CA0-001 Certified Associate in Project Management (CAPM) Certification Question and Answers

Question # 4

You have been with the organization; you constantly hear rumours about a certain CAPM failing to live up to the CAPM Code. What you should do?

A.

You can gather as much information as you can before proceeding

B.

Confront the person immediately

C.

Ignore the rumours

D.

^ass the rumours along

Full Access
Question # 5

A complete set of indexed project records is called __________.

A.

Project archives

B.

Index

C.

sow

D.

Project History

Full Access
Question # 6

Delivery dates and availability of resources can be found in the details of the __________.

A.

Work Breakdown Structure

B.

sow

C.

Project Charter

D.

Project Scope Statement

Full Access
Question # 7

Which one of the following is not an output of contract closure?

A.

close contracts

B.

Lessons learned documentation

C.

Deliverable acceptance

D.

Scope statement

Full Access
Question # 8

Assumptions are factors that, for planning purposes, are considered to be ______.

A.

True, real, or certain

B.

True, real, or uncertain

C.

Real

D.

Verbal

Full Access
Question # 9

Who is responsible for the creation of the final project plan?

A.

Project Manager

B.

Team Leader

C.

Sponsor

D.

Project Team

Full Access
Question # 10

From whom do you need to gain the formal acceptance at project closure?

A.

The customer

B.

The qualify director

C.

Project management office

D.

Project manager

Full Access
Question # 11

Adjusting Leads and Lags is a technique for:

A.

Develop Schedule

B.

Estimate Activity Durations

C.

Estimate Activity Resources

D.

Sequence Activities

Full Access
Question # 12

Given the following estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days, what is the PERT weighted average?

A.

6

B.

4

C.

6.3

D.

6.1

Full Access
Question # 13

A scope management plan In which of the following scope management processes is the scope management plan prepared?

A.

Initiation

B.

Collect Requirements

C.

Define Scope

D.

Verify Scope

Full Access
Question # 14

Customer formally accepts the deliverables of each project phase. This process is known as ________.

A.

Verify Scope

B.

Quality Assurance

C.

Quality Control

D.

Quality Measurement

Full Access
Question # 15

You are the project manager of a project. Your project just went into integration mode. This means that your project __________.

A.

Has been accepted by the sponsor and the client

B.

Will be closed due to lack of resources

C.

Resources are being assigned to other areas of the business

D.

None of the above

Full Access
Question # 16

A Reserve Analysis is a technique for:

A.

Estimate Activity Durations

B.

Estimate Activity Resources

C.

Sequence Activities

D.

Define Activities

Full Access
Question # 17

Your project team is composed of team members in three countries plus a contractor team in a fourth country. What tool would optimize communication?

A.

Extranet-based electronic document repository

B.

Manual filing system

C.

War loom

D.

Verbal

Full Access
Question # 18

An activity that consumes no time or resource and shows only that a dependency exists between two activities is called:

A.

A milestone

B.

A hammock

C.

A dummy activity

D.

a and c

Full Access
Question # 19

Which is not included in Performance improvements :

A.

Improvements in amount of overtime worked

B.

Improvements in individual skills

C.

Improvements in team behaviours

D.

Improvements in team capabilities

Full Access
Question # 20

You are the project manager of a project .You have just completed the Collect Requirements and Define Scope. What should you do next?

A.

Create WBS

B.

Vei*

C.

Value analysis

D.

Control Scope

Full Access
Question # 21

Which of the following is a common characteristic of most project life cycle descriptions?

A.

Cost and staffing are low at the start, higher towards the end. and drop rapidly as the project nears completion.

B.

The probability of successfully completing the project is highest at the start of the project.

C.

Stakeholders have the most influence on the final characteristics of the product at the end of the project.

D.

a and b

Full Access
Question # 22

You are the project manager of a project .You have just completed the Define Activities, activity resources estimating, and Estimate Activity Durations processes. Which process have you left out?

A.

Control Schedule

B.

Create WBS

C.

Sequence Activities

D.

Operations

Full Access
Question # 23

Which process group is for detailed resource assignments and responsibilities?

A.

Human resources management plan

B.

Project charter

C.

Aplan

D.

Project management plan

Full Access
Question # 24

In PMBOK, the buyer is ________ to the project team.

A.

Internal

B.

External

C.

Outside

D.

Assigned

Full Access
Question # 25

Define Scope involves subdividing the major project deliverables into smaller, more manageable components to __________.

A.

Improve the accuracy of cost, time and resource estimates

B.

Define a baseline for performance measurement and control

C.

Facilitate clear responsibility assignments

D.

Al1 of the above

Full Access
Question # 26

Which is not the tools and techniques used in Contract Administration:

A.

Contract change control system

B.

Contract negotiation

C.

Payment system

D.

Performance rating

Full Access
Question # 27

You are the project manager of a project. Project is installing AC to hotel rooms. You have done project cost and time estimates, told the customer that the estimates provided will be accurate if the rooms meet the requirements like (wooden coated). This is an example of which of the following?

A.

Risk

B.

Assumption

C.

Constraint

D.

Budget

Full Access
Question # 28

A _______ is a series of actions bringing about a result.

A.

Project plan

B.

Process

C.

Schedule

D.

Flowchart

Full Access
Question # 29

Which of the following relationship is used in the Arrow Diagramming Method [ADM] :

A.

Start-to-Finish

B.

Finish-to-Start

C.

Start-to-Start

D.

Finish-to-Finish

Full Access
Question # 30

Which of the following is NOT input of Identify Risks?

A.

Project Charter

B.

Stakeholder Register

C.

Pis'* Management Plan

D.

Activity Cost Estimates

Full Access
Question # 31

A major assumption of all network scheduling methods is that the activity duration must be _____.

A.

Statistically dependent

B.

Variance distributed

C.

Statistically independent

D.

Deterministic

Full Access
Question # 32

Purchasing insurance is an example of __________.

A.

Transfer

B.

Acceptances

C.

Mitigation

D.

Contingency

Full Access
Question # 33

You are the project manager for the software Project. This project must be completed within one year. This is an example of which of the following?

A.

Schedule

B.

Assumption

C.

Constraint

D.

Planning process

Full Access
Question # 34

A Resource Leveling is a technique for:

A.

Develop Schedule

B.

Estimate Activity Durations

C.

Estimate Activity Resources

D.

Sequence Activities

Full Access
Question # 35

A process that is not part of a Project Risk Management is:

A.

Identification

B.

Solicitation

C.

Quantification

D.

Response Development

Full Access
Question # 36

When you are developing the estimates for project, you choose in a mathematical model to predict estimate. What type of estimation method are you using?

A.

Parametric estimating

B.

Bottom-up estimating

C.

Top-down estimating

D.

Analogous estimating

Full Access
Question # 37

Which document formally authorizes a project?

A.

The project charter

B.

Project scope statement

C.

The P'oject contract

D.

Project closing document

Full Access
Question # 38

Which statement is true about Bottom-up estimating?

A.

Estimating the cost of individual work items and then rolling up the costs to arrive at a project total.

B.

Uses the actual cost of a previous similar project as the basis for estimating the cost of the current project.

C.

Using project characteristics (or parameters) in a mathematical model to predict costs.

D.

Cost of quality can also be used to prepare the schedule activity cost estimate.

Full Access
Question # 39

Which of the following provides the least accurate in estimating?

A.

Rough order of magnitude

B.

Budget estimate

C.

WBS estimate

D.

Definitive estimate

Full Access
Question # 40

Function of the __________ is to make sure that changes to anything in the project are recorded and agreed to by the stakeholders.

A.

Project Manager

B.

Sponsor

C.

Team Lead

D.

Management

Full Access
Question # 41

During the planning phase of your project, your project team members have discovered another way to complete a portion of the project scope. This method is safer for the project team, but may cost more for the customer. This is an example of _______.

A.

Alternative identification

B.

"'s^ assessment

C.

Alternative selection

D.

Product analysis

Full Access
Question # 42

If a project with a CPI of 0.8, what you tell?

A.

The project is consuming more resources than anticipated.

B.

The project is using fewer resources than anticipated.

C.

The project is falling behind.

D.

The project is running ahead of schedule.

Full Access
Question # 43

What is the communication channel delta if the members in the communication plan are increased from 5 to 10?

A.

35

B.

5

C.

15

D.

75

Full Access
Question # 44

Which risk response is most likely to involve contingency reserves?

A.

Acceptance

B.

shaie

C.

Mitigate

D.

Transfer

Full Access
Question # 45

Project success can be achieved only if:

A.

There is a clear link between the project deliverables and the business strategy.

B.

The project sponsor leads the initiatives.

C.

The project manager is an expert in managing resources.

D.

Team members like project manager.

Full Access
Question # 46

In PMBOK, the seller is ________ to the project team.

A.

Internal

B.

External

C.

Outside

D.

Assigned

Full Access
Question # 47

Which of the following is conflict resolution technique?

A.

Compromise

B.

Smoothing

C.

Foimal

D.

Coercive

Full Access
Question # 48

Create Procurement document is done in _______.

A.

Plan Procurements

B.

Conduct Procurements

C.

Administer Procurements

D.

Close Procurements

Full Access
Question # 49

You are the project manager of a project and budgeted money to provide cash awards to team members that exceed expectations. A project team member that is motivated by the chance to earn cash reward can most accurately be explained by which theory

A.

Hierarchy of needs

B.

Expectancy theory

C.

Achievement theory

D.

Al1 of the above

Full Access
Question # 50

A Risk Register is a part of the ________.

A.

Project Scope Statement

B.

Project Management plan

C.

Project Scheduling plan

D.

Project Charter

Full Access
Question # 51

You are creating your WBS and keep decomposing tasks into smaller units. How can you tell when you are done?

A.

Keep decomposing tasks until you reach an amount of work that is small enough to reliably estimate required resources and duration.

B.

Keep decomposing work until you reach a predetermined number of hierarchy levels to keep the WBS balanced.

C.

Keep decomposing tasks until you reach an amount of work that can be accomplished in one DAY.

D.

Keep decomposing tasks until you reach an amount of work that can be accomplished in one WEEK.

Full Access
Question # 52

___________ is a group of processes required to purchase or acquire the products, services, or results needed from outside the project team to perform the work.

A.

Procurement Management

B.

Planning Management

C.

Scope Management

D.

Control Management

Full Access
Question # 53

Which document contains initial requirements that satisfy stakeholders' needs and expectations?

A.

Project charter

B.

Project management plan

C.

Project statement of work

D.

Project scope statement

Full Access
Question # 54

Final product transition is an output of which process?

A.

Direct and Manage Project Execution

B.

Close Project or Phase

C.

Perform Integrated Change Control

D.

Monitor and Control Project Work

Full Access
Question # 55

Which of the following is a Process Group?

A.

Scoping

B.

Budgeting

C.

Closing

D.

Quality

Full Access
Question # 56

What is the expected activity cost for a project having a most likely cost of $140, a best case scenario of $115, and a worst case scenario of $165?

A.

$115

B.

$138

C.

$140

D.

$165

Full Access
Question # 57

Which of the following is the definition of a project?

A.

Temporary endeavor undertaken to create a temporary business process or product

B.

Temporary endeavor undertaken to create a unique product, service, or result

C.

Permanent endeavor that produces repetitive outputs

D.

Temporary endeavor that produces repetitive outputs

Full Access
Question # 58

Which of the following is the correct network diagram for the table?

A.

Begin - A - C - D - E - End - B - D

B.

Begin - A - B - C - D - E - End

C.

Begin - A - B - D - E - End A - C - D

D.

Begin - A - C - D - E - End - B - C

Full Access
Question # 59

Which of the following is one of the key components of the basic communications model?

A.

Push

B.

Decode

C.

Pull

D.

Duration

Full Access
Question # 60

The decomposition technique is used to do which of the following?

A.

Subdivide the estimated costs of individual activities

B.

Subdivide project deliverables and project work into smaller, more manageable components

C.

Relate the work packages to the performing organizational units

D.

Shorten the project schedule duration and the amount of resources needed

Full Access
Question # 61

Which of the following techniques is used during Control Scope?

A.

Cost-Benefit Analysis

B.

Variance Analysis

C.

Reserve Analysis

D.

Stakeholder Analysis

Full Access
Question # 62

Which of the following can be used to track the requirements throughout the project life cycle?

A.

Requirements traceability matrix

B.

Scope management plan

C.

Project charter

D.

Work breakdown structure

Full Access
Question # 63

Which of the following is an example of a risk symptom?

A.

Failure to meet intermediate milestones

B.

Force of nature, such as a flood

C.

Risk threshold target

D.

Crashing front loading or fast tracking

Full Access
Question # 64

What tool or technique of Estimate Activity Durations uses parameters such as duration, budget, size, weight, and complexity from a previous, similar project as the basis for estimating the same parameter or measure for a future project?

A.

Bottom-up estimating

B.

Analogous estimating

C.

Parametric estimating

D.

Three-point estimates

Full Access
Question # 65

What is the status of a project if the Cost Performance Index is 1.25 and the Schedule Performance Index is 0.75?

A.

Under budget and behind schedule

B.

Over budget and ahead of schedule

C.

Under budget and ahead of schedule

D.

Over budget and behind schedule

Full Access
Question # 66

The Monitoring and Controlling process group contains which of the following processes?

A.

Plan Quality

B.

Perform Quality Assurance

C.

Perform Quality Control

D.

Identify Stakeholders

Full Access
Question # 67

A Project Management Office (PMO) manages a number of aspects, including what?

A.

Project scope, schedule, cost, and quality of the products of the work packages

B.

Central coordinator of communication management across projects, and for the delivery of specific project objectives, organization opportunity assessment

C.

Assigns project resources to best meet project objectives

D.

Overall risk, overall opportunity and interdependencies among projects

Full Access
Question # 68

Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?

A.

Work breakdown structure

B.

Organizational breakdown structure

C.

Resource breakdown structure

D.

Bill of materials

Full Access
Question # 69

What is Project Portfolio Management?

A.

Management of a project by dividing the project into more manageable sub-projects.

B.

Management of a project by utilizing a portfolio of general management skills, such as planning, organizing, staffing, executing and controlling.

C.

Management of all projects undertaken by a company.

D.

Management of a collection of projects that are grouped together to facilitate effective management and meet strategic business objectives.

Full Access
Question # 70

Which process involves aggregating the estimated costs of the individual schedule activities or work packages?

A.

Cost baseline

B.

Cost forecasting

C.

Cost variance

D.

Cost budgeting

Full Access
Question # 71

A project manager has limited authority in which type of organizational structure?

A.

Weak matrix

B.

Functional

C.

Balanced matrix

D.

Projectized

Full Access
Question # 72

What is the total float of the critical path?

A.

Can be any number

B.

Zero or positive

C.

Zero or negative

D.

Depends on the calendar

Full Access
Question # 73

Which analysis uses beta and triangular distributions as a tool and technique?

A.

Quantitative risk analysis

B.

Qualitative risk analysis

C.

Perform quality assurance

D.

Perform quality control

Full Access
Question # 74

Which of the following is an output of Define Scope?

A.

Project document updates

B.

Project management plan

C.

Scope baseline

D.

Product analysis

Full Access
Question # 75

Which of these are logical dependencies in a precedence diagram method?

A.

End-to-end

B.

Finish-to-end

C.

Start-to-end

D.

Start-to-start

Full Access
Question # 76

Initiating, Planning, Executing, Monitoring and Controlling and Closing are called:

A.

process groups.

B.

phase gates.

C.

knowledge areas.

D.

project phases.

Full Access
Question # 77

Quality and credibility of the qualitative risk analysis process requires that different levels of the risk's probabilities and impacts be defined is the definition of what?

A.

Risk breakdown structure (RBS)

B.

Risk probability and impact

C.

Qualitative risk analysis

D.

Risk response planning

Full Access
Question # 78

If the Schedule Variance (SV) =$55, and the Planned Value (PV) =$11, what is the Earned Value (EV)?

A.

$0.2

B.

$5

C.

$44

D.

$66