Pre-Summer Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: mxmas70

Home > Autodesk > Autodesk Certified Professional > BIM_MGT_101

BIM_MGT_101 Autodesk Certified Professional in BIM Management for Building Design Question and Answers

Question # 4

The BIM manager is coordinating a multi-building project in which each building must maintain a unique internal coordinate system but share a common origin point for site-wide references.

Which two actions are required to correctly manage the coordinate setup in this scenario? (Select two.)

A.

Place the Survey Point at the shared site origin for all buildings.

B.

Create unique Survey and Project Base Points for all buildings, maintaining individual Building Coordination.

C.

Place the Project Base Point at the shared site origin for all buildings.

D.

Share coordinates by acquiring from the master site model, using a single Survey and Project Base Point.

E.

Assign a unique Project Base Point for each building model.

Full Access
Question # 5

A BIM manager is preparing to share a federated model package with an external cost estimator. The estimator only needs access to quantities and location-based metadata, but not design intent or proprietary elements from other teams.

What is the first step the BIM manager should take to ensure appropriate use and minimize data-related risk?

A.

Export the models as PDFs to prevent the third party from modifying geometry.

B.

Confirm that the model content, format, and permissions match the recipient’s defined scope of use.

C.

Verify that the file sizes are small enough for email transmission.

D.

Convert the models into 2D views to avoid exposing embedded metadata.

Full Access
Question # 6

A museum project anticipating generative iterations is being designed by a team working across multiple time zones under a tight schedule. The client hosts weekly meetings to review various façade options, document sustainability goals, and evaluate numerous energy analyses.

What project-specific training should the design technology team provide to prepare the team for client meetings and ensure successful project execution?

A.

AutoCAD, Autodesk Forma, generative design.

B.

Generative design, AutoCAD, Civil 3D.

C.

Forma Site Design, generative design, Autodesk Forma.

D.

Sustainability certification, Revit, Forma Site Design.

Full Access
Question # 7

A campus project of several duplicated links of a building model has received an updated civil background, with revised GIS coordinates.

Drag and drop to indicate the correct order of steps the BIM manager should perform to revise the architectural model.

Full Access
Question # 8

A project model, which includes multidisciplinary and DWG links, has been exhibiting problematic behavior. It takes a long time to save and synchronize, or crashes unexpectedly. Even though there are no imported DWGs, a scan of the model reveals a large number of IMPORT line patterns that typically come from DWG imports and links and are a possible cause of model-performance loss.

To remedy and prevent a repetition of this situation, the BIM manager is attempting to mentor the team on best practices for preparing DWGs for linking to a Revit model.

Which workflow steps will optimize the DWG files and prevent inefficiencies and loss of productive time due to repeated poor DWG-linking practices?

A.

Delete all XREFs; change all fonts to Arial.

B.

Delete all text; explode all geometry.

C.

PROXYGRAPHICS=0, PURGE, AUDIT, OVERKILL.

D.

PROXYGRAPHICS=1, PURGE ALL, AUDIT, OVERKILL.

Full Access
Question # 9

The BIM manager is conducting a health check of a design model submitted by a consultant to assess its readiness for coordination. Several model performance concerns have been raised, including long open times, sluggish navigation, and excessive file size.

Which of the following actions would best help to evaluate the model’s health and identify areas of improvement?

A.

Run a performance audit using review tools and evaluate the number of warnings, file size, and modeling practices such as in-place families.

B.

Notify the consultant to reduce the model file size by deleting sheets and exporting only 3D views.

C.

Review the consultant’s coordination clash reports to determine if unresolved issues are impacting performance.

D.

Disable all linked files and re-enable them one at a time to identify which one is causing performance issues.

Full Access
Question # 10

A design team is distributing models to a construction team’s coordinator, who reports that the various models are not aligned to each other when linked into the coordination environment.

What step should the design team’s lead BIM manager take to resolve the positioning issue?

A.

Reset coordinates and advise the coordinator to link all models by Internal Origin to Internal Origin.

B.

Publish coordinates from the Main Model out to all linked consumed consultant files.

C.

Report coordinates to provide the coordinator with the desired positioning of each model for them to reposition.

D.

Advise consultants to acquire coordinates from the primary design team’s model and resubmit updated models.

Full Access
Question # 11

During an initial coordination meeting, the team agreed that the contractor will be able to mark up the latest model and sheets in Autodesk Forma every week.

Which two actions should the BIM Manager take to ensure this is implemented correctly? (Select two.)

A.

Email PDFs to the contractor every week.

B.

Update Publish Settings to include sheets.

C.

Create blank sheets for all disciplines.

D.

Enable Model Coordination.

E.

Schedule Publishes in Design Collaboration.

Full Access
Question # 12

An AEC company has received a design model from the Architect of Record to begin creating construction documentation. The BIM Execution Plan identifies a fast-track delivery schedule, and the project team includes new consultants with limited exposure to the client’s preferred toolset and workflows. The BIM manager must determine how best to prepare the delivery team and assess the model’s compatibility with internal systems.

As the BIM manager prepares for the Project Kickoff meeting, which two pieces of information are most critical to avoid issues related to digital compatibility? (Select two.)

A.

Any add-ins required.

B.

Project units.

C.

Software version and build.

D.

Shared Coordinates.

E.

Graphic standards.

Full Access
Question # 13

Refer to the exhibit.

Upon opening a model, the following warnings saying “Room Tag is outside of its Room” appear.

What action should the BIM manager ask the design team to take in order to identify any Room Tags that need a leader because the tag may be too big to fit within the room?

A.

Select Show to address each tag.

B.

Select Export to move the warnings outside the model.

C.

Select Close to exit the Warnings window.

D.

Select Delete Checked to resolve each tag.

Full Access
Question # 14

What is included in a BIM Execution Plan?

A.

Project schedule and design playbook.

B.

Modeling standards and technology ecosystem.

C.

LOD Matrix and project specifications.

D.

Collaboration protocols and project playbook.

Full Access
Question # 15

During a weekly BIM health review, the BIM manager compares two versions of the same architectural Revit model submitted one month apart. The newer model’s file size has doubled, synchronization time has increased by 40%, and users report sluggish performance. A model audit reveals no major geometry changes, but warnings have increased from 600 to 750, and several Civil CAD files are now imported.

What is the most likely root cause of the model performance degradation?

A.

A rise in geometry complexity.

B.

An accumulation of audit history and backup data.

C.

The presence of imported Civil CAD files.

D.

The increase in model warnings.

Full Access
Question # 16

A Revit model in Autodesk Forma that does not have any consultant links is opening for all team members except one. The project BIM manager has already audited and compacted the model.

What should the BIM manager do so that the team member can open the model?

A.

Clear the user’s collaboration cache files and retry again.

B.

Agree to a user request for a hardware upgrade.

C.

Roll back the model to a previous version.

D.

Publish the model to Autodesk Forma and ask the user to retry again.

Full Access
Question # 17

During a coordination meeting, project leads ask for a report showing only active clashes between mechanical systems and structural framing in patient-room zones, following the approved clash matrix.

What is the most effective way to provide this report using Model Coordination?

A.

Create a custom View from the published models, then export the filtered clash-list results.

B.

Ask each discipline to review its own clash results and report any critical issues from its perspective.

C.

Export all clash results to a spreadsheet and manually filter by trade and zone.

D.

Assign all relevant clashes to mechanical and structural teams using the Issues tool.

Full Access