Which 2 statements explain why the Timber Tigers ' Site Manager would be an appropriate Solution Developer?
Which information could be recorded on an ‘empathy map’ for the marketing staff?
The change management team is creating the change analytics strategy for the change programme.
Below is an extract of recipients, measures and source data that have been proposed.
Answer the following question about the sources of conflict in change
situations.
Column 1 is a list of statements about sources of conflict in change situations.
Column 2 contains the names of the eight sources of conflict identified by Art
Bell and Brett Hart. For each statement in Column 1, select from Column 2 the
source of conflict to which it MOST relates. Each selection from Column 2 can
be used once, more than once or not at all.



The Change Manager is discussing the relocation of the Selco staff to the UniCo office with the Operations Director. They are using the SCARF framework of people ' s social experience to guide management actions.
Answer the following questions about the use of David Rock ' s SCARF framework to increase the motivation for change.
The founder of Selco, now the Applications Manager, is moving from an individual office to a desk in the shared area for the Operations Director ' s leadership team in the UniCo building. At the last Operations ' group meeting, the Operations Director thanked the Applications Manager for cooperating fully with the relocation.
Is this an appropriate approach to reward the brain in the need for ' status ' , and
why?
Using the additional information provided for this question in the
Scenario Booklet, answer the following question about using Kotter ' s
eight-processes cyclical model. This model is being used for planning
and leading the change required to rebrand and reposition UniCo in the
market place.
Lines 1 to 4 in the table below consist of an assertion statement and a reason
statement. For each line identify the appropriate option, from options A to E,
that applies. Each option can be used once, more than once or not at all.



For cognitive learning, which is the BEST example of providing ' learning feedback ' ?
Sales staff failed to achieve last month’s sales targets when training in the mobile products and supporting sales systems and processes was first started. This month the sales team is working after hours and weekends to try to meet the current targets while developing the new skills needed. It is generally felt that this situation is unsustainable.
Which 2 actions by the Sales Director are the MOST appropriate when responding to this type of resistance?
Which statement should be recorded under the Change Management Team and Relationships heading?
Answer the following question about Schein ' s concept of survival and learning
anxieties.
Column 1 is a list of messages about the change given to Sales staff. For each
message in Column 1, select from Column 2 the appropriate element of
Schein ' s concept of survival and learning anxieties. Each selection from
Column 2 can be used once, more than once or not at all.


Which participant characteristic is likely to be the MOST appropriate to the success of a workshop to design a process?
The Change Manager is looking to develop the change agent network that will support the changes related to the Operational delivery processes workstream.
Which approach is MOST likely to be relevant when deciding on the size of the change network for the Operational delivery processes workstream?
(To keep Business Sponsor, Sarah, informed, Hira has set up a real-time dashboard displaying project progress, risks, and actions from planning events.
Will this meet Sarah ' s needs?)
Resources are limited. The Sales Manager has two marketing assistants who
may be able to give a few hours a week between them to the project.
What action should the Project Manager take?
The Business Ambassador assigned to the project is only available 2 days a
week. The Project Manager has stated that the Investigation stage for each
Timebox should, where possible, be planned around the availability of the
Business Ambassador.
Is this an appropriate application of the DSDM lifecycle?
Several of the web developers working on the project have no Agile
experience. When answering the questions in the Project Approach
Questionnaire (PAQ), the Project Manager could not agree with the statement
' all members of the project understand and accept the DSDM approach ' .
What action should the Project Manager take?
Time is running short and the Must Have requirements for the data entry screen
of the web page, as recorded in the Prioritised Requirements List, are not going
to be completed on time.
What action should the Project Manager take?
Xan Insurance Company operates from one location - a large, open-plan
office in the centre of a city. Those employees that will be working within the
Solution Development Team are all based in this office but work at different
ends of the office in separate departments.
What action should the Project Manager suggest to ensure the most effective
collaboration of the Solution Development Team?
Xan Insurance Company is a friendly company with no separate private offices
for individual managers. Staff members prefer to wander around the office
space and have one-to-one chats rather than use email or have lots of
meetings.
What action should the Project Manager take when planning for effective
communication throughout the Web project?
Which 2 statements represent appropriate entries for the plan for Post-Project
activities?
The Solution Development Team are progressing through the first Structured
Timebox.
What should the Project Manager do to lead the team at this time?
Which 2 statements represent appropriate entries for the Development
Approach Definition?
Which 2 actions should the Project Manager take to implement the new Must
Have requirement?
Answer the following questions about the DSDM Lifecycle.
Decide if each observation is an appropriate application of Agile Project Management for
this project and select the option that supports your decision.
When the project was in the Feasibility phase it was initially proposed by the Finance
Manager that it was a fixed price for a fixed specification ' project. The Project Manager
has decided that the best way to tackle it would be to leave the development of the least
valuable features of the product until last.
Is this an appropriate application of the DSDM lifecycle?
The Web Content Manager has provided the Web Developer with a mock up
of the ' Contact Us ' page, to be created for the new coffee bar insurance
product. When producing the code, the Web Developer has created a button
that reads ' Delete ' instead of ' Cancel ' .
What action should the Web Content Manager take?
Column 1 is a list of individuals from within the Xan Insurance Company
and their key responsibility within the Web project.
For each individual in Column 1, select from Column 2 the Agile Project
Management team role they are fulfilling. Each selection from Column 2 can
be used once, more than once or not at all.
Column 1
Manager of Web & Digital
Media - will oversee and report
progress on the delivery of the
overall system.
Finance Director - has
budgetary control and will
release finance for the project
subject to expected benefits.
Sales Manager - will formulate
design options for new
business processes that do not
adversely affect business as
usual.
Operations Manager - oversees
the design and integrity of the
technical aspects of the
solution.
Column 2
Business Sponsor
Business Analyst
Business Ambassador
Business Advisor
Solution Developer
Technical Coordinator
DSDM Coach
Project Manager

Using the Project Scenario and the additional information provided for
this question in the Scenario Booklet, answer the following question
about assigning the Agile Project Management team roles within this
project.
Lines 1 to 5 in the table below consist of an assertion statement and a
reason statement. For each line identify the appropriate option, from options
A to E. that applies. Each option can be used once, more than once or not
at all.

The building has had all the old utility services removed and new wiring and plumbing is being installed during Evolutionary Development. On average there are
four electrical and six plumbing contractors who are engaged for between a few days and a few weeks. They are finding it difficult to work round each other and
to know who should be where. Some of the contractors have started to turn up late to the site.
Many floor boards have been lifted in preparation but it is not clear where the radiators are being situated or when each room is going to be worked on by the plumbers. The
Chief Accountant, acting as Business Ambassador, is also alarmed that the electrical sockets are being installed in rooms in inaccessible locations.
Answer the following questions about motivating the contractor teams according to Agile Project Management.
How should the Project Manager encourage the resources to operate more successfully?
Using the Project Scenario and the additional information provided for
this question in the Scenario Booklet, answer the following questions
about Feasibility.
Remember to limit your answers to the number of selections requested in each
question.
Which 2 statements describe the appropriate application of Agile Project
Management when developing the Feasibility Assessment?
What action should the Project Manager take to plan the deployment activities?
Which 2 statements explain why the Architecture Angels ' Operations Director would be an appropriate Business Advisor?
Once the change of priority has been approved, who is then responsible for including the requirement for a secondary exit from the upstairs of the building to the Timebox
Plan for Timebox B?
Review sessions have been scheduled at end of Investigation, Refinement and Consolidation for the later Timeboxes to ensure that the mistakes made in Timebox A do not
happen again.
Which Agile principle MOST influences this course of action?
What should be done to allow the requirement for a secondary exit from the upstairs of the building to be changed into a Must Have priority and moved into Timebox B?
Using the project timeline given in the Project Scenario, answer the following question about application of Timeboxing on the Hoy Hall project.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies.
Each option can be used once, more than once or not at all.

Assertion :
1. All internal works to be assigned to Timber Tigers throughout the project should be consolidated into one Structured Timebox.
BECAUSE
The Investigation step within each Structured Timebox requires everyone working within the team to jointly agree how the requirements of the Timebox will be met.
2. Acceptance criteria for the front rooms to be developed in Timebox A should be described in detail and agreed during the Timebox Kick-Off
BECAUSE
The aim of the Investigation step within each Timebox is to complete as much of
the development work as possible.
3. It is appropriate that both the Evolutionary Development phase and Deployment phase are shown in the first Project Increment.
BECAUSE
Each Timebox should comprise an Evolutionary Development phase and
Deployment phase.
4. It is appropriate that the outputs of Timebox C are scheduled for deployment at the end of the first Project Increment.
BECAUSE
A typical Timebox Plan should provide a schedule of high-level activities for the
imminent Project Increment.
5. It is appropriate that Earth Excavations create a detailed plan of activities they will complete during Timebox C.
Reason
BECAUSE
The Solution Development Team is responsible for planning the detail of all the
work of each Timebox.


(Which one of the following actions should Hira take to balance the benefit of agile leadership whilst ensuring alignment of the Project Increment with project objectives?)
As Sprint 5 comes to an end, the Infrastructure Delivery Team is facing delays due to:
. Heavy rainfall affecting the Wellness Garden.
. Local supplier issues causing material delivery delays.
· Dependency on external contractors for hydrotherapy equipment.
The Operations Delivery Team is unable to finalize details of the hydrotherapy treatments without testing them in the
context of the facilities being constructed. The marketing materials cannot be generated until this work is complete.
In addition to the Developers, the teams include:

(The Wellness Garden (a Should Have) is delayed. Sukra Aroon suggests a workaround, using the River Pool Patio instead, and classifying the Garden as a ' Won ' t Have this time ' .
Is this an appropriate suggestion?)
(During Sprint Planning, the Delivery Team identifies a potential risk in integrating Spa systems with the resort ' s client management system.
Which 2 statements describe how this risk should be handled within the AgilePM framework?)
(Hira is considering splitting the Developers into two Delivery Teams: one focused on Spa infrastructure and the other on guest experience. Mira Bachar, the Guest Services Manager, will be the Product Owner for both teams.

Which one of the following statements support Hira ' s proposed Delivery Team structure?)
(Which 2 statements describe appropriate team behaviour for effective risk management?)
Mira Bachar has spoken with a guest who wanted an aromatherapy scent to remember their holiday. Inspired by this, Mira suggested creating a unique aromatherapy oil for spa treatments and guest sales, which could also serve as a marketing tool.
Brinda Vyas supports exploring the idea, but Sukra Aroon notes that selling products is not in scope and could introduce complexities.

(Which 2 of the following actions align with AgilePM practices for defining and estimating the work of Project Increment 4 during the Foundations phase?)
Mira Bachar has spoken with a guest who wanted an aromatherapy scent to remember their holiday. Inspired by this, Mira suggested creating a unique aromatherapy oil for spa treatments and guest sales, which could also serve as a marketing tool.
Brinda Vyas supports exploring the idea, but Sukra Aroon notes that selling products is not in scope and could introduce complexities.

(When defining and estimating work for Project Increment 4, the Delivery Teams must account for uncertainty in integrating the Eco-spa into the guest experience.
Which 2 of the following approaches align with AgilePM principles for managing uncertainty in estimation?)
As Sprint 5 comes to an end, the Infrastructure Delivery Team is facing delays due to:
. Heavy rainfall affecting the Wellness Garden.
. Local supplier issues causing material delivery delays.
· Dependency on external contractors for hydrotherapy equipment.
The Operations Delivery Team is unable to finalize details of the hydrotherapy treatments without testing them in the
context of the facilities being constructed. The marketing materials cannot be generated until this work is complete.
In addition to the Developers, the teams include:

(Hira decides to update the Delivery Plan to prioritize the delivery of the hydrotherapy facilities first for early testing.
Is this action appropriate?)
During the Foundations phase for Project Increment 4, Sukra Aroon held a meeting with Hira, Mira Bachar, andWanida Anong, to ensure alignment and compliance with EPR company policies, local regulations, and international standards. The meeting also clarified how financial and investment decisions would be made for Project Increment 4, ensuring alignment with EPR business priorities, and how this information will be tracked,
controlled and evidenced.
Wanida Anong, who works across multiple sites worldwide, attended the meeting in person but has limited availability throughout the Project Increment.

(During the meeting, Mira Bachar asked Sukra Aroon which AgilePM project artifacts should use to provide an auditable record of compliance requirements throughout Project Increment 4.
Based on AgilePM guidance, which of the following is an appropriate response?)
Brinda Vyas and Mira Bachar have agreed to use content from a marketing brochure to describe guest-centric Product Goals for the Eco-Spa. These goals describe specific treatments that the Spa might offer and will be used to identify prioritizable Product Backlog items that could contribute to that treatment. One such Product Goal is described as:
Hydrotherapy in Mineral-Rich Spring Pools
Immerse yourself in mineral-rich hydrotherapy pools designed to soothe muscies, improve circulation, and promote
deep relaxation. Experience the gentle power of temperature-controlled waters and therapeutic massage jets in a lush
and tranquil tropical garden setting and let nature ' s healing embrace rejuvenate both your body and your mind.
In addition to the Developers, the teams include:

(Which one of the following actions will ensure that Product Backlog items for the Hydrotherapy infrastructure remain aligned with the planned treatment experience throughout development?)
Midway through Project Increment 4, a joint Sprint Retrospective is held with Developers from both Delivery Teams.
Some members from Marketing and IT, based in India, join via video conferencing.
Issues raised:
. Dependency management challenges
· Concerns about AgilePM principle ' Demonstrate Control '
To address this, Mira Bachar and the Developers invite Hira and Sukra Aroon to help Delivery Teams understand the
issues, assess the consequences, and collaborate on solutions that align with AgilePM and Scrum.
In addition to the Developers, the teams include:

(Developers in the Infrastructure Team report integration issues between climate control and lighting systems, leading to an excessive energy demand beyond the capacity of the solar panels.
Which 2 of the following actions align with the AgilePM guidance on addressing risk?)
Mira Bachar has spoken with a guest who wanted an aromatherapy scent to remember their holiday. Inspired by this, Mira suggested creating a unique aromatherapy oil for spa treatments and guest sales, which could also serve as a marketing tool.
Brinda Vyas supports exploring the idea, but Sukra Aroon notes that selling products is not in scope and could introduce complexities.

(Mira Bachar is running a workshop with Sukra Aroon and Developers, to create an initial Product Backlog.
Which 2 of the following actions will help shape the Backlog?)
Midway through Project Increment 4, a joint Sprint Retrospective is held with Developers from both Delivery Teams.
Some members from Marketing and IT, based in India, join via video conferencing.
Issues raised:
. Dependency management challenges
· Concerns about AgilePM principle ' Demonstrate Control '
To address this, Mira Bachar and the Developers invite Hira and Sukra Aroon to help Delivery Teams understand the
issues, assess the consequences, and collaborate on solutions that align with AgilePM and Scrum.
In addition to the Developers, the teams include:

(Another of the EPR Eco-spa ' s commissioned in India experienced major quality issues, causing a three-week shutdown. Stakeholders are now worried about similar problems in Project Increment 4.
Which 2 of the following actions would appropriately reassure stakeholders that the same quality issues will not arise in this project?)
There are several tests planned throughout the project to ensure the solution is fit for purpose and to validate the business solution as
it evolves.
Column 1 is a list of tests. For each test in Column 1, select from Column 2 the testing concept that it represents. Each selection from Column 2
can be used once, more than once or not at all.
Column 1
1) In order to get an objective
view, the financial transaction
function is to be tested by
someone from Finance who
has had no involvement in its
development.
2) Before the developer works on
the printing function for the
policy documents, the Sales
Manager will review a prototype
of the online application form
for the new coffee shop
insurance product with the
solution tester.
3) Security test scripts have been
provided by the company ' s
bank. These scripts will be used
to test the link from the
company ' s website to the
banking system, which is to be
developed specifically to achieve these tests
4.
The addition of the new coffee
shop insurance product may
threaten the stability of the
existing website. As a primary
route to market this is
unacceptable. The website ' s
capacity to run additional pages
is to be verified before any
other tests are performed.
5.
The Must Have and Should
Have requirements are to be
tested before the Could Have
requirements.
Column 2
Collaborative Testing
Repeatable Testing
Independent Testing
Prioritised Testing
Test-Driven Development

Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following question about the
responsibilities of the roles in the Agile team.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies.
Each option can be used once, more than once or not at all.

Assertion
The Marketing Director, in the role of Business Visionary, is empowered to overrule cost restrictions advised by the Chief Accountant, who is appointed as Business Ambassador.
BECAUSE
The Project-level roles are responsible for directing, managing and co-
ordinating the project.
The Procurement Manager is an appropriate representative of the end user of the solution.
BECAUSE
The Business Ambassador should be empowered to make decisions within
the boundaries of their role, without referral to higher authorities outside
the Solution Development Team.
The other specialist gardening team members from Earth Excavations would be suitable as Solution Developers, assigned alongside the Head Landscape Gardener.
BECAUSE
Extra Solution Developers can provide a supporting role for a Lead
Developer.
The ' Hoy for Hoy Hall ' Action Group members should be assigned as Business Ambassadors.
BECAUSE
The Business Ambassador is responsible for ensuring that business needs
are properly analysed.
The Project Manager should plan the communication needed between the Marketing Director, in the role of Business Visionary, and the ' Hoy for Hoy Hall ' Action Group.
BECAUSE
The Business Visionary is responsible for promoting the business vision to
all interested parties.

How should the Project Manager encourage the contractors to turn up on time?
Which 2 statements explain why the Contract Architect would be an appropriate Technical Co-ordinator?
Answer the following questions about the acceptance criteria within the project.
Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.
The requirement to ' install a heat reclamation system ' shows as a Should Have in the Prioritised Requirements List. During Investigation in Solution Development Timebox B, the Project Manager advised the team NOT to set detailed acceptance criteria for this requirement until later in the Timebox, since the requirement may have to be dropped and the work would be wasted.
Is this an appropriate action related to acceptance criteria?