zones under a tight schedule. The client hosts weekly meetings to review various façade options, document sustainability goals, and evaluate numerous energy analyses.
What project-specific training should the design technology team provide to prepare the team for client meetings and ensure successful project execution?
A campus project of several duplicated links of a building model has received an updated civil background, with revised GIS coordinates.
Drag and drop to indicate the correct order of steps the BIM manager should perform to revise the architectural model.

A project model, which includes multidisciplinary and DWG links, has been exhibiting problematic behavior. It takes a long time to save and synchronize, or crashes unexpectedly. Even though there are no imported DWGs, a scan of the model reveals a large number of IMPORT line patterns that typically come from DWG imports and links and are a possible cause of model-performance loss.
To remedy and prevent a repetition of this situation, the BIM manager is attempting to mentor the team on best practices for preparing DWGs for linking to a Revit model.
Which workflow steps will optimize the DWG files and prevent inefficiencies and loss of productive time due to repeated poor DWG-linking practices?
The BIM manager is conducting a health check of a design model submitted by a consultant to assess its readiness for coordination. Several model performance concerns have been raised, including long open times, sluggish navigation, and excessive file size.
Which of the following actions would best help to evaluate the model’s health and identify areas of improvement?
A design team is distributing models to a construction team’s coordinator, who reports that the various models are not aligned to each other when linked into the coordination environment.
What step should the design team’s lead BIM manager take to resolve the positioning issue?
During an initial coordination meeting, the team agreed that the contractor will be able to mark up the latest model and sheets in Autodesk Forma every week.
Which two actions should the BIM Manager take to ensure this is implemented correctly? (Select two.)
An AEC company has received a design model from the Architect of Record to begin creating construction documentation. The BIM Execution Plan identifies a fast-track delivery schedule, and the project team includes new consultants with limited exposure to the client’s preferred toolset and workflows. The BIM manager must determine how best to prepare the delivery team and assess the model’s compatibility with internal systems.
As the BIM manager prepares for the Project Kickoff meeting, which two pieces of information are most critical to avoid issues related to digital compatibility? (Select two.)
Refer to the exhibit.

Upon opening a model, the following warnings saying “Room Tag is outside of its Room†appear.
What action should the BIM manager ask the design team to take in order to identify any Room Tags that need a leader because the tag may be too big to fit within the room?
During a weekly BIM health review, the BIM manager compares two versions of the same architectural Revit model submitted one month apart. The newer model’s file size has doubled, synchronization time has increased by 40%, and users report sluggish performance. A model audit reveals no major geometry changes, but warnings have increased from 600 to 750, and several Civil CAD files are now imported.
What is the most likely root cause of the model performance degradation?
A Revit model in Autodesk Forma that does not have any consultant links is opening for all team members except one. The project BIM manager has already audited and compacted the model.
What should the BIM manager do so that the team member can open the model?
During a coordination meeting, project leads ask for a report showing only active clashes between mechanical systems and structural framing in patient-room zones, following the approved clash matrix.
What is the most effective way to provide this report using Model Coordination?