Pre-Summer Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: mxmas70

Home > APMG-International > AgilePM > AgilePM-Practitioner

AgilePM-Practitioner Agile Project Management (AgilePM) Practitioner Exam Question and Answers

Question # 4

Which 2 statements explain why the Timber Tigers ' Site Manager would be an appropriate Solution Developer?

A.

Accustomed to bringing in contract staff for short periods of time.

B.

Closely manages the building team so that they consistently produce high-quality work.

C.

Is able to represent the team in all daily meetings.

D.

An experienced builder who is good at turning a brief into a practical design.

E.

Is empowered by Timber Tigers ' management to make decisions on the building work.

Full Access
Question # 5

Which information could be recorded on an ‘empathy map’ for the marketing staff?

A.

The Promotions Team Leader has noted that staff have raised concerns about how the change may reduce their sales during the seasonal promotions.

B.

The Marketing Manager has identified potential stakeholders, drawn symbolic figures of each of them and positioned them on a visual diagram.

C.

The Marketing analyst staff have made a list of potential stakeholders and plan to share this with everyone else at the next sales meeting.

D.

During a meeting of Brand Team Leaders, each participant created a list of stakeholders and then compared these lists in small groups.

Full Access
Question # 6

The change management team is creating the change analytics strategy for the change programme.

Below is an extract of recipients, measures and source data that have been proposed.

Answer the following question about the sources of conflict in change

situations.

Column 1 is a list of statements about sources of conflict in change situations.

Column 2 contains the names of the eight sources of conflict identified by Art

Bell and Brett Hart. For each statement in Column 1, select from Column 2 the

source of conflict to which it MOST relates. Each selection from Column 2 can

be used once, more than once or not at all.

Full Access
Question # 7

The Change Manager is discussing the relocation of the Selco staff to the UniCo office with the Operations Director. They are using the SCARF framework of people ' s social experience to guide management actions.

Answer the following questions about the use of David Rock ' s SCARF framework to increase the motivation for change.

The founder of Selco, now the Applications Manager, is moving from an individual office to a desk in the shared area for the Operations Director ' s leadership team in the UniCo building. At the last Operations ' group meeting, the Operations Director thanked the Applications Manager for cooperating fully with the relocation.

Is this an appropriate approach to reward the brain in the need for ' status ' , and

why?

A.

No, because ' status ' should be rewarded by ensuring open, two-way

communication using rich channels.

B.

No, because the Application Manager ' s knowledge and skills are still

relevant and there no threat to ' status ' .

C.

Yes, because highlighting cooperation provides an opportunity for the

Applications Manager to learn and develop.

D.

Yes, because praising people publicly helps to improve a person ' s

informal importance in the organization.

Full Access
Question # 8

Using the additional information provided for this question in the

Scenario Booklet, answer the following question about using Kotter ' s

eight-processes cyclical model. This model is being used for planning

and leading the change required to rebrand and reposition UniCo in the

market place.

Lines 1 to 4 in the table below consist of an assertion statement and a reason

statement. For each line identify the appropriate option, from options A to E,

that applies. Each option can be used once, more than once or not at all.

Full Access
Question # 9

For cognitive learning, which is the BEST example of providing ' learning feedback ' ?

A.

Giving supervisor feedback on return to work.

B.

Testing before and after learning.

C.

Reviewing learners’ ideas in a group discussion.

D.

Discussion at the learners ' next annual performance reviews.

Full Access
Question # 10

Sales staff failed to achieve last month’s sales targets when training in the mobile products and supporting sales systems and processes was first started. This month the sales team is working after hours and weekends to try to meet the current targets while developing the new skills needed. It is generally felt that this situation is unsustainable.

Which 2 actions by the Sales Director are the MOST appropriate when responding to this type of resistance?

A.

Visibly celebrate examples of the Sales staff using the new skills and systems.

B.

Allow those Sales staff with opposing attitudes to use the old systems in parallel.

C.

Identify the options available for moving people out of the Sales area to other jobs.

D.

Assign some of the sales team to work exclusively on developing the necessary skills.

E.

Provide a clear timetable of change to those Sales staff preparing for future operations.

Full Access
Question # 11

Which statement should be recorded under the Change Management Team and Relationships heading?

A.

The training available to UniCo staff needs to be realigned to include mobile application technology, so that the necessary skills are developed to support customers.

B.

The CEO seems to be a little concerned about taking the company in a different direction and his reservations need to be addressed.

C.

The Project Management Office has offered to provide support in planning, scheduling, monitoring, and control.

D.

The Sales staff need to understand how the changes will lead to greater opportunities for increased commissions before they are likely to participate.

Full Access
Question # 12

Answer the following question about Schein ' s concept of survival and learning

anxieties.

Column 1 is a list of messages about the change given to Sales staff. For each

message in Column 1, select from Column 2 the appropriate element of

Schein ' s concept of survival and learning anxieties. Each selection from

Column 2 can be used once, more than once or not at all.

Full Access
Question # 13

Which participant characteristic is likely to be the MOST appropriate to the success of a workshop to design a process?

A.

They understand the culture of the organization.

B.

They have a good history of change implementation.

C.

They are confident in discussing ideas with others.

D.

They are willing to be involved and enthusiastic.

Full Access
Question # 14

The Change Manager is looking to develop the change agent network that will support the changes related to the Operational delivery processes workstream.

Which approach is MOST likely to be relevant when deciding on the size of the change network for the Operational delivery processes workstream?

A.

Immediately assign two change agents as the fulfillment of the new contract will focus the change.

B.

Recruit change agents mainly from the IT support staff experiencing the most change.

C.

Select change agents in the Applications and IT Support areas to cover both locations.

D.

Involve as many agents as possible from the Selco staff to utilize their experience.

Full Access
Question # 15

(To keep Business Sponsor, Sarah, informed, Hira has set up a real-time dashboard displaying project progress, risks, and actions from planning events.

Will this meet Sarah ' s needs?)

A.

Yes, because she will have access to progress updates, removing all meeting dependency.

B.

Yes, because she can rely solely on the dashboard for all her updates.

C.

No, because dashboards lack the context and detail required for strategic decision-making.

D.

No, because she will need Hira to compile and present the data in a physical report for sharing.

Full Access
Question # 16

Resources are limited. The Sales Manager has two marketing assistants who

may be able to give a few hours a week between them to the project.

What action should the Project Manager take?

A.

Try to secure formal agreement as to how many hours per week the

marketing assistants will spend on the project.

B.

Accept that members of the Solution Development Team will be

inconsistent.

C.

Make each Timebox as long as possible to ensure the marketing

assistants have enough time to complete any work allocated to them

within the boundaries of the Timebox.

D.

Schedule the two marketing assistants to work at different times so they

can hand matters over to one another.

Full Access
Question # 17

The Business Ambassador assigned to the project is only available 2 days a

week. The Project Manager has stated that the Investigation stage for each

Timebox should, where possible, be planned around the availability of the

Business Ambassador.

Is this an appropriate application of the DSDM lifecycle?

A.

Yes, because this is where any final quality control checks should be

carried out to ensure all products meet the business need.

B.

Yes, because the Investigation stage of a Timebox requires intense

engagement with the Business Ambassador.

C.

No, because it is the Refinement stage of a Timebox that requires intense

engagement with the Business Ambassador.

D.

No, because Timeboxes are only used during Evolutionary Development

and at this point the Business Ambassador is NOT required.

Full Access
Question # 18

Several of the web developers working on the project have no Agile

experience. When answering the questions in the Project Approach

Questionnaire (PAQ), the Project Manager could not agree with the statement

' all members of the project understand and accept the DSDM approach ' .

What action should the Project Manager take?

A.

Replace the web developers with experienced Agile practitioners.

B.

Agree with the statement in the PAQ and keep a close watch on the web

developers throughout the project.

C.

Organize a training workshop to brief all project-level and Solution

Development Team roles in the Agile approach.

D.

Accept that the web developers are experts in their field and will be

adopting their own approach throughout the project.

Full Access
Question # 19

Time is running short and the Must Have requirements for the data entry screen

of the web page, as recorded in the Prioritised Requirements List, are not going

to be completed on time.

What action should the Project Manager take?

A.

Change the end date of the Timebox.

B.

Ensure that this issue is escalated to the project level roles.

C.

Amend the end date in the Delivery Plan.

D.

Accept that the Must Have requirements will not be delivered on time.

Full Access
Question # 20

Xan Insurance Company operates from one location - a large, open-plan

office in the centre of a city. Those employees that will be working within the

Solution Development Team are all based in this office but work at different

ends of the office in separate departments.

What action should the Project Manager suggest to ensure the most effective

collaboration of the Solution Development Team?

A.

Create an email group for the Solution Development Team to collaborate

on ideas.

B.

Set up a telephone or video conferencing facility so that all members of

the team can collaborate effectively.

C.

Relocate these employees to a new project area, with a number of desks

where the Solution Development Team can sit together.

D.

No action required as these employees are located in the same office.

Full Access
Question # 21

Xan Insurance Company is a friendly company with no separate private offices

for individual managers. Staff members prefer to wander around the office

space and have one-to-one chats rather than use email or have lots of

meetings.

What action should the Project Manager take when planning for effective

communication throughout the Web project?

A.

Identify those individuals with power and influence over the project and

what information they require.

B.

No action is required as the existing form of spontaneous informal

communication is suitable for all project level and Solution Development

Team members.

C.

As this is already common practice, assume all Solution Development

Team members have effective communication skills.

D.

Mandate the use of email so that all communications are recorded for

future reference.

Full Access
Question # 22

Which 2 statements represent appropriate entries for the plan for Post-Project

activities?

A.

The Sales Manager will create a company-wide email showing the

number of policies sold weekly by each of the sales assistants.

B.

Before the product is deployed, the Sales Manager will circulate a copy of

the revised sales procedure for processing coffee shop insurance sales.

C.

The Project Manager will attend Daily Stand-up meetings to observe

progress.

D.

A report showing the number of application forms completed online

through the website for coffee shop insurance policies will be produced

weekly.

E.

Once the new system has been deployed, the time it takes to process

sales online will be compared with the time it takes to process new

policies sold through telephone sales.

Full Access
Question # 23

The Solution Development Team are progressing through the first Structured

Timebox.

What should the Project Manager do to lead the team at this time?

A.

Maintain a tight control on progress, recording all discussions and making

all decisions.

B.

The Project Manager should do nothing during a Timebox.

C.

Attend the Daily Stand-up and discuss any problems at the end.

D.

Update the Team Board with a summary of team progress and the current

status of work.

Full Access
Question # 24

Which 2 statements represent appropriate entries for the Development

Approach Definition?

A.

The Sales Manager will introduce an awards or bonus scheme, designed

to create competition between the sales assistants.

B.

Once deployed, the number of policies sold through traditional telephone

sales will be compared with the number of sales processed online

through the website.

C.

An easy to use web development tool called ' WebMatrix ' is to be used to

develop and maintain the website extension.

D.

The Finance Director has requested a detailed report be produced after

12 weeks, showing costs to date and forecast cost to complete.

E.

Accessibility and performance of the new online quotation area is to be

tested using a tool called Sitebeam.

Full Access
Question # 25

Which 2 actions should the Project Manager take to implement the new Must

Have requirement?

A.

Check for any documented standards which need to be applied to the

development of online financial transaction functionality.

B.

Add the tasks required to develop the new financial transaction

functionality to the Delivery Plan.

C.

Update the Delivery Plan to show the new financial transaction

functionality as a deliverable.

D.

Source and hire a web developer with experience in developing online

financial transaction functionality.

E.

Consolidate and circulate an agenda for the workshop.

Full Access
Question # 26

Answer the following questions about the DSDM Lifecycle.

Decide if each observation is an appropriate application of Agile Project Management for

this project and select the option that supports your decision.

When the project was in the Feasibility phase it was initially proposed by the Finance

Manager that it was a fixed price for a fixed specification ' project. The Project Manager

has decided that the best way to tackle it would be to leave the development of the least

valuable features of the product until last.

Is this an appropriate application of the DSDM lifecycle?

A.

Yes, because the later parts of the project should reflect the least valuable features

of the product being built.

B.

Yes, because in a DSDM project there is no detailed specification upfront.

C.

No, because the Solution Development Team should decide which features are left

until last.

D.

No, because the most valuable features of the project should be delivered last.

Full Access
Question # 27

The Web Content Manager has provided the Web Developer with a mock up

of the ' Contact Us ' page, to be created for the new coffee bar insurance

product. When producing the code, the Web Developer has created a button

that reads ' Delete ' instead of ' Cancel ' .

What action should the Web Content Manager take?

A.

Prepare a defence for when the problem is identified, ensuring the

responsibility is with the Web Developer.

B.

Hide the problem and hope that this detail can be changed at a later date.

C.

Raise an issue to the Project Manager when the solution is deployed.

D.

Discuss the issue with the Web Developer and decide what action is

required to change this detail.

Full Access
Question # 28

Column 1 is a list of individuals from within the Xan Insurance Company

and their key responsibility within the Web project.

For each individual in Column 1, select from Column 2 the Agile Project

Management team role they are fulfilling. Each selection from Column 2 can

be used once, more than once or not at all.

Column 1

Manager of Web & Digital

Media - will oversee and report

progress on the delivery of the

overall system.

Finance Director - has

budgetary control and will

release finance for the project

subject to expected benefits.

Sales Manager - will formulate

design options for new

business processes that do not

adversely affect business as

usual.

Operations Manager - oversees

the design and integrity of the

technical aspects of the

solution.

Column 2

    Business Sponsor

    Business Analyst

    Business Ambassador

    Business Advisor

    Solution Developer

    Technical Coordinator

    DSDM Coach

    Project Manager

Full Access
Question # 29

Using the Project Scenario and the additional information provided for

this question in the Scenario Booklet, answer the following question

about assigning the Agile Project Management team roles within this

project.

Lines 1 to 5 in the table below consist of an assertion statement and a

reason statement. For each line identify the appropriate option, from options

A to E. that applies. Each option can be used once, more than once or not

at all.

Full Access
Question # 30

The building has had all the old utility services removed and new wiring and plumbing is being installed during Evolutionary Development. On average there are

four electrical and six plumbing contractors who are engaged for between a few days and a few weeks. They are finding it difficult to work round each other and

to know who should be where. Some of the contractors have started to turn up late to the site.

Many floor boards have been lifted in preparation but it is not clear where the radiators are being situated or when each room is going to be worked on by the plumbers. The

Chief Accountant, acting as Business Ambassador, is also alarmed that the electrical sockets are being installed in rooms in inaccessible locations.

Answer the following questions about motivating the contractor teams according to Agile Project Management.

How should the Project Manager encourage the resources to operate more successfully?

A.

Facilitate a workshop with the Solution Development Team to establish a co-ordinated Timebox Plan.

B.

Hold a separate Daily Stand-up meeting for contractors only.

C.

Provide a detailed plan of activity for each contractor team.

D.

Schedule the electrical and plumbing teams so that they work on different Timeboxes.

Full Access
Question # 31

Using the Project Scenario and the additional information provided for

this question in the Scenario Booklet, answer the following questions

about Feasibility.

Remember to limit your answers to the number of selections requested in each

question.

Which 2 statements describe the appropriate application of Agile Project

Management when developing the Feasibility Assessment?

A.

The new Project Manager should NOT be involved in finalising the

Feasibility Assessment.

B.

The Architecture Angels ' Finance Director should approve the final

Business Case as part of the Feasibility Assessment.

C.

The Earth Excavations ' Head Gardener should contribute to the outline

solutions considered for the gardens.

D.

The different options should be presented to the ' Hoy for Hoy Hall ' Action

Group for their feedback before the chosen outline solution is finalised.

E.

The Timber Tigers ' Site Manager should be the sole approver of the

finalised Feasibility Assessment before development commences.

Full Access
Question # 32

What action should the Project Manager take to plan the deployment activities?

A.

Prepare a Timebox Plan for the next Development Timebox.

B.

Check the Delivery Plan for deployment activities and update as required.

C.

Create a plan of activities to deploy the solution at the end of Timebox C.

D.

Update the Timebox Plan for Timebox C with the activities required to deploy the solution.

Full Access
Question # 33

Which 2 statements explain why the Architecture Angels ' Operations Director would be an appropriate Business Advisor?

A.

Is in charge of providing appropriate scenarios to check the security systems.

B.

Is one of the original four founders of the company.

C.

Can provide input about problems experienced by the people who run the hotels.

D.

Has specialist knowledge about the targets for staff performance.

E.

Has been involved with monitoring the progress of previous company projects.

Full Access
Question # 34

Once the change of priority has been approved, who is then responsible for including the requirement for a secondary exit from the upstairs of the building to the Timebox

Plan for Timebox B?

A.

Marketing Director, in the role of Business Visionary.

B.

Team Leader.

C.

Project Manager and Architect, in the role of Technical Co-ordinator.

D.

Architecture Angels ' Senior Management Team.

Full Access
Question # 35

Review sessions have been scheduled at end of Investigation, Refinement and Consolidation for the later Timeboxes to ensure that the mistakes made in Timebox A do not

happen again.

Which Agile principle MOST influences this course of action?

A.

Focus on the business need.

B.

Deliver on time.

C.

Build incrementally from firm foundations.

D.

Demonstrate control.

Full Access
Question # 36

What should be done to allow the requirement for a secondary exit from the upstairs of the building to be changed into a Must Have priority and moved into Timebox B?

A.

The Project Manager should extend the timescale of Timebox B and shorten Timebox C.

B.

The Solution Development Team should change a Must Have requirement into a Should Have in the Prioritised Requirements List.

C.

The Business Visionary, Business Sponsor and Solution Development Team should reassess the Prioritised Requirements List and its priorities.

D.

The Project Manager should move a Must Have requirement from Timebox B into Timebox C.

Full Access
Question # 37

Using the project timeline given in the Project Scenario, answer the following question about application of Timeboxing on the Hoy Hall project.

Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies.

Each option can be used once, more than once or not at all.

Assertion :

1. All internal works to be assigned to Timber Tigers throughout the project should be consolidated into one Structured Timebox.

BECAUSE

The Investigation step within each Structured Timebox requires everyone working within the team to jointly agree how the requirements of the Timebox will be met.

2. Acceptance criteria for the front rooms to be developed in Timebox A should be described in detail and agreed during the Timebox Kick-Off

BECAUSE

The aim of the Investigation step within each Timebox is to complete as much of

the development work as possible.

3. It is appropriate that both the Evolutionary Development phase and Deployment phase are shown in the first Project Increment.

BECAUSE

Each Timebox should comprise an Evolutionary Development phase and

Deployment phase.

4. It is appropriate that the outputs of Timebox C are scheduled for deployment at the end of the first Project Increment.

BECAUSE

A typical Timebox Plan should provide a schedule of high-level activities for the

imminent Project Increment.

5. It is appropriate that Earth Excavations create a detailed plan of activities they will complete during Timebox C.

Reason

BECAUSE

The Solution Development Team is responsible for planning the detail of all the

work of each Timebox.

Full Access
Question # 38

(Which one of the following actions should Hira take to balance the benefit of agile leadership whilst ensuring alignment of the Project Increment with project objectives?)

A.

Create a Delivery Plan outlining high-level activities for an aligned Eco-spa solution.

B.

Organize workshops with Brinda, the Delivery Teams and stakeholders to co-create a shared vision.

C.

Delegate to Team Leaders the task of defining deliverables that align with Brinda ' s vision.

D.

Collaborate with Brinda and Sukra to define actionable Product Backlog items.

Full Access
Question # 39

As Sprint 5 comes to an end, the Infrastructure Delivery Team is facing delays due to:

. Heavy rainfall affecting the Wellness Garden.

. Local supplier issues causing material delivery delays.

· Dependency on external contractors for hydrotherapy equipment.

The Operations Delivery Team is unable to finalize details of the hydrotherapy treatments without testing them in the

context of the facilities being constructed. The marketing materials cannot be generated until this work is complete.

In addition to the Developers, the teams include:

(The Wellness Garden (a Should Have) is delayed. Sukra Aroon suggests a workaround, using the River Pool Patio instead, and classifying the Garden as a ' Won ' t Have this time ' .

Is this an appropriate suggestion?)

A.

Yes, because reclassifying the garden reduces risk while maintaining an outdoor option.

B.

Yes, because unresolved dependencies justify removing requirements to prevent disruption.

C.

No, because a Should Have requirement should NOT be removed unless it threatens the delivery of a Must Have.

D.

No, because workarounds reduce quality and undermine the business case.

Full Access
Question # 40

(During Sprint Planning, the Delivery Team identifies a potential risk in integrating Spa systems with the resort ' s client management system.

Which 2 statements describe how this risk should be handled within the AgilePM framework?)

A.

Escalate immediately to Hira who will devise and implement a mitigation plan.

B.

The Delivery Team should address technical challenges collaboratively while keeping project-level roles informed.

C.

Hira should instruct Sukra Aroon to resolve the issue independently to ensure there is no risk to the overall solution.

D.

The Delivery Team should escalate to project level roles and focus on other work until a resolution is found.

E.

Hira should coordinate with Sukra Aroon and Brinda Vyas to align team risk management activities with overall project priorities.

Full Access
Question # 41

(Hira is considering splitting the Developers into two Delivery Teams: one focused on Spa infrastructure and the other on guest experience. Mira Bachar, the Guest Services Manager, will be the Product Owner for both teams.

Which one of the following statements support Hira ' s proposed Delivery Team structure?)

A.

The Guest Experience team can dictate the Infrastructure team priorities, ensuring guest satisfaction.

B.

Each Delivery Team can work independently, delivering valuable increments without needing to coordinate with the other.

C.

Each Delivery Team can refine their own practices without unnecessary distractions from other skill sets.

D.

Collaboration within specialized teams improves communication and commitment to goals.

Full Access
Question # 42

(Which 2 statements describe appropriate team behaviour for effective risk management?)

A.

Team members should adopt a collaborative mindset, sharing responsibility for identifying and mitigating risks.

B.

Hira should have sole responsibility for managing all risks with clear accountability.

C.

Developers should resolve all risks collaboratively and promptly without escalation.

D.

Sukra Aroon should handle all technical risks independently to ensure the solution is fit for purpose.

E.

Risk management should be proactive and part of daily activities, not a separate process.

Full Access
Question # 43

Mira Bachar has spoken with a guest who wanted an aromatherapy scent to remember their holiday. Inspired by this, Mira suggested creating a unique aromatherapy oil for spa treatments and guest sales, which could also serve as a marketing tool.

Brinda Vyas supports exploring the idea, but Sukra Aroon notes that selling products is not in scope and could introduce complexities.

(Which 2 of the following actions align with AgilePM practices for defining and estimating the work of Project Increment 4 during the Foundations phase?)

A.

Conduct a full analysis of Spa treatments to create a fixed guest service specification.

B.

Host a stakeholder workshop to prioritize integrating the Spa into the resort experience.

C.

Develop high-level estimates of effort and cost for Spa facilities and IT systems.

D.

Prepare a risk report on aligning Spa services with guest experience.

E.

Define work items in enough detail for Developers to start design work on treatments.

Full Access
Question # 44

Mira Bachar has spoken with a guest who wanted an aromatherapy scent to remember their holiday. Inspired by this, Mira suggested creating a unique aromatherapy oil for spa treatments and guest sales, which could also serve as a marketing tool.

Brinda Vyas supports exploring the idea, but Sukra Aroon notes that selling products is not in scope and could introduce complexities.

(When defining and estimating work for Project Increment 4, the Delivery Teams must account for uncertainty in integrating the Eco-spa into the guest experience.

Which 2 of the following approaches align with AgilePM principles for managing uncertainty in estimation?)

A.

Use broad estimation ranges for high-uncertainty work and refine estimates as more information becomes available.

B.

Avoid committing to estimates for uncertain work until all unknowns are resolved.

C.

Identify key assumptions behind estimates and revisit them regularly as the project evolves.

D.

Ensure all estimates are fixed early to maintain control over scope and budget.

E.

Exclude uncertain work from estimation until development is underway and clearer details emerge.

Full Access
Question # 45

As Sprint 5 comes to an end, the Infrastructure Delivery Team is facing delays due to:

. Heavy rainfall affecting the Wellness Garden.

. Local supplier issues causing material delivery delays.

· Dependency on external contractors for hydrotherapy equipment.

The Operations Delivery Team is unable to finalize details of the hydrotherapy treatments without testing them in the

context of the facilities being constructed. The marketing materials cannot be generated until this work is complete.

In addition to the Developers, the teams include:

(Hira decides to update the Delivery Plan to prioritize the delivery of the hydrotherapy facilities first for early testing.

Is this action appropriate?)

A.

Yes, because the Delivery Plan should adapt to real-world conditions.

B.

Yes, because all sequencing changes should be documented in the Delivery Plan.

C.

No, because the Delivery Plan is fixed after the Foundations phase unless a Must Have requirement is at risk.

D.

No, because sequencing should be a collaborative decision, not determined by Hira alone.

Full Access
Question # 46

During the Foundations phase for Project Increment 4, Sukra Aroon held a meeting with Hira, Mira Bachar, andWanida Anong, to ensure alignment and compliance with EPR company policies, local regulations, and international standards. The meeting also clarified how financial and investment decisions would be made for Project Increment 4, ensuring alignment with EPR business priorities, and how this information will be tracked,

controlled and evidenced.

Wanida Anong, who works across multiple sites worldwide, attended the meeting in person but has limited availability throughout the Project Increment.

(During the meeting, Mira Bachar asked Sukra Aroon which AgilePM project artifacts should use to provide an auditable record of compliance requirements throughout Project Increment 4.

Based on AgilePM guidance, which of the following is an appropriate response?)

A.

Use the Management Approach Definition, as it describes how governance and compliance responsibilities are structured within the project.

B.

Use the Project Review Report, as it provides a retrospective assessment of how the project was managed, including compliance considerations.

C.

Use the Sprint Review Records, as these document what was delivered in each Sprint and whether it was compliant with regulatory requirements.

D.

Use the Solution Architecture Definition, as it captures technical decisions related to compliance and regulatory requirements.

Full Access
Question # 47

Brinda Vyas and Mira Bachar have agreed to use content from a marketing brochure to describe guest-centric Product Goals for the Eco-Spa. These goals describe specific treatments that the Spa might offer and will be used to identify prioritizable Product Backlog items that could contribute to that treatment. One such Product Goal is described as:

Hydrotherapy in Mineral-Rich Spring Pools

Immerse yourself in mineral-rich hydrotherapy pools designed to soothe muscies, improve circulation, and promote

deep relaxation. Experience the gentle power of temperature-controlled waters and therapeutic massage jets in a lush

and tranquil tropical garden setting and let nature ' s healing embrace rejuvenate both your body and your mind.

In addition to the Developers, the teams include:

(Which one of the following actions will ensure that Product Backlog items for the Hydrotherapy infrastructure remain aligned with the planned treatment experience throughout development?)

A.

The Infrastructure Team should regularly review and refine Backlog items with Mira Bachar to maintain alignment.

B.

Lock all Backlog items after initial prioritization to prevent scope change and allow the Infrastructure Team to focus on delivering them.

C.

Frequently reassess the priority of Product Backlog items to ensure the Infrastructure Team remain focused on the highest value features.

D.

Encourage the Infrastructure Team to prioritize features for the hydrotherapy treatments since they understand what can be achieved within each Sprint.

Full Access
Question # 48

Midway through Project Increment 4, a joint Sprint Retrospective is held with Developers from both Delivery Teams.

Some members from Marketing and IT, based in India, join via video conferencing.

Issues raised:

. Dependency management challenges

· Concerns about AgilePM principle ' Demonstrate Control '

To address this, Mira Bachar and the Developers invite Hira and Sukra Aroon to help Delivery Teams understand the

issues, assess the consequences, and collaborate on solutions that align with AgilePM and Scrum.

In addition to the Developers, the teams include:

(Developers in the Infrastructure Team report integration issues between climate control and lighting systems, leading to an excessive energy demand beyond the capacity of the solar panels.

Which 2 of the following actions align with the AgilePM guidance on addressing risk?)

A.

Extend the length of the Sprint to allow time to resolve integration issues.

B.

Document all integration risks and have Sukra Aroon decide appropriate mitigation actions.

C.

Add integration testing to acceptance criteria for relevant Backlog items.

D.

Include explicit integration test scenarios in the Sprint Backlog.

E.

Schedule integration workshops at the end of the all Sprints to address any integration concerns.

Full Access
Question # 49

Mira Bachar has spoken with a guest who wanted an aromatherapy scent to remember their holiday. Inspired by this, Mira suggested creating a unique aromatherapy oil for spa treatments and guest sales, which could also serve as a marketing tool.

Brinda Vyas supports exploring the idea, but Sukra Aroon notes that selling products is not in scope and could introduce complexities.

(Mira Bachar is running a workshop with Sukra Aroon and Developers, to create an initial Product Backlog.

Which 2 of the following actions will help shape the Backlog?)

A.

Ensure all Product Backlog items contain detailed specifications with fixed priorities.

B.

Capture dependencies between Product Backlog items to proactively prevent blockers in development.

C.

Prioritize Product Backlog items based on speed of completion to ensure rapid delivery.

D.

Allow Product Backlog flexibility so it evolves based on feedback and business needs.

E.

Keep business and technical Product Backlog items separate for oversight by Brinda Vyas and Sukra Aroon.

Full Access
Question # 50

Midway through Project Increment 4, a joint Sprint Retrospective is held with Developers from both Delivery Teams.

Some members from Marketing and IT, based in India, join via video conferencing.

Issues raised:

. Dependency management challenges

· Concerns about AgilePM principle ' Demonstrate Control '

To address this, Mira Bachar and the Developers invite Hira and Sukra Aroon to help Delivery Teams understand the

issues, assess the consequences, and collaborate on solutions that align with AgilePM and Scrum.

In addition to the Developers, the teams include:

(Another of the EPR Eco-spa ' s commissioned in India experienced major quality issues, causing a three-week shutdown. Stakeholders are now worried about similar problems in Project Increment 4.

Which 2 of the following actions would appropriately reassure stakeholders that the same quality issues will not arise in this project?)

A.

Engage stakeholders in Sprint Reviews and encourage detailed quality discussions on delivered increments.

B.

Define and make visible quality criteria for Backlog items, and ensure the Delivery Teams collectively confirm compliance before declaring ' Done ' .

C.

Explain to stakeholders that AgilePM prevents quality issues through iterative development, incremental delivery, and continuous improvement.

D.

Appoint an independent Quality Manager to approve completed work before it is released.

E.

Review the India project ' s issues with stakeholders and demonstrate how Project Increment 4 addresses them differently.

Full Access
Question # 51

There are several tests planned throughout the project to ensure the solution is fit for purpose and to validate the business solution as

it evolves.

Column 1 is a list of tests. For each test in Column 1, select from Column 2 the testing concept that it represents. Each selection from Column 2

can be used once, more than once or not at all.

Column 1

1) In order to get an objective

view, the financial transaction

function is to be tested by

someone from Finance who

has had no involvement in its

development.

2) Before the developer works on

the printing function for the

policy documents, the Sales

Manager will review a prototype

of the online application form

for the new coffee shop

insurance product with the

solution tester.

3) Security test scripts have been

provided by the company ' s

bank. These scripts will be used

to test the link from the

company ' s website to the

banking system, which is to be

developed specifically to achieve these tests

4.

The addition of the new coffee

shop insurance product may

threaten the stability of the

existing website. As a primary

route to market this is

unacceptable. The website ' s

capacity to run additional pages

is to be verified before any

other tests are performed.

5.

The Must Have and Should

Have requirements are to be

tested before the Could Have

requirements.

Column 2

    Collaborative Testing

    Repeatable Testing

    Independent Testing

    Prioritised Testing

    Test-Driven Development

Full Access
Question # 52

Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following question about the

responsibilities of the roles in the Agile team.

Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies.

Each option can be used once, more than once or not at all.

Assertion

    The Marketing Director, in the role of Business Visionary, is empowered to overrule cost restrictions advised by the Chief Accountant, who is appointed as Business Ambassador.

BECAUSE

The Project-level roles are responsible for directing, managing and co-

ordinating the project.

    The Procurement Manager is an appropriate representative of the end user of the solution.

BECAUSE

The Business Ambassador should be empowered to make decisions within

the boundaries of their role, without referral to higher authorities outside

the Solution Development Team.

    The other specialist gardening team members from Earth Excavations would be suitable as Solution Developers, assigned alongside the Head Landscape Gardener.

BECAUSE

Extra Solution Developers can provide a supporting role for a Lead

Developer.

    The ' Hoy for Hoy Hall ' Action Group members should be assigned as Business Ambassadors.

BECAUSE

The Business Ambassador is responsible for ensuring that business needs

are properly analysed.

    The Project Manager should plan the communication needed between the Marketing Director, in the role of Business Visionary, and the ' Hoy for Hoy Hall ' Action Group.

BECAUSE

The Business Visionary is responsible for promoting the business vision to

all interested parties.

Full Access
Question # 53

How should the Project Manager encourage the contractors to turn up on time?

A.

Place a penalty clause on all contractors for late arrival.

B.

Appoint Team Leaders to each of the electrical and plumbing teams.

C.

Encourage open and honest communication to re-establish an environment of trust.

D.

Hold a separate Daily Stand-up meeting early in the morning, for the contractors only.

Full Access
Question # 54

Which 2 statements explain why the Contract Architect would be an appropriate Technical Co-ordinator?

A.

Is an external consultant.

B.

Has good leadership skills.

C.

Has experience of working with the company previously.

D.

Has a good, technical understanding of the work of the other professionals engaged in the project.

E.

Is an authority on local planning applications.

Full Access
Question # 55

Answer the following questions about the acceptance criteria within the project.

Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.

The requirement to ' install a heat reclamation system ' shows as a Should Have in the Prioritised Requirements List. During Investigation in Solution Development Timebox B, the Project Manager advised the team NOT to set detailed acceptance criteria for this requirement until later in the Timebox, since the requirement may have to be dropped and the work would be wasted.

Is this an appropriate action related to acceptance criteria?

A.

Yes, because only Must Have requirements should be fully understood.

B.

Yes, because the acceptance criteria might need to be changed during the Solution Development Timebox.

C.

No, because it is necessary to understand the full detail of all the work for completion in the Solution Development Timebox during Investigation.

D.

No, because it indicates that the Solution Development Team has NO intention of delivering the Should Have requirements.

Full Access