Labour Day Sale - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: mxmas70

Home > PMI > CAPM > CAPM

CAPM Certified Associate in Project Management (CAPM) Question and Answers

Question # 4

A project manager at a publishing company decides to initiate the editing phase of the project as soon as each chapter is written. Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start relationship with a 15-day delay?

A.

Slack

B.

Float

C.

Lag

D.

Lead

Full Access
Question # 5

The diagram below is an example of a:

A.

Risk breakdown structure (RBS).

B.

Project team.

C.

SWOT Analysis.

D.

Work breakdown structure (WBS).

Full Access
Question # 6

Which baselines make up the performance measurement baseline?

A.

Scope baseline, cost baseline, and schedule baseline

B.

Scope baseline, project management baseline, and quality baseline

C.

Cost baseline, schedule baseline, and risk baseline

D.

Cost baseline, project management baseline, and schedule baseline

Full Access
Question # 7

Which of the following is an output of Close Procurements?

A.

Accepted deliverables

B.

Organizational process assets updates

C.

Managing stakeholder expectations

D.

Performance reports

Full Access
Question # 8

Which of the following are an enterprise environmental factor that can influence the Identify Risks process?

A.

Work performance reports

B.

Assumptions logs

C.

Network diagrams

D.

Academic studies

Full Access
Question # 9

The process improvement plan details the steps for analyzing processes to identify activities which enhance their:

A.

quality.

B.

value.

C.

technical performance.

D.

status.

Full Access
Question # 10

A tool and technique used during the Define Scope process is:

A.

facilitated workshops.

B.

observations.

C.

questionnaires and surveys.

D.

group creativity techniques.

Full Access
Question # 11

The process to ensure that appropriate quality standards and operational definitions are used is:

A.

Plan Quality.

B.

Perform Quality Assurance.

C.

Perform Quality Control.

D.

Total Quality Management.

Full Access
Question # 12

Which type of diagram includes groups of information and shows relationships between factors, causes, and objectives?

A.

Affinity

B.

Scatter

C.

Fishbone

D.

Matrix

Full Access
Question # 13

Expected monetary value (EMV) is computed by which equation?

A.

Value of each possible outcome multiplied by probability of occurrence

B.

Value of each possible outcome multiplied by probability of non-occurrence

C.

Multiplying the value of each possible outcome by the probability of occurrence and adding the products together

D.

Multiplying the value of each possible outcome by the probability of non-occurrence and adding the products together

Full Access
Question # 14

After Define Activities and Sequence Activities, the next process is:

A.

Estimate Activity Resources.

B.

Estimate Activity Durations,

C.

Develop Schedule.

D.

Control Schedule.

Full Access
Question # 15

Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?

A.

Reserve analysis

B.

Three-point estimating

C.

Parametric estimating

D.

Analogous estimating

Full Access
Question # 16

How should a stakeholder who is classified as high power and low interest be grouped in a power/interest grid during stakeholder analysis?

A.

Keep satisfied

B.

Keep informed

C.

Manage closely

D.

Monitor

Full Access
Question # 17

Which process is responsible for monitoring the status of the project and product scope and managing changes to the scope baseline?

A.

Variance Analysis

B.

Define Scope

C.

Verify Scope

D.

Control Scope

Full Access
Question # 18

In which type of contract are the performance targets established at the onset and the final contract price determined after completion of all work based on the sellers performance?

A.

Firm-Fixed-Price (FFP)

B.

Fixed Price with Economic Price Adjustments (FP-EPA)

C.

Fixed-Price-Incentive-Fee (FPIF)

D.

Cost Plus Fixed Fee (CPFF)

Full Access
Question # 19

Exhibit A is an example of which of the following types of Sequence Activities?

A.

Activity-on-arrow diagramming

B.

Precedence diagramming

C.

Project schedule network diagramming

D.

Mathematical analysis diagramming

Full Access
Question # 20

Which of the following includes how requirements activities will be planned, tracked, and reported?

A.

Configuration management plan

B.

Scope baseline

C.

Requirements management plan

D.

Schedule baseline

Full Access
Question # 21

The cost benefit analysis tool is used for creating:

A.

Pareto charts.

B.

quality metrics.

C.

change requests,

D.

Ishikawa diagrams.

Full Access
Question # 22

Which quality control technique illustrates the 80/20 principle?

A.

Ishikawa diagram

B.

Control chart

C.

Run chart

D.

Pareto chart

Full Access
Question # 23

Which of the following is a tool or technique used in the Acquire Project Team process?

A.

Networking

B.

Training

C.

Negotiation

D.

Issue log

Full Access
Question # 24

Which type of dependency is contractually required or inherent in the nature of the work?

A.

External

B.

Lead

C.

Discretionary

D.

Mandatory

Full Access
Question # 25

Which input will be used when tasked with developing the human resource plan?

A.

Project management plan

B.

Activity resource requirements

C.

Resource calendar

D.

Project staff assignments

Full Access
Question # 26

At the completion of a project, a report is prepared that details the outcome of the research conducted on a global trend during the project. Which item did this project create?

A.

Result

B.

Product

C.

Service

D.

Improvement

Full Access
Question # 27

A project manager who communicates to the project team though email is using which type of communication?

A.

Formal

B.

Informal r

C.

Horizontal

D.

Unofficial

Full Access
Question # 28

The following is a network diagram for a project.

The total float for the project is how many days?

A.

5

B.

9

C.

12

D.

14

Full Access
Question # 29

Which action is included in the Control Costs process?

A.

Identify how the project costs will be planned, structured, and controlled

B.

Determine policies, objectives, and responsibilities to satisfy stakeholder needs

C.

Develop an approximation of the monetary resources needed to complete project activities

D.

Monitor cost performance to isolate and understand variances from the approved cost baseline

Full Access
Question # 30

Which Define Activities tool or technique is used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts?

A.

Decomposition

B.

Inspection

C.

Project analysis

D.

Document analysis

Full Access
Question # 31

Plan Communications Management develops an approach and plan for project communications based on stakeholders' needs and requirements and:

A.

Available organizational assets

B.

Project staff assignments

C.

Interpersonal skills

D.

Enterprise environmental factors

Full Access
Question # 32

Variance and trend analysis is a tool and technique used in which process?

A.

Perform Qualitative Risk Analysis

B.

Perform Quantitative Risk Analysis

C.

Control Risks

D.

Plan Risk Responses

Full Access
Question # 33

The risk response strategy in which the project team acts to reduce the probability of occurrence or impact of a risk is known as:

A.

exploit

B.

avoid

C.

mitigate

D.

share

Full Access
Question # 34

A project requires a component with well-understood specifications. Performance targets are established at the outset, and the final contract price is determined after completion of all work based on the seller's performance. The most appropriate agreement with the supplier is:

A.

Cost Plus Incentive Fee (CPIF).

B.

Fixed Price Incentive Fee (FPIF).

C.

Cost Plus Award Fee (CPAF).

D.

Fixed Price with Economic Price Adjustment (FP-EPA).

Full Access
Question # 35

The following chart contains information about the tasks in a project.

Based on the chart, what is the cost performance index (CPI) for Task 2?

A.

0.8

B.

1

C.

1.25

D.

1.8

Full Access
Question # 36

In which phase of team building activities do team members begin to work together and adjust their work habits and behavior to support the team?

A.

Performing

B.

Storming

C.

Norming

D.

Forming

Full Access
Question # 37

Those who enter into a contractual agreement to provide services necessary for a project are:

A.

buyers

B.

sellers

C.

business partners

D.

product users

Full Access
Question # 38

Impacts to other organizational areas, levels of service, and acceptance criteria are typical components of which document?

A.

Business case

B.

Work breakdown structure

C.

Requirements documentation

D.

Risk register

Full Access
Question # 39

The degree, amount, or volume of risk that an organization or individual will withstand is known as its risk:

A.

Analysis

B.

Appetite

C.

Tolerance

D.

Response

Full Access
Question # 40

Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk Responses?

A.

Identify Risks

B.

Plan Risk Management

C.

Perform Qualitative Risk Analysis

D.

Perform Quantitative Risk Analysis

Full Access
Question # 41

The zero duration of milestones in project planning occurs because milestones:

A.

Are unpredictable and challenge the Plan Schedule Management process.

B.

Occur at random times in the project plans.

C.

Represent a moment in time such as a significant project point or event.

D.

Represent both significant and insignificant points in the project and are difficult to anticipate.

Full Access
Question # 42

Which type of graphic is displayed below?

A.

Work breakdown structure

B.

Context diagram

C.

Control chart

D.

Pareto diagram

Full Access
Question # 43

Which is an enterprise environmental factor?

A.

Marketplace conditions

B.

Policies and procedures

C.

Project files from previous projects

D.

Lessons learned from previous projects

Full Access
Question # 44

Which stakeholder approves a project's result?

A.

Customer

B.

Sponsor

C.

Seller

D.

Functional manager

Full Access
Question # 45

The degree of uncertainty an entity is willing to take on in anticipation of a reward is known as its risk:

A.

management

B.

response

C.

tolerance

D.

appetite

Full Access
Question # 46

When painting a bedroom, preparing the walls can be done while the paint is being chosen. This is an example of a:

A.

lead

B.

lag

C.

mandatory dependency

D.

internal dependency

Full Access
Question # 47

The following is a network diagram for a project.

The free float for Activity E is how many days?

A.

2

B.

3

C.

5

D.

8

Full Access
Question # 48

The cost baseline and project funding requirements are outputs of which process in Project Cost Management?

A.

Estimate Costs

B.

Control Costs

C.

Plan Cost Management

D.

Determine Budget

Full Access
Question # 49

A project team member agrees to change a project deliverable after a conversation with an external stakeholder. It is later discovered that the change has had an adverse effect on another deliverable. This could have been avoided if the project team had implemented:

A.

Quality assurance.

B.

A stakeholder management plan.

C.

Project team building.

D.

Integrated change control.

Full Access
Question # 50

Which type of organizational structure is displayed in the diagram provided?

A.

Balanced matrix

B.

Projectized

C.

Strong matrix

D.

Functional

Full Access
Question # 51

In complex projects/ initiating processes should be completed:

A.

Within a work package.

B.

In each phase of the project.

C.

To estimate schedule constraints.

D.

To estimate resource allocations.

Full Access
Question # 52

The following chart contains information about the tasks in a project.

Based on the chart, what is the schedule performance index (5PI) for Task 4?

A.

0.83

B.

0.9

C.

1.11

D.

1.33

Full Access
Question # 53

Through whom do project managers accomplish work?

A.

Consultants and stakeholders

B.

Stakeholders and functional managers

C.

Project team members and consultants

D.

Project team members and stakeholders

Full Access
Question # 54

Which Perform Quality Assurance tool or technique is used to identify a problem, discover the underlying causes that lead to it, and develop preventative actions?

A.

Inspection

B.

Quality audits

C.

Design of experiments

D.

Root cause analysis

Full Access
Question # 55

The Project Human Resource Management process that involves confirming human resource availability and obtaining the team necessary to complete project activities is:

A.

Acquire Project Team.

B.

Plan Human Resource Management.

C.

Manage Project Team.

D.

Develop Project Team.

Full Access
Question # 56

Skills necessary for project management such as motivating to provide encouragement; listening actively; persuading a team to perform an action; and summarizing, recapping, and identifying next steps are known as:

A.

organizational skills

B.

technical skills

C.

communication skills

D.

hard skills

Full Access
Question # 57

An input to the Control Quality process is:

A.

Activity attributes

B.

Quality control measurements

C.

Enterprise environmental factors

D.

Deliverables

Full Access
Question # 58

Project Scope Management is primarily concerned with:

A.

Developing a detailed description of the project and product.

B.

Determining how requirements will be analyzed, documented, and managed.

C.

Defining and controlling what is and is not included in the project.

D.

Formalizing acceptance of the completed project deliverables.

Full Access
Question # 59

The purpose of developing a project scope management plan is to:

A.

Manage the timely completion of the project.

B.

Ensure that the project includes all of the work required.

C.

Make sure the project will satisfy the needs for which it was begun.

D.

Reduce the risk of negative events in the project.

Full Access
Question # 60

Which Process Group includes the Manage Stakeholder Engagement process?

A.

Executing

B.

Planning

C.

Monitoring and Controlling

D.

Initiating

Full Access
Question # 61

The following is a network diagram for a project.

The critical path for the project is how many days in duration?

A.

10

B.

12

C.

14

D.

17

Full Access
Question # 62

Which tool or technique is required in order to determine the project budget?

A.

Cost of quality

B.

Historical relationships

C.

Project management software

D.

Forecasting

Full Access
Question # 63

Which process is conducted from project inception through completion and is ultimately the responsibility of the project manager?

A.

Control Quality

B.

Monitor and Control Project Work

C.

Control Scope

D.

Perform Integrated Change Control

Full Access
Question # 64

Completion of the product scope is measured against the product:

A.

prototypes

B.

requirements

C.

analyses

D.

benchmarks

Full Access
Question # 65

Every project creates a unique product, service, or result that may be:

A.

tangible

B.

targeted

C.

organized

D.

variable

Full Access
Question # 66

Outputs of the Control Communications process include:

A.

expert judgment and change requests.

B.

work performance information and change requests.

C.

organizational process asset updates and an issue log.

D.

project management plan updates and an issue log.

Full Access
Question # 67

Which change request is an intentional activity that realigns the performance of the project work with the project management plan?

A.

Update

B.

Preventive action

C.

Defect repair

D.

Corrective action

Full Access
Question # 68

The following chart contains information about the tasks in a project.

Based on the chart, what is the cost variance (CV) for Task 6?

A.

-2,000

B.

0

C.

1,000

D.

2,000

Full Access
Question # 69

One of the key benefits of the Plan Human Resource Management process is that it:

A.

outlines team selection guidelines and team member responsibilities.

B.

establishes project roles and responsibilities.

C.

improves teamwork, interpersonal skills, and competencies.

D.

provides an accurate appraisal of team member performance.

Full Access
Question # 70

The component of the human resource management plan that includes ways in which team members can obtain certifications that support their ability to benefit the project is known as:

A.

recognition and rewards

B.

compliance

C.

staff acquisition

D.

training needs

Full Access
Question # 71

The process of monitoring the status of the project and product scope as well as managing the changes to the scope baseline is known as:

A.

Validate Scope.

B.

Plan Scope Management.

C.

Control Scope.

D.

Define Scope.

Full Access
Question # 72

The following is a network diagram for a project.

The total float for the project is how many days?

A.

3

B.

5

C.

7

D.

9

Full Access
Question # 73

The following chart contains information about the tasks in a project.

Based on the chart, what is the schedulevariance (SV) for Task 8?

A.

-2,000

B.

-1,000

C.

1,000

D.

2,000

Full Access
Question # 74

Perform Integrated Change Control is the process of:

A.

Reviewing, approving, and managing all change requests

B.

Facilitating change management, manuals, or automation tools

C.

Comparing actual results with planned results in order to expand or change a project

D.

Documenting changes according to the change control system by the change control board

Full Access
Question # 75

What is the name of a graphic display of project team members and their reporting relationships?

A.

Role dependencies chart

B.

Reporting flow diagram

C.

Project organization chart

D.

Project team structure diagram

Full Access
Question # 76

Which process documents the business needs of a project and the new product, service, or other result that is intended to satisfy those requirements?

A.

Develop Project Management Plan

B.

Develop Project Charter

C.

Direct and Manage Project Execution

D.

Collect Requirements

Full Access
Question # 77

What cost control technique is used to compare actual project performance to planned or expected performance?

A.

Cost aggregation

B.

Trend analysis

C.

Forecasting

D.

Variance analysis

Full Access
Question # 78

Which Knowledge Area is concerned with the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?

A.

Project Integration Management

B.

Project Communications Management

C.

Project Information Management System (PIMS)

D.

Project Scope Management

Full Access
Question # 79

When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?

A.

Bottom-up

B.

Parametric

C.

Analogous

D.

Three-point

Full Access
Question # 80

Projects are undertaken by an organization to support the:

A.

Product performance.

B.

Budget process.

C.

Collective capabilities.

D.

Organizational strategy.

Full Access
Question # 81

Which process involves documenting the actions necessary to define, prepare, integrate, and coordinate all subsidiary plans?

A.

Collect Requirements

B.

Direct and Manage Project Execution

C.

Monitor and Control Project Work

D.

Develop Project Management Plan

Full Access
Question # 82

Change requests are an output from which Project Integration Management process?

A.

Direct and Manage Project Execution

B.

Develop Project Management Plan

C.

Close Project

D.

Develop Project Charter

Full Access
Question # 83

What is the function of a Project Management Office (PMO)?

A.

To focus on the coordinated planning, prioritization, and execution of projects and subprojects that are tied to the parent organizations or the client's overall business objectives.

B.

To coordinate and manage the procurement of projects relevant to the parent organization's business objectives and to administer the project charters accordingly.

C.

To administer performance reviews for the project manager and the project team members and to handle any personnel and payroll issues.

D.

To focus on the specified project objectives and to manage the scope, schedule, cost, and quality of the work packages.

Full Access
Question # 84

What is one of the objectives of Project Risk Management?

A.

Decrease the probability and impact of an event on project objectives.

B.

Distinguish between a project risk and a project issue so that a risk mitigation plan can be put in place.

C.

Increase the probability and impact of positive events.

D.

Removal of project risk.

Full Access
Question # 85

Which type of analysis systemically gathers and analyzes qualitative and quantitative information to determine which interests should be taken into account throughout the project?

A.

Product

B.

Cost-benefit

C.

Stakeholder

D.

Research

Full Access
Question # 86

Which is a tool or technique used in Define Scope?

A.

Templates, forms, and standards

B.

Change requests

C.

Product analysis

D.

Project assumptions

Full Access
Question # 87

When does Monitor and Control Risks occur?

A.

At project initiation

B.

During work performance analysis

C.

Throughout the life of the project

D.

At project milestones

Full Access
Question # 88

Outputs of the Control Communications process include:

A.

expert judgment and change requests

B.

work performance information and change requests

C.

project management plan updates and work performance information

D.

issue logs and organizational process assets updates

Full Access
Question # 89

During which process group is the quality policy determined?

A.

Initiating

B.

Executing

C.

Planning

D.

Controlling

Full Access
Question # 90

Which Project Management Process Group includes Collect Requirements, Define Activities, Sequence Activities, Perform Qualitative Risk Analysis, and Perform Quantitative Risk Analysis?

A.

Initiating

B.

Monitoring and Controlling

C.

Planning

D.

Closing

Full Access
Question # 91

The Human Resource Management processes are:

A.

Develop Human Resource Plan, Acquire Project Team, Develop Project Team, and Manage Project Team.

B.

Acquire Project Team, Manage Project Team, Manage Stakeholder Expectations, and Develop Project Team.

C.

Acquire Project Team, Develop Human Resource Plan, Conflict Management, and Manage Project Team.

D.

Develop Project Team, Manage Project Team, Estimate Activity Resources, and Acquire Project Team.

Full Access
Question # 92

Which defines the portion of work included in a contract for items being purchased or acquired?

A.

Procurement management plan

B.

Evaluation criteria

C.

Work breakdown structure

D.

Procurement statement of work

Full Access
Question # 93

A procurement management plan is a subsidiary of which other type of plan?

A.

Resource plan

B.

Project management plan

C.

Cost control plan

D.

Expected monetary value plan

Full Access
Question # 94

Which technique should a project manager use in a situation in which a collaborative approach to conflict management is not possible?

A.

Coaching

B.

Avoidance

C.

Consensus

D.

Influencing

Full Access
Question # 95

Which technique is used in Perform Quantitative Risk Analysis?

A.

Sensitivity analysis

B.

Probability and impact matrix

C.

Risk data quality assessment

D.

Risk categorization

Full Access
Question # 96

A collection of projects managed as a group to achieve strategic objectives is referred to as a:

A.

plan

B.

process

C.

program

D.

portfolio

Full Access
Question # 97

An output of the Create WBS process is:

A.

Scope baseline.

B.

Project scope statement.

C.

Organizational process assets.

D.

Requirements traceability matrix.

Full Access
Question # 98

The project manager notes that stakeholders are aware of the project and potential impacts and are actively engaged in ensuring that the project is a success. The engagement level of the stakeholders should be classified as:

A.

Supportive

B.

Leading

C.

Neutral

D.

Resistant

Full Access
Question # 99

Which schedule compression technique has phases or activities done in parallel that would normally have been done sequentially?

A.

Crashing

B.

Fast tracking

C.

Leads and lags adjustment

D.

Parallel task development

Full Access
Question # 100

An output of Control Schedule is:

A.

A project schedule network diagram

B.

A schedule management plan

C.

Schedule data

D.

Schedule forecasts

Full Access
Question # 101

The links between the processes in the Process Groups are often:

A.

Intuitive

B.

Iterative

C.

Measured

D.

Monitored

Full Access
Question # 102

Organizational planning impacts projects by means of project prioritization based on risk, funding, and an organizations:

A.

Budget plan

B.

Resource plan

C.

Scope plan

D.

Strategic plan

Full Access
Question # 103

Conflict should be best addressed in which manner?

A.

Early, in private, using a direct, collaborative approach

B.

Early, in public, using an indirect, collaborative approach

C.

Early, in private, using an indirect, cooperative approach

D.

As late as possible, in public, using a direct, confrontational approach

Full Access
Question # 104

The Verify Scope process is primarily concerned with:

A.

formalizing acceptance of the completed project deliverables.

B.

accuracy of the work deliverables.

C.

formalizing approval of the scope statement.

D.

accuracy of the work breakdown structure (WBS).

Full Access
Question # 105

What is the total float of the critical path?

A.

Can be any number

B.

Zero or positive

C.

Zero or negative

D.

Depends on the calendar

Full Access
Question # 106

Which illustrates the connection between work that needs to be done and its project team members?

A.

Work breakdown structure (WBS)

B.

Network diagrams

C.

Staffing management plan

D.

Responsibility assignment matrix (RAM)

Full Access
Question # 107

Which activity is an input to the Conduct Procurements process?

A.

Organizational process assets

B.

Resource availability

C.

Perform Integrated Change Control

D.

Team performance assessment

Full Access
Question # 108

Which of the following statements best describes the influence of stakeholders and the cost of changes as project time advances?

A.

The influence of the stakeholders increases, the cost of changes increases.

B.

The influence of the stakeholders decreases, the cost of changes increases.

C.

The influence of the stakeholders increases, the cost of changes decreases.

D.

The influence of the stakeholders decreases, the cost of changes decreases.

Full Access
Question # 109

The CPI is .92, and the EV is US$172,500.What is the actual cost of the project?

A.

US$158,700

B.

US$172,500

C.

US$187,500

D.

US$245,600

Full Access
Question # 110

If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?

A.

One

B.

Five

C.

Six

D.

Seven

Full Access
Question # 111

The product scope description is used to:

A.

Gain stakeholders' support for the project.

B.

Progressively elaborate the characteristics of the product, service, or result.

C.

Describe the project in great detail.

D.

Define the process and criteria for accepting a completed product, service, or result.

Full Access
Question # 112

Which tool is used to develop technical details within the project management plan?

A.

Expert judgment

B.

Project management methodology

C.

Project management information system (PMIS)

D.

Project selection methods

Full Access
Question # 113

What is the definition of Direct and Manage Project Execution?

A.

Integrating all planned activities

B.

Performing the activities included in the plan

C.

Developing and maintaining the plan

D.

Execution of deliverables

Full Access
Question # 114

Which group creativity technique asks a selected group of experts to answer questionnaires and provide feedback regarding the responses from each round of requirements gathering?

A.

The Delphi technique

B.

Nominal group technique

C.

Affinity diagram

D.

Brainstorming

Full Access
Question # 115

A change log for communications can be used to communicate to the appropriate stakeholders that there are changes:

A.

To the project management plan.

B.

To the risk register.

C.

In the scope verification processes.

D.

And their impact to the project in terms of time, cost, and risk.

Full Access
Question # 116

Which process is included in the Project Integration Management Knowledge Area?

A.

Manage Project Team

B.

Collect Requirements

C.

Sequence Activities

D.

Direct and Manage Project Work

Full Access
Question # 117

What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?

A.

Finish-to-start planning

B.

Rolling wave planning

C.

Short term planning

D.

Dependency determination

Full Access
Question # 118

Which tool or technique of Plan Quality involves comparing actual or planned practices to those of other projects to generate ideas for improvement and provide a basis by which to measure performance?

A.

Histogram

B.

Quality audits

C.

Benchmarking

D.

Performance measurement analysis

Full Access
Question # 119

An input required in Define Scope is an organizational:

A.

structure.

B.

process asset.

C.

matrix.

D.

breakdown structure.

Full Access
Question # 120

Which process includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?

A.

Perform Qualitative Risk Analysis

B.

Perform Quantitative Risk Analysis

C.

Plan Risk Management

D.

Plan Risk Responses

Full Access
Question # 121

What tool and technique is used to determine whether work and deliverables meet requirements and product acceptance criteria?

A.

Decomposition

B.

Benchmarking

C.

Inspection

D.

Checklist analysis

Full Access
Question # 122

Taking out insurance in relation to risk management is called what?

A.

Transference

B.

Avoidance

C.

Exploring

D.

Mitigation

Full Access
Question # 123

Activity resource requirements and the resource breakdown structure (RBS) are outputs of which Project Time Management process?

A.

Control Schedule

B.

Define Activities

C.

Develop Schedule

D.

Estimate Activity Resources

Full Access
Question # 124

The technique of subdividing project deliverables into smaller, more manageable components until the work and deliverables are defined to the work package level is called:

A.

a control chart.

B.

baseline.

C.

Create WBS.

D.

decomposition.

Full Access
Question # 125

Prototype development may be used as a tool for which of the following risk response strategies?

A.

Avoid

B.

Accept

C.

Mitigate

D.

Exploit

Full Access
Question # 126

The project has a current cost performance index of 0.80. Assuming this performance wi continue, the new estimate at completion is $1000. What was the original budget at completion for the project?

A.

$800

B.

$1000

C.

$1250

D.

$1800

Full Access
Question # 127

The contract in which the seller is reimbursed for all allowable costs for performing the contract work and then receives a fee based upon achieving certain performance objectives is called a:

A.

Cost Plus Incentive Fee Contract (CPIF).

B.

Cost Plus Fixed Fee Contract (CPFF).

C.

Fixed Price Incentive Fee Contract (FPIF).

D.

Time and Material Contract (T&M).

Full Access
Question # 128

Activity cost estimates are quantitative assessments of the probable costs required to:

A.

Create WBS.

B.

complete project work.

C.

calculate costs.

D.

Develop Project Management Plan.

Full Access
Question # 129

Which of the following is a project constraint?

A.

Twenty-five percent staff turnover is expected.

B.

The technology to be used is cutting-edge.

C.

Project leadership may change due to volatile political environment.

D.

The product is needed in 250 days.

Full Access
Question # 130

The item that provides more detailed descriptions of the components in the work breakdown structure (WB5) is called a WBS:

A.

dictionary.

B.

chart.

C.

report.

D.

register.

Full Access
Question # 131

The group technique that enhances brainstorming with a voting process used to rank the most useful ideas for prioritization is called the:

A.

majority rule technique.

B.

nominal group technique.

C.

Delphi technique,

D.

idea/mind mapping technique.

Full Access
Question # 132

Under which type of contract does the seller receive reimbursement for all allowable costs for performing contract work, as well as a fixed-fee payment calculated as a percentage of the initial estimated project costs?

A.

Cost Plus Fixed Fee Contract (CPFF)

B.

Cost Plus Incentive Fee Contract (CPIF)

C.

Firm Fixed Price Contract (FFP)

D.

Fixed Price with Economic Price Adjustment Contract (FP-EPA)

Full Access
Question # 133

Plan-do-check-act is also known as:

A.

prevention over inspection.

B.

statistical sampling.

C.

management responsibility,

D.

continuous improvement.

Full Access
Question # 134

Which Control Scope input is compared to actual results to determine if corrective action is required for the project?

A.

Scope baseline

B.

Scope management plan

C.

Change management plan

D.

Cost baseline

Full Access
Question # 135

One of the objectives of a quality audit is to:

A.

highlight the need for root cause analysis.

B.

share the process documentation among stakeholders.

C.

offer assistance with non-value-added activities.

D.

identify all of the gaps or shortcomings.

Full Access
Question # 136

Which of the following is an output of Define Scope?

A.

Project scope statement

B.

Project charter

C.

Project plan

D.

Project schedule

Full Access
Question # 137

Which of the following change requests can bring expected future performance of the project work in line with the project management plan?

A.

Corrective action

B.

Defect repair

C.

Preventative action

D.

Probable action

Full Access
Question # 138

What is project management?

A.

A logical grouping of project management inputs, outputs, tools, and techniques

B.

Applying knowledge, skills, tools, and techniques to project activities to meet the project requirements

C.

Launching a process that can result in the authorization of a new project

D.

A formal, approved document that defines how the project is executed, monitored, and controlled

Full Access
Question # 139

Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen?

A.

Sensitivity analysis

B.

Three-point estimate

C.

Modeling and simulation

D.

Expected monetary value analysis

Full Access
Question # 140

At the end of the project, what will be the value of SV?

A.

Positive

B.

Zero

C.

Negative

D.

Greater than one

Full Access
Question # 141

The total of the planned value (PV) is also known as:

A.

work breakdown structure (WBS).

B.

schedule target.

C.

performance measurement baseline (PMB).

D.

earned value baseline.

Full Access
Question # 142

During project selection, which factor is most important?

A.

Types of constraints

B.

Internal business needs

C.

Budget

D.

Schedule

Full Access
Question # 143

Which Process Group contains the processes performed to complete the work defined in the project management plan to satisfy the project specifications?

A.

Initiating

B.

Planning

C.

Executing

D.

Closing

Full Access
Question # 144

Which tool or technique can a project manager use to select in advance a team member who will be crucial to the task?

A.

Acquisition

B.

Negotiation

C.

Virtual team

D.

Pre-assignment

Full Access
Question # 145

Risk responses reflect an organization's perceived balance between:

A.

risk taking and risk avoidance.

B.

known risk and unknown risk.

C.

identified risk and analyzed risk.

D.

varying degrees of risk.

Full Access
Question # 146

Which is an output of the Collect Requirements process?

A.

Requirements traceability matrix

B.

Project scope statement

C.

WBS dictionary

D.

Work performance measurements

Full Access
Question # 147

Which of the following is an output of the Conduct Procurements process?

A.

Project statement of work

B.

Selected sellers

C.

Risk register updates

D.

Teaming agreements

Full Access
Question # 148

Which procurement management process includes obtaining seller response, seller selection, and contract awarding?

A.

Plan Procurement

B.

Manage Procurement

C.

Conduct Procurements

D.

Perform Procurement

Full Access
Question # 149

What purpose does the hierarchical focus of stakeholder communications serve?

A.

Maintains the focus on project and organizational stakeholders

B.

Preserves the focus on external stakeholders—such as customers and vendors—as well as on other projects

C.

Sustains the focus on general communication activities using email, social media and websites

D.

Keeps the focus on the position of the stakeholder or group with respect to the project team

Full Access
Question # 150

Which of the following is least influenced by a project manager, according to the project manager's sphere of influence?

A.

Sponsors

B.

Project team

C.

Steering committees

D.

Stakeholders

Full Access
Question # 151

What internal enterprise environmental factor (EEF) can impact a project?

A.

Cultural influences

B.

Physical environmental elements

C.

Commercial databases

D.

Infrastructure

Full Access
Question # 152

After defining activities in project schedule management, which processes should a project manager follow?

A.

Sequence Activities and Estimate Activity Durations

B.

Estimate Activity Durations and Control Schedule

C.

Develop Schedule and Control schedule

D.

Review Activities and Develop Schedule

Full Access
Question # 153

Which project management process is used by the project manager to ensure that stakeholders receive timely and relevant information?

A.

Plan Communications Management

B.

Manage Communications

C.

Monitor Communications

D.

Develop Project Management Plan

Full Access
Question # 154

Which sentence summarizes the salience model?

A.

Classifies stakeholders based on assessment ol Iheir power, urgency and legitimacy

B.

A chart in which the Stakeholders are ropiosented as dots according to then level ol power and influence

C.

A three-dimensional model that ran be useful to engage the stakeholder community

D.

Classifies stakeholders and the project toam by the impact of their work in the project

Full Access
Question # 155

What benefit does the Manage Stakeholder Engagement process offer?

A.

Allows the project manager to increase support and minimize resistance from stakeholders

B.

Maintains or increases the efficiency and effectiveness of stakeholder engagement activities as the project evolves and its environment changes

C.

Provides an actionable plan to interact effectively with stakeholders

D.

Enables the project team to identify the appropriate focus for engagement of each stakeholder or group of stakeholders

Full Access
Question # 156

Which can be used to convert a verified deliverable to an accepted deliverable?

A.

Decomposition

B.

Reporting

C.

Voting

D.

Brainstorming

Full Access
Question # 157

Which of the following lists represents trends and emerging practices in Project Risk Management?

A.

Integrated risk management, non-event risks, and project resilience

B.

Representation of uncertainty, strategies for opportunities, and strategies for overall project risk

C.

Dormancy, proximity, and propinquity

D.

Simulation, sensitivity analysis, and decision tree analysis

Full Access
Question # 158

Which is an example of an internal enterprise environmental factor?

A.

Market Share brand recognition

B.

Factory location

C.

Local government regulation

D.

Industry research

Full Access
Question # 159

During project execution, a team member has identified and then analyzed an opportunity that

will yield a net saving of 10% and reduce time in the schedule by 20%

Which strategy should the project manager adopt to accommodate this opportunity?

A.

Escalate to upper management to build awareness of the opportunity.

B.

Exploit the opportunity immediately, since the cost saving makes it worthwhile.

C.

Transfer the opportunity to a partner and start a partner contract.

D.

Create a trail of the opportunity before full adoption, because of the risk associated.

Full Access
Question # 160

To ensure stakeholder satisfaction; identified stakeholder needs should all be

A.

Vetted

B.

Ranked from greatest to least

C.

Qualified

D.

Documented in the stakeholder engagement plan

Full Access
Question # 161

In a preliminary meeting for a project, team members decide to execute the project with methodology A finance team member wants to know how project cost will be determined at this early stage. How will the project team determine project cost?

A.

Use a lightweight cost estimation due to the nature of angile projects.

B.

Use a detailed cost estimation for agile projects.

C.

Retrieve a dudget from a previous project and create a baseline of this project based on it.

D.

Use a detailed work breakdown structure (WBS) to get cost estimation.

Full Access
Question # 162

Which of these statements is true of subsidiary management plans?

A.

Subsidiary management plans are mandatory for any project

B.

Subsidiary management plans use the project charier as input

C.

Subsidiary management plans can be independently managed

D.

Subsidiary management plans do not need regular updates

Full Access
Question # 163

It’s time to perform code review on a software project that has over three million lines of code written. Which management tool should the project manager use?

A.

Pareto chart

B.

Regression analysis

C.

Statistical sampling

D.

Automated testing tools

Full Access
Question # 164

Which component of the project management plan should be updated if a change occurs?

A.

Project charter

B.

Project baseline

C.

Assumption log

D.

Schedule forecast

Full Access
Question # 165

What is the Project Schedule Management practice used to deliver incremental value to the customer'?

A.

Resource optimization

B.

Iterative scheduling with a backlog

C.

On-demand scheduling

D.

Critical path method

Full Access
Question # 166

When developing a schedule which tools and techniques should a project manager use?

A.

Schedule Networfc Analysis and Critical Path Method

B.

Activity I ist and Fxpert Judgement

C.

Milestone Iist and Risk Register

D.

Basis ot estimates and Rolling Wave Planning

Full Access
Question # 167

At what stages of project should the identify Stakeholder process be performed?

A.

When beginning each phase of the project

B.

At the beginning of the project only

C.

Only when the project manager is concerned about stakeholder satisfaction

D.

When the project charter is produced, at the beginning of each phase, and when significant changes occur

Full Access
Question # 168

What is purpose of using the building information model (BIM) in software tools in the construction field?

A.

Reduce significant amount of time and money

B.

Help manage risks in large projects

C.

Keep up with emerging trends

D.

Provide sellers with multiple sources for documents

Full Access
Question # 169

Match each tool or technique with its corresponding Project Cost Management process.

Full Access
Question # 170

Which of the following lists of tools and techniques is used when conducting procurements?

A.

Expert judgement, procurement negotiations, bidder conferences, proposal evaluation advertising and independent estimates

B.

Budgeting procurement negotiations, bidder conferences, proposal evaluation and advertising, and seller's proposal C. Expert judgement, procurement negotiations bidder conferences, proposal evaluation and advertising, and make-or-buy decisions

C.

Agreements procurement negotiations, bidder conferences, proposal evaluation and advertising selected seller

Full Access
Question # 171

What is a key benefit of using virtual project teams?

A.

Ensures appropriate behavior, security, and the protection of proprietary information

B.

Reduces the risk of conflict due to interpersonal communications and other interactions

C.

Assures that all team members have a clear and common understanding of the project

D.

Reduces project cost by use of modern technologies allowing seamless team collaboration

Full Access
Question # 172

The project manager is working in the Resource Management process. Which items may the project manager need to include in the team charter?

A.

Cultural norms, roles and responsibilities, and organizational chart

B.

Assumption logs, resource calendars and training schedule

C.

Communication guidelines, conflict resolution process, and team agreements

D.

Company policies, recognition plan, and roles and responsibilities

Full Access
Question # 173

What is the recommended approach for handling risk in a high-variability environment?

A.

Adaptive

B.

Predictive

C.

Iterative

D.

Incremental

Full Access
Question # 174

The project manager implemented the stakeholder engagement plan and realized that some uploads should be made. Which components of the project management plan should be modified?

A.

Project charter and stakeholder engagement plan

B.

Risk management plan and stakeholder engagement plan

C.

Communications management plan and stakeholder engagement plan

D.

Project charter and communications management plan

Full Access
Question # 175

A stakeholder is reading project documents given by the project manager. The stakeholder is

curious about the difference between a verified deliverable and an accepted deliverable.

Which of the following definitions can the project manager use to explain the difference?

A.

An accepted deliverable is approved by the project team; a verified deliverable is approved and formally signed off by the customer or sponsor.

B.

An accepted deliverable has been checked and confirmed for accuracy through the Control Quality process; a verified deliverable meets acceptance criteria that is formally signed off and approved by the customer or sponsor.

C.

An accepted deliverable meets acceptance criteria and is formally signed off and approved by the customer or sponsor, a verified deliverable is a completed project deliverable that has been checked and confirmed for accuracy through the Control Quality process

D.

An accepted deliverable meets acceptance criteria and is signed off by the project manager; a verified deliverable meets acceptance criteria and is signed off by the customer or sponsor.

Full Access
Question # 176

What is an emerging practice in stakeholder engagement?

A.

Confirming that all identified stakeholders are engaged and actually affected by the work

B.

Assuring that team leadership is primarily involved in stakeholder engagement

C.

Ensuring that stakeholders do not change after stakeholder identification

D.

Ensuring that stakeholders most affected by the work are involved as collaborative team partners

Full Access
Question # 177

A project manager is updating their CV or resume and realizes that they need to improve skills related to expertise in the industry and organizational knowledge. Which dimension of PMI’s Talent Triangle best relates to this need to improve?

A.

Strategic and business management skills

B.

Leadership skills

C.

Technical project management

D.

Organizational management

Full Access
Question # 178

During a project's execution phase, the project manager reviews the communications management plan for communication technology factors. What can affect the choice of communications?

A.

Legal requirements

B.

Politics and power structures

C.

Internal information needs

D.

Sensitivity and confidentiality of the information

Full Access
Question # 179

When paying a consultation fee to a technical expert, what type of contract is often used'?

A.

Time and materials (T&M)

B.

Cost plus incentive fee (CPIF)

C.

Fixed price incentive fee (FPIF)

D.

Cost plus award fee (CPAF)

Full Access
Question # 180

Which is an aspect of the requirements management plan?

A.

Detailed project scope statement

B.

Creation of work breakdown strucure (WBS)

C.

Impact analysis

D.

Duration for implementation

Full Access
Question # 181

Two members of the team are having a conflict..............or partially resolve the problem

Two members of the team are having a conflict. The project manager decides that, in this case, the best solution is to bring some degree of satisfaction to all parties, in order to temporarily or partially resolve the problem.

Which technique should the project manager use?

A.

Withdraw/Avoid

B.

Smooth/Accommodate

C.

Compromise/Reconcile

D.

Collaborate/Problem Solve

Full Access
Question # 182

What is the common factor among portfolios, programs, and projects, regardless of the hierarchy within an organization?

A.

Resources and stakeholders

B.

Operations and performance

C.

Subsidiary projects

D.

Project manager

Full Access
Question # 183

Which key benefit can a project manager obtain by identifying stakeholders?

A.

Identify the appropriate focus for engagement of each stakeholder.

B.

Assess the risk exposure for each stakeholder.

C.

Map stakeholder power and influence grid.

D.

Identify the appropriate channels of communication with all stakeholders.

Full Access
Question # 184

Which statement describes the various purposes of project scheduling?

A.

Define the policies, rules, and techniques to run a schedule; serve as a tool to manage stakeholder expectations; and serve as a base for backlog management

B.

Define how and when deliverables will be completed, serve as communication tool, and serve as a base for performance reporting

C.

Define the life cycle, traditional or agile approach, and tools to control schedule; serve as a reference for scope management; and serve as a base for risk management

D.

Define activities, sequences, duration, and dependencies, serve as a reference for resource allocation, serve as a base for earned value analysis.

Full Access
Question # 185

What statement describes the function or responsibility of a project manager?

A.

Works with the sponsor to address internal political and strategic issues that may impact the team

B.

Seeks ways to develop relationships that assist the team in achieving organizational goals and objectives

C.

Ensures that the project's business operations are efficient

D.

Provides management oversight for a project’s functional or business units

Full Access
Question # 186

After an internal deliverable review session with the team, the project manager indicates some issues that need to be fixed before submitting the deliverable for formal approval. The project manager will need to manage the additional costs and the required network. How would the project manager define extra costs?

A.

Appraisal costs

B.

Management reserves

C.

Cost of nonconformance

D.

Cost of conformance

Full Access
Question # 187

A software development team is working on a project to adapt an application to new, government-established data-privacy rules. What factor led to the creation of this project?

A.

Legal requirement

B.

New technology

C.

Social need

D.

Economic change

Full Access
Question # 188

What is the purpose of the protect management process groups?

A.

To define a new project

B.

To track and monitor processes easily

C.

To logically group processes to achieve specific project objectives

D.

To link specific process inputs and outputs

Full Access
Question # 189

What is an example of an emerging trend in procurement management?

A.

Online technology enable projects to postpone ordering long lead items until the items are needed

B.

Online technologies allow a project's progress to be viewed by all stakeholders to build better relations

C.

Online procurement tools provide buyers with multiple sources to advertise to sellers.

D.

Online procurement tools provide sellers with designated sources for procurement documents and the resources to complete them.

Full Access
Question # 190

What characteristic of servant leadership supports resource management in an agile environment?

A.

Lecturing

B.

Construing

C.

Measuring

D.

Coaching

Full Access
Question # 191

Which document can help a project manager to leverage historical project information?

A.

Lessons learned register

B.

Schedule baseline

C.

Work performance data

D.

Deliverable acceptance forms

Full Access
Question # 192

What important qualities should project managers possess for strategic and business management?

A.

Skills and behaviors related to specific domains of project management

B.

Knowledge and competencies needed to guide and motivate a team

C.

Skills and behaviors needed to help an organization achieve its goals

D.

Expertise in the industry and organization that deliver better outcomes

Full Access
Question # 193

A software development team is pulling work from its backlog to be performed immediately as they become available. What emerging practice for project scheduling is the team using?

A.

Iterative

B.

On-demand

C.

Interactive

D.

Quality

Full Access
Question # 194

A company has implemented an adaptive project management framework for a new project. When planning for an iteration, how should risks be addressed? Choose two.

A.

Risks should be considered when selecting the content of each iteration.

B.

Risks should be tailored for each iteration.

C.

Risks should be identified, analyzed, and managed during each iteration.

D.

Risks should be documented prior to each iteration.

E.

Risks should be reviewed only once during each iteration.

Full Access
Question # 195

What quantitative risk analysis technique is used to select the optimum course of action from a number of alternatives?

A.

Sensitivity analysis

B.

Simulation

C.

Decision tree analysis

D.

Influence diagram

Full Access
Question # 196

The project manager released a report. A few stakeholders express the view that the report should not have been directed to them.

Which of the 5Cs of written communications does the project manager need to address?

A.

Correct grammar and spelling

B.

Concise expression and elimination of excess words

C.

Clear purpose and expression directed to the needs of the reader

D.

Coherent logical flow of ideas

Full Access
Question # 197

Which tool or technique is used to develop the human resource management plan?

A.

Ground rules

B.

Expert judgment

C.

Team-building activities

D.

Interpersonal skills

Full Access
Question # 198

The review of a sellers progress toward achieving the goals of scope and quality within cost and schedule compared to the contract is known as:

A.

Work performance information.

B.

Inspections and audits.

C.

Payment systems.

D.

Procurement performance reviews.

Full Access
Question # 199

Plan Schedule Management is a process in which Knowledge Area?

A.

Project Scope Management

B.

Project Human Resource Management

C.

Project Integration Management

D.

Project Time Management

Full Access
Question # 200

The ability to influence cost is greatest during which stages of the project?

A.

Early

B.

Middle

C.

Late

D.

Completion

Full Access
Question # 201

Conditions that are not under the control of the project team that influence, direct, or constrain a project are called:

A.

Enterprise environmental factors

B.

Work performance reports

C.

Organizational process assets

D.

Context diagrams

Full Access
Question # 202

Lessons learned are created and project resources are released in which Process Group?

A.

Planning

B.

Executing

C.

Closing

D.

Initiating

Full Access
Question # 203

Which process involves monitoring the status of the project to update the project costs and managing changes to the cost baseline?

A.

Estimate Costs

B.

Control Costs

C.

Determine Budget

D.

Plan Cost Management

Full Access
Question # 204

Sending letters, memos, reports, emails, and faxes to share information is an example of which type of communication?

A.

Direct

B.

Interactive

C.

Pull

D.

Push

Full Access
Question # 205

Which tool or technique is effective in a project in which the deliverable is not a service or result?

A.

Inspection

B.

Variance analysis

C.

Decomposition

D.

Product analysis

Full Access
Question # 206

An input to the Manage Project Team process is:

A.

Work performance reports.

B.

Change requests.

C.

Activity resource requirements.

D.

Enterprise environmental factors.

Full Access
Question # 207

Which type of project management office (PMO) supplies templates, best practices, and training to project teams?

A.

Supportive

B.

Directive

C.

Controlling

D.

Instructive

Full Access
Question # 208

Which process involves subdividing project deliverables and project work into smaller, more manageable portions?

A.

Develop Schedule

B.

Create VVBS

C.

Estimate Activity Resources

D.

Define Scope

Full Access
Question # 209

Which cost is associated with nonconformance?

A.

Liabilities

B.

Inspections

C.

Training

D.

Equipment

Full Access
Question # 210

Which basic quality tool is most useful when gathering attributes data in an inspection to identify defects?

A.

Control charts

B.

Pareto diagrams

C.

Ishikavva diagrams

D.

Checksheets

Full Access
Question # 211

The process of identifying and documenting project roles, responsibilities, required skills, and reporting relationships and creating a staffing management plan is known as:

A.

Develop Project Team.

B.

Manage Project Team.

C.

Acquire Project Team.

D.

Plan Human Resource Management.

Full Access
Question # 212

Which input to the Manage Stakeholder Engagement process is used to document changes that occur during the project?

A.

Issue log

B.

Change log

C.

Expert judgment

D.

Change requests

Full Access
Question # 213

A method of obtaining early feedback on requirements by providing a working model of the expected product before actually building is known as:

A.

Benchmarking.

B.

Context diagrams.

C.

Brainstorming.

D.

Prototyping.

Full Access
Question # 214

The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:

A.

Project management plan.

B.

Project charter.

C.

Work breakdown structure.

D.

Stakeholder register.

Full Access
Question # 215

What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the earned value (EV) is $50?

A.

0.50

B.

0.67

C.

1.50

D.

2.00

Full Access
Question # 216

Which item is an example of personnel assessment?

A.

Resource calendar

B.

Tight matrix

C.

Team-building activity

D.

Focus group

Full Access
Question # 217

The only Process Group that comprises processes that typically occur from the beginning to the end of the project life cycle is:

A.

Planning.

B.

Executing,

C.

Monitoring and Controlling.

D.

Closing.

Full Access
Question # 218

Which tool or technique is used in the Perform Integrated Change Control process?

A.

Decomposition

B.

Modeling techniques

C.

Resource optimization

D.

Meetings

Full Access
Question # 219

Stakeholder satisfaction should be managed as a key project:

A.

Benefit

B.

Initiative

C.

Objective

D.

Process

Full Access
Question # 220

A large portion of a projects budget is typically expended on the processes in which Process Group?

A.

Executing

B.

Planning

C.

Monitoring and Controlling

D.

Closing

Full Access
Question # 221

Which process determines the risks that may affect the project and documents their characteristics?

A.

Control Risks

B.

Plan Risk Management

C.

Plan Risk Responses

D.

Identify Risks

Full Access
Question # 222

An input to the Identify Stakeholders process is:

A.

The project management plan.

B.

The stakeholder register.

C.

Procurement documents.

D.

Stakeholder analysis.

Full Access
Question # 223

The iterative process of increasing the level of detail in a project management plan as greater amounts of information become available is known as:

A.

Continuous improvement.

B.

Predictive planning.

C.

Progressive elaboration.

D.

Quality assurance.

Full Access
Question # 224

In the Plan Stakeholder Management process, expert judgment is used to:

A.

Provide information needed to plan appropriate ways to engage project stakeholders.

B.

Ensure comprehensive identification and listing of new stakeholders.

C.

Analyze the information needed to develop the project scope statement.

D.

Decide the level of engagement of the stakeholders at each required stage.

Full Access
Question # 225

The number of potential communication channels for a project with 5 stakeholders is:

A.

10.

B.

12.

C.

20.

D.

24.

Full Access
Question # 226

A project in which the scope, time, and cost of delivery are determined as early as possible is following a life cycle that is:

A.

Adaptive

B.

Predictive

C.

Incremental

D.

Iterative

Full Access
Question # 227

An element of the project scope statement is:

A.

Acceptance criteria.

B.

A stakeholder list.

C.

A summary budget,

D.

High-level risks.

Full Access
Question # 228

A key benefit of the Manage Communications process is that it enables:

A.

The best use of communication methods.

B.

An efficient and effective communication flow.

C.

Project costs to be reduced.

D.

The best use of communication technology.

Full Access
Question # 229

Identify Risks is part of which Process Group?

A.

Planning

B.

Executing

C.

Closing

D.

Initiating

Full Access
Question # 230

Which Plan Schedule Management tool or technique may involve choosing strategic options to estimate and schedule the project?

A.

Facilitation techniques

B.

Expert judgment

C.

Analytical techniques

D.

Variance analysis

Full Access
Question # 231

Which tool or technique allows a large number of ideas to be classified into groups for review and analysis?

A.

Nominal group technique

B.

Idea/mind mapping

C.

Affinity diagram

D.

Brainstorming

Full Access
Question # 232

Which item is a formal proposal to modify any document, deliverable, or baseline?

A.

Change request

B.

Requirements documentation

C.

Scope baseline

D.

Risk urgency assessment

Full Access
Question # 233

The process of estimating the type and quantity of material, human resources, equipment, or supplies required to perform each activity is known as:

A.

Collect Requirements.

B.

Conduct Procurements.

C.

Estimate Activity Durations.

D.

Estimate Activity Resources.

Full Access
Question # 234

Which tool or technique of the Define Activities process allows for work to exist at various levels of detail depending on where it is in the project life cycle?

A.

Historical relationships

B.

Dependency determination

C.

Bottom-up estimating

D.

Rolling wave planning

Full Access
Question # 235

Which stakeholder classification model groups stakeholders based on their level of authority and their active involvement in the project?

A.

Power/influence grid

B.

Power/interest grid

C.

Influence/impact grid

D.

Salience model

Full Access
Question # 236

A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:

A.

Start-to-start (SS).

B.

Start-to-finish (SF).

C.

Finish-to-start (FS).

D.

Finish-to-finish (FF).

Full Access
Question # 237

Which process in Project Time Management includes reserve analysis as a tool or technique?

A.

Estimate Activity Resources

B.

Sequence Activities

C.

Estimate Activity Durations

D.

Develop Schedule

Full Access
Question # 238

The process of confirming human resource availability and obtaining the team necessary to complete project activities is known as:

A.

Plan Human Resource Management.

B.

Acquire Project Team.

C.

Manage Project Team.

D.

Develop Project Team.

Full Access
Question # 239

The ways in which the roles and responsibilities, reporting relationships, and staffing management will be addressed and structured within a project is described in the:

A.

Human resource management plan.

B.

Activity resource requirements.

C.

Personnel assessment tools,

D.

Multi-criteria decision analysis.

Full Access
Question # 240

A technique used to determine the cause and degree of difference between baseline and actual performance is:

A.

Product analysis.

B.

Variance analysis.

C.

Document analysis,

D.

Decomposition.

Full Access
Question # 241

The Identify Stakeholders process is found in which Process Group?

A.

Initiating

B.

Monitoring and Controlling

C.

Planning

D.

Executing

Full Access
Question # 242

Which document describes the necessary information to determine if a project is worth the required investment?

A.

Cost baseline

B.

Service level agreement

C.

Memorandum of understanding

D.

Business case

Full Access
Question # 243

A tool or technique used in the Control Procurements process is:

A.

Expert judgment.

B.

Performance reporting.

C.

Bidder conferences.

D.

Reserve analysis.

Full Access
Question # 244

An example of a group decision-ma king technique is:

A.

Nominal group technique.

B.

Majority.

C.

Affinity diagram.

D.

Multi-criteria decision analysis.

Full Access
Question # 245

Which Process Group and Knowledge Area include the Sequence Activities process?

A.

Executing Process Group and Project Time Management

B.

Executing Process Group and Project Cost Management

C.

Planning Process Group and Project Time Management

D.

Planning Process Group and Project Cost Management

Full Access
Question # 246

The project manager at an organization has just realized that some of the engineering staff has been allocated to project Y and will not be available to finish task X. The project manager has also discovered that at the current pace, it will not be possible to complete the project on time. Due to cost constraints, hiring more work force is not a viable option. Which tools are at the manager's disposal?

A.

Resource leveling and fast tracking

B.

Fast tracking and crashing

C.

Crashing and applying leads and lags

D.

Scheduling tools and applying leads and lags

Full Access
Question # 247

Which of the following types of a dependency determination is used to define the sequence of activities?

A.

Legal

B.

Discretionary

C.

Internal

D.

Resource

Full Access
Question # 248

Which of the following are outputs of Develop Project Team?

A.

Human resources plan changes and project staff assignment updates

B.

Project management plan updates and enterprise environmental factor updates

C.

Resource calendars and project management plan updates

D.

Team performance assessments and enterprise environmental factor updates

Full Access
Question # 249

The definition of operations is a/an:

A.

organizational function performing the temporary execution of activities that produce the same product or provide repetitive service.

B.

temporary endeavor undertaken to create a unique product, service, or result.

C.

organization that provides oversight for an administrative area.

D.

organizational function performing the ongoing execution of activities that produce the same product or provide repetitive service.

Full Access
Question # 250

A required input for Create WBS is a project:

A.

quality plan.

B.

schedule network.

C.

management document update.

D.

scope statement.

Full Access
Question # 251

Prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact takes place in which process?

A.

Monitor and Control Risks

B.

Plan Risk Management

C.

Perform Qualitative Risk Analysis

D.

Perform Quantitative Risk Analysis

Full Access
Question # 252

What is the responsibility of the project manager and the functional manager respectively?

A.

Oversight for an administrative area; a facet of the core business

B.

Achieving the project objectives; providing management oversight for an administrative area

C.

A facet of the core business; achieving the project objectives

D.

Both are responsible for achieving the project objectives.

Full Access
Question # 253

Which Perform Quality Control tool graphically represents how various elements of a system interrelate?

A.

Control chart

B.

Flowchart

C.

Run chart

D.

Pareto chart

Full Access
Question # 254

Which is an output from Distribute Information?

A.

Earned value analysis

B.

Trend analysis

C.

Project records

D.

Performance reviews

Full Access
Question # 255

To please the customer, a project team member delivers a requirement which is uncontrolled. This is not part of the plan. This describes:

A.

scope creep.

B.

a change request.

C.

work performance information.

D.

deliverables.

Full Access
Question # 256

A project has an EV of 100 workdays, an AC of 120 workdays, and a PV of 80 workdays. What should be the concern?

A.

There is a cost underrun.

B.

There is a cost overrun.

C.

The project may not meet the deadline.

D.

The project is 20 days behind schedule.

Full Access
Question # 257

Which technique is commonly used for the Perform Quantitative Risk Analysis process?

A.

Brainstorming

B.

Strategies for opportunities

C.

Decision tree analysis

D.

Risk data quality assessment

Full Access
Question # 258

Which type of elaboration allows a project management team to manage at a greater level of detail as the project evolves?

A.

Cyclic

B.

Progressive

C.

Repetitive

D.

Iterative

Full Access
Question # 259

The progressive detailing of the project management plan is called:

A.

expert judgment.

B.

rolling wave planning.

C.

work performance information.

D.

specification.

Full Access
Question # 260

Which technique helps to determine the risks that have the most potential impact on a project?

A.

Cost risk simulation analysis

B.

Expected monetary value analysis

C.

Modeling and simulation

D.

Sensitivity analysis

Full Access
Question # 261

A weighting system is a tool for which area of Conduct Procurements?

A.

Plan contracting

B.

Requesting seller responses

C.

Selecting seller's

D.

Planning purchase and acquisition

Full Access
Question # 262

What risk technique is used to quantify the probability and impact of risks on project objectives?

A.

Expert judgment

B.

Risk registry

C.

Risk response planning

D.

Interviewing

Full Access
Question # 263

Based on the following metrics: EV= $20,000, AC= $22,000, and PV= $28,000, what is the project CV?

A.

-8000

B.

-2000

C.

2000

D.

8000

Full Access
Question # 264

Project contracts generally fall into which of the following three broad categories?

A.

Fixed-price, cost reimbursable, time and materials

B.

Make-or-buy, margin analysis, fixed-price

C.

Time and materials, fixed-price, margin analysis

D.

Make-or-buy, lump-sum, cost-plus-incentive

Full Access
Question # 265

What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?

A.

Organizational breakdown structure (OBS)

B.

Work performance information

C.

Work package

D.

Work breakdown structure (WBS)

Full Access
Question # 266

Which standard has interrelationships to other project management disciplines such as program management and portfolio management?

A.

Program Management Body of Knowledge Guide

B.

The Standard for Program Management

C.

Organizational Project Management Maturity Model (OPM3$)

D.

Guide to the Project Management Body of Knowledge (PMBOK®)

Full Access
Question # 267

The key benefit of the Monitoring and Controlling Process Group is the ability to:

A.

establish and manage project communication channels, both external and internal to the project team.

B.

influence the stakeholders that want to circumvent integrated change control so that their changes are implemented.

C.

monitor the ongoing project team against the team performance assessments and the project performance baseline.

D.

observe and measure project performance regularly and consistently to identify variances from the project management plan.

Full Access
Question # 268

In Project Cost Management, which input is exclusive to the Determine Budget process?

A.

Scope baseline

B.

Organizational process assets

C.

Project schedule

D.

Resource calendars

Full Access
Question # 269

Which category of contracts are sellers legally obligated to complete, with possible financial damages if the project objectives are not met?

A.

Cost-reimbursable contracts

B.

Time and Material contracts (T&M)

C.

Fixed-price contracts

D.

Cost Plus Fixed Fee Contracts (CPFF)

Full Access
Question # 270

Which of the following is an input to the Perform Qualitative Risk Analysis process?

A.

Risk register

B.

Risk data quality assessment

C.

Risk categorization

D.

Risk urgency

Full Access
Question # 271

Which of the following Project Communication Management processes uses performance reports as an input?

A.

Manage Stakeholder Expectations

B.

Report Performance

C.

Distribute Information

D.

Plan Communications

Full Access
Question # 272

Which process determines the risks that might affect the project?

A.

Perform Qualitative Risk Analysis

B.

Identify Risks

C.

Plan Risk Management

D.

Perform Quantitative Risk Analysis

Full Access
Question # 273

Which type of risk diagram is useful for showing time ordering of events?

A.

Ishikawa

B.

Milestone

C.

Influence

D.

Decision tree

Full Access
Question # 274

Analogous cost estimating relies on which of the following techniques?

A.

Expert judgment

B.

Project management software

C.

Vendor bid analysis

D.

Reserve analysis

Full Access
Question # 275

The project manager needs to review the templates in use. The templates are part of the:

A.

Enterprise environmental factors.

B.

Historical information,

C.

Organizational process assets.

D.

Corporate knowledge base.

Full Access
Question # 276

Which can be used to determine whether a process is stable or has predictable performance?

A.

Matrix diagram

B.

Histogram

C.

Control chart

D.

Flowchart

Full Access
Question # 277

In a construction project schedule, what is the logical relationship between the delivery of the concrete materials and the pouring of concrete?

A.

Start-to-start (SS)

B.

Start-to-finish (SF)

C.

Rnish-to-finish (FF)

D.

Finish-to-start (FS)

Full Access
Question # 278

The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline is:

A.

Determine Budget.

B.

Baseline Budget.

C.

Control Costs.

D.

Estimate Costs.

Full Access
Question # 279

Which type of chart is a graphic representation of a process showing the relationships among process steps?

A.

Control

B.

Bar

C.

Flow

D.

Pareto

Full Access
Question # 280

When sequencing activities, what does the common acronym FF stand for?

A.

Fixed Fee

B.

Free Float

C.

Fixed Finish

D.

Finish-to-Finish

Full Access
Question # 281

Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?

A.

WBS directory

B.

Activity list

C.

WBS

D.

Project schedule

Full Access
Question # 282

What provides information regarding the ways people, teams, and organizational units behave?

A.

Organizational chart

B.

Organizational theory

C.

Organizational structure

D.

Organizational behavior

Full Access
Question # 283

Change requests, project management plan updates, project document updates, and organizational process assets updates are all outputs of which project management process?

A.

Plan Risk Responses

B.

Manage Stakeholder Expectations

C.

Define Scope

D.

Report Performance

Full Access
Question # 284

The Project Management Process Group in which performance is observed and measured regularly from project initiation through completion is:

A.

Executing.

B.

Initiating,

C.

Monitoring and Controlling.

D.

Planning.

Full Access
Question # 285

Testing falls into which of the following categories of cost of quality?

A.

Internal failure costs

B.

Prevention costs

C.

Appraisal costs

D.

External failure costs

Full Access
Question # 286

A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what type of contract?

A.

Cost-reimbursable

B.

Time and material

C.

Fixed price or lump-sum

D.

Cost-plus-fixed-fee

Full Access
Question # 287

Which of the following processes audits the quality requirements and the results from quality control measures to ensure appropriate quality standards and operational definitions are used?

A.

Perform Quality Control

B.

Quality Metrics

C.

Perform Quality Assurance

D.

Plan Quality

Full Access
Question # 288

Which is an input to the Verify Scope process?

A.

Performance report

B.

Work breakdown structure (WBS)

C.

Requested changes

D.

Project management plan

Full Access
Question # 289

Which of the following helps to ensure that each requirement adds business value by linking it to the business and project objectives?

A.

Requirements traceability matrix

B.

Work breakdown structure (WBS) dictionary

C.

Requirements management plan

D.

Requirements documentation

Full Access
Question # 290

Which of the following project documents is an input to the Control Scope process?

A.

Vendor risk assessment diagram

B.

Risk register

C.

Requirements traceability matrix

D.

Area of responsibility summary

Full Access
Question # 291

Which of the following events would result in a baseline update?

A.

A project is behind schedule and the project manager wants the baseline to reflect estimated actual completion.

B.

A customer has approved a change request broadening the project scope and increasing the budget.

C.

One of the risks identified in the risk management plan occurs, resulting in a schedule delay.

D.

One of the key project team resources has left the team and no replacement is available.

Full Access
Question # 292

Which of the following is an input to the Direct and Manage Project Execution process?

A.

Approved change requests

B.

Approved contract documentation

C.

Work performance information

D.

Rejected change requests

Full Access
Question # 293

During which process would stakeholders provide formal acceptance of the completed project scope?

A.

Perform Quality Control

B.

Verify Scope

C.

Control Scope

D.

Develop Schedule

Full Access
Question # 294

Which of the following is a set of interrelated actions and activities performed to achieve a prespecified product, result, or service?

A.

Portfolio

B.

Process

C.

Project

D.

Program

Full Access
Question # 295

A project manager needs to demonstrate that the project meets quality standards and success criteria. For that reason, the project manager is defining the quality objectives of the project, the quality tools that will be used, and quality metrics for the project deliverables.

Which process is the project manager executing?

A.

Manage Quality

B.

Plan Quality Management

C.

Control Quality

D.

Plan Scope Management

Full Access
Question # 296

During the execution phase of a project a detect is found. The project manager takes responsibility and with the correct documentation, begins the task necessary to repair the defect. What process was applied?

A.

Change request

B.

Risk response

C.

Risk management plan

D.

Lessons learned

Full Access
Question # 297

How can a project manager maintain the engagement of stakeholders in a project with a high degree of change?

A.

Monitor project stakeholder relationships using engaging strategies and plans

B.

Send all project documents to stakeholders each time they are modified

C.

Schedule monthly meetings with the stakeholders, including team members

D.

Engage only with the project sponsors

Full Access
Question # 298

A new project manager wishes to recommend creating a project management office to senior management. Which statement would the project manager use to describe the Importance of creating the project management office?

A.

It will give the project manager Independence to make decisions without other departmental input.

B.

It Integrates organizational data and information to ensure that strategic objectives are fulfilled.

C.

The project management office can execute administrative tasks.

D.

The project management office can coordinate projects.

Full Access
Question # 299

Which knowledge area includes the processes to identify, define, and unify the various project management processes?

A.

Project Integration Management

B.

Project Communications Management

C.

Project Qualify Management

D.

Project Risk Management

Full Access
Question # 300

A team receives four different requests from separate stakeholders related to one application Match each requirement with its corresponding type of change request.

Full Access
Question # 301

Which group of inputs will a project manager use during the Monitor Stakeholder Engagement process?

A.

Project charter, business documents, and project management plan

B.

Agreements, scope baseline, and project management plan

C.

Project charter, business case, and project management plan

D.

Work performance data, enterprise environmental factors, and project management plan

Full Access
Question # 302

A project manager has to share a status report with a new stakeholder and is trying to determine the level of detail to include in the report. Which document best details the information the project manager needs lo make this decision?

A.

Organizational process assets

B.

Change management plan

C.

Communications management plan

D.

Resource management plan

Full Access
Question # 303

The project manager is working in the processes of Project Resource Management. Which process is the project manager developing if they are using parametric estimation?

A.

Plan Resource Management

B.

Estimate Activity Resources

C.

Estimate Costs

D.

Acquire Resources

Full Access
Question # 304

Which of the following lists represents the outputs of the Monitor Communications process?

A.

Project communications, project management plan updates, project documents updates, and organizational process assets updates

B.

Work performance information, change requests, project management plan updates, and project documents updates

C.

Communications management plan, project management plan updates, work performance report, and project documents update

D.

Stakeholder engagement plan, change requests, project management plan updates, and project documents updates

Full Access
Question # 305

Which statement summarizes the role of the change control board?

A.

The change control board is responsible for presenting the change for approval.

B.

The change control board will analyze the change impact in terms of cost and schedule.

C.

The change control board is responsible for managing the change management and configuration management systems.

D.

The change control board is responsible for reviewing and approving changes to the project.

Full Access
Question # 306

What does an S-curve from a Monte Carlo analysis show?

A.

Cumulative probability distribution representing probability of achieving a particular outcome

B.

Individual project risks or uncertainties that have the most potential impact on outcome

C.

Best alternative out of the possible solutions, incorporating associated risks and opportunities

D.

Diagram for all project uncertainties and their influence over a period of time

Full Access
Question # 307

Why is tailoring required in a project?

A.

Because a one-size-fits-all approach avoids complications and saves time.

B.

Because every project is unique and not every tool, technique, input, or output identified in the PMBOK Guide is required.

C.

Because tailoring allows us to identify the techniques, procedures, and system practices used by those in the project.

D.

Project managers should apply every process in the PMBOK Guide to the project, so tailoring is not required.

Full Access
Question # 308

Which of the following must be included in the risk register when the project manager completes the Identify Risks process?

A.

List of identified risks, potential risk owners, list of potential risk response

B.

List of identified risks, list of causes, list of risk categories

C.

Short risk titles, list of potential risk owners, list of impacts on objectives

D.

List of activities affected, list of potential risk responses, list of causes

Full Access
Question # 309

A project manager held a meeting and listed all team members' ideas for improving the product on a white board. What data gathering technique did the project manager apply?

A.

Focus groups

B.

Interviews

C.

Brainstorming

D.

Delphi technique

Full Access
Question # 310

Given the following information.

Activity A takes one week.

Activity B takes three weeks.

Activity C takes two weeks.

Activity D takes five weeks.

Activity A starts at the same time as Activity B.

Activity C follows Activity B and Activity A.

Activity D follows Activity C.

How long will it take to complete the project?

A.

Eleven weeks

B.

Nine weeks

C.

Eight weeks

D.

Ten weeks

Full Access
Question # 311

A new project has been set. Four main stakeholders besides the project manager and four other team members have been identified. How many communication channels are available?

A.

8

B.

18

C.

36

D.

40

Full Access
Question # 312

At the beginning of an iteration, the team will work to determine how many of the highest-priority items on the backlog list can be delivered within the next iteration. Which of the following activities is done first?

A.

Create Work Breakdown Structure (WBS)

B.

Create Scope Baseline

C.

Collect Requirements

D.

Define Scope

Full Access
Question # 313

A project manager uses their networking skills to build agreement with a difficult stakeholder. What level of influence did the project manager apply?

A.

Project level

B.

Organizational level

C.

Industry level

D.

Influential level

Full Access
Question # 314

What does expert judgment provide as an input to the resource management plan?

A.

Geographic distribution of facilities and resources

B.

Physical resource management policies and procedures

C.

Estimated lead times based on lessons learned

D.

Templates for the resource management plan

Full Access
Question # 315

In an agile or adaptive environment. when should risk be monitored and prioritized?

A.

Only during the initiation and Closing phases

B.

During the initiation and Planning phases

C.

During each iteration as the project progresses

D.

Throughout the Planning process group and retrospective meeting

Full Access
Question # 316

Match each dimension of the communications management plan to its corresponding focus.

Full Access
Question # 317

A project manager Is addressing risks and potential concerns related to stakeholder management, and Is clarifying and resolving previously Identified issues. In which process is the project manager engaged?

A.

Identify Stakeholders

B.

Plan Stakeholder Engagement

C.

Manage Stakeholder Engagement

D.

Monitor Slakeholder Engagement

Full Access
Question # 318

The procurement requirements for a project include working with several vendors. What should the project manager take into consideration during the Project Procurement Management processes?

A.

Work performance information

B.

Bidder conferences

C.

Complexity of procurement

D.

Procurement management plan

Full Access
Question # 319

A project manager is identifying the risks of a project. Which technique should the project manager use?

A.

Representations of uncertainty

B.

Prompt lists

C.

Audits

D.

Risk categorization

Full Access
Question # 320

Which of the following is an example of facit knowledge?

A.

Risk register

B.

Project requirements

C.

Expert judgment

D.

Make-or-buy analysis

Full Access
Question # 321

What can increase the complexity of the Manage Stakeholder Engagement process?

A.

The project must be of high quality.

B.

The stakeholders are from different countries.

C.

The project must comply with strict local government regulations.

D.

The project has a tight budget and timeline.

Full Access
Question # 322

Which set of competencies should a project manager have?

A.

Leadership, strategic and business management, and technical project management

B.

Expertise in the Industry, leadership and business management, and bilingual skills

C.

Technical project management, expertise in every role, and PMP certification

D.

Expertise in every detail on project activities. PMP certification, and leadership

Full Access
Question # 323

Match the influence with its corresponding category of influence.

Full Access
Question # 324

A functional manager is delegating a key project to a project team without a project manager. Which communication method will be most effective?

A.

Interactive

B.

Push

C.

Verbal

D.

Oral

Full Access
Question # 325

What charts and (igures should project managers use during the Perform Quantitative Risk Analysis process?

A.

Tornado diagrams and influence diagrams

B.

Detectability bubble charts and probability and impact matrix

C.

Hierarchical charts and burndown charts

D.

Flow charts and responsible, accountable, consult, and inform (RACI) charts

Full Access
Question # 326

Which is a list of organizational systems that may have an impact on a project?

A.

Internal policies, company procedures, and organizational resources

B.

Company culture, purchasing system, and project management information system

C.

Organizational structure, governance framework, and management elements

D.

Organizational process assets, enterprise environmental factors, and corporate knowledge

Full Access
Question # 327

What is the difference between quality metrics and quality measurements?

A.

Quality metrics are product attributes and the measurement is the result of the Monitor and Control Project process

B.

Quality metrics are the result of the Monitor and Control Project process and the measurements are product attributes

C.

Quality metrics and measurements are the same concept

D.

Quality metrics is the general objective and the measurements are the specific objectives

Full Access
Question # 328

Which term refers to the work performed to deliver results with specified features and functions?

A.

Project scope

B.

Product scope

C.

Change request

D.

Acceptance criteria

Full Access
Question # 329

What is the best tool to calculate the critical path on a project?

A.

Critical chain method

B.

Graphical evaluation and review technique (GERT) diagram

C.

Gantt chart

D.

Project network diagram

Full Access
Question # 330

A project manager is launching an information system to provide a lessons learned database. This action is necessary for recipients to access content at their own discretion. Which communication method is described?

A.

Push communication

B.

Pull communication

C.

Interactive communication

D.

Stakeholder communication

Full Access
Question # 331

A project manager is assigned to a strategic project Senior management asks the project manager to give a presentation in order to request support that will ensure the success of the project.

Which entities will the project manager attempt to influence?

A.

The project and the organization

B.

The organization and the industry

C.

The subject matter experts and the project

D.

The change control board and the organization

Full Access
Question # 332

Which of the following set of elements is part of an effective communications management plan?

A.

Escalation processes, person responsible for communicating the information, glossary of common terminology, methods or technologies used to convey the information

B.

Phone book directory, stakeholder communication requirements, project charter, glossary of common terminology

C.

Organizational chart, escalation processes, person responsible for communicating the information, project management plan, glossary of common terminology

D.

Glossary of common terminology, constraints denved from specific legislation and regulation, person responsible for communicating information, project management plan, resource management plan

Full Access
Question # 333

A project manager is monitoring and recording results of executing the quality management activities to assess performance and ensure the project outputs are complete, correct, and meet customer expectations. Which output is the project manager using?

A.

Approved change requests

B.

Verified deliverables

C.

Lessons learned

D.

Work performance data

Full Access
Question # 334

Which is the best way for a project manager to ensure efficient and frequent communication with management and stakeholders in an agile/adaptive environment?

A.

Post project artifacts in a transparent fashion and engage stakeholders on a regular basis.

B.

Make surveys among the stakeholders and meet with the team once a month.

C.

Create a social network and post news there.

D.

Create personalized emails for each stakeholder, asking for requests and reviewing objectives with them periodically.

Full Access
Question # 335

During which process of Project Cost Management does a project manager produce the cost baseline?

A.

Estimate Costs

B.

Control Schedule

C.

Determine Budget

D.

Develop Project Charter

Full Access
Question # 336

Which is the order of steps in the Procurement Management process?

A.

Identifying and planning procurement requirements, obtaining quotes or proposals, negotiating with vendors, contracting with selected vendors, and controlling procurements

B.

Identifying and planning procurement requirements, negotiating with vendors, contracting with selected vendors, obtaining quotes or proposals, and controlling procurements

C.

Controlling procurements, identifying and planning procurement requirements, obtaining quotes or proposals, negotiating with vendors, and contracting with selected vendors

D.

Obtaining quotes or proposals, identifying and planning procurement requirements, negotiating with vendors, contracting with selected vendors, and controlling procurements

Full Access
Question # 337

Which tasks should a project manager accomplish in order to manage project scope correctly?

A.

Define. Validate, and Control Scope. Control Schedule; Control Costs and Manage Stakeholder Engagement

B.

Collect Requirements. Define Scope. Create WBS. Develop Schedule, and Manage Stakeholder Engagement

C.

Plan Scope Management; Collect Requirements; Define. Validate, and Control Scope; and Create WBS

D.

Define. Validate, and Control Scope. Control Costs. Manage Stakeholder Engagement, and keep budget under control

Full Access
Question # 338

A project team conducts regular standup meetings to keep everyone updated on what each one of them is working on. What type of communication is this?

A.

Informal

B.

Unofficial

C.

Formal

D.

Hierarchical

Full Access
Question # 339

What is a tool or technique used in the Control Quality process?

A.

Attribute sampling

B.

Parametric estimating

C.

Statistical sampling

D.

Expert judgment

Full Access
Question # 340

Which tools and techniques will a project manager use to develop a project charter?

A.

Project manager experience, expert judgment, scope statement, and meetings

B.

Lessons learned database. Interpersonal and team skills, cost baseline, and meetings

C.

Expert judgment, data gathering. scope statement, schedule baseline, and meetings

D.

Expert judgment, data gathering. interpersonal and team skills, and meetings

Full Access