AD0-E911 Adobe Workfront Project Manager Certified Professional Question and Answers

Question # 4

A project manager is managing a project and realizes a task is delayed. They want to see how downstream tasks are impacted.

Which feature of the Gantt chart will help them understand this?

A.

Actual Dates

B.

% Complete

C.

Critical Path

Full Access
Question # 5

A project manager is looking to create a task that must take place from September 10th through September 17th of this year.

Which action must be taken?

A.

Set the Task Constraint to Fixed Dates.

B.

Set a Predecessor for the task.

C.

Set the Duration of One week.

Full Access
Question # 6

A client has negotiated a discounted billing rate for video editing in a specific initiative.

How can the project manager override the default billing rate for the Video Editor within a project?

A.

Temporarily change the billing rate for the Video Editor in the Workfront system, and then reset it once the client has been billed.

B.

Add a new billing rate to all tasks that involve video editing.

C.

Add a new billing rate within the project.

Full Access
Question # 7

A task was originally planned with a 10-day duration and 40 planned hours. The client needs it done in 3 days.

What task setting needs to change to allow 4 users to complete this in less than 3 days?

A.

Change the Task Duration Type to Effort Driven

B.

Change the Task Duration Type to Calculated Work

C.

Change the Task Constraint to Fixed Dates

D.

Change the Task Constraint to As Soon As Possible

Full Access
Question # 8

Task 2 has a 5-day duration, is tied to Task 1 with a predecessor, and is expected to begin once Task 1 is completed. Due to a resource availability conflict, Task 1 was rescheduled to start 1 week later. Once Task 1 was rescheduled, the planned start date on Task 2 did not dynamically shift by 5 days as expected but instead remained the same planned start date that existed before the change to Task 1.

What may have caused the planned start date of Task 2 to remain the same?

A.

The primary assignee had already submitted a Commit Date for the previous planned start date on Task 2, even though the project owner did not accept this Commit Date, the project plan made this date a Must Start On Constraint on Task 2.

B.

The project owner has at some point made a manual change to the planned start date of Task 2, which has in turn changed the Task Constraint of Task 2 to Must Start On.

C.

The primary assignee had scheduled time off during the new planned start date that Task 2 should have shifted toward. Due to this time off scheduled the date remained the same.

D.

The project owner has at some point made a manual change to the Task Constraint of Task 2 to As Soon As Possible, which has forced the date of Task 2 to be static.

Full Access
Question # 9

A company has decided that all projects for the year need to be created from templates and staffed in the following quarter. The projects will need to remain in a backlog until the team has capacity to work on them. There has been confusion previously because the team used Planning status for all work not started.

What should the project manager do to help the team see the difference between work in the backlog versus work that is now being planned?

A.

Load the project template once the team has bandwidth to start on the project.

B.

Create projects but leave the roles in place without assigning users.

C.

Create a custom status for Backlog to use prior to using the Planning status.

Full Access
Question # 10

An organization has created unique data fields relevant to their projects. Starting by navigating from a project ' s landing page, where is this data found?

A.

Project Details > Custom Forms

B.

Project Details > Overview

C.

Business Case > Project Info

Full Access
Question # 11

What occurs when an individual enters a new commit date that is after the original planned date of a task?

A.

The assignee of any task that has the original task set as a predecessor is notified.

B.

The Project Owner is notified whether this change will impact the Project Timeline.

C.

The Planned Completion Date of the task automatically changes to match the new Commit Date.

Full Access
Question # 12

An IT department needs to see the Group and Portfolio of each of its projects for reporting purposes.

In which project area does this information reside?

A.

Queue Details

B.

Project Details

C.

Metrics

Full Access
Question # 13

A project manager needs to see specific tasks and issues across all of their projects in a single view. The project manager only needs to see tasks and issues that are currently pending approval, and the results should be grouped by project. What steps should the project manager take to create this view?

A.

Visit the Project page and create a new filter. Update the " Pending Approval " filter to " true " and update the Project Owner ID field to the project manager’s name. In the grouping tab, add a grouping for project name.

B.

Visit the Reports page and create a task report and an issue report. In the filter tab for each report, update the " Pending Approval " filter to " true, " and update the Project Owner ID field with the project manager’s name. In the grouping tab for each report, add a grouping for project name. Add both reports to a new dashboard.

C.

Visit the Reports page and create a Pending Approvals report. In the filter tab, update the Project Owner ID field with the project manager’s name and update the Object ID field to " tasks " and " issues. " In the grouping tab, add a grouping for project name.

Full Access
Question # 14

A team lead needs to regularly report on the adherence of budget and timeline of a group of projects.

What should the team lead use to organize these projects to allow them to be tracked together?

A.

Layout template

B.

Program

C.

Group

Full Access
Question # 15

What do the green symbols in the report below signify?

A.

On Time

B.

At Risk

C.

Late

Full Access
Question # 16

How would a project manager create a custom Workfront report to show information about issues logged to the projects they own?

A.

Visit the Dashboard page, create a new Issue report, and update the Issue Owner ID filter with their name, and group by project name.

B.

Visit the Reports page, create a new Project report, update the Project Owner ID filter with their name, and add a column for issues.

C.

Visit the Reports page, create a new Issue report, update the Project Owner ID filter with their name, and group by project name.

Full Access
Question # 17

Executive stakeholders require both current metric reports and a weekly recap on a project.

How can both needs be met?

A.

Create a program-specific dashboard for the metrics and set up a weekly automated report to send.

B.

Create a program-specific dashboard for the metrics, then download a dashboard weekly to email to the stakeholder team.

C.

Create a program-specific dashboard for the metrics and add a calendar reminder for the team to review the report.

Full Access
Question # 18

Which project status will default the automatic Project Condition to “On Time”?

A.

Idea

B.

Planning

C.

On Hold

Full Access
Question # 19

A team member has five days to complete a critical path task, and the task requires only one hour. Today is the fourth day in the timeframe, and the team member has not yet worked on it.

What impact does this have on the project progress status?

A.

The next team member cannot start his task.

B.

No impact as the task is not overdue.

C.

The project shows an At Risk automatic condition.

Full Access
Question # 20

What are two ways to associate milestone steps to tasks? (Choose two.)

A.

In-line editing a task list on a project

B.

From the Milestone View in the Projects area

C.

Through bulk-editing multiple tasks

D.

In the settings area of a task

Full Access
Question # 21

A project manager would like to see the Budgeted Variances between the hours for the current week. Where is that information found at the project level?

A.

Utilization section

B.

Hours tab

C.

Finance section

Full Access
Question # 22

Taking into consideration any applied task constraints, a project manager needs to know the date that a task is likely to be finished based upon the current progress of the task and its predecessors. Which date type should the project manager utilize?

A.

Projected Date

B.

Planned Date

C.

Estimated Date

Full Access
Question # 23

Which two statements are true about Groups and Teams? (Choose two.)

A.

A Team can be assigned to a task, but a Group cannot be assigned to a task.

B.

Objects can be shared with either a Group or a Team.

C.

A Group can be assigned to a task, but a Team cannot be assigned to a task.

D.

Work requests can be routed to either a Group or a Team.

Full Access
Question # 24

An assignee clicks Work On It for a task, and a new finish date appears on the task while the original planned finish stays the same.

What does this new date communicate to the project manager?

A.

It indicates that the assignee’s finish date is wrong and should be ignored.

B.

It indicates that the assignee’s finish date replaces the Planned Completion Date.

C.

It indicates the assignee’s own estimate of when they expect to finish the task, which can differ from the Planned Completion Date.

Full Access
Question # 25

A project manager is asked to provide a list of all projects the Marketing Group is working on for Acme Company.

What steps should the project manager take to create a custom Workfront report with this information?

A.

Visit the Reports page, create a new Project report, and add filters for Company ID and Group ID.

B.

Visit the Reports page, create a new Project report, and add filters for Company ID and Owner ID.

C.

Visit the Reports page, create a new Project report, and add filters for Owner ID and Project Status.

Full Access
Question # 26

A portfolio owner has asked to see milestone statuses for all projects in their portfolio. The report must filter out any complete projects. What steps should the project manager take to create this view?

A.

Visit the Dashboards page and create a Milestone Path report. In the filter, update the Portfolio Owner ID to the Portfolio Owner’s name and update the Project Status to exclude complete projects.

B.

Visit the Projects page and create a Milestone Path report. In the filter, update the Portfolio Owner ID to the Portfolio Owner’s name and update the Project Status to exclude complete projects. In Report Options, select " Show the Milestone view on the Details tab. "

C.

Visit the Reports page and create a Project report. In the filter, update the Portfolio Owner ID to the Portfolio Owner’s name and update the Project Status to exclude complete projects. In Report Options, select " Show the Milestone view on the Details tab. "

Full Access
Question # 27

A company expects managers to complete a Workfront Business Case and submit it to the Project Sponsor for approval before a project enters Planning status.

What Workfront process will effectively facilitate the Project Sponsor review?

A.

Request Approval Process

B.

Request Submission Process

C.

Project Submission Process

D.

Project Approval Process

Full Access
Question # 28

A project manager has set up and launched a new project for an annual marketing campaign.

Where can the project team locate their work requests?

A.

Email, Workfront Home, Project tasks list

B.

Email, Automatic Reminders, Workfront Home

C.

Event Notifications, Approval processes, Email

Full Access